ILLINOIS POLLUTION CONTROL BOARD
    April 16, 1981
    THE VILLAGE OF SAUGET
    AND THE CITY OF EAST ST. LOUIS,
    )
    )
    Petitioners,
    v.
    )
    PCB 80—176
    ILLINOIS ENVIRONMENTAL PROTECTION
    )
    AGENCY,
    )
    Respondent.
    OPINION AND ORDER OF THE BOARD (by J.D. Dumelle):
    On September 30, 1980, Petitioners filed a variance
    petition requesting relief from Rule 602(c)(1) and (2) of Chapter
    3: Water Pollution. On October 31, 1980, the Environmental
    Protection Agency (Agency) filed a recommendation that the
    variance be granted subject to certain conditions. Hearing
    was waived and none was held.
    Petitioners are Illinois municipal corporations situated
    in St. Clair County, Illinois, on the east bank of the Mississiopt
    River. All wastewater within the East St. Louis sewer systeri
    is currently transported to the East St. Louis wastewater
    treatment plant. During periods of increased flow due to
    rainfall, wastewater is discharged directly to the Mississippi
    River.
    In September, 1977, the Village of Sauget was designated
    as lead agency for the design, construction and operation
    of a Regional Wastewater Treatment Facility to provide primary
    and secondary treatment of the wastewater from the Cities of
    East St. Louis, Centreville, and the Villages of Sauget,
    Cahokia, Brooklyn, Allorton and National City.
    Part of Sauget’s responsibilities under the Step I
    Facilities Plan were to conduct a first flush analysis of the
    East St. Louis combined sewer system. According to Agency
    determinations any rainfall—related flows in a combined sewer
    system with levels of contaminants in excess of those concen-
    trations expected on an average daily basis are deemed to be
    first flush flow. These flows normally have high concentrations
    of pollutants, (BOD5, suspended solids, metals, etc.) Which
    have accumulated in the system at times of dry weather. When
    resuspended from increased flow to the sewer system, the
    first flush is required under 602(c)(1) to receive the same
    degree of treatment as dry weather flow. Compliance with
    Rule 602(c) (2) requires a minimum of primary treatment for
    4 1—255

    —2—
    not less than ten times the average dry weather flow. Theso
    f lows are alleged to consist of approximately 20.9 million
    gallons, and 87 million gallons, respectively (see “East St.
    Louis’ First Flush Analysis for the American Bottoms Regional
    Treatment Wastewater Facility” conducted by Russell and Axon,
    Inc., and submitted with the petition).
    The Russell study concluded that the most cost—effective
    means of treating first flush flows would be to construct a 21
    million gallon equalization basin to store the first flush
    and to provide subsequent transportation to the treatment
    facility. Total capital cost is estimated at $9.2 million
    and annual operating costs at $249,000.
    The study further determined that primary treatment and
    disinfection of “10 times” average dry weather flow would
    require a facility with the capability of treating 87 million
    gallons. The most cost—effective approach was found to be
    the construction of a settling basin with a 21.8 million gallon
    capacity to provide one hour detention time for peak flow rates.
    Total capital cost is estimated at $6.6 million and annual
    operating costs at $312,000.
    It is alleged that these costs are unreasonable in light
    of the minimal environmental damage that will result from a
    granting of this variance. Due to the large assimilative
    capacity of the Mississippi River, even at low river flow the
    concentration of BODç is estimated to increase to 10.0 mg/i
    from 9.9 mg/i while total suspended solids (TSS) should actually
    decrease from 359.0 mg/i to 358.7 mg/l. Petitioners, therefore,
    allege that for all practical purposes no detectable environr!vmtzti
    impact would result.
    The Agency recommends a variance grant to eliminate
    unnecessary delays in the design or construction of the American
    Bottoms Regional Wastewater Treatment Faciiities (ABRWTF),
    while Petitioners expeditiously pursue a permanent regulatory
    change. It asserts that such a delay would impose an arbitrary
    or unreasonable hardship upon the petitioners and the communities
    expecting to discharge to ABRWTF. If the variance is not
    granted, the Agency contends that present plans could not receive
    Agency approval until the regulatory proceeding has been decided.
    The Agency states that denial will cause “unnecessary
    delays,” but the delay will have been unnecessary only if the
    Board adopts the proposed site—specific regulation (R81—12).
    If the proposal is denied, a granting of the variance would,
    apparently, cause delay in that the approved plans would not
    have included design and construction of the basins. Further,
    without such inclusion, there is no showing of a compliance
    plan other than the hope that the regulatory proceeding will
    be decided in favor of Sauget. In other words, the granting
    of variance requires a plan which will lead to compliance
    with existing regulations within a five—year period. A compliance
    plan cannot be based solely upon the assumption that the regula-
    tions will change.
    4 1—256

    —3—
    To decide a variance, as the Agency appears to recommend,
    based solely on a pending regulation serves to encourage vari-mce
    petitioners to file rulemaking proceedings before the Board
    in order to bootstrap their way to a favorable variance decision.
    Setting aside the consideration of the regulatory proceeding,
    the petition is inadequate to warrant a variance grant in
    three respects. First, the environmental impact computations
    cited are deceiving. The water quality standards of the Board
    deal with pollutant concentrations outside of the mixing zone.
    The theoretically derived concentrations using the entire volume
    of the Mississippi River as a mixing zone are not of primary
    interest. A mixing zone of that size is impermissible under
    Rule 201(b) of Chapter 3: Water Pollution. The “mixing zones
    must be quite small if the water quality standards are to have
    any meaning” (Rule 201(a)). The record is silent as to pollutant
    concentrations immediately outside of a mixing zone of acceptable
    size.
    Second, the record is silent as to contaminants other than
    BOD5 and TSS. Certainly these are not the only contaminants
    involved. Heavy metals and organics, among others, should
    also have been evaluated.
    Third, wastewater from combined sewers will by definition
    carry objects of sewage origin. These are repugnant to the
    eye. In addition they carry bacterial and viral contamination.
    No statement is made about these environmental impacts.
    Finally, even the economic hardship figures are deceptive.
    Much of the funding may well come from external sources. Further,
    if the regulatory proposal is adopted, the construction costs
    will be avoided. Only the unavoidable costs, most notably
    design fees for which no costs are given, constitute certain
    hardship. These figures should have been presented, as should
    costs of a shorter detention—time facility.
    For these reasons, the Board will dismiss this petition
    as insufficient but will grant leave to refile.
    This Opinion constitutes the Board’s findings of fact
    and conclusions of law in this matter.
    ORDER
    Proceedings in PCB 80—176 are hereby dismissed without
    prejudice.
    IT IS SO ORDERED.
    I. Goodman concurs.
    4 1—2 57

    —4—
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify that the above Opinion and Order
    was adopted on the /~day of ~
    ,
    1981 by
    a vote of
    5_p .
    Christan
    ~
    L. Moffett,
    I
    C~k
    Illinois Pollution Control Board
    41—258

    Back to top