Ir1T~INOIs POLLUTION CONTROL BOARD
April 5, 1985
IN
THE MATTER OF:
JOINT PETITION OF THE CITY OF
)
PONTIAC AND THE ILLINOIS
)
ENVIRONMENTAL PROTECTION AGENCY
)
PCB 83-231
FOR EXCEPTION TO THE COMBINED
SEWER OVERFLOW REGULATIONS
)
ALAN M. SCHROCK, ASSISTANT CITY ATTORNEY, APPEARED ON BEHALF OF
THE CITY OF PONTIAC: AND
DAVID L. RIESER APPEARED ON BEHALF OF THE AGENCY.
OPINION AND
ORDER OF T~IE BOARD (by 3. Anderson):
This matter
comes before the Board on the December 14, 1983
-ioint petition o~
the City of Pontiac (City) and the IEPA (Agency)
for an exception to 35 Iii.. Mm. Code 306.305(b) of the Board’s
combined sewer overflow (CSO) ~egulations
which provides that
“Additional flows i.e. not dry weather flows or
first flush storm flows, as determined by the
Agency hut not less than ten times the average dry
weather flow Eo.r the design year, shall receive a
minimum
of
primary treatment and disinfection with
adequate retention time”.
Th~ joint petition alleges that the City’s
existing
CSO discharges
have minimal impact on Vermillion River water quality, and that
construction of CSO treatment facilities at an estimated cost of
$1.1 million would produce little benefit.
This
case
is the first utilization of the Board’s CSO
“Exception Procedure”, 35 Ill. Adm. Code 306.350 et seq. Hearing
in this matter was held on February 15, 1984, at which some
members of the public and press were in attendance. Testimony
and exhibits
(Exh. 1-5) were presented by the parties at hearing.
Information not available at the time of hearing was filed in
letter
form
by the Agency March 8, 1984; this letter, concerning
the
City’s status
on the Agency’s restricted status or critical
review lists, is hereby accepted as Exhibit 6, and the Board
Orders
referred to therein are incorporated by
reference as
if
fully set forth. No other written submittals or comments con—
57-359
cerning this
matter
have been received. This matter is being
given expedited consideration by the Board
*
as requested in the
petition
and at hearing,
so as to improve the City’s chances
of
receiving a 75 federal construction grant.
THE PONTIAC TREATMENT PLANT AND ITS CSO DISCHARGES
The City presented five witnesses at hearing: Mayor Dale
Campbell, City Administrator Robert Karls, Department Head for
the Sewer Department David Sullivan, Pontiac’s engineering con-
sultant George A. Farnsworth of Farnsworth & Wylie, and Glenn 0.
Chenoweth, who has resided since 1951 about 1½ miles downstream
of the Pontiac sewage treatment plant (STP) in a home about 30
feet from the bank of the Vermillion River (R. 23—25, Exh. 1).
The Agency presented one witness, Toby Frevert, an engineer in
the
Agency’s Division of Water Pollution Control, whose duties
include
coordination of CSO exception applications and analysis.
As much of the testimony related to the petition itself (Exh. 4)
and exhibits submitted therewith (Exh. 2), hearing testimony will
not be separately set forth, hut will instead be referenced as
appropriate.
The City of Pontiac, Livingston County, population 12,400 is
located at the junction of Interstate 55 and Illinois Route 116
about 100 miles south of Chicago. The
Vermillion River
flows
from east to west through the center of the City. Malor local
industries/institutions are Caterpillar Tractor Company, Kreger
Printing, Interlake Steel Company and an Illinois State Correc-
tional Center. The City is seeking relief from Section 306.305(b)
which would require that the City construct combined sewer
overflow pumping, grit removal, primary settling and disinfection
facilities
to treat
excess storm flows up to 11.7 MGD.
The City is served by 7.9 miles of separate sanitary sewers
and 25.5
miles of combined storm and sanitary sewers all col:1ect-
ing wastes
from
3300 sewer users and draining 1400 urban acres.
Five sewer interceptors,
having a total capacity of 20.1 MGD,
transport sewage to the treatment plant. The plant provides
three—stage
treatment
and disinfection for dry weather flows and
*The
Board
wishes to note that the parties have greatly
facilitated the Board~sconsideration of the first of these CSO
cases by the
manner
in which the presentation was made. The
joint
petition itself properly included the engineering reports,
stream use
and water quality data, etc. supporting the con-
clusions in the petition.
