1. none were reasonably available at that time, and
      2. _Averaging Time
      3. Pollutant Annual 24-Hour 8—Hour 3—Hour 1—Hour
      4. SO2 1.0 ug/m3 5 ug/m3 25 ug/m3
      5. TSP 1.0 ug/m3 5 ug/m~NO 1.0 ug/m3
      6. Co 0.5 mg/rn 2 mg/rn

ILLINOIS POLLUTION CONTROL BOARD
June 16,
1983
IN THE MATTER OF:
MAJOR STATIONARY SOURCES
)
R81-l6
CONSTRUCTION AND MODIFICATION
)
Docket
B
PART 203 OF CHAPTER
2:
AIR POLLUTION
PROPOSED ORDER.
SECOND NOTICE
ORDER OF THE BOARD
(by J.
D.
Dumeile):
It is the Order of the Pollution Control Board that Chapter
2:
Air Pollution Regulations be amended by the addition of
Part 203:
Major Stationary Source Construction and Modification,
as follows:
TITLE
35:
ENVIRONMENTAL PROTECTION
SUBTITLE B:
AIR POLLUTION
CHAPTER
I:
POLLUTION CONTROL BOARD
SUBCHAPTER
a:
PERMITS AND GENERAL PROVISIONS
PART
203
MAJOR STATIONARY SOURCES CONSTRUCTION AND MODIFICATION
SUBPART
A:
GENERAL PROVISIONS
Section 203.101
Definitions
Unless
.a
different meaning of the term
is clear from its
context1
the definitions of terms used
for this Part shall
be the same as
those used
in
the Pollution Control Board Rules and Regulations,
Chapter
2:
Air Pollution.
Section 203.102
Actual Emissions
The
actual rate of annual emissions
of a pollutant from an
operational emission source for a particular date equal to
the mean rate at
which the emission source actually emitted
the pollutant during the two-year period which immediately
precedes the
particular date and which is determined by the
Illinois Environmental Protection Agency (Agency)
to be
representative of
normal emission source operation;
however:
52-387

2
a)
The Agency shall allow the use of a different time
period upon a determination that it is more repre-
sentative of normal emission source operation.
The
burden shall be on the applicant to demonstrate that
another time period
is more representative.
Actual
emissions shall be calculated using the emission
source’s actual operating hours, production rates,
and types of materials processed, stored,
or
corn—
busted during the selected time period.
b)
If the Agency determines that there
is inadequate
information to determine actual emissions as indi-
cated in the preceding paragraphs,
the Agency shall
use the potential to emit of the emission source.
Section 203.103
Allowable Emissions
a)
The emission rate of an emission source is calculated
using the maximum rated capacity of the emission
source
(unless the emission source is subject to permit
conditions or other enforceable limits which restrict
the operating rate,
or hours
of operation, or both)
and the more stringent of the following:
1)
the applicable emission standard or limitation
contained
in this Chapter,
including those with
a future compliance date;
or
2)
the emissions rate specified as a permit condition
including those with
a future compliance date.
b)
The allowable emissions may be expressed as a permit
condition limiting annual
emissions or material or
fuel throughput.
c)
Allowable emissions shall include
a reasonable esti-
mate of emissions in excess of applicable standards
during start-up, malfunction, or breakdown,
as appro-
priate, only if the provisions of Rule 105 of this
Chapter have been complied with.
d)
If an emission source is not subject to an emission
standard under provision
(a)
and is not conditioned
pursuant to provision
(h),
the allowable emissions
shall
be the source’s potential to emit.
Section 203.104 Available Growth Margin
The difference between total
allowable emissions consistent
with reasonable further progress and projected actual
emissions
in a nonattainment area.

