1. Respondent.
      2. 1. This variance will expire on July 2, 1985.
      3. suspended solids (TSS) and ammonia nitrogen measured as N.
      4. Monthly Average Flow-weightedDaily Composite
      5. BOD5 20 mg/i 40 mg/i
      6. TSS 25 mg/i 50 mg/i
      7. Ammonia Nitrogen 15 mg/i 30 mg/i
      8. consistent with applicable NPDES permit and variance effluentlimitations.
      9. the conditions set forth in this Order.
      10. CERTIFICATION
      11. SIGNED __________________________
      12. DATE ___________________________
      13.  
      14. Illinois Pollution trol Board

ILLINOIS POLLUTION CONTROL
BOARD
March
5, 1981
CITIZENS UTILITIES
COMPANY
)
OF ILLINOIS,
)
Petitioner,
)
v.
)
PCB 78—313
)
ILLINOIS ENVIRON!~NTAL
PROTECTION AGENCY,
)
Respondent.
MR.
DANIEL
J.
KUCERA, CHAPMAN
&
CUTLER, APPEARED
ON
BEHALF OF
THE PETITIONER.
MR. THOMAS CHIOLA, ASSISTANT ATTORNEY GENERAL, APPEARED
ON BEHALF
OF
THE
RESPONDENT.
OPINION
AND
ORDER OF THE
BOARD
(by D.
Satchell):
This matter
con’~esbefore the Board upon
a petition for var!-
ar.:e filcd
December
29, 1978 by Citizens Utilities Company of
Illinois
(Citizens Utilities)
,
an Illinois corporation
and
a.
public utility within the meaning of Section
10 of the Illinois
Public Utilities Act.
The petition requests
a variance from the
effluent limitations for five day biochemical oxygen demand
(BOD)
suspended solids
(TSS)
and
ammonia nitrogen
as specified in NPDES
permit
1L0032727.
The Board will construe this
as
a petition for
a variance from Rules
402.1(b)
and 404(c)
of Chapter
3:
Water
Pollution.
The requested variance is
in connection with waste—
water treatment plants operated by Citizens Utilities in the
Village of Bolingbrook, Will County
(Bolingbrook).
On January
17,
1979 Bolingbrook filed an objection to the
variance petition.
On February 1,
1979 Bolingbrook was granted
leave to intervefle
arid
hearings were authorized.
On February 15,
1979 the Illinois Environmental Protection Agency
(Agency)
filed
a recommendation to deny the variance.
Nine days of hearings were
held,
corrur~encingon January 11, 1980.
On December
17,
1980 Citizens Utilities filed an amended
petition for variance.
On January 16,
1981 the Agency filed an
amended recoinmendation to grant a variance with conditions.
On
January 23, 1981 Citizens Utilities filed
a response regarding
certain conditions which were recommended.
A public hearing was held on January
23, 1981
in Chicago,
Cook County.
At that hearing the parties noted the absence of

—2—
Bolingbrook’s attorney.
The parties indicated that Bolingbrook
was in agreement with the grant of the variance as outlined in the
amended pleadings
CR.
12, 42).
On January 23,
1981 Citizens Utilities and the Agency filed
a stipulation.
This requested that the Board decide the case based
upon the amended variance petition, amended recommendation and re-
sponse.
The Board will grant this request in part.
Since the
amended petition does not contain
a sufficient description of the
facilities,
the Board will
make
reference to the original petition
for the basic information.
Citizens Utilities provides water and sanitary sewer service
to approximately 20,000 customers
in the metropolitan Chicago area.
Citizens Utilities operates two wastewater treatment plants
in
Bolingbrook.
Its West Suburban Wastewater Treatment Plant No.
1
(WSB No.
1)
is located at the intersection of Glengary Drive and
Briarcliff Road in the Village of Bolingbrook.
This WSB No.
1 is
the subject of this variance petition.
Citizens Utilities also operates its West Suburban Wastewater
Treatment Plant No.
2
(WSB No.
2)
north of Boughton Road in the
westerly portion of Bolingbrook.
In addition, Bolingbrook owns
a
collection system and wastewater treatment plant serving that por-
tion of Eolirigbrook which IS not within Citizens Utilities’
service
area.
Bolingbrook’s treatment plant is located off Route
53 and
Royce Road.
Citizens Utilities’ West Suburban Wastewater Treatment Plant
No.
1 is an activated sludge plant of the contact stabilization
type designed for
a dry weather flow of 1.28 MGD
(4.84 Mi/day)
The WSB No.
1 includes bar screens,
corriminutor, two primary rec-
tangular clarifiers with mechanisms for sludge removal
and skimming,
contact aeration with spiral roll aeration, reaeration, five rec-
tangular secondary clarifiers,
seven day polishing lagoon, chlorine
contact tank,
two aerobic sludge digesters, eight sludge drying
beds
and
a blower building
(Pet.
2).
In the three years preceding the variance petition Citizens
Utilities expended approximat~’ly$220,000 to make improvements
on the WSB No.
1
(Pet.
6).
Thece improvements included addition
of air capacity for biological treatment, installation of six new
ultrasonic flow meters and revision of main pump room piping to
provide improved pumping sequence.
In addition, Citizens Utili-
ties made improvements to its collection system to reduce storm
water inflow at a cost of over $250,000
(Pet.
7).
Citizens Util-
ities
also added
a second shift and rescheduled working hours to
cover peak flow periods, initiated an operator training program
and
employed consulting professional engineers to assist in design
and
operation
(Pet.
7).

