ILLINOIS POLLUTION CONTROL BOARD
    September
    3,
    1981
    H.J. BERGMAN BUILDERS, INC.,
    and THE CITY OF PONTIAC,
    )
    Petitioners,
    v.
    )
    PCB
    81—67
    tLLINOIS ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent.
    CHARLES W. KOHR, MATHIS, SLOAN, LITTLER & KOUR, APPEARED
    ON
    BE!Th~
    O~’PETITIONER BERGMAN,
    BRUCE
    L.
    CARLSON APPEARED
    ON
    BEHALF OF RESPONDENT.
    OPINION AND ORDER OF THE BOARD
    (by J.
    Anderson):
    This matter comes before the Board on the petition for
    variance filed April 29,
    1981 by H.J. Bergman Builders,
    Inc.
    (Bergman).
    On May
    1,
    1981 the Board ordered joinder of the
    City of Pontiac
    (City);
    on May
    14,
    1981 Bergman filed an amended
    petition verifying service of process on the City pursuant to
    Procedural Rule 305(a).
    On June 15,
    1981 the Illinois Environ-
    mental Protection Agency
    (Agency)
    recommended that variance be
    denied.
    The hearing requested by Bergman was held July
    23,
    1981.
    Bergman petitions for variance from Sections 12(h) and 39(a)
    of the Environmental Protection Act and Rule 962(a)
    of Chapter
    3: Water Pollution in order to obtain 7ermits to construct and
    operate a sewer extension to serve a proposed Farmers Home
    Administration (FmHA) funded 16 unit multi-family rural rental
    housing project
    to be constructed in Pontiac,
    Illinois.
    The
    City was joined as a necessary party, as the owner of the sewage
    treatment plant to which the sewer
    is tributary.
    The expected
    additional P.E.
    loading to the City’s North Street sewer and its
    plant is
    36 P.E,
    from the proposed
    2 buildings,
    each containing
    4 one bedroom and
    4 two bedroom apartments.
    Although petitioners did not provide the Board with hearing
    transcripts until September 1,
    1981,
    this action is being given
    expedited consideration in view of the fact that the Board’s
    decision will determine whether Bergman receives $510,000 in FmHA
    funding, obligation of which must be finally approved before
    the close this month of the current federal fiscal year.
    As
    the balance of equities in a variance petition of this sort
    43—299

    2
    is dependent on the timing of events,
    initially a “bare-hones”
    chronological approach will be taken toward
    the presentation of
    facts.
    CHRONOLOGY OF EVENTS
    Bergman is a specialist in FmHA construction and has
    participated in some 60 to 70 such projects
    (R. 17—20).
    Beginning
    in January,
    1979,
    it initiated FmHA—required housing market
    studies in Pontiac.
    Receiving FmHA approval of need, Bergman
    proceeded to select a site and in September,
    1979 petitioned the
    City Council for a special use permit for that site
    (Pet.
    7).
    Although the original site is not the subject of this petition,
    as Bergman’s option lapsed before the site could be purchased,
    the subject is germane.
    On February 23,
    1979 the Pontiac sewage treatment jñant
    ~za’;
    notified it might be placed on the Agency’s critical review list
    because it had reached 95
    of its hydraulic
    load capacity of
    21,300 P.R.
    It was
    in
    fact placed on critical review April
    6,
    1979
    (Resp.
    Ex.
    3).
    Rule 604(a)
    of Chapter
    3 requires that a
    treatment plant owner notify individuals requesting connections
    that the plant has been placed on critical review or restricted
    status.
    This
    individual notice is required by Rule 604(a)
    to
    be published by the Agency.J
    Bergman was not informed by the
    City of critical review status at that time, or
    in September,
    1979.
    In March,
    1980 the current site was proposed to
    FnHA
    for
    its approval,
    the property optioned and monies deposited
    (Pet.
    7).
    The Agency’s March
    31,
    1980 quarterly Critical Review List,
    of
    which Bergman was unaware,
    listed Pontiac as having zero remaining
    hydraulic capacity
    (Rec.
