ILLINOIS POLLUTION CONTROL BOARD
    October 18, 1979
    CITY OF LaHARPE,
    )
    Petitioner,
    v.
    )
    PCB 79—121
    I
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent.
    OPINION AND ORDER OF
    THE
    BOARD
    (by
    Mr.
    Goodman):
    The
    City
    of Lallarpe requests a variance from items listed
    in a complaint filed with the Board by the Environmental Pro-
    tection Agency (Agency) against Petitioner
    (PCB 79—102)
    on May
    2,
    1979.
    The complaint alleges violations of Sections 12(a)
    and 12(f)
    of the Environmental Protection Act
    (Act) and of
    Rules 410(a),
    502(a)
    sic,
    601(a),
    602(b),
    901 and 1201 of
    Chapter 3:
    Water Pollution Control Rules and Regulations
    (Chapter
    3).
    The
    Agency
    recommends
    that
    the
    variance
    be
    denied.
    Petitioner
    has
    waived
    its
    right
    to
    a
    hearing.
    The
    City
    of
    LaHarpe,
    located in Hancock County,
    owns
    and
    operates a sewage treatment plant and sewer system that serves
    approximately 690 customers.
    Lift station *1 expels overflow
    sewage through
    a pipe into a nearby watercourse during wet
    weather.
    Excess flow causes the other
    lift station,
    located
    at the treatment plant,
    to allow sewage to bypass an activated
    sludge unit and to
    flow directly into a polishing lagoon.
    The
    frequency,
    duration and magnitude of the overflows are unknown.
    Discharge monitoring reports indicate that the Petitioner
    has been exceeding the effluent limitations of its NPDES per-
    mit of
    30 mg/I BOD6 and 30 mg/I suspended solids
    (SS).
    Peti-
    tioner has failed
    Eo monitor the overflows or to install an
    auxiliary pump at lift station #1.
    Installation of a total
    sewage flow meter and an auxiliary pump is presumed to now
    have been installed
    (p.5).
    Petitioner claims that violations
    of the BOD5 and SS effluent
    limitations,
    overflow at the lift
    station,
    and bypassing at the treatment plant can only be
    eliminated
    if federal funding
    for upgrading the treatment
    plant is obtained.
    Petitioner contends that denial of the variance would im-
    pose an arbitrary and unreasonable hardship upon
    it.
    Petitioner
    35—523

    —2—
    indicates that the estimated cost of compliance of $381,880
    cannot
    be borne
    by 690 customers,
    and that significantly in-
    creased user
    rates would promote an exodus o~residents to
    nearby
    towns having
    lower rates.
    Revenue bonds
    issued when
    the present
    sewer
    system was constructed have not been retired;
    therefore,
    the
    city
    is not
    in a strong position to obtain local
    financing
    for extensive upgrading of
    its treatment plant.
    The
    Petitioner has applied for Step
    1 funding
    in the Municipal
    Wastewater Treatment Works Construction Grant Program.
    The Board, pursuant to Section 35 o~the
    Act,
    must grant
    variances consistently with the provisions of the Clean Water
    Act.
    Sections 304(b) and 304(d)
    of the Clean Water Act author-
    ize the Administrator of
    the U.
    S. Environmental Protection
    Agency to set effluent limitations.
    Effluent from a secondary
    tr(~atmentworks may have
    a maximum average concentration of
    30 mg/i BOD5 and 30 mg/i SS for
    a 30 consecutive day period.
    41
    FR
    30785,
    §133.102(a) and
    (b)
    (July 26,
    1976).
    Petitioner’s current NPDES permit requires that SOD5 and
    SS concentrations each be limited to 30 mg/l.
    Petitioner’s
    request
    for a variance from Section 12(f) of the Act and from
    Rules
    401(a) and
    901 of Chapter
    3 asks that it he allowed to
    ecceed these permit limits.
    Under Section 3011(1) of the
    Clean Water Act, Petitioner h~duntil June 26,
    1978 to request
    that these permit limitations be modified by the Agency and
    to gain an exemption until July 1,
    1983 from the effluent reg-
    ulations.
    Petitioner failed to make such a request and must
    be held to the current permit limitations.
    Granting a variance
    that would allow discharges beyond the 30 mg/i SOD5 and 30
    mg/i SS
    limitations would be inconsistent with the Clean Water
    Act.
    The Board denies Petitioner a variance from Rules
    401(a)
    and
    901 of Chapter
    3 and from Section 12(f)
    of the Act.
    Turning to Petitioner’s request for a variance from Rules
    502 and 602(b) of Chapter
    3 the Board notes that the Agency
    describes Section 502 when referring to Section 502(a).
    Since
    Rule 502 has no subsections,
    the Board presumes that the Agency
    has made a clerical error and interprets
    all references
    to
    502(a)
    as referring to Rule
    502.
    Rule 502 requires that all effluent be measured.
    The
    City has made funds available for the installation of a flow
    meter at the plant.
    Completion of this project is scheduled
    for mid—October,
    1979.
    Without the variance, Petitioner could
    be subject to
    a penalty in an enforcement action for a con-
    tinuing violation of Rule 502.
    However, upon examination of
    Exhibits 2—6 to the Agency’s recommendation,
    the Board finds
    that Petitioner was made aware of the need for the flow meas-
    uring device as early as March of 1974 and was reminded no
    less than five times
    in the subsequent four-year period of
    the deficiency.
    Under these circumstances the Board
    finds
    that any hardship imposed by refusing to grant a variance
    35—524