—3—
Bolingbrook at the time of the filing of the variance petition
had received approval of a grant to conduct an infiltration and in-
flow analysis of the entire village including that portion served
by Citizens Utilities.
Citizens Utilities will cooperate with
Bolingbrook towards completion of this study.
WSB No.
1 discharges to Lily Cache Creek.
Citizens Utilities
describes this
as “a dry weather Creek”
(Pet.
3,
12).
The
dilu-
tion ratio is less than five to one.
The following Board regulations from Chapter
3
may be applic-
able to the WSB No.
1:
1.
Rule 203(f)
sets a standard of 1.5 mg/i for ammonia
nitrogen in the waters of the receiving stream.
2.
Rule
402 provides that no effluent shall
alone or in
combination with other sources cause
a violation of water quality
standards, including Rule 203(f).
3.
Rule 402.1(b) provides an exception to Rule 402 which
allows effluent discharges of ammonia nitrogen up to 4.0
mg/l
during the months
of November through March.
4.
Rule 402.1(c)
requires compliance with Rule 402.l(b)
by
March
31, 1979
“or
such other dates
as required by NPDES permit
or as ordered by the Board under Title VII or Title IX of the
Act.”
5.
Rule 402.1(d) provides a termination date for Rule 402.1
in July,
1982.
6.
Rule 404(b)
sets effluent standards of 20 mg/i for BOD
and 25 mg/i for TSS
(this will later be referred to as 20/25).
7.
Rule 404(c)
provides that no effluent whose dilution ratio
is less than five to one shall exceed 10 mg/i for BOD and 12 mg/i
for TSS
(10/12)
On November 5, 1975 the Agency issued Citizens Utilities
NPDES permit 1L0032727 for the WSB No.
1
(Pet.
5).
This permit
contained conditions, based on Rule 404(c), requiring a 10/12
effluent limitation.
In addition there was a condition that
effluent ammonia nitrogen not cause violation of Rule 203 water
quality standards in the receiving stream.
Effluent data from the WSB No.
1 for twelve months preceding
November 1978 is presented in the petition
(Pet.
7).
41—13

—4—
Monthly averages
(mg/i)
Minimum
average
Maximum
BOD
7
12.4
19
TSS
5
14.4
24
Effluent Ammonia
4.1
8.6
13.8
Stream Ammonia
1.5
4.9
10.1
The Board previously granted Citizens Utilities
a variance
for WSB No.
1 providing a 20/25
limitation and up to 15 mg/l for
ammonia nitrogen
(20/25/15)
(PCB 78-123,
31 PCB lii, July 20,
1978).
Citizens Utilities was to submit a schedule for final com-
pliance to the Agency no later than October
1,
1978.
However,
an
extension to November 18,
1978 was granted in
a subsequent vari-
ance (PCB 78—265,
31 PCB 711, October
19, 1978;
32 PCB 283, Decem-
ber 14,
1978).
Citizens Utilities ultimately filed its compliance
program with the Agency
(Pet.
Ex. B).
Citizens Utilities’ study determined that the cost effective
long term solution for wastewater treatment is regionalization
with one central plant.
The Northeastern Illinois Regional Planning
Commission in its 208 study recommended that WSB Plant No.
2
be
the regional plant.
Regional planning is underway.
However, im-
mediate closing of WSB No.
1 and routing of sewage to WSB No.
2
would interfere with regionalization.
Citizens Utilities seeks to
operate WSB No.
1 on an interim basis pending regionalization
(Pet.
10)
Citizens Utilities estimated that achieving compliance in the
short term with the 10/12 limitations would require capital costs
of $3,090,000 and an additional annual cost to each customer of
over $250,
a 326
increase over the current rates
(Pet.
10).
This
figure was disputed at the earlier hearings.
Citizens Utilities
also presented evidence that due to the
intermittent nature of Lily Cache Creek no significant or endanger-
ed species of aquatic life exist.
It had no secondary use and
could not be used for recreational purposes.
If the WSB No.
1 dis-
charge were removed the Creek would not sustain any fish life and
improvement in effluent quality would not enhance aquatic life
(Pet.
13).
These conclusions were also disputed at the earlier
hearings.
In the amended petition Citizens Utilities now requests ef-
fluent limitations of 20/25/15.
The variance is requested to and
including July
1,
1985.
Citizens Utilities intends to file on or
about Janaury
1,
1981 a petition for regulatory change for WSB No.
1 to provide a site specific regulation incorporating the 20/25/15
41—14