3
Section 203.105 Commence
As applied to construction of
a major stationary source
or major modification means that the owner or operator has:
a)
Begun, Q~caused to begin,
a continuous program of
actual on-site construction of the source, to be com-
pleted within a reasonable time; or
b)
Entered into binding agreements or contractual obliga-
tions, which cannot be cancelled or modified without
substantial
loss to the owner or operator,
to undertake
a program of actual construction of the source to be
completed within a reasonable time.
Section 203.106 Construction
Any physical change or change
in the method of operation,
including but not limited to fabrication, erection, installation,
demolition,
or modification of an emissions source,
which would
result in a change in actual emissions.
Section 203.107 Emission Baseline
The starting point or reference level
from which increases and
decreases
in emissions are measured.
The rules governing
determination of emission offsets, calculations of
net emission
increases,
and evaluation of alternative control strategies
specify the particular emission baseline that applies for that
purpose.
Section 203.108 Emission Offset
A creditable emission reduction
used
to compensate
for the increase
in emissions resulting from
a new najor source or a major
modification.
Section 203.109 LAER
Abbreviation for lowest achievable emission rate.
Section 203.110 Potential
to
Emit
The maximum capacity of a stationary source to emit a pollutant
under its physical and operational design. Any physical or
operational
limitation on the capacity of the source to emit
a pollutant,
including air pollution control equipment and
restrictions on hours of operation or on the type or amount of
material combusted,
stored,
or processed,
shall be treated as
part of its design only if the limitation or the
effect it
would have on emissions is enforceable.
Secondary emissions
do not count in determining the potential to emit of a
stationary source.
oor~

4
Section 203.111 Reasonable
Further Progress
Annual incremental reductions
in the emissions of the applicable
air pollutant sufficient to provide for attainment of the
National Ambient Air Quality Standards
as expeditiously as
practicable,
in accordance with Part D of the Clean Air Act
42 U.S.C.
7501 et ~g.
and 40 CFR 51.15 adopted thereunder.
Section 203.112 Secondary Emissions
Emissions which occur as a result of the construction or
operation of a major stationary source or major modification,
hut do not come
from the major stationary source or major
modification itself.
For the purpose of this Part,
secondary
emissions must be specific, well defined, quantifiable, and impact
the same general area as the stationary source or modification
which causes the secondary emissions.
Secondary emissions may
include, but are not limited
to emissions from any reasonably
foreseeable offsite support facility which would not otherwise
be constructed or increase its emissions as a result of the
construction or operation of the major stationary source or
major modification.
Section 203.113
Public Participation
At the initiation of a permit application pursuant
to Subpart
B,
the Agency shall provide at a minimum, notice of the same
and a comment period pursuant
to the Agency public partici-
pation procedures.
Section 203.114
Severability
Notwithstanding Rule 113 of this Chapter,
if any provision
of Part 203 is stayed or declared invalid by a final order,
no longer subject to appeal, of any court of competent juris-
diction, then the entirety of Part 203 shall be deemed stayed
or invalidated until
the stay is lifted or the Pollution
Control Board acts to revalidate
the Part.
SUBPART
B:
MAJOR STATIONARY EMISSIONS SOURCES IN NONATTAINt4ENT
AREAS
Section 203.201
Prohibition
No person shall cause or allow the construction of a new
major
stationary source or major modification in
an area designated
as rionattainment as defined at Section 171(2) of the Clean
Air Act
(42 U.S.C.
7501.2) with respect to that pollutant,
except as in compliance with this Part
for that pollutant.

5
Section 203.202
Preconstruction “ermit Requirement and Application
a)
A preconstruction permit designating the proposed
construction as a new major source or major modifica-
tion is required prior to:
1)
entering into binding agreements or contractual
obligations, which cannot be cancelled or
modified without substantial loss to the owner
or operator, to undertake a program of actual
construction of a source to be completed within
a reasonable time;
2)
initiating physical on—site construction activities
which are permanent in nature including but
not limited to installation of building supports
and foundations,
laying underground pipework
and construction of permanent storage structures;
or
3)
initiating a change in operations which may be
subject to this Subpart and Subpart C.
b)
Applications for preconstruction permits shall contain
sufficient information to demonstrate that the source
constitutes or does not constitute a new major source
or major modification pursuant to this Subpart.
Section 203.203 Construction Permit Requirement and Application
a)
A construction permit is required prior to having
begun or having caused to begin
a continuous program
of actual on—site construction or change
in opera—
tioris of thc ~ourcc, Such permit shall contain enforce-
able conditions satisfying the requirements Subparts
B
and C.
b)
Applications
for construction permits required
under this Section shall contain sufficient information
to demonstrate compliance with Rule 103, and the
requirements of this Subchapter including,
but not
limited to, Subpart
C.
Section 203.204
Duration of Construction Permit
A permit to construct shall become invalid if the permittee has
not commenced construction within
18 months after receipt of
such permit, construction is discontinued for a period of
18
consecutive months or more, or construction is not completed
within a reasonable time.
However, this provision does not
apply to the time period between construction of the approved
phases of
a phased construction project; each phase must begin
actual construction within
18 months of the dates contained in
the permit application.
52-391