Each party made its necessary and
knowledgable resource persons available for explanations and
questioning at hearing, avoiding the need for additional hearings
to plug record gaps. Future CSO exception petitioners would be
advised to examine the record in this matter.
57-360
primary treatment and disinfection for excess MCD flow. Design
capacities are
2.13
MGD average and 4,3 MGI) maximum for dry
weather flow and up to 4.3 MGD excess flow, The plant is located
on the west side of the City on Old Route 66 and discharges
treated effluent to the Vermillion River.
There are four combined sewer overflows from the City’s
sewer system. (See Exh. 3). Two overflows (003 and 004) located
near the treatment plant have a combined capacity of about 9 MCD
(14 cfs)
and
bypass storm flows fro~nthe interceptors directly to
the Vermillion River. The other two overflows (004 and 005)
having a total capacity of 5.9 MCD (9 cfs) are located in the
upper part of the sewer system on the north side of the City and
bypass storm flow to a storm sewer which discharges to the North
Ditch, a drainage ditch tributary to the Vermillion River.
Overflow points 004 and 005 were constructed about
3
years ago to
bypass flows from the North Street sewer, a 100 year old 2’ x 3’
elliptical brick sewer. Overflow points 003 and 004 have been in
existence for “many years,” with NPDES 003 also being a bypass
mechanism for the North Street sewer.
Studies of sewer hydraulics which have been confirmed by
field sampling show that overflows do not operate until the wet
weather first flush has passed. (See Exh.2, Section 3.3, Exhibit
A.)* For comparison to overf low capacities
cited, the Vermillion
Rivers’s mean annual flow is about 380 cfs. During normal dry
weather, flow ranges from 20 to 60 cfs. Typical flow in the
North Ditch, a srrtall, man-cut drainage ditch with intermittent
flow, is about 5 cis. (See R. 37—40, Exh, 2, Exhibit C.)
The overflows are not monitored continuously, but it is
known that bypassing begins at the two overflows located near th~
plant (003 and 004) during rains ranging from 0.5 to 1.0 inch/hour.
One of the upstream overflows (005) will
operate at about
0.3
inch/hour rainfall and the other (006) rarely operates.
Exhibit 2, Appendix
to Exhibit A gives an analysis of
the
typical first flush
and CSO
pollutant load. The upstream over-
flow is usually quite dilute with BOD less than 50 mg/i and
suspended solids less than 150 mg/i (see Figure 4—2B Appendix to
Exhibit A). The overflows near the treatment plant after the
first flush has passed show BOD around 100 mg/i. Suspended
solids are 400÷mg/i but the volatile solids level of about 40
indicates that this is mostly inorganic grit. (See Figure
4—2A
Appendix
to Exhibit A.)
*Recere~c~sto Exh. 2 will
contain references to a letter
exhibit within the group exhibit, as this
reflects the parties’
original :Ldentiiication scheme.
57-361
—4,,
The City’s treatment plant was upgraded in 1976 under the
old “PL660~ grant program. Because that plant was designed
before
the major rule
changes
of PL92—500,
that expansion did not
include facilities for nitrification and the required
amount
of
CSO treatment,
On February 23, 1979, the City received an Agency “notice of
critical review,” because it had reached
95 of its hydraulic
load capacity
of 21.3 MCD, It was in fact
placed on critical
review ApriL 6, 1979. On March 6, 1981, the
Agency issued a
“notice of impending restricted status”,
because of lack of
hydraulic capacity, organic overloading in
excess of the 16,000
P.E. design capacity, and failure to meet certain
interim ‘SOD and
TSS limitations. Treatment plant discharges
were polluting the
receiving stream sewer surcharging,
and basement backups were a
common occurrence, particularly along
the North Street sewer (see
Exh. 5, and Drake v, IEPA, PCB 81-54, Oct.
22, 1981 and Bergman
v. IEPA, PCP, 81—67, Sept. 3, 1981,)
Since 1981, the City has taken major steps to turn around a
rapidly deteriorating STP and sewer situation. Since 1981, the
City has spent $831,000 to separate combined
sewers (R. 18). An
ongoing program for the yearly cleaning of all combined sewers in
the months between May and November was instituted, at a cost in
1981 of $57,000 (H. 79, 96). iBy contrast,
sewer
cleaning in
other commun:Ltias is done on a 3 to 5 year rotation basis (R.