—5—
condition.
Citizens Utilities intends to prosecute its regulatory
proceeding on a timely
and
expeditious basis.
Citizens Utilities
will do such design, engineering, procurement, contracting and con-
struction as may be necessary to bring the plant into compliance
with whatever effluent limitations are effective and applicable on
July 2,
1985.
Citizens Utilities will commence work no later than
July 1,
1983.
Citizens Utilities has offered to provide assurance of com-
pletion of work before July 2,
1985.
However,
it asks that prose-
cution of its regulatory change be conditioned upon expeditious
participation by all other participants.
The compliance date
is
also subject to the Agency’s expeditious review of permit applica-
tions and delays arising from acts of God and causes not within
control of Citizens Utilities.
Citizens Utilities also agrees to continue efforts with the
manufacturer to keep its flow meters operating, to provide flow
data, to continue to file NPDES and other reports on
a timely
basis and to operate the WSB No.
1 in such manner as to minimize
transfer of influent to the pond consistent with continued compli-
ance with the variance effluent limitations.
The Agency has recommended a grant of the variance with the
20/25/15 limitation.
The Agency has recommended detailed condi-
tions which are similar to those offered by Citizens Utilities
with some differences.
The Agency has requested a performance
bond in an amount not to exceed the cost of construction.
The parties are in agreement that the variance should be con-
ditioned upon diligent pursuit of the regulatory change.
Citizens
Utilities wishes the 1983 date to be extended in the event the
regulatory proceeding is still pending or under appeal.
The 1985
date, however,
is to be subject only to postponement if there is
not expeditious review of permit applications or if there are de-
lays arising from causes not within the control of the petitioner.
The Agency wants both of these dates to be unconditional.
The Board declines to condition the variance on diligent pur-
suit of the regulatory change.
Such a condition could be difficult
to police.
If the variance is conditioned on a
firm
compliance
date then petitioner will have an incentive to avoid delay.
Citizens Utilities should be advised that two and one half
years is a tight schedule considering the many procedural obstacles
Board rulemaking must now confront.
Furthermore,
it
is unlikely
that the reclassification of stream segments
in R79-6 will reach
the area in question before 1983.
Petitioner will be obliged to commence construction by July
1,
1983.
Rule 902
of. Chapter 3 requires permit applications 180
41—15

—6—
days before the permit is needed.
This variance is not intended
as a variance from the requirement to obtain appropriate construc-
tion permits or authorizations.
Accordingly, Citizens Utilities
will be obliged to submit prior to January 2, 1983, permit applica-
tions for such construction as it intends to undertake.
The 1985 final compliance date will be conditioned on delays
arising from acts of God and causes not under control of Citizens
Utilities.
To condition this date upon expeditious review of per-
mit applications by the Agency would give Citizens Utilities the
opportunity to obtain delay merely by filing incomplete applica-
tions.
Citizens Utilities may file a petition for variance from
this Order to extend this date if other circumstances arise.
Although the grant of this variance contemplates a site speci-
ic regulation, the Board does not in any way intend to infer that
it has agreed to adopt any regulation which Citizens Utilities may
propose.
This will be treated as any other site specific regula-
tion.
In the event the Board rejects the regulatory proposal,
Citizens Utilities will be expected to comply with the generally
applicable standards by the 1985 date.
The Board notes that compliance with the regulations involved
in this proceeding was required many years
ago.
If Citizens Util-
ities had commenced upgrading before these deadlines had passed,
the Board would be more receptive to claims of hardship.
The hard-
ship now alleged is self-imposed to the extent that it is occasion-
ed by delays, including the dilatory prosecution of this case.
However, since the Citizens Utilities has agreed to
a compliance
plan with definite dates, the Board will grant the variance.
The
Board finds that it would impose an arbitrary and unreasonable
hardship to deny Citizens Utilities a variance under these circum-
stances.
The original petition requested a variance from the NPDES per-
mit conditions rather than the Board regulations.
Since the permit
conditions are not a “rule or regulation,
requirement or Order of
the Board,” Section
35 of the Act does not authorize variances
from
them.
Accordingly, the Board will grant the variance
from the
regulations which appear to require the permit conditions.
The
Agency will be ordered to modify the permit conditions pursuant to
Rule 914 and Section 39(b)
of the Act.
This Opinion constitutes the Board’s findings of fact and
conclusions of law in this matter.
4 1—16