    5,
    Resp.
    Ex.
    7).
    In May, 1980 final
    site and building plans and an application for financing were
    submitted to FmHA (Pet.
    7).
    It should be noted that
    in May,
    1980 the Board rendered a
    decision on a Bergman petition for variance concerning another
    FmHA financed project, HJ. Bergman Builders
    Inc.
    V.
    IEP1~,
    PCB 79—264
    (May
    1,
    1980J.
    in
    that action, the Board granted
    variance to allow connection of a 32—unit project to the sewage
    treatment plant of the City on Monmouth, which was on critical
    review status at the time Bergrnan’s permit application was denied,
    and which soon after was placed
    on
    restricted status.
    Bergman
    first
    learned
    of
    problems
    concerning
    the
    Pontiac
    plant
    at
    a
    City
    Council
    meeting
    in
    December,
    1980
    (R.
    72),
    at
    which an enforcement action against Pontiac apparently was
    discussed, IEP~v.
    City
    of Pontiac, PCB 78—124
    (December
    18,
    1980).
    In that case, the City stipulated to several violations,
    including failure to meet the BOD5 and TSS limitations of the
    Board’s Rules.
    A detailed compliance plan was stipulated to ~nd
    43—300

    3
    accepted by the Board.
    At hearing, Bergman’s treasurer Eugene P.
    Couglon,
    testified that
    “I don’t recall...that
    prior
    to that
    December council meeting, did it ever come up that we needed a
    permit”
    (R.
    73).
    Bergman states in its petition and testimony that it had been
    acting in reliance on a sewer permit previously issued to the
    developer of the “Illini Subdivision” in which Bergman’s proposed
    and optioned site is located.
    This developer,
    Pontiac Held Corp.,
    was issued a two—year permit allowing sewer connections
    for 39
    P.R. on May 10,
    1979.
    (This permit lapsed in May,
    1981 without
    being used.)
    Plans and specifications submitted in connection with
    this lot show that the sewer extension was
    to serve lots 135,
    136,
    137, and 138, although the permit does not so state on its face.
    As Bergman’s project has an estimated loading of only 36 P.E.,
    if the permit were transferable,
    no problem would have occurred.
    Bergman’s optioned site does not, however, contain these four
    lots,
    and the permit is not transferable.
    In addition, Bergman’s
    optioned site would discharge into a sewer
    line different than
    the line into which Lots 135—138 would discharge
    (Resp.
    Ex.
    2,
    R.
    200—215).
    In either February or March,
    1981 FmHA “obligated”
    approximately $510,000 in loan funds
    for the Bergman project.
    On February
    5,
    1981 the Agency received Bergman’s application
    for sewer permits.
    On March
    6,
    1981,
    the Agency issued a “Notice
    of Impending Restricted Status” to the City, citing 1) that the
    plant was not meeting the BOD5 and TSS loadings established
    in
    PCB 78—214,
    2) the plant was receiving BOD5 loadings of 17,280
    P.R.,
    and organic load in excess of its design capacity of 16,000
    P.R., and 3) the critical review status because of hydraulic
    capacity imposed April
    6,
    1979
    (Resp.
    Ex.
    3).
    On March 23,
    1981
    Bergman’s permit was denied by the Agency.
    The reasons for denial
    listed in the letter essentially restate the reasons listed above
    (Pet.
    Ex.
    D).
    BERGMAN’S HARDSHIP
    Economic Effect
    In support of its allegation that denial of variance would
    impose an arbitrary or unreasonable hardship, Bergman makes several
    arguments.
    It is uncontroverted that if Bergman is not allowed to
    connect to the City’s sewer system,
    it will be ineligible
    for the
    $510,000 FmHA loan,
    since FmHA policy requires connection to any
    existing community sewer system.
    While this alone would be
    insufficient to support a grant of variance (Bergman,
    supra, at 2),
    it is also Bergman’s unchallenged testimony that this FmHA project
    is “all we have projected for the year of 1981,
    from here on in”
    (R.