6
Section 203.205
Effect of Preconstruction and Construction Permits
Neither a preconstruction nor a construction permit shall
relieve
any person of the responsibility to comply fully with applicable
provisions of state,
local or federal
law.
Section 203.206
Major Stationary Emission Source
A major stationary emission source that is major for organic
material
shall
be considered major
for ozone.
The following
constitutes
a major stationary emission source:
a)
Any stationary emission source of air pollutants which
emits, or has the potential to emit,
100 tons per year
or more of any pollutant.
b)
Any physical change that would occur at a stationary
emission source not qualifying under paragraph
(a)
as a major stationary emission source,
if the change
would constitute a major stationary emission source
by itself.
c)
The reconstruction of a stationary emission source
will
be treated as the construction of a new major
stationary source if the fixed capital cost of new
components exceeds approximately half of the fixed
capital
cost of an entirely new stationary source.
Determining whether reconstruction will occur is
based on the following:
1)
fixed capital cost shall mean the capital needed
to provide all the depreciable components;
2)
the fixed capital cost for the replacements
in
comparison to the fixed capital cost that would
be required to construct a comparable entirely
new source;
3)
the estimated life of the source after the replace-
ments compared to the life of a comparable entirely
new source;
and
4)
the extent to which the components being replaced
cause or contribute to the emissions from the source.
Section 203.207
Major Modification of a Source
Any
physical change, or change in the method of operation of
a stationary emission source that would result in
a significant
net emissions increase of any pollutant,
except that a physical
change or change
in the method of operation shall
not include
any activity listed below.
Any net emissions increase that
is
~2~~Q2

7
significant for organic material
shall be considered significant
for ozone.
a)
Routine maintenance,
repair,
and replacement of com-
ponents which do not constitute reconstruction pursuant
to Section 203.206(c),
b)
Use of an alternative
fuel or raw material by reason
of any order under Sections
2(a) and
(b)
of the Energy
supply and Environmental Coordination Act of 1974,
15
U.S.C.
791, the Power Plant and Industrial Fuel Use
Act of
1978,
42 U.S.C.
8301
(or any superseding
legislation)
or by reason of
a natural gas curtailment
plan pursuant to the Federal Power Act,
16 U.S.C.
791, et seq.
c)
Use of an alternative
fuel by reason of an order or
rule under Section
125 of the Clean Air Act,
42
U.S.C.
7425.
d)
Use of an alternative
fuel
at a steam generating unit
to the extent that the fuel
is generated from munici-
pal solid waste.
e)
Use of an alternative
fuel
or raw material by a sta-
tionary source which:
1)
it was capable of accommodating
before December 21,
1976 unless such change would be prohibited under
any enforceable permit condition which was
established after that date pursuant to 40 CFR
52.2l~or
2)
is approved for use under any permit issued
pursuant to 40 CFR 52.21 or this Chapter.
f)
An increase in the hours of operation or in the pro-
duction rate,
unless such change would be prohibited
under any enforceable permit condition
which was
established after December 21,
1976 pursuant to
40 CFR 52.21 or this Chapter.
g)
Any increase
in emissions of organic material due to
the temporary shutdown of
a control device during
seasonal periods as allowed by this Chapter.
h)
Any change
in ownership at a stationary source.
Section 203.208
Net Emission Determination
A net emissions increase is the amount by which the sum of any
increase in actual emissions from
a particular physical change or
52-393