*7—
ORDER
Petitioner Citizens Utilities Company of Illinois is
granted
a variance from Rules
404(c), 402.1(b) and 402
as it applies to
the ammonia nitrogen standard of Rule 203(f)
of Chapter
3,
sub--
ject to the following conditions:
1.
This variance will expire on July 2, 1985.
2.
This variance applies to effluent discharges from Peti-
tioner’s West Suburban Wastewater Treatment Plant No.
1
(WSB Plant
No.
1)
located at the intersection of Glengary Drive and Briar-
cliff Road in the Village of Bolingbrook.
3.
Petitioner shall meet the following interim effluent
limitations for five day biochemical oxygen demand
(BOD), total
suspended solids
(TSS)
and ammonia nitrogen measured as N.
Monthly Average
Flow-weighted
Daily Composite
BOD5
20 mg/i
40 mg/i
TSS
25 mg/i
50 mg/i
Ammonia Nitrogen
15 mg/i
30 mg/i
4.
On or before January 2, 1983 Petitioner shall submit to
the Illinois Environmental Protection Agency a permit application
including
plans
and specifications for upgrading WSB Plant No.
1
to meet Chapter
3 limitations.
5.
On or before July 1, 1983 Petitioner shall commence such
design, engineering, procurement of major equipment items, con-
tract letting
and
construction as may be necessary for WSB Plant
No.
1 to be in compliance with then applicable effluent limita-
tions before July 2,
1985.
6.
On or before July 2, 1985 Petitioner shall be in compli-
ance with applicable effluent limitations for five day biochemical
oxygen demand, total suspended solids and ammonia nitrogen.
Com-
pliance with this condition before July 2, 1985 shall be excused
by delays arising from acts of God
or causes not within control
of the Petitioner.
7.
Within ninety days of the date of this Order, Petitioner
shall execute and forward to the Illinois Environmental Protection
Agency a performance bond in a form acceptable to the Agency con-
ditioned upon compliance with paragraph
6 above.
41—17

—8—
8.
Petitioner shall operate WSB Plant No.
1 in such a manner
as to minimize the total quantities of BOD5 and TSS discharged,
consistent with applicable NPDES permit and variance effluent
limitations.
9.
Petitioner shall on a continuous basis monitor the flow
which is diverted from plant No.
1 to the polishing pond and the
flow diverted to WSB Plant No.
2.
Petitioner shall keep in oper-
ating condition flow meters necessary to perform this monitoring.
Records of these flows shall be maintained for the period of this
variance.
Flow results shall be submitted to the Agency on a
monthly basis at the
same
time
as and together with the discharge
monitoring reports required by its NPDES permit.
10.
The Agency, pursuant to Rule 914 of Chapter 3:
Water
pollution,
shall modify NPDES permit 1L0032727 consistent with
the conditions set forth in this Order.
11.
Within forty-five days of the date of this Order, Peti--
tioner shall execute and forward to the Illinois Environmental
Protection Agency, Variance Section, 2200 Churchill Road, Spring-
field, Illinois 62706,
a Certificate of Acceptance and Agreement
to be bound to all terms
and
conditions of this variance.
This
forty-five day period shall be held in abeyance for any period
this matter is being appealed.
The form of the Certificate shall
be as follows:
CERTIFICATION
I,
(We), _____________________________,
having read and
fully understanding
the
Order in PCB 78-313, hereby accept that
Order
and
agree to be bound by all of its terms and conditions.
SIGNED __________________________
TITLE
___________________________
DATE
___________________________
IT IS SO ORDERED.
Mr. Jacob D. Dumelle concurs.
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board hereby çe~tifythat the above Opinion and Order
were ~dopted on the
~
~
day of
#S74,t,tL,
,
1981 by a vote
of
~-O
Christan L.
4offet
,
lerk
Illinois Pollution
trol Board
4 1—18

Back to top