POLLUTION CONTROL BOARD
    February 9,
    1984
    DUPAGE PUBLICATION COMPANY,
    Petitioner,
    V.
    )
    PCB 84—12
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY
    Respondent.
    ORDER OF THE BOARD
    (by
    J.
    Theodore Meyer):
    Based on the information submitted by the Petitioner on
    January 26,
    1984,
    it appears to
    the
    Board that variance
    is
    requested from
    35
    Iii,
    Adm,
    Code 203, entitled Major Stationary
    Source Construction and Modification,
    Petitioner
    is directed to
    clarify the Sections
    in that and any other part of the Board’s
    air regulations contained in 35
    Ill, Adm. Code 200 et
    ~.
    it
    seeks variance from,
    The Petition for Variance
    is deficient
    for additional rea-
    sons.
    It fails
    to include any specifics about the construction
    or modification apparently already done on Press
    No.
    4,
    for which
    it sought a permit from the Illinois Environmental
    Protection
    Agency.
    The dates and details of the work done should be sub—
    initted to the Board,
    as well as a more detailed account of the
    press’
    actual operation and emissions,
    Petitioner
    is likewise
    directed to submit the standard information
    required by the
    Board’s Procedural
    Pules
    at 35 Iii,
    Adm,
    Code 104.121, entitled
    Contents of a Variance Petition.
    Petitioner has forty—five days from the date of this order
    to amend its original Petition for Variance with the information
    requested.
    The
    90 day decision period will begin the day of the
    amendments are filed,
    Failure to do so will render the Petition
    subject to dismissal.
    IT IS SO ORDERED.
    I, Christan L.
    Moffett, Clerk of the Illinois Pollution
    Control ~oard hereby ~çertify that the above Order was adopted on
    the
    ~/.4~”-~day ~
    1984 by a vote of
    I
    Christan L.
    Moffett, Cl~!
    Illinois Pollution Cont~.àlBoard
    56-181