8
change in method of operation at an emission source, and any
other increases and decreases in actual
emissions at the emis-
sion source that are contemporaneous with the particular change
and are otherwise creditable, exceeds
zero.
The following steps
determine whether the increase or decrease
in emissions
is
available.
a)
An increase or decrease in actual emissions is contem-
poraneous only if it occurs between the date that an
increase from a particular change occurs and the date
five years before
a timely and complete application is
submitted for the particular change.
In the case of
an increase,
it must also occur after either April
24,
1979 or the date the area
is designated by United
States Environmental Protection Agency as
a
nonattainment area for the pollutant, whichever
is
more recent;
b)
An increase or decrease
in actual emissions is credit-
able:
1)
only if no other permit has been issued, and is
still
in effect when the particular change occurs,
which relied on the same increase or decrease
in
actual emissions;
2)
in the case of a shutdown of an emission source,
only to the extent that
it is being replaced
by a similar source;
and
3)
only to the extent the new and old levels differ.
c)
~ decrease in actual emissions is creditable to
the extent that:
1)
it is enforceable at and after the time that
actual construction on the particular change
begins;
2)
it has approximately the same qualitative sig-
nificance for public health and welfare as that
attributed
to the increase from the particular
change;
3)
that the old level
of
actual
emissions or the
old level of allowable emissions, whichever
is
lower, exceeds the
new
level of actual
emissions;
and
4)
it is demonstrated by the Agency not to have
been previously relied on for demonstrating
~
~Qd

Q
attainment on reasonable further progress in
the nonattainment area which the physical
change
will impact.
Section 203.209
significant Emissions Determination
A net emission increase
in the pollutant emitted
is significant
if the rate of emission is equal
to or in excess of the following:
a)
Carbon monoxide:
100 tons per year
(tpy)
b)
Nitrogen oxides:
40 tpy
c)
Sulfur dioxide:
40 tpy
d)
Particulate matter:
25 tpy
e)
Ozone:
40 tpy of organic material
f)
Lead:
0,6 tpy
g)
Asbestos:
0.007 tpy
h)
Beryllium:
0.0004 tpy
1)
Mercury:
0.1 tpy
j)
Vinyl chloride:
I tpy
k)
Fluorides:
3 tpy
1)
Sulfuric acid mist:
7 tpy
m)
Hydroyen sulfide
(H2s):
10 tpy
n)
Total reduced sulfur (including
H2S):
10 tpy
o)
Reduced sulfur compounds (including
H2S):
10 tpy
Section 203.210
Relaxation of a Source—Specific Limitation
Except those modifications exempted pursuant to Section 203.207,
at such time that a particular source or modification becomes a
major stationary source or major modification by virtue of a
relaxation in any enforceable limitation which establishes a
specific standard for that source to emit a pollutant, this
Subpart shall apply to the source or modification as though
construction had not yet commenced.
52-395

10
SUBPART
C:
REQUIREMENTS
POR
~tAJOR
STATIONARY
SOURCES
Ii’~
NONATTAINMENT ARE~AS
Section 203.301
Lowest Achievable Emission Rate
a)
For any source,
lowest achievable emission rate
(LAER)
will he the most
stringent
rate
of emissions based on
the
following:
1)
The lowest emission limitation which
is
contained
in the
implementation
plan
of
any
state
for
such
class
or
category
of
stationary
source,
unless
it
is
demonstrated
that
such
limitation
is not achievable;
2)
The
lowest
emission
limitation which
is achieved
in practice or
is
achievable by such
a class
or category
of stationary source;
or
3)
The applicable
new
source performance standard
contained
in
Part
IX of this Chapter.
b)
The owner or operator
of a new major
stationary source
shall
demonstrate
that the control
equipment and process
measures applied
to the source will
produce LAER.
c)
The owner or operator
of
a major modification
shall demonstrate
that
the control equipment
and process measures applied
to the modifica-
tion will produce LAER at each emissions
source
at which
a significant
incr~.~c~
in emissions of
the
pollutant has occurred
or would occur as
a result
of a
physical
change or change
in the method of operation.
d)
The owner or
operator
shall provide a
detailed showing
that the
proposed
emission limitations constitute LAER.
Such demonstration
shall include:
1)
a description
of
the
manner
in
which
the
proposed
emission
limitation was
selected,
including
a detailed
listing
of
information
resources,
2)
alternative
emission limitations, and
3)
such other
reasonable information as
the Agency may request as necessary to
determine
whether
the proposed emission
limitation
is I~AER,
52-~96