    26).
    Bergman’s “field people” have been laid off since
    approximately June,
    1981, waiting to begin work on the Pontiac
    project.
    While Bergman has submitted other project applications
    43—30 1

    4
    to FmHA,
    President Herbert J. Bergman stated that it is FmHA belief
    that “none of them will be funded at all before some time in 1982”
    ——
    dependent of course on the level of funding FmHA itself receives
    in the new federal fiscal year.
    The effect of variance denial
    on
    the company was described simply as “devastating”.
    In addition to loss of future
    funds, Bergman states that it
    has to date spent upwards of $28,500 pursuing the Pontiac project
    ($4500 site selection,
    $8900 market studies administrative,
    $10,000
    architectural/site plans 4,000,
    legal fees $1,000, building permit,
    and other unquantified)
    (Pet.
    8,
    R.
    24,
    25).
    While Bergman does
    not explicitly state when most of these expenditures were made, he
    believes that all were made
    in reasonable reliance on information
    available to him.
    Reasonable Reliance
    Bergman believes that his reliance on the Pontiac Held permit
    was reasonable, based on the developer’s own assertions that
    adequate P.E.
    had been “reserved”
    for the subdivision and therefore
    the project.
    When made aware of the critical review status of the
    City’s plant, he relied on the City’s opinion that the plant had
    or soon would have capacity
    to accept his effluent,
    as would the
    sewers
    *
    Bergman called David L. Sullivan, superintendent of the
    City’s treatment plant,
    as a witness
    in support of its position.
    Mr. Sullivan explained that it was his opinion that in April,
    1979 when critical review began, that the plant was
    in fact
    hydraulically and organically “ri9ht at the design limitations”
    (R.
    98).
    The hydraulic and organic overloads were attributed
    in part to the largely anticipated continuing large volume and
    nature of the effluent received by the City from Interlake Steel,
    as well
    as the largely unanticipated increase in the volume and
    concentration of the effluent received from the Pontiac Correctional
    Center.
    Since 1979,
    however, the City has been negotiating with
    both entities to achieve hydraulic and organic reductions
    in their
    effluent.
    Discharge Monitoring Reports submitted by the City to
    the Agency for the months February,
    1980 to February,
    1981 bear
    out Mr.
    Sullivan’s opinion that these and other efforts to improve
    plant loading and performance were in part successful; during this
    period,
    the actual hydraulic
    loading was 1.43 million gallons per
    day (mgd),
    or 65
    of the 2.3 mgd design capacity.
    However, the
    BOD5 loading was 16,694
    P.E. or 104
    of the 16,000 P.E. design
    capacity, while the SS loading was 15,260
    P.E. or 95
    of the
    16,000 P.E. design
    (Resp.
    Ex.
    6).
    The City
    is actively pursuing
    upgrading of the facility through the Construction Grants Program.
    In July,
    1981, the Agency issued a permit for “interim” improve-
    ments to increase the plant’s organic capacity
    to 23,000 P.E.
    This project would be completed approximately one year from its
    initiation.
    The date is uncertain, however,
    as it is contingent
    on receipt of state funding
    (the status of which was not
    explained).
    (R.
    99,
    103)
    43—302

    5
    Mr. Sullivan also testified that there were in fact problems
    with the City’s sewer and drainage systems.
    The North Street
    combined sewer,
    to which Bergman’s effluent would be tributary,
    has overflow problems which would not be addressed by the interim
    plan
    (R.
    102—103).
    The North Street sewer
    “is a tremendously
    large interceptor
    sewer that has been prone to flooding” in part
    from rise in levels of the Vermillion River.
    It
    is believed that
    this sewer, which
    is a
    2’
    X
    3’
    elliptical brick sewer built circa
    1890,
    overflows because of one or more major blockages.
    The
    existence of blockages is surmised from observation that past a
    certain section containing
    4 railroad crossings the sewer flows
    only half full,
    when after 1½ inches of rain sewers tributary to
    it are surcharging
    (R.