    —3—
    from the requirements of Rule 502 is
    a self-imposed one.
    The
    Board therefore denies Petitioner a variance from Rule 502 of
    Chapter
    3.
    Rule 602(b) prohibits overflows
    in sanitary sewers.
    Over-
    flows occur
    in the City of LaHarpe during wet weather.
    The
    overflow problem cannot be rectified until the treatment plant
    is reconstructed.
    Federal
    funding
    is necessary to finance
    this project and without the variance requested,
    the City of
    LaHarpe would be subject to an enforcement proceeding for the
    continuing violation of
    602(b).
    On August 10,
    1978 the Agency
    advised Petitioner that Step
    1 funding was available from the
    federal government
    for the purpose of starting the reconstruc-
    tion of the treatment plant
    (Agency Rec.,
    Ex.1).
    Petitioner
    did not apply for such funding until June 19,
    1979, with the
    apparent results that Petitioner will not be added to the
    priority list until 1980 and that it will be at least three
    to five years beyond that date until Step
    2 or Step
    3
    funds for
    engineering and construction may become available.
    Indeed,
    Petitioner has filed no application for federal aid from 1971
    until
    1979.
    In
    its amendment to the petition for variance
    filed August
    21,
    1979 Petitioner states “past City adminis-
    trations for the Petitioner have not applied for funding
    available to them through the Agency because of a number of
    complex political and personal reasons.”
    The Board finds that
    Petitioner’s inaction has been self—serving and constitutes a
    significantly delayed compliance.
    The Board therefore denies
    Petitioner’s request for variance from Rule 602(b)
    of Chapter
    3.
    The City’s variance petition requests relief from all
    violations alleged in the Agency’s complaint in EPA v. LaHa~,
    PCB 79—102.
    Variances from Rules
    601(a) and 1201 of Chapter
    3,
    as well
    as from Section 12(a)
    of the Act, remain to be con-
    sidered.
    Rule 601(a) requires that an auxiliary power source
    be available at a sewage treatment plant in cases
    of emergen-
    cies or power outages, while Rule 1201 requires that a properly
    certified operator be employed at the plant.
    Petitioner indi-
    cates that an auxiliary pump was scheduled to be installed by
    August
    1,
    1979
    (p.5) and that proper certification has been
    obtained by its plant operator
    (p.7).
    From these statements
    the Board presumes that the City has no need for a variance
    from these
    rules; consequently, the petition as it requests
    relief from Rules 601(a) and 1201 of Chapter
    3 is hereby dis-
    missed as moot.
    Section 12(a) provides that no person shall cause or
    threaten
    the
    discharge of contaminants that cause or tend to
    cause water pollution within the State or that violate the
    regulations and standards of the Board.
    Because of problems
    of
    interpretation,
    the Board does not favor granting variances
    from general provisions
    of the Environmental Protection Act.
    From our rulings herein, the Board finds
    that Petitioner is
    not entitled to any such extraordinary relief and denies
    variance from Section 12(a)
    of the Act.
    3
    5—525

    —4—
    This Opinion constitutes the findings of fact and conclu-
    sions
    of law of the Board in this matter.
    ORDER
    1)
    The City of LaHarpe’s petition for variance from Rules
    601(a) and 1201 of Chapter
    3:
    Water Pollution Control
    Rules and Regulations is hereby dismissed as moot.
    2)
    The City of LaHarpe is hereby denied a variance from
    Rules
    410(a),
    502,
    602(b) and
    901 of Chapter 3:
    Water
    Pollution Control Rules and Regulations and from Sections
    12(a)
    and
    12(f)
    of the Environmental Protection Act.
    IT
    tS SO ORDERED.
    I,
    Christan L.
    Moffett,
    Clerk of the Illinois Pollution
    Control Board,
    herelly certify
    the a
    o e Ooinion and Order were
    adopted on the
    ~‘
    day of
    __________________
    ,
    1979
    by
    a vote of
    o4t~tL
    --
    Christan L. Moffe~
    erk
    Illinois Pollution
    rol Board
    35—526

    Back to top