ILLINOIS POLLUTION CONTROL BOARD
April 16, 1981
THE VILLAGE OF SAUGET
AND THE CITY OF EAST ST. LOUIS,
)
)
Petitioners,
v.
)
PCB 80—176
ILLINOIS ENVIRONMENTAL PROTECTION
)
AGENCY,
)
Respondent.
OPINION AND ORDER OF THE BOARD (by J.D. Dumelle):
On September 30, 1980, Petitioners filed a variance
petition requesting relief from Rule 602(c)(1) and (2) of Chapter
3: Water Pollution. On October 31, 1980, the Environmental
Protection Agency (Agency) filed a recommendation that the
variance be granted subject to certain conditions. Hearing
was waived and none was held.
Petitioners are Illinois municipal corporations situated
in St. Clair County, Illinois, on the east bank of the Mississiopt
River. All wastewater within the East St. Louis sewer systeri
is currently transported to the East St. Louis wastewater
treatment plant. During periods of increased flow due to
rainfall, wastewater is discharged directly to the Mississippi
River.
In September, 1977, the Village of Sauget was designated
as lead agency for the design, construction and operation
of a Regional Wastewater Treatment Facility to provide primary
and secondary treatment of the wastewater from the Cities of
East St. Louis, Centreville, and the Villages of Sauget,
Cahokia, Brooklyn, Allorton and National City.
Part of Sauget’s responsibilities under the Step I
Facilities Plan were to conduct a first flush analysis of the
East St. Louis combined sewer system. According to Agency
determinations any rainfall—related flows in a combined sewer
system with levels of contaminants in excess of those concen-
trations expected on an average daily basis are deemed to be
first flush flow. These flows normally have high concentrations
of pollutants, (BOD5, suspended solids, metals, etc.) Which
have accumulated in the system at times of dry weather. When
resuspended from increased flow to the sewer system, the
first flush is required under 602(c)(1) to receive the same
degree of treatment as dry weather flow. Compliance with
Rule 602(c) (2) requires a minimum of primary treatment for
4 1—255
—2—
not less than ten times the average dry weather flow. Theso
f lows are alleged to consist of approximately 20.9 million
gallons, and 87 million gallons, respectively (see “East St.
Louis’ First Flush Analysis for the American Bottoms Regional
Treatment Wastewater Facility” conducted by Russell and Axon,
Inc., and submitted with the petition).
The Russell study concluded that the most cost—effective
means of treating first flush flows would be to construct a 21
million gallon equalization basin to store the first flush
and to provide subsequent transportation to the treatment
facility. Total capital cost is estimated at $9.2 million
and annual operating costs at $249,000.
The study further determined that primary treatment and
disinfection of “10 times” average dry weather flow would
require a facility with the capability of treating 87 million
gallons. The most cost—effective approach was found to be
the construction of a settling basin with a 21.8 million gallon
capacity to provide one hour detention time for peak flow rates.
Total capital cost is estimated at $6.6 million and annual
operating costs at $312,000.
It is alleged that these costs are unreasonable in light
of the minimal environmental damage that will result from a
granting of this variance. Due to the large assimilative
capacity of the Mississippi River, even at low river flow the
concentration of BODç is estimated to increase to 10.0 mg/i
from 9.9 mg/i while total suspended solids (TSS) should actually
decrease from 359.0 mg/i to 358.7 mg/l. Petitioners, therefore,
allege that for all practical purposes no detectable environr!vmtzti
impact would result.
The Agency recommends a variance grant to eliminate
unnecessary delays in the design or construction of the American
Bottoms Regional Wastewater Treatment Faciiities (ABRWTF),
while Petitioners expeditiously pursue a permanent regulatory
change. It asserts that such a delay would impose an arbitrary
or unreasonable hardship upon the petitioners and the communities
expecting to discharge to ABRWTF. If the variance is not
granted, the Agency contends that present plans could not receive
Agency approval until the regulatory proceeding has been decided.
The Agency states that denial will cause “unnecessary
delays,” but the delay will have been unnecessary only if the
Board adopts the proposed site—specific regulation (R81—12).
If the proposal is denied, a granting of the variance would,
apparently, cause delay in that the approved plans would not
have included design and construction of the basins. Further,
without such inclusion, there is no showing of a compliance
plan other than the hope that the regulatory proceeding will
be decided in favor of Sauget. In other words, the granting
of variance requires a plan which will lead to compliance
with existing regulations within a five—year period. A compliance
plan cannot be based solely upon the assumption that the regula-
tions will change.
4 1—256
—3—
To decide a variance, as the Agency appears to recommend,
based solely on a pending regulation serves to encourage vari-mce
petitioners to file rulemaking proceedings before the Board
in order to bootstrap their way to a favorable variance decision.
Setting aside the consideration of the regulatory proceeding,
the petition is inadequate to warrant a variance grant in
three respects. First, the environmental impact computations
cited are deceiving. The water quality standards of the Board
deal with pollutant concentrations outside of the mixing zone.
The theoretically derived concentrations using the entire volume
of the Mississippi River as a mixing zone are not of primary
interest. A mixing zone of that size is impermissible under
Rule 201(b) of Chapter 3: Water Pollution. The “mixing zones
must be quite small if the water quality standards are to have
any meaning” (Rule 201(a)). The record is silent as to pollutant
concentrations immediately outside of a mixing zone of acceptable
size.
Second, the record is silent as to contaminants other than
BOD5 and TSS. Certainly these are not the only contaminants
involved. Heavy metals and organics, among others, should
also have been evaluated.
Third, wastewater from combined sewers will by definition
carry objects of sewage origin. These are repugnant to the
eye. In addition they carry bacterial and viral contamination.
No statement is made about these environmental impacts.
Finally, even the economic hardship figures are deceptive.
Much of the funding may well come from external sources. Further,
if the regulatory proposal is adopted, the construction costs
will be avoided. Only the unavoidable costs, most notably
design fees for which no costs are given, constitute certain
hardship. These figures should have been presented, as should
costs of a shorter detention—time facility.
For these reasons, the Board will dismiss this petition
as insufficient but will grant leave to refile.
This Opinion constitutes the Board’s findings of fact
and conclusions of law in this matter.
ORDER
Proceedings in PCB 80—176 are hereby dismissed without
prejudice.
IT IS SO ORDERED.
I. Goodman concurs.
4 1—2 57
—4—
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board, hereby certify that the above Opinion and Order
was adopted on the /~day of ~
,
1981 by
a vote of
5_p .
Christan
~
L. Moffett,
I
C~k
Illinois Pollution Control Board
41—258