    115—116).
    In addition to routine cleaning,
    the City anticipates investigating the sewer
    for blockages with
    the possibility of making extensive repairs.
    There is no projected
    time schedule or stated funding source for North Street sewer work
    (R.
    95—97).
    Bergman does not address the sewer problem in detail, arguing
    only
    that
    the
    proposed
    36
    P.E.
    addition
    to
    the
    sewer
    will
    have
    minimal additional effect.
    Bergman strongly argues that his
    reliance on probable sewer capacity was rendered even more
    reasonable by permitting decisions made by the Agency during the
    critical review period.
    Since April,
    1979 the Agency has issued permits allowing 1705
    P.E.
    to be added to the Pontiac plant——including the permit issued
    to Pontiac Held.
    A permit to add 1,000 of these P.E. was issued
    to one facility, Caterpillar Tractor Co., on July
    22,
    1980,
    afte.r
    the Agency had listed capacity in March, 1980 at zero.
    While
    Bergman himself was unaware of and never requested the Agency’s
    critical review
    lists,
    lists during this period did not reflect
    permits issued as they should have been consistent with Agency
    practice.
    Which,
    if any,
    of these permits may have lapsed without
    use as did Pontiac Held’s,
    and which have been used and sewers
    connected,
    is not contained
    in the Agency’s files
    (R.
    154—155).
    Based on these facts, Bergman essentially argues that it is
    inequitable to deny it a permit to add
    .2
    to the plant’s total
    load during the same critical review period
    in
    which one permit
    alone added 6
    to the total.
    Housing Need
    Finally, Bergman argues that variance denial would impose a
    hardship on the City, which has FmHA determined need for housing
    in the size and income range to be provided by Bergman’s project.
    Seth Marvin,
    manager of an FmHA project near Bergman’s site,
    verified that his experience was that the demand particularly for
    one bedroom units
    far exceeded the supply
    (R.
    6-16).
    The City
    itself did not address this hardship argument made in its behalf.
    43—303

    6
    THE AGENCY’S ENVIRONMENTAL
    ASSESSMENT
    Plant Effluent and Receiving Stream Quali~
    Stephen E. Baldwin, an Agency Environmental Protection
    Specialist,
    testified as
    to
    his observations concerning the
    plant’s discharge and the Vermilion River during an inspection
    on January
    27,
    1981.
    Upstream of
    a discharge point,
    no
    sign of
    degradation was observed.
    The effluent discharged from the
    plant contained
    “a substantial quantity of tiny suspended solid
    particles, and ...moderate turbidity”.
    Downstream of the dis-
    charge,
    unnatural “black colored septic smelling bottom deposits”
    were observed.
    These
    same conditions, as well as a gray colored
    slime growth or sewage mold and minor localized foaming, were
    observed a year before on February 13—14,
    1980
    (R.
    128—129).
    In
    addition to discharging treated effluent, the City also
    can discharge untreated combined sewer overflow into the river
    at two discharge points north of the plant
    (R.
    126—127).
    It can
    be inferred that during the wet months when plant hydraulic
    overload has been measured to have occurred
    (Resp.
    Ex.
    5), that
    such untreated overflow is directly discharged into the river.
    It is the Agency’s position that aggravation of the river pol-
    lution problem by the permitting of Bergman’s project should not
    be allowed.
    Sewer
    problems
    Much of the Agency’s case at hearing related to the condition
    of the City’s sewers and problems related thereto.
    In the City
    of Pontiac Facilities Planning Report, Wastewater Treatment Plant
    Ex2ansion—Phase
    II,
    the City’s consulting engineers reported that
    “During dry weather there are no known problems in
    the City attributable
    to infiltration.
    Some sewer
    backups do occur in dry weather but is usually due
    to
    collapsed or root-bound service
    lines.
    During
    storms,
    basements flood
    in
    ten to fifty percent of the City
    depending upon the Vermilion River water level.