86)), The City believes that its sewer
separation program,
in
combination with its
street and sewer cleaning efforts, have
reduced
the occurrences
of sewer surcharging and basement back-ups
due to
plugged sewers,
The
City notes,
however, that some base-
ment
flooding continues to occur due to the
nature of the Pontiac
system
and it~s
relation to the river,
Many of the areas served
by combined sewers
are
in the
floodway
or floodplain, and so are
flooding
when the river backs up into low-lying,
flat sewers (H.
82, 88—92).
Pursuant: to
permits
issued in July,
1981, the City has made
certain ~interim~r improvements
to
its STP,
including expansion of
its
capacity
to handle
organic loads. The City currently remains
on critical review
with
1470 P.E, of capacity remaining. The
Agency notes that
the City may apply for
review of its status by
submitting additional
capacity
and influent
information (Exh.
5).
The City has,
meanwhile,
completed
design work for additional
upgrading
of
its
STP. The City
Step
I Facilities Plan for Phase
II was approved by the Agency and certified
to Region V USEPA on
September 30, 1983. This expansion will cost in
excess of $8
million.
Under the assumption that is would be eligible for a 75
federal construction grant (rather than the 55 grant available
57-362
—5-
after October 1, 1984), the
City petitioned
the
courts
for per—
nission to hold a special election to get authority to issue
bonds for the 25
matching
funds
-e
$2 million.
On February 6,
1983, the Agency advised the City that no grant
funds
were
available to it in 1983
because
of its priority number. The
referendum was nonetheless held on February 7, 1983, and
approved
by a vote of 882-119. (The City notes that it would lack legal
authority to issue
bonds
to raise a 45 match,
even
with voter
approval, because of restrictions on total bonding levels in
relation to the City’s total assets). The City is nonetheless
proceeding with finalization of design work
and
other pre—grant
activities, since, in the
words
of Mr. Frevert;
V~Jj
is still a horse race amongst the munici-
palities in
the
State of Illinois for grant
funds..
•
The
name
of the game is to have your
planning work done, and to have your local funding
available, have your design work done,
and
have
your plans and specs ready to
go, so
you
are in
the starting gate, and realistically are in com-
petition for those funds when they
become
available.’
(R.
105—106)
The approved STP
improvement
plan (described in Exh. 2,
Sections 3.1 and 3.2 of Exhibit A) proposes construction of
facilities for;
a.
kdditional capacity for three-stage dry weather flow
treatment
(average of 3.45 MGD up
to
maximum
of 8.40
MGS).
b. Capture
and
storage of ‘first flush’ (0.41 MG) for
treatment later during
dry
weather.
c. Nitrification of all dry weather and first flush flows.
d. Sludge stabilization and disposal.
e. CSO treatment of up to 11.7
MCD
above maximum
dry
weather flow for compliance with Section 306.305(b).
The construction (capital) cost of the
proposed
improvements
were extimated as follows;
a. Dry weather flow treatment, nitrification,
$7,100,000
first flush capture and sludge treatment
b. Additional CSO treatment to meet
1,100,000
Section 306.305(b)
e,zoo,ooo
The estimated annual cost of sewer maintenance and the
operation and maintenance (O&M) of the existing and proposed
treatment plant shown in Exh, 2, Exhibit B are as follows.
Figures shown do not include financing and
capital costs.
a.
Existing treatment plant and sewer
$470,000/yr.
system O&M
b. Additional O&M of proposed dry
80,000/yr.
weather flow treatment, nitri—
fication, first flush capture and
sludge treatment
c.
Additional
CSO treatment O&M
50,000/yr.
Total Annual O&M
$600,000/yr.
The estimated
cost of financing of the city’s share of the
proposed Phase II project costs is as follows.
Costs shown
assume a 25 percent city share financed with a
20—year revenue
bond issued at
11 percent interest requiring 25 percent annual
coverage of principal
and
interest.
a,
Additional
dry weather flow
$275,000/yr.
treatment, nitrification,
first
flush
capture
b.
CSO treatment
45,000/yr.
Total Annual
Financing Cost
$320,000/yr.
The above shows
that the relief sought by the Petitioners to
avoid constructing the CSO treatment facilities
would
save
$1,100,000
in
construction
costs and $95,000 per year in O&M and
financing costs.
