ILLINOIS POLLUTION CONTROL BOARD
    October
    4,
    1979
    CORPORATE WEST DEVELOPMENT, INC.,
    and COUNTY OF DUPAGE,
    Petitioners,
    v.
    )
    PCB 79—163
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION OF THE BOARD
    (by Mr.
    Dumelle):
    Petitioner Corporate West Development,
    Inc.
    (Corporate
    West)
    requested a variance from Sections
    12 and 39 of the
    Act and Rules 951,
    952, and 962 of Chapter
    3: Water Pollution
    to construct and operate a sewer connection from
    a proposed
    hotel
    site
    to the DuPage County Department of Public Works
    Lisle—Woodridge sewage treatment plant.
    This plant has been
    placed on restricted status.
    The Agency recommended that a
    variance be granted to allow construction of the sewer
    extension with operation conditioned on a number of factors.
    No hearing was held. At an emergency meeting on September
    13, 1979 the Board granted a variance to construct and
    operate the requested extension subject to conditions.
    This
    Opinion supports the Board’s Order.
    On November 20,
    1975 the Agency issued a permit to
    Corporate West which authorized the construction and operation
    of
    a sewer extension to carry 42,000 gallons of wastewater
    per day.
    By July 28,
    1977 Corporate West had obtained
    permits from the Village of Lisle for two office buildings
    which consumed 6,000 gallons
    of the 42,000 gallon allocation.
    On October
    5,
    1978 Corporate West entered into a contract
    with Fireside West Development Company
    (Fireside)
    to sell 15
    acres of property to build a hotel and restaurant facility.
    The contract included a warranty that adequate sewerage
    would be available.
    On May
    31, 1979 the Agency notified
    DuPage County
    (the county) that the Lisle—Woodridge plant
    was on restricted status and had no additional capacity.
    On
    July 24,
    1979 Corporate West was informed by the Agency that
    an additional permit would be required to construct and
    operate the connecting
    lines for the hotel.
    Since the plant
    was on restricted status,
    this permit could not be issued.
    Corporate West and the Agency disagree on whether or
    not an additional permit is needed, but this
    is not a permit
    denial appeal.
    Corporate West has requested a variance
    because Fireside will not proceed to a closing until the
    35—487

    —2—
    matter
    is resolved.
    Fireside must execute
    a loan commitment
    in the near future and the hotel franchisor needs
    a demonstration
    that all necessary financing has been obtained.
    Corporate
    West needs a large payment from Fireside
    ($1.1 million) by
    the end of this year to avoid excess interest payments on an
    outstanding loan of $6 million.
    Corporate West claims that
    construction, already underway, must continue so that the
    hotel
    is under roof before winter makes outdoor work impractical.
    Corporate West admits that although the Lisle—Woodridge
    plant
    .
    .
    .
    is not necessarily hydraulically overloaded
    the plant’s discharge has recorded violations of its
    NPDES permit.
    Corporate West claims that all hydraulic and
    organic overloadings will be corrected by the construction
    of an interim expansion of 1.0 million gallons per day
    (MGD)
    and a permanent expansion of 04 MGD by the county within
    the next year and
    a
    0.3 MGD interim expansion by the Village
    of Lisle.
    In addition Corporate West points
    to additional
    plans by the county to permanently expand the plant and the
    fact that an additional 0.032
    MGD
    from the hotel will have
    no measurable impact on the 6.94 MGD plant.
    Corporate West’s hardship
    in this matter consists of
    economic losses
    it would suffer
    if the project
    is placed in
    jeopardy.
    Corporate West claims that this hardship
    is
    rendered arbitrary and unreasonable when it is balanced
    against reliance on a previously issued permit and the fact
    that projected expansions may precede the completion of the
    hotel.
    In its Recommendation,
    the Agency claims that Corporate
    West has never obtained connection permits for the two
    office buildings.
    The Agency first notified the county of
    pending restricted status on April
    25, 1979 and actual
    designation on May 31,
    1979 pursuant to Rule 604(a) of
    Chapter
    3: Water Pollution.
    The Agency’s
    latest data show
    that from July 12 to July 31,
    1979 the flow from the plant
    averaged 7.16 MGD,
    indicating hydraulic overloading.
    The
    Agency believes that outstanding permits exist which would
    authorize an additional 1.7
    NIGD.
    The Agency cites discharge
    monitoring reports which show that both the Lisle and Woodridge
    plants have exceeded NPDES standards for BOD, Suspended
    Solids,
    and Ammonia Nitrogen consistently from August,
    1978
    through June,
    1979.
    The Agency
    is aware of the county’s
    commitment to expand the Woodridge plant with an additional
    1.4 MGD by September 15,
    1980 but has not been advised of
    any plans by Lisle.
    The Agency recommends that
    a variance be granted which
    would allow construction of the sewer
    lines but that operation
    be conditioned upon:
    1)
    an order from the Board directing
    the county to complete the 1.4
    NIGD
    expansions and any other
    necessary expansions and,
    2)
    a similar order from the
    Circuit Court for the 18th Judicial District
    in pending
    litigation.
    The Agency also asks that this variance be

    —3—
    limited to the connection from the proposed hotel
    arid
    that
    variance relief from
    Rules
    951 and 952 be dismissed.
    In
    a Response, Corporate West claims that the Agency’s
    requested conditions are unreasonable on three counts.
    First,
    it has
    no control over the actions of the Circuit
    Court.
    Second,
    any additional variance requests should be
    handled by the Board when they arise.
    Third,
    financing may
    be withheld if
    a cloud remains over Corporate West’s or
    Fireside’s right to operate the hotel
    sewer connection.
    The Board concludes that denial of
    a variance would
    constitute arbitrary or unreasonable hardship.
    Corporate
    West appears
    to have proceeded in good faith reliance on a
    42,000 gallon per day allocation made in 1975.
    Since the
    contribution from
    the
    hotel
    is small
    in relation to the
    total plant flow and since the county is proceeding to
    remedy the plant’s shortcomings, the chance for any measurable
    environmental damage appears slight.
    The Board sees no
    reason to tie this matter to any future variance petitions
    since they can be evaluated individually at a later date.
    The county was named as
    a Respondent throughout this proceeding,
    but has never been joined formally.
    The Board has
    named
    the
    county as
    a Petitioner in the Order because its interests
    are more closely aligned with Corporate West’s than
    with
    the
    Agency’s. The county has been ordered to perform the necessary
    expansions and operation of the sewer connection is contingent
    upon a similar order from the circuit court because the
    Board was advised at its emergency meeting that the county
    had agreed to this action.
    In general,
    the Board
    is
    extremely
    reluctant to condition its order upon a court action with
    which it
    is not familiar.
    Similarly, Corporate West stated
    its agreement with these actions.
    The Board felt it would
    be inappropriate to require the county to execute a certification
    because time was of the essence.
    The Board’s Order has not addressed Petitioner’s requests
    for relief from Section 12 of the Act since a variance from
    Rule
    962 renders statutory relief unnecessary.
    Relief from
    Section 39 and Rules
    951 and 952 are similarly not addressed
    since there has been no showing that Corporate West should
    not be required to comply with those permitting procedures.
    This Opinion constitutes the Board’s findings of fact
    and conclusions of law in this matter.
    I,
    Christan L. Moffett, Clerk of the Illinois Pollution
    Control Boa
    s1~
    hereby certify the a ov
    Opinion was adopted
    on the
    ________________
    day of
    ______________,
    1979 by a
    vote of
    ______
    —____
    Christan L.
    Moffett, /~k
    Illinois Pollution CoT~folBoard

    Back to top