11
Section 203.302
Maintenance
of
Reasonable
Further
Progress
and
Emission
Offsets
a)
For particulate
matter,
sulfur dioxide, nitrogen
oxides, or carbon monoxide emissions,
the owner
or operator of a new major source or major
modification shall demonstrate that the source
or modification will not interfere with reasonable
further progress by meeting one of the following
requirements:
1)
Providing
equal
or
greater
emission offsets
for
the allowable emissions from the source or the
net increase
in emissions
from the
modification,
and
demonstrating
that
actual
average
air
quality
will be improved in the nonattainment area and
that at no location will
the impact
exceed
the
significant air quality impact levels contained
in Section 203.304(d);
2)
Demonstrating that air
quality in the
nonattainment area will be improved at
every location affected by the new major
source or modification, barring the use of
dispersion enhancement techniques; or
3)
Providing in the immediate vicinity of the source
or modification actual emission offsets at a
ratio
of 1.25:1 or greater
(i.e.,
for each ton of new
allowable emissions,
there shall be at
least 1.25
tons of actual emission offsets) provided
that
stack or emission parameters do not indicate a
significant adverse effect on air quality in
accordance with Section 203.304(d),
due to
the
operation
of
the
source
or
modification.
b)
For organic material emissions,
the owner or operator
of a new major source or major modification shall
demonstrate that it does not interfere
with reasonable
further progress by providing actual emission
offsets
in excess of the allowable emissions from the new
source
or
the net increase
in
emissions from the
modification.
Section 203.303
Baseline and Emission Offsets Determination
a)
An emission offset must be obtained from a source in
operation prior to the permit application for the new
or modified source.
Emission offsets can be obtained
from stationary or fugitive sources.
b)
The emission offsets provided must be:
52-397

12
1)
of
a type with approximately the same quali-
tative significance for public health and wel-
fare as that attributed
to the increase
in
a
particular change;
2)
in the case of a shutdown,
it
must have occurred
since
April
24,
1979
or
the
date
the
area
is
designated by the United States Environmental
Protection Agency as
a nonattainment area for
the pollutant,
whichever
is more recent, and
the shutdown source is being replaced by
a similar new source;
and
3)
enforceable
by
permit.
c)
The baselines for deterrning emission offsets are as
follows:
1)
For particulate matter
(TSP),
sulfur dioxide
(SO
),
nitrogen oxide
(NO
) and carbon monoxide
(CO~,the applicable emishon limit contained
in
this
Chapter.
If
this
rate
is
greater
than
the uncontrolled emission rate, the baseline
shall be the uncontrolled rate.
2)
Except for organic material,
if
no emission rate
is contained
in this Chapter,
the baseline shall
be the actual emission rate.
3)
The baseline for organic material shall be the
lesser of the actual
or allowable emission rate.
d)
The location of emission sources providing the emis-
sion offsets must he
1)
for TSP, SO2,
NO
,
or
CO, these sources must be
significant cont~ihutorsto or located in the
nonattainment area affected by the new or
modified
source;
or
2)
for organic material,
these sources must be
located
within
100 miles of the new or modified
source.
If
the
applicant
can
demonstrate
using
generally accepted air quality models,
that the
effect
of
the
proposed
offsets
on
air
quality is
at least as great
as
if the source of the offsets
was within the
100 mile radius,
these offsets
shall
be acceptable.
Section 203.304
Exemptions from Emissions Offset Requirement
a)
The Agency shall allow the use of
all or some portion
52-398