    The
    major bottleneck to drainage of the north areas during
    web weather
    is the
    North
    Street
    2’
    X
    3’ elliptical
    trunk which flows at full capacity even during small
    storms,
    backing
    up sewers in tributary areas,
    In the
    northeast subdivision
    (shown on Figure 3—1 as area A)
    Resp.
    Ex.
    1A
    there is evidence that footing drain
    discharge is causing backup of sanitary sewers during
    wet weather.
    More work needs
    to be done
    to determine
    extent of the connections and identify means of
    relief
    (Res.
    Ex.
    1,
    p.
    3—5,
    6).
    Bergman’s project
    is tributary to the North Street sewer, and is within
    the area within which backups occur.
    43—304

    7
    Agency files contain 1980 reports of complaints concerning
    flooding, draining,
    and basement backups incidents
    (R.
    146—147).
    The effects of such incidents were graphically described in the
    testimony of Mrs.
    Betty Jane Pouliot,
    a long term resident of
    Pontiac and alderman of Pontiac’s 1st Ward for the past six years.
    In addition to personally observing sewer problems, Mrs.
    Pouliot
    is the recipient of complaints from her constituents.
    Mrs. Pouliot
    has personally observed two manholes
    on
    or near North Street whose
    covers blow off “everytime there is an inch of rain”.
    Of a cover
    located at North and Walnut,
    Mrs.
    Pouliot states
    “Now,
    I
    haven’t
    seen it as high as
    they tell me it goes,
    I’ve only seen it about
    three feet into the air.”
    When the covers
    lift,
    “raw sewerage
    (sic)
    spills out into the street onto the berm”, and even flowed into a
    neighboring park.
    Heavier covers have not been installed because
    “this will force the sewerage back into the homes.
    And there have
    been cases of even floors buckling because of the sewerage under-
    neath the homes.”
    Mrs. Pouliot stated that the relatively recent
    installation of storm sewers and initiation of sewer maintenance
    programs have not solved these problems, which have occurred as
    recently as July,
    1981.
    The Agency believes that addition of any loading to the sewer
    could increase the frequency or duration of surcharge events,
    even
    if minimally.
    The presence of sewage and sewage related debris
    is
    said to pose a serious threat to public health and safety,
    as well
    as being a nuisance.
    The Agency therefore urges the Board to deny
    the requested variance.
    BALANCE OF EQUITIES
    As
    in many of the Board’s recent Rule 962(a) variance cases,
    the facts as presented show that many parties have mishandled
    environmentally unsound situations
    for years at a stretch.
    While
    the City would seem to be making progress in handling the problems
    of its plant,
    it is remiss in failing to notify Bergman of its
    critical review
    status
    in April,
    1979.
    While placement of a
    treatment plant on critical review status does not in itself
    preclude Agency issuance of additional connection permits,
    the
    Board seriously questions the soundness of some of the Agency’s
    permitting decisions, particularly those that allowed additional
    P.R.
    to be added to the load
    on
    Pontiac’s plant after
    the Agency
    listed remaining plant capacity at zero.
    Failure to include the
    fact of issuance of such permits on the critical review list is
    also questionable, as it frustrates the purpose of such lists,
    which is
    to keep interested parties as
    “up
    to the minute”
    as
    possible concerning a problem plant.
    However,
    these omissions do not serve
    to exculpate Bergman’s
    failure to investigate the status of the City’s plant and sewer
    system.
    While the Board might consider such failure reasonable
    prior
    to
    1980,
    it is the Board~sopinion that a reasonable person
    who had encountered problems concerning
    sewer permits on one
    4 3—305

    8
    project,
    would
    take
    all
    steps
    necessary
    to
    ensure
    that
    no
    such
    unwelcome surprises
    would occur during
    the
    course of
    a later
    project.
    The PCB
    79—264 petition to allow
    connection
    of
    the
    t4onmouth project was
    filed December 13,
    1979 and decided May
    1,
    1980.