ENVIRONMENTAL IMPACT OF THE DISCHARGE
The parties~ conclusions that existing storm overflows from
the Pontiac
combined
sewer system are having minimal impact on
Vermillion
River
water quality, and that
stream
use is not beina
restricted~ are based
on reviews
of existing water quality data,
as well as
field observations by Agency personnel and George
Farnsworth,
the
City~s consulting engineer.
Historical data
available, as
summarized at p. 7 of the petition (Exh. 4) reveals
the Eollowing (references
are to
letter exhibits within Exhibit
2):
~‘a.
Exhibit
D summarizes existing stream biological data
from
various stations in the Vermillion
River basin.
Researchers noted consistent
minor violations of
ammonia,
boron and lead standards up to
1980.
Fisheries
data showed good
diversity of
species and
57-364
—7-
high numbers of sport and non-tolerant species present.
No conclusion on basin condition
was
made because of•
limited data.
(This report was
prepared
as part of the
Section 208 Water Quality Management Program.
b. Exhibit E is water quality data for land collected by
the Streator, Illinois water treatment plant intake
located 25 miles downstream from Pontiac. Streator is
the nearest point
downstream
where the River is used
for domestic water supply. There appears to be no
impact on raw water quality at Streator’s intake from
Pontiac’s discharges.
*
c. Exhibit F is a compilation of available water quality
data for stations near Pontiac (furnished by the U.S.
Geological Survey and the Agency. Stream water
quality violations noted in Exhibit I are sumearized in
Exhibit F. No correlation in violations
with
Pontiac
CSO
events
is evident
and
violations are minor. (No
data is
presented for 1982-1983; water quality
standards violated are usually those for total iron and
fecal coliform.
d.
Exhibit C is a compilation of available river flow data
at Pontiac from 1942 to 1982 furnished by the U.S.
Geological Survey and the
Agency. Average flow of
record is 380 cfs. Extremes of flow are
one
no—flow
event in 1953 and 14,500 cfs in 1980.’
Visual inspections of the areas for about 300 feet below
each CSO outfall and the treatment plant outfall were made by Mr.
Farnsworth on June 21, 1983 (R. 48—49, Exh. 2, Exhibit A, S4.1).
Some
evidence of sludge deposition was discovered near the
STP
outfall.
However, the source of that sludge is believed to be a
floor drain connected to the outfall sewer, and the City intends
to correct that design flaw in the plant expansion project.
Evidence of sludge deposition was found in the first 30 feet
of the river downstream of Outfalls 003 and 004,
but
the
deposits
were shallow (less than 2 inches deep) and difficult to differ-
entiate from natural stream silt. Odor was evident only when the
deposits were
disturbed.
Some
small amount of CSO—related
‘trash’ was discovered near Outfall 003 for about 10 feet down-
stream,
but
it was quickly collected.
*It
should additionally be noted that Streator
pumps
water
from the Vermillion into a side channel reservoir. Water from
the reservoir is then pumped into the water purification plant
for treatment (R. 112).
57-885
In
the
area of the North Ditch outf ails, one sludge
deposit
less than 2
inches deep and roughly 5 feet by 6 feet
was
dis-
covered immediately downstream of the outfall, Ditch flow was
low, with isolated pools evident
(from which
children were catch-
ing minnows).
On September 14, 1983, two Agency field biologists inspected
the
river and the North Ditch (Exh, 2, Exhibit C). Their report
concluded that conditions in the river have not changed since a
1976 biological
survey indicated “unbalanced” stream conditions.*
As to the North Ditch, at a sampling point just downstream
of Outfalls 005 and 006, no sludge was found but the stream
condition
was “semi—polluted.” However, sludge and oil was found
at a sampling station upstream of the outfalls where the stream
condition was also semi—polluted. The biologists concluded that:
“The two CSO’s that discharge directly to the
Verrnillion River appear to have no more adverse
effect on the River than does the STP discharge.
