ILLINOIS POLLUTION CONTROL BOARD
July 26, 1983
CITY OF EAST PEORIA,
)
Petitioner,
v.
)
PCB 83—38
ILLINOIS ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION
AND
ORDER OF THE BOARD
(by J. Anderson):
This matter comes before the Board on the March 16,
1983
petition for variance filed by the City of East Peoria (City).
The City seeks variance from 35
Ill. Adm. Code 305.102(b), 306.303
and 306.304 in order to bypass excess
flows without monitoring
during periods of wet weather and mechanical failure of lift
station pumps,
during its pursuit of grant funding for sanitary
sewer rehabilitation work.
19 overflow and bypass points from
its sanitary sewer system were specified in the petition.
16 of
these overflow points were the subject of a prior variance
from
the predecessor Chapter
3 Rules 501(c) and 602(b) granted in
PCB 81-36, May 14, 1983,
11 of which 16 were the subject of a
still earlier variance in PCB 79—244, February 21,
1980.
The
records of these proceedings are hereby incorporated into this
action.
On May 2,
1983 the Illinois Environmental Protection Agency
(Agency)
filed a Recommendation that variance from Section
305.102(b) be denied as unnecessary on the grounds that the City’s
NPDES permit contains no monitoring requirements with which the
rule would require the City to comply.
The Agency recommends
grant of variance from Sections 306.303 and 306.304, but only as
to 18 over-flow points and subject to a variety of conditions.
These include compliance with conditions established in the
PCB 81-36 variance, and with those contained in the Board Order
in PCB 78-263——an Agency enforcement action against the City
concerning permit violations and failure to have
a permit relating
to sanitary sewer overflows.
On June 13,
1983 the City filed a
response to the Recommendation challenging certain facts and
conclusions, and commenting on the proposed conditions.
Hearing
was waived and none has been held.
The City owns and operates
3 wastewater treatment plants and
their tributary sanitary sewer systems.
During dry weather, the
City’s main problem
is routine maintenance of the lift stations,
53-97
2
where one or both pumps could he out of service.
During wet
weather,
the sewer system is subject
to
severe infiltration and
inflow, causing basement backups.
To relieve the backups and
other related problems, the
City
maintains several
sanitary sewer
system bypasses~
The
19 overflow points,
discharge points,
and the plant to
which they are tributary are as
listed below, with new overflow
points indicated by an asterisk:
Plant
Overflow
r~?oi~
STP
1
STP2
STP3
700
Springfield Rd—Manhole
30
1020 Springfield Rd—Manhole
27
400
Meadows Ave—Manhole 44
1500 Meadows Ave—Manhole
41
Maybee Ave—between Manhole
14 and 15
Cracklewood
Ct~Manhole
*Flossmar Ct—Manhole
Woodlawn Lift Station
Field
Grove
Lift
Station
Lincoln Parkway Lift Station
Alice Street Lift Station
Brentwood Lift Station
Maria Street Lift Station
Pebble Court Lift Station
Crawford Street and
Railroad
Alley-Manhole 64
*Rejnders~,Manhol~34
*~j~
Oaks
Ct-near
Manhole
37
*Crest
arms Ct—Manhole
*East Oakwood Ave-Manhole
Cole Creek
Cole Creek
Dry Run Creek
Dry Run Creek
unnamed ditches
tributary to
Dry Run Creek
unnamed ditches
tributary to
Illinois River
Ackerman Creek
drainage area
behind Fondulac
Dam
All
of the above referenced creeks and the drainage area are
tributary to Farm Creek, which is tributary to the Illinois River.
The Agency
reports
that most of
these
points
were inspected
on April
6,
1983,
As
to
the
5
new
overflow
points, the Agency
reports that
the
Flossmar
and
Reinders
overflows were installed
summer, 1982 without
its
knowledge,
to
relieve basement backups
in a “few” nearby homes,
No comment was made as to installation
time of the Twin Oaks and Crestarms Ct. overflows.
Each of these
4 overflow points are equipped with high—level overflows.
None
was discharging on the date of Agency inspection.
in
However,
a bypass was occurring at the fifth,
the East
Oakwood overflow,
This bypass originates on an 8-inch sewer about
50 feet downstream of a manhole.
it was installed to relieve
53-98
3
backups
in two homes against the Agency~sadvice:
the Agency
believes the bypass was unnecessary, believing that backups
resulted from improper sewer maintenance rather than lack of
hydraulic capacity.
The City, however, notes that the plugging
of this sewer is due
to
solids accumulation
in
combination with
low flow conditions,
and that it had installed necessary valves
and piping near the floor of Fondulac
Darn to allow for cleaning
in this remote area with limited
access.
During sewer cleaning,
discharge will
occur
when access valves are opened.
The City
believes that this overflow point is the most desirable of the
admittedly undesirable alternatives during storm events,
since
equipping the affected
homes
with
check
valves
to
prevent
backflow
would
likely cause a discharge from
a
manhole
whose
overflow would flow past a community well.
The City also states
that
it is raising the elevation of
the
overflow
to prevent
bypassing
from
occurring
until
just
prior
to
residential
flooding,
and
that
a
flow
level alarm
is
also
being
installed
to allow
time
for
a
crew
to
respond.
