ILLINOIS POLLUTION CONTROL BOARD
    December 14, 1978
    SOUTHERN ILLINOIS POWER COOPERATIVE,
    Petitioner,
    PCB 78—255
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION AND ORDER OF
    THE
    BOARD
    (by Dr. Satcheil)
    This matter comes before the Board upon a petition filed on
    September
    18,
    1978
    by
    Southern Illinois Power Cooperative
    (SIPC)
    requesting a variance from
    Rule 204(a) (1)
    of the Chapter
    2:
    Air
    Pollution Control Regulations
    (Chapter
    2) until December
    31,
    1978.
    An amended petition was filed on October 19,
    1978.
    The Environ-
    mental Protection Agency
    (Agency)
    filed
    its recommendation on
    November
    6,
    1978.
    No hearing was held.
    SIPC is
    a public utility and operates three identical
    cyclone-fired boilers,
    rated at 33 megawatts each.
    These boilers
    exhaust through two stacks, each 210 feet tall.
    Units
    1 and
    2
    exhaust through stack number
    1 and Unit number
    3 exhausts through
    stack number
    2.
    Unit number
    4 is
    a cyclone-fired boiler with
    a
    designed generating capacity of 175 megawatts which will exhaust
    through
    a stack 400 feet tall.
    It
    is Unit number
    4
    for which
    a variance is sought.
    This
    unit has an SO2 scrubber which will bring the emissions
    of the unit
    into compliance;
    however,
    tile power wiring,
    control wiring and
    instrumentation are not yet convoletelv installed and the scrubber
    is presently inoperable.
    These components were originally scheduled
    to be completed July
    1,
    1978 when the boiler commenced operations
    and are now expected to be installed and complete by December
    1,
    1978.
    The delay was because the contractor installed wiring with
    insufficient
    insulation and consequently had to reorder and rewire
    the unit.
    There was also
    a delay in obtaining rubber coated fiber
    pipes
    from the factory.
    The pipes leaked when pressure tested and
    had to he remanufactured.
    Petitioner currently forecasts its peak winter power demands
    at 196 megawatts for 1978.
    Without the fourth qeneratincr unit the
    available capacity is 140 MW.
    Petitioner~sUnits
    1,
    2 and
    3 can
    deliver 105
    MW
    and
    35
    MW
    peaking power is available from South
    Eastern Power Association
    (SEPA)
    Petitioner also has a contract
    with Big Rivers Rural Electric Corporation for 100 MW from September
    30,
    1978 through September 15,
    1979.
    Thus to meet its own needs and
    32—275

    --2—
    its contract obligations Petitioner will need to obtain the extra
    megawatts
    from Unit number
    4.
    Petitioner thus claims that compli-
    ance with Rule 204 will prevent the use of Unit number
    4 and would
    impose an arbitrary and unreasonable hardship on Petitioner.
    The SIPC facility
    is located on the Lake of Eqypt, approxi-
    mately eight miles south of Marion,
    Illinois.
    Marion has a popu-
    lations
    of approximately 12,000 and
    is the major population center
    of Williamson County.
    The nearest permanent residences near the
    facility are located at
    a distance from one-fourth to one—half
    mile from the plant.
    The nearest ambient air quality reporting station monitoring
    sulfur dioxide
    levels is located at 2209 West Main Street in Marion,
    Illinois, approximately eight miles north of
    the
    facility.
    The 1977
    Annual Air Quality Report indicates no violation of the primary or
    secondary standards
    for ambient air levels of SO2.
    The hiqhest
    3—hour average was recorded as
    0.201 ppm as compared to the secondary
    standard of
    0.5 ppm.
    The annual arithmetic mean was indicated as
    0.014 ppm as compared to the primary standard of 0.03 ppm, and no
    violations
    of the primary standard 24—hour average in excess of
    0.14 ppm were recorded.
    At the time the recommendation was filed
    the Agency had received no objections to the qrant of the variance.
    The Agency does believe that SO2 emissions
    from Unit number
    4
    in
    combination with SIPC’s three existing units could cause violations
    of the 24-hour SO~air quality standard of 0.14 ppm and the 3-hour
    secondary standard of 0.5 ppm.
    The possibility of such violations
    could be minimized through continuous monitoring
    of loads and
    resulting boiler operations.
    The Petitioner’s Unit number
    4 is classified as a new source
    and the facility is located in an attainment area for SO2.
    Mod-
    eling was done by the Agency’s Air Resources Analysis Section for
    Unit number
    4 and by Burns
    & McDonnell Engineering Company, Pet-
    itioner’s consultant.
    The Agency’s conclusion was that the
    modeling revealed no apparent future violations of the primary and
    secondary standards
    as long as
    the .802 scrubbers performed to design
    specifications.
    The Agency’s study was conducted using maximum
    boiler operations and worst case fuel.
    If the scrubber is bypassed,
    the dispersion characteristics
    of emissions from Unit number
    4 may
    be somewhat improved because of the increased temperature of the
    exhaust gases.
    Petitioner’s
    study reinforces the Agency’s conclu-
    sions.
    The Board will grant Petitioner’s requested variance subject
    to conditions
    in order to meet the requirements of Section 35 of
    the Enivronmental Protection Act and Section
    113(d)
    of the Federal
    Clean Air Act.
    The Board finds that Petitioner
    is currently unable
    32—276