Similarly, the CSO’s on North Ditch also appear to
have no adverse effect on the Vermillion River
although there does seem to be some degradation of
North Ditch. Because of these findings, we feel
that the complete treatment
of
the Pontiac CSO’s
would not significatly improve the water quality
of the Vermillion River.” (Exh. 2, Exhibit C)
~t hearing, it was stated that is was the “definite opinion” of
the authors of the
report that the water quality deterioration in
the North
Ditch was not attributable to
the
City’s CSO overflows,
but to some other upstream source (R. 106),
Uses of the Vermillion River and the North Ditch were dis-
cussed both by the City and the Agency. In addition to the
River’s use as a public water supply for Pontiac and for down-
stream Streator, it provides an “aesthetic quality” for the
residential homes along its banks, and a “desirable and utilized
recreational opportunity” (R. 103). The area near the Vermillion
River CSO outfalls
has become an increasingly popular fishing
spot, as, in the last 5 years, the type and quality of fish
caught have improved; shallow ponds in the North Ditch are a
popular source of minnows for bait. The River is used for
canoeing, although it is too shallow ~or swimming. Mr. Chenowith,
a 30—plus year resident of a river
bank
home a mile and a half
*In this classification system, based on analysis
of~
the henthic macroinvertebrate population in a
water body, the
“best” stream condition is “balanced”, followed by “unbalanced”,
“semi—polluted”, and “polluted”.
57-366
—9—
downstream of the STP outfall, and a longtime outdoorsman and
conservationist, characterizes the River as currently “nice and
clear”, and “look (ing) real good” (R. 28, 26).
Given all of the above, the Agency, in its concluding
remarks, noted that it feels that the Vermillion River is a
valuable resource worthy of protection in the way of additional
improvements to the City’s STP and control of first flush.
However, capture and treatment of ten times dry weather flow at a
capital cost of $1.1 million would not result “in a justifiable
improvement or return in water quality” (R. 104).
THE RESOLUTION
The Board finds, based on the uncontroverted evidence in
this record, that the granting of an exception to 35 Ill. Mm.
Code 306.305(b) has been justified. This determination is based
on the general improvement to water quality attributable to
upgrading of the City’s STP, the Agency’s assessment of the
minimal environmental impact attributable to the City’s CSO
discharges, the high cost of 10 times dry weather flow capture
and treatment facilities, particularly given the City’s grant
funding prospects. However, the question arises as to whether
this exception should be granted without conditions.
Much discussion at hearing centered around the City’s com-
bined sewer cleaning program, and the effect it might have on
CSO discharges. As aforementioned, the program was instituted,
not to control the strength of first flush storm flows, hut to
eliminate basement back ups resulting from sewer blockages.
According to Mr. Sullivan and Mr. Farnsworth, the investment in
metering and sampling equipment necessary to determine the effect
of the program on CSO flows would be substantial, so that no
quantitative evidence has been gathered~ Their qualitative
observation is that there is substantial solids removal. While
Mr. Farnsworth believes that “a rainfall a month would keep the
sewers pretty clean”, nonetheless annual combined sewer cleaning
is “more or less insurance”. It is, however, Mr. Farnsworth’s
conclusion that, even if the City did not perform sewer cleaning,
the impact of grant of an exception from the ten times dry
weather flow capture and treatment provision would be the same
——
minimal (R. 84—85, 63).
When inclusion of a sewer cleaning requirement was discussed
at hearing, the City stated that is has no specific objections to
such a condition, based on its intent to continue the program for
its own purposes. To the extent there is an objection, it relates
to the removal of discretion from a City administration “twenty
years down the road” (R. 121).
57-367
The data preuented to the hoard reflects observations and
estimates based on cleaning of the combined sewers. The Board
therefore believes that, to maintain the status quo, it is the
better course to require continuation of the sewer cleaning
program despite lack of data quantifying its effects, and will
so order. However, to provide the City with a measure of flexi-
bility, the Board will order only that the City clean its com-
bined sewers once every three years, in line with the practice in
other communities. The Board does, however, encourage con-
tinuation of annual combined sewer cleaning.
This Opinion constititutes the Board’s findings of fact and
conclusions of law in this matter.
ORDER
The City of Pontiac is hereby granted an exception from 35
(11. Mm. Code 306.305(b) requiring treatment and disinfection of
10 times dry weather storm flows, provided that the City cleans
its combined sewers at least once every three years, in the manner,
described in the hearing in this matter on February 15, 1984.
IT IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board, hereby certify that the, above Opinion and Order
was adopted pn the~’~— day of
~-~Li
,
1984 by
a vote of
_j~(~
.
V
Illinois Pollution
57-368