Such
response
would amount
to
pumping
of
the
line,
since
during wet
weather
the
City
installs
portable
pumps at various
manholes to
relieve
surcharging,
By
way
of
example,
between
April
1—4,
5 areas
were
pumped.
This estimated bypass of 10
million gallons would have been in addition to those from the
previously listed permanent bypasses.
Another point noted in the April
6 inspection was that the
7 lift stations tributary to STP
I were equipped with the high—
level overflows,
red light high level alarm systems and 2
submersible pumps required by previous variances,
and those
tested were in operating order,
The Agency additionally noted
that there were problems with the sewer
line that diverts flow
from the Springfield Road sewer to the Cole Creek interceptor.
The City explains that a 60 foot section of ductile iron pipe
running through a fault area was ruptured when the fault shifted
“dramatically~during December,
1982.
A flexible pipe was
installed to accommodate further movement until permanent repairs,
scheduled for this summer, can he made.
The City states that
it intends to eliminate all of these
overflows, provided that it receives grant funds to do so.
The
City currently has a Step
1 grant, with its Sewer System
Evaluation Study scheduled to be completed in July,
1983.
The
City anticipates that design and construction of needed repairs
would presently cost over $6 million (its estimate in 1977 was
$2.5 million),
Assuming it
is awarded a Step 2—3 grant,
the City
believes sewer rehabilitation could be completed within 13 months
of its receipt of a grant.
The City asserts that elimination of its sewer system
overflows prior to receipt of grant funding would impose an
arbitrary or unreasonable hardship,
as
it “does not have the
financial capacity to fund a project of this magnitude” by itself.
53-99
As
to
past
expenditures,
it
notes
that
it
expended
$25,000
in 1981
to
install
the
required visual
and
audible
alarms
at
lift
stations,
$15,000
in
1978
to
build
sewers
to
divert
flows
from
Springfie~.d
Road
to
Cole
Street,
(No
figures
or
further
information
were
given
as
to
the sewer cleaning program, or pump system
and
trailer
mounted
generator
mentioned in the petition.)
The
City
contends
that
its
system
of
bypassing
is
more
environmentally
desirable
than
the
basement
backup
problems
which
would
result without
the
system,
Several
of
the
overflows
discharge
at the bottom of steep ravines, while others
discharge
to storm sewers~
Sarnpi:Lng
information
is
therefore not
available,
but the City suggests that the environmental
:Lrnpact of its
bypassing
is
minimized
because
of
dilution
of
sewage
by
the
infiltration/inflow
to
which
the
sewer
system
is
subject,
and
because
of
the
h:Lgh flows in the receiving streams during
the
bypass events,
The Agency is
in
support
of
continued
grant
of
variance
from
Section 306.303 and
:306. 304
subject to conditions,
as to all
but
the East Oakwood hypass~
The Agency agrees that the plugging of
the bypasses
without
necessary
sewer
rehabilitation
would result
in a health
hazard
from
basement
backups
which
is more serious
than
that
from
bypassing
of
dilute
sewage.
However,
the
Agency
doubts
whether
grant funding for sewer
rehabilitation
would
be
available,
The
Agency anticipates that
the
City’s
SSES will not
be
submitted
or
approved
before
passage of another
6—12
months,
and “at this time,
funds
for actual construction of the
City’s
project are not available, and funding at any time in the near
future appears slim”.
The variance
conditions
suggested
by
the
Agency
were
the
subject of response by
the
City,
so
their
arguments
will
be
presented
in
tandem
as
to
certain
of
the
conditions,
The
Agency
first
suggests
that
the
City
be
required
to
adhere
to
a
proposed
compliance
schedule
which
would
require
elimination
of
all
overflows
as of
April
1,
1986
if
grant
funds
are
received,
and
as
of
April
1,
1988 if
they
are
not,
upon
penalty
of
imposition
of
a
sewer
ban,
The
City
responded
that
it
could
not
commit
itself
to
the
compliance
schedule
as
proposed
because
of
uncertainty
of
funding
sources,
The
Agency
suggests
that
audible
alarms
be
installed
at
all
lift
stations,
to eliminate unreported bypasses
due
to pump
failure,
blown
fuses,
etc.
The
City
responds
that
the
particular
incident
referred
to in
the
Recommendation
was
a
situation
wherein
an
electrical
malfunction resulted in outage of all
power
to
the
lift station, in which case
an audible alarm would have been as
inoperative as a visual
one.
The
City doubts that installation
of
audible
alarms would be ~cost—effective”, or result in more
rapid
response
than
through
its
practice
of
monitoring
visual
alarms.
53400
5
A third condition, that the Springfield Road-Cole Creek
interceptor be permanently repaired,
was not objected to by the
City.
The Agency recommends denial
of variance for the East Oakwood
bypass, as
it believes that to do so would encourage the City to
“add a bypass”
to support new development.
The City responds
that the area is already developed, and was as of 1974 when the
problem sewer
line was installed to serve the area in replacement
of septic
tanks.