    It was in
    March,
    :L980
    that.
    Bergman applied for
    FmHA
    funding for this
    project without having checked
    with the Agency
    concerning permit
    needs and possible problems.
    It was a full year
    later
    before
    Bergman
    contacted the Agency~
    Bergman
    states
    in
    his
    petition that
    it
    is now too late in the design and
    funding process
    to
    redesign
    his
    project
    to fall
    into Rule 95l(b)(2)
    of Chapter
    3,
    which provides that permits are
    not required for single buildings
    discharging
    1500 gpd or less
    (Pet.
    6).
    Had earlier attention been
    paid to the permit question, design changes may have been possible.
    While early reliance on
    the Pontiac Held permit was
    certainly
    understandable,
    failure to confirm transferability with the Agency
    ceased to be reasonable
    after May
    1,
    1980
    if not before.
    While
    loss of FmHA
    funding will have considerable adverse effect
    on
    Bergman,
    the Board
    reminds Bergman that
    it was
    warned that “denial
    of federal
    funding or lack of other access to
    funding does not
    constitute an
    arbitrary or unreasonable hardship,
    especially where
    a project is a proposed
    one,”
    ~
    supra,
    at
    2,
    The Board
    finds that Bergman’s
    economic hardship
    is
    largely of its
    own
    making,
    and can be
    afforded little weight.
    The weight given to
    the allegations of
    potential hardship to
    the City’s middle—income
    residents and would be
    residents is over-
    balanced by the actual
    hardship which has been
    and will continue
    to be imposed
    on residents experiencing the health
    threats and
    nuisance of sewage
    backup.
    Denial of variance to
    Bergman
    certainly will
    not stop North Street sewer
    back—ups, or clean
    up
    ‘the Vermilion River,
    it is also the case that
    Bergman’s proposed
    additional
    loading
    is not
    in and of itself great, but the
    hydraulic and organic
    loadings will aggravate
    existing problems
    even if minimally,
    an occurrence which the Board
    does not favor
    Cit~ofAssum2~~v.IEPA,
    PCI3
    80—223
    (February
    19,
    1981)
    at
    2.
    As to the increase to the plant itself,
    the Board
    continues
    to conclude
    that while
    ‘the additional
    flow expected from
    the
    project
    may
    appear small
    in relation to the total
    flow
    handled
    by the ....plant,
    “lines must be drawn somewhere
    even
    though
    such successive
    increase
    in
    t:he
    load in a
    sewer may have
    minimal
    effect (Sp4~~ieid_MarineBank
    v.
    Pollution Control
    Board
    (1975),
    27 Ill.App.ed 582,
    327 N,E.2d 486,
    491).”
    Wiliowbrook_Devel22ment
    Corporation v.
    Illinois ProtectionAenc
    (198:L),
    92 Ill.App.3d
    1074,
    416
    N.E,2d 385,
    392.
    Variance
    from Rule 962(a)
    is therefore denied for failure
    to
    prove
    existence
    of an arbitrary or unreasonable hardship
    and,
    certainly,
    as balanced against the water pollution
    situation in
    Pontiac.
    43—306

    9
    ORDER
    Variance
    from Rule 962(a) of Chapter
    3:
    Water Pollution to
    allow issuance
    of a permit to construct and operate sewers
    to
    service
    8 proposed apartment units to be constructed in Pontiac,
    Illinois is
    hereby denied.
    IT
    IS SO
    ORDERED,
    J.
    Dumelle
    concurred.
    I,
    Christan
    L.
    Moffett, Clerk of the Illinois
    Pollution
    Control Board,
    hereby certify that the above Opinion
    and
    Order
    was
    adopted on
    the
    ~i’
    day of
    ~
    1981
    by
    a
    vote
    of
    ‘.
    ~
    /‘
    £~‘~i~_~-
    ~,:-~-~---~-
    Christan
    L, Moffett,,C’lerk
    Illinois Pollution
    Control
    Board
    43-~307

    Back to top