    —3—
    to comply with the SO7 standards and would suffer an arbitrary
    and unreasonable hardship if denied the variance.
    Environmental
    damage is unlikely while Petitioner would suffer financial hard-
    ship.
    Compliance will he met by December 31,
    1978.
    This
    Opinion constitutes the Board’s findinqs of fact and
    conclusions of law in this matter.
    ORDER
    It
    is the Order of the Pollution Control Board that Southern
    Illinois Power Cooperative is granted
    a variance from Rule 204
    (a) (1)
    of the Chapter
    2:
    Air Pollution Control Regulations for
    its steam electric generating Unit number
    4 until December
    31,
    1978 subject to the following conditions:
    1.
    That SIPCO utilizes its 175 megawatt unit
    (Unit number
    4)
    to its capacity in conjunction with the maximum obtain-
    able power from its
    35 megawatt tie in line before
    commencing operation of any one of its existing
    33
    megawatt units.
    The remaining units will be operated
    only to the extent of supplying the system’s specific
    power needs.
    2.
    If at any time during the period of variance, the
    Marion air sampling station indicates a violation of
    the 24—hour sulfur dioxide air quality standard, or
    the 3-hour secondary sulfur dioxide air quality
    standard,
    the Petitioner shall restrict or reduce
    its total sulfur dioxide emission rate as soon as
    possible.
    3.
    The Petitioner shall submit monthly reports
    to the
    Agency summarizing the operation
    of all power pro-
    ducing units at its Lake of Egypt facility and the
    amount of power received through the
    35 megawatt tie
    in line for each day of operation.
    The report should
    also indicate the status of completion of construction
    of the SO2 scrubber for Unit number
    4.
    4.
    Within thirty days
    of the granting of the variance, the
    Petitioner should make application for an Operating
    Permit from the Agency for the generating Unit number
    4.
    32—27 7

    —4—
    5.
    Within thirty days of commencement of scrubber
    operations,
    the particulate matter concentrations
    in the effluent stream should be measured by an
    approved independent testing service.
    The measure-
    ments to be conducted using the procedures described
    in the “Stack Sampling Manual Methods and Procedures,”
    as filed by the Agency, pursuant to PCB Regulations,
    Chapter
    2, Part
    I, Rule 106(h), with the Secretary
    of
    State’s Office on June 16, 1975 and revised from time
    to time.
    The results of these tests, in triplicate,
    should be forwarded to the Agency’s Regional Office
    immediately after the test results are compiled and
    finalized.
    The address of the Agency’s Regional
    Office
    is:
    Illinois Environmental Protection Agency,
    Division of Air Pollution Control,
    ll5A West Main
    Street, Collinsville, Illinois 62234.
    6.
    The Agency should be allowed to witness the tests and
    should be notified a minimum of thirty days prior to
    the expected date of the tests, and further notification
    of a minimum of five working days prior to the test of
    the exact date,
    time and place that the test will he
    performed.
    7.
    Within thirty days
    of commencement of scrubber operation,
    the sulfur dioxide concentration in the effluent stream
    shall be measured, using the procedures described in
    Rule 204(g) (1)
    of Chapter
    2 of the Illinois Air Pollution
    Control Regulations,
    by an approved independent testing
    service.
    The results
    of these tests should be forwarded
    in triplicate
    to the Agency’s Collinsville Office
    (see
    address above)
    immediately after the test results are
    compiled and finalized.
    The Agency should also be
    allowed to witness these tests and should be notified
    a minimum of thirty days prior
    to the expected date of
    these tests and further notified a minimum of five
    working days prior
    to the test of the exact date,
    time
    and place of the tests.
    8.
    The Petitioner shall, within forty—five days of the date
    of this Order,
    execute and send to John D.
    Williams,
    Technical Advisor, Enforcement Programs, Illinois Environ-
    mental Protection Agency, 2200 Churchill Road, Springfield,
    Illinois
    62706, a Certification of Acceptance of this
    variance
    by which it agrees to be bound by its terms and
    conditions.
    This forty-five day period shall be held in
    abeyance for any period
    in which this matter is appealed.
    The form of said Certification shall be as follows:
    32—278

    —5—
    CERTIFICATION
    I,
    (We)
    ,
    ______________________________,
    having read and
    fully understanding the Order of the Illinois Pollution Control
    Board in PCB 78—255 hereby accept said Order and agree to be
    bound by all terms and conditions
    thereof.
    TITLE
    DATE
    Final
    compliance must be achieved by December 31,
    1978 or the
    Petitioner may be subject to noncompliance penalties under
    Section 120 of the Clean Air Act as amended August,
    1977.
    I,
    Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify the ahoy
    Opini
    n and Order were
    adtopted on the
    ~
    day of
    ______________
    1978 by a
    vote of
    ~
    Christan
    L. Mof
    ,
    Clerk
    Illinois Polluti
    Control Board
    32—279

    Back to top