The City would not object to having variance
conditioned on twice—yearly sewer cleaning
(as alternatively
suggested by the Agency), and would further agree to obtain
variance relief prior to installation of any further bypasses.
Finally,
as to the requested variance from Section 305.102(a),
the Agency recommends denial because the City’s NPDES permit does
not contain monitoring, sampling,
and reporting conditions.
(One
suggested variance condition unobjectionable to the City was that
monthly overflow reports be submitted in a specified form.)
The Board continues to find that denial of variance would
impose
an arbitrary or unreasonable hardship.
Given the City’s
explanation of the East Oakwood problem, variance from Section
306.303 and 306.304 for all
19 overflows will be granted; variance
from Section 305.102(b)
will
be denied as unnecessary.
The real issue in this case is not whether variance should
be granted, but what its duration and conditions should be given
the almost certain unavailability of grant funding.
The Board
agrees that the City must be forced to contemplate and prepare
for unassisted commencement of sanitary sewer rehabilitation,
but
is not inclined to adopt the 1986/1988 schedule proposed by the
Agency.
The Board will grant variance until October
1, 1984,
during which time the City will be required to complete its SSES,
complete design work
so that its actual funding needs have been
determined, devise a plan for funding the necessary work,
and to
present
a construction/compliance schedule.
As to other conditions, the Agency’s suggestion that a
variance contain a sewer ban triggered by violation of variance
conditions is inappropriate.
The Agency itself could impose a
sewer ban at any time, or could seek such relief during the course
of an enforcement action should the variance terms be violated.
The
grant of this variance does not limit
the Agency’s authority
pursuant to Sections 306.402 or 306.403 to place tho~eportions
of the sewer system which have reached hydraulic cap~cityon
restricted
status, or those portions approaching hydraulic
capacity on critical review.
Grant of this variance (and
previous variances)
temporarily excuses non—compliance with the
otherwise applicable provisions of the Act and regulations, but
does not cause
it to “disappear”, and deprive the Agency of the
ability to determine whether additional hook-ons would result
in or contribute to violations of the type which are admitted
in a
petition for variance,
53-101
6
Finally, the Board will not require installation of audible
alarms,
for the reasons offered by the City.
However,
in that
the City has stated that it is installing hour meters on its
alarms to document the extent of future overflows
(Response p.
2), this installation shall
be included as a condition.
The
balance of the conditions
as suggested will be included in the
Board’s Order.
This Opinion constitutes the findings of fact and conclusions
of law of the Board in this matter,
ORDER
1.
Petitioner,
the City of East Peoria, is granted variance
from 35
Ill. Mm, Code 306.303 and 306,304 until October
1,
1984,
subject
to the following conditions:
a)
This variance applies only to the 19 overflow
points listed at p.
2, supra
b)
The City shall submit to the Agency
i)
a completed SSES on or before October 1,
1983,
ii)
a completed sewer rehabilitation plan on
or before March
1,
1984,
and
iii)
a construction schedule/compliance plan
on or before August
1,
1984,
detailing how the work
will be funded by the City in the event that the City
is advised by the Agency that federal or state grant
funding is unavailable;
c)
The City shall maintain the Springfield Road to
Cole Creek Interceptor flexible pipe connection in the best
manner practicable until permanent repairs are completed,
Such repairs shall
be commenced and completed in summer,
1983;
d)
The City
shall continue to submit monthly overflow
reports.
Beginning August
1,
1983, these reports shall
additionally include all bypasses,
shall separa~ebypasses
into individual events rather than monthly totals,
and shall
indicate how durations were determined;
e)
The City shall comply with all conditions of
PCB 78—263;
f)
The City shall not install any additional bypasses
without obtaining appropriate variance relief prior to their
installation;
53-102
7
g)
The City shall clean the East Oakwood sewer as
necessary to minimize bypassing,
but in no event less than
twice
yearly;
and
h)
The City shall install the hour meters on its
existing alarms as referred to on p.
2 of its Response as
expeditiously as is practicable.
2.
Variance from 35 Ill.
Adm. Code 305.102(b)
is denied as
unnecessary.
3.
Within thirty—five
(35) days of the date of this Order,
the City shall execute and send to Steven
M.
Spiegel, Attorney
Advisor,
Enforcement Programs,
Illinois Environmental Protection
Agency,
2200 Churchill Road, Springfield,
Illinois
62706,
a
Certification of Acceptance by which
it agrees to be bound by
the terms and conditions.
This
35 day period shall be held in
abeyance for any period for which this matter is being appealed.
The form of said certification shall be
as follows:
CERTIFICATE
I,
(We),
,
having read
the Order of the Illinois Pollution Control Board in PCB 83—38,
dated _______________________________, understand and accept the
said Order, realizing that such acceptance renders all terms and
conditions thereto binding and enforceable.
Petitioner
By:
Authorized Agent
Title
Date
IT IS SO ORDERED.
I, Christan L.
Moffett, Clerk of the Illinois Pollution
Control Board, hereby certify that
thfi above Opinion and Order
was adopted on the ~
g~
‘~.-dayof
___________________,
1983 by
a vote of
5-0
.
7
Christan
L. Moffett, perk
Illinois Pollution Control Board
53-103