13
of the available growth margin to satisfy Section
203.
303 if:
1)
the owner or operator can show that possible
sources of emission offsets were investigated and
none were reasonably available at that time, and
2)
the owner or operator agrees to accept permit
conditions on all future permits for the source
or modification designed to provide the required
emission offset at the earliest future time such
offsets become reasonably available.
b)
Section 203.302 shall
not apply to a major stationary
source or major modification if the emissions from
the source,
or the net emissions increase from the
modification would be temporary, that is, existing
for a period of time less
than two years.
c)
Section 203.302(a)
shall not apply to a major sta-
tionary source or major modification if an air quality
analysis shows
it is located in a portion of a given
nonattainment area where the air quality standards
are not being violated and it will not cause an impact
in the area in which air quality standards are
being
violated greater than the significant air quality im-
pact levels in subparagraph
(d).
Such an analysis
shall be based upon dispersion modeling and air quality
monitoring performed by the Agency or in accordance
with Agency procedures.
The date when the emission
offset requirements may be restricted to a limited
part of the nonattainment area is the date that such
analysis
is completed by the Agency or the date such
analysis is approved by the Agency, and redesignation
of the area where the major source or major modifica’.
tion is to be located is under federal review.
d)
If the emissions from a major stationary source or major
modification are demonstrated to be greater than the
following levels, exemption pursuant to subparagraph
(c)
is not available for the major stationary source or
major modification.
_Averaging
Time
Pollutant
Annual
24-Hour
8—Hour
3—Hour
1—Hour
SO2
1.0 ug/m3
5 ug/m3
25 ug/m3
TSP
1.0 ug/m3
5 ug/m~
NO
1.0 ug/m3
Co
0.5 mg/rn
2
mg/rn

.t4
e)
Section 203.302(a)
shall not apply to a major sta-
tionary source or major modification for particulate
matter if it will
be located in an area which meets
the following criteria:
1)
the area is an attainment area for the primary
total suspended particulate air quality standard;
2)
the area is lacking reasonably available emission
offsets;
3)
the air ‘quality of the area is dominated by agri-
cultural and related fugitive pollutant sources;
4)
the area lacks major industrial development;
and
5)
the area
is
of
a low urban population density.
Section 203.305
Compliance by Existing Sources
The owner or operator shall demonstrate that all major stationary
sources which he or she owns or operates
(or which are owned or
operated by any entity controlling or controlled by,
or under
common control with the owner ~r operator)
in Illinois are in
compliance, or on a schedule
for compliance, with all applicable
state and federal air pollution control requirements.
Section 203.306
Analysis
of Alternatives
For emission of organic material
or carbon monoxide, the owner or
operator shall demonstrate that benefits of the new major source
or major modification significantly outweigh the environmental
and soöial dosts imposed as
a result
of its location, con-
struction, or modification, based upon
an
analysis of alter-
native sites,
sizes, production processe, and environmental
control techniques for such proposed source.
SUBPART
D:
RESERVED
SUBPART E:
RESERVED
SUBPART
F:
OPERATION OF
A MAJOR STATIONARY SOURCE
OR MAJOR MODIFICATION
Section 203.601
Lowest Achievable Emission Rate Compliance
Requirement
No person shall cause or allow the operation of a new major
stationary source or major modification subject to the con-
struction requirements of Subpart
C,
except as
in compliance
with applicable LAER provisions established pursuant to
Section 203.301 for such
source or modification.
~fl
Ar.r.

15
Section
203.602
Emission
Offset
Maintenance
Requirement
No
person
shall
cause
or
allow
the
operation
of
a
new
major
stationary source or major modification which is required to
demonstrate
that
it
would
not
interfere
with
reasonable
further
progress, or which must include emission offsets in a demon
stration pursuant to Sections 203.302 and 203.303 without
maintaining those emission offsets or other equivalent offsets.
Section 203.603
Ambient
Monitoring Requirement
The
owner or operator of a new stationary source or major
modification shall conduct such ambient monitoring as the Agency
determines
is reasonably necessary to establish the effect of the
emissions from the source or modification on ambient air quality
in the area.
This
Order
conforms
to
the
Opinion
adopted
this
same
day.
These regulations are directed to Second Notice.
IT IS SO ORDERED.
I,
Christan
L.
Moffett,
Clerk
of
the
Illinois
Pollution
Control
Board,
hereby
certçLfy
that
the
above
Order
was
adopted
on
the
j(~*~-
day of
_____
_____
,
1983 by
a vote
of
~
I
A
Christan L. Moff~X~hClerk
Illinois Pollution Control Board
52-401

Back to top