ILLINOIS POLLUTION CONTROL
BOARD
May 27, 1982
COUNTY OF DuPAGE,
)
Petitioner,
)
V.
)
PCB 82—24
ILLINOIS ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD (by 3. Anderson):
This matter comes before the Board on the March ii, 1982
petition for variance filed by the County of DuPage (County).
The County seeks variance for “at least one year” from the 15
pCi/i gross alpha particle activity limitation of Rule 304(C) (1)
of Chapter 6: Public Water Supply. On April 5, 1982 the I1.iinots
Environmental Protection Agency (Agency) filed its Recommendation
in support of grant of variance until January 1, 1984. Hearing
was waived and none has been held.
The County, through its Department of Public Works, supplies
drinking water to the 5,425 residents (1981 Agency estimate)
(1,550 service connections) of the Rosewood Trace Subdivision,
which is located in an unincorporated area of southeastern DuPage
County adjacent to the Village of Burr Ridge. The County seeks
variance to continue use of deep (1,610’) Rosewood Trace No. 1
Well and its distribution system. A composite of four quarterly
distribution system samples taken between September 24, 1980 and
July 14, 1981 showed a gross alpha level of 22.0 ±4.45 pCi/i.
However, single samples taken from two points
in
the distribution
system on September 24, 1980 and December 21, 1981 showed gross
alpha levels in pCi/i, respectively, of 7.11 ±2.74 and 10.8 ±
3.55. The Agency also notes the existence of a shallow (300’)
well, which “is on standby”. The pumping capacity and the gross
alpha particle activity levels of each well have not been provided.
The County states that it has received no test results concerning
radium 226 and 228 levels.
In support of its petition, the County states that it has
considered three compliance options. One option would be to
construct treatment facilities, construction costs for which are
estimated to be $133,000. Another option would be to replace
the well water by, for instance, Lake Michigan water, for which
the County has received an allocation (the size and initial
availability of which was not specified). The petition indicates,
47-157
2
without elaboration, that Lake Michigan water would be delivered
by the DuPage Water Commission, but no timetable or cost estimates
concerning this option were provided, A third short term solution
would be a blending approach, in which water from (unspecified)
other wells would be used to dilute the water of Well No. 1, with
estimated construction costs of $25,000 and an estimated implemen-
tation timetable of 5 months, The County intends to obtain, hut
has not yet done so, professional services “to assist in reviewing
and evaluating this situation and to prepare recommendations for
resolving this problem”. Subject to receipt of a professional
recommendation, the County states that it “presently anticipates”
implementation of a blending program to achieve compliance.
The County asserts that denial of variance would impose an
arbitrary or unreasonable hardship because “there is a great need
for the expansion of the Rosewood Trace water distribution
system in order to serve the domestic and fire protection
requirements of the local population”; however, the Village does
not provide any details supporting these bare conclusions. The
Village believes that to require the expenditure of funds for
immediate installation of treatment facilities would not be in
the public interest, particularly since such facilities “would
probably” be abandoned when Lake Michigan water is obtained.
The Agency generally agrees with the facts asserted in the
petition, and states its belief that grant of variance “will not
result in an unreasonable risk to health”. The Agency therefore
recommends grant of variance until January 1, 1984 subject to
conditions, including engagement of professional consulting
services.
While the two single samples indicate compliance with Rule
304(C)(1), the Board finds that the result of the test of the com-
posite sample is determinative of non—compliance for the purposes
of justification and need for Board consideration of the County’s
variance request (see Village of Round Lake v. IEPA, PCB 82—17,
May 13, 1982). The Board does not find the peti?T~n’slack of
data concerning compliance options to be a fatal deficiency in
light of the Village’s asserted willingness to develop such
information.
The Board finds that to require immediate compliance would
impose an arbitrary or unreasonable hardship, particularly since
there would appear to be little immediate risk to health from
consuming the Village’s water if variance is granted (see Villaae
of Lemont v. IEPA, PCB 80-48, April 30, 1981). The Board will
therefore grant a short—term variance until June 1, 1983, subject
to conditions, during which time the County shall investigate
blending and other compliance options. (The County should note
that should it join a regional water supply system such as the
DuPage Water Commission, variance relief is available through
January 1, 1986.)
47-158
3
The Board notes that this is the second recent case in which
the gross alpha readings as indicated by tests of composite samples
is significantly higher than tests of single samples (see Viliaqe.
of Round Lake, supra), It is discomforting that the discrepancies
were explained in neither case and the Board is concerned that
these results may indicate flaws in the technique for holding or
analyzing composite samples. Given the divergent sample results,
it is even more than usually important that gross alpha testing
continue, and that radium testing commence, and the Board will so
order.
This Opinion constitutes the Board~s findings of fact and
conclusions of law in this matter.
ORDER
1. Petitioner, the County of DuPage, is granted a variance
from the 15 pCi/I gross alpha particle activity limit of Rule
304(C)(1)(b) of Chapter 6: Public Water Supply to allow continued
operation of Rosewood Trace No, 1 Well until June 1, 1983, subject.
to the following conditions:
a. Petitioner shall, in consultation with the Agency,
continue its sampling program to determine as accurately as
possible the level of radioactivity in its wells and finished
water. Testing for radium 226 and 22$ shall be commenced.
b. On or before September 15, 1982 the Petitioner
shall secure professional assistance (either from present
staff or an outside consultant) in investigating compliance
options, including the possibility and feasibility of
achieving compliance by blending water from its shallow well
with that of its deep well. On or before October 15, 1982,
evidence that such professional assistance has been secured
shall be submitted to Wayne Weirnersiage, Enforcement Programs,
at the address stated in paragraph 2, below.
c. As expeditiously after identification of a
feasible compliance method as is practicable, hut no later
than April 1, 1983, Petitioner shall submit a program (with
increments of progress) for bringing its system into
compliance with radiological quality standards to the Agency’s
Division of Public Water Supplies, FOS, at the address sLated
in paragraph 2, below.
d. Pursuant to Rule 313(D) (1) of Chapter 6, in i~.s
first set of water bills or within three months after the
date of this Order, whichever occurs first, and every t.hree
months thereafter, Petitioner will send to each user of its
public water supply a written notice to the efEect that
Petitioner has been granted by the Pollution Control Board
a variance from the 15 pCi/l maximum gross alpha particle
activity standard. The notice shall state the average
content of gross alpha particle activity in samples taken
since the last notice period during which samples were taken.
47-159
4
2. Within forty—five days of the date of this Order,
Petitioner shall execute and forward to the Illinois Environmental
Protection Agency, PWS Enforcement Programs, 2200 Churchill Road,
Springfield, Illinois 62706, a Certificate of Acceptance and
Agreement to be bound to all, terms and conditions of this variance.
This forty—five day period shall be held in abeyance for any
period this matter is being appealed. The form of the certificate
shall be as follows:
CERTIFICATE
I, (We),
,
having read
the Order of the Illinois Pollution Control Board in PCB 82-24,
dated __________________________________, understand and accept the
said Order, realizing that such acceptance renders all terms and
conditions thereto binding and enforceable.
Petitioner
By: Authorized Agent
Title
Date
IT IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board, hereby certify that the above Opinion and Order
was adopted on the ~
day of
_________________,
1982 by
a vote of
?-(~ .
I
~
1.
~
.~ ~
Christan L. Mof~ett, C~rk
Illinois Pollution Conl~rol Board
47- 160