1. given leave to file an amended petition.
    2. completion of the Green Valley plant between August and October,1983.
    3. The Hea4flj
      1. Fi5-~l7

ILLINOIS
POLLUTION
CONTROL
BOARD
December
15,
1983
UNITY
VENTURES,
Petitioner,
PC1~ p0—175
ILLINOIS ENVIRONMENTAL PROTECTION
AGENCY
ANT) COUNTY OF DUPAGE,
)
Respondents.
RICHARD
J.
KISSEL
& ROY M. HARSCH
(MARTIN, CRAIG, CHESTER,
&
SONNENSCHEIN),
APPEARED ON
HEHALF
OF
PETITIONER;
JUDITH
A.
GOODIE
&
THOMAS
R.
CHIOLA,
ASSISTANT ATTORNEYS
GENERAL, APPEARED ON BEHALF OF THE ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY; and
ALVIN
G.
SCHUERING, ASSISTANT STATE’S ATTORNEY, APPEARED ON
BEHALF
OF
DUPAGE.
O~tNION
AND
ORDER
OF
THE
BOARD
(by
J,
Anderson):
PROCEDURAL
HISTORY
This matter
comes
before
the
Board on
the
petition for
variance filed by Unity Ventures
(Unity) October
9,
1980,
as
amended January 17,
1983.
35
Iii. Mm.
Code 309.242(a)
formerly
Rule
963(a)
of Chapter
3:
Water Pollution.
This
rule,
in summary, provides that sewer construction permits
expire two years after issuance.*
The purpose
of the variance
is to extend the life of a sewer construction permit issued
by
*
The
complete
text of the rule
is
as
follows:
“Construction permits
for sewers and wastewater sources
shall
require that construction
be completed within two
years.
Construction
permits
for
treatment
works
and
pretreatment
works
shall
require that construction be
completed within
three years.
In situations where the
magnitude
and complexity of the project require
it, the
Agency may issue
a
construction
permit,
requiring
completion
within
a period not to exceed
five
years.”
55-209

—2—
the Illinois
Environmental Protection Agency (Agency) January
31,
1979, which would have expired by its terms January
31,
1981.
The sewer would
serve the proposed Ilobson Greene Unit
2
real estate development project, which
is
to be constructed on a
58.9 acre parcel
of land located at the northwest corner of 75th
Street
&
Greene Road
in
Lisle Township,
DuPaqe County.
The
proposed development would consist of
78 single family dwelling
units and 22 multiple family dwelling units, which would
generate an average 239,200 gallons per day
(gpd)
of sewage, or
2,392 population equivalents (P,EJ.
Title to the proposed
sanitary sewer extension at issue, once constructed, would
lie
with the DuPage County Department of Public Works
(County).
Flows from this sewer extension would be tributary to the
County’s Lisle—Woodridge Sewage Treatment Plant
(STP).
The Lisle—Woodridge STP has been on restricted status since
May
31,
1979,
due to hydraulic overloading and violation of
various permit conditions.
This resulted
in the filing of an
action
in the Du Page County Circuit Court entitled
Corporate West
Development v.
IEPA,
et al.,
No.
79 MR 257.*
A
counterclaim for sewage related violations
of the Act was filed
by the Agency against the County of DuPage, and the Village’s of
Lisle and Woodridge.
Pursuant to stipulation,
on August 13,
1980 Judge Teschner issued an Order granting partial
summary
judgment to the Agency.
Upon entering the order the court,
made various
findings
including:
a)
The Woodridge—Lisle plant was hydraulically
overloaded and
in violation of
its permit
conditions;
b)
new treatment plant capacity was needed;
c)
additional
loading
to
the
overloaded
plant
absent some control would result in
a
threat
to
public
health
and
welfare
by
adding pollutants to the waters of the
State and aggravating existing overflows
of
raw
sewage.
The
court
ordered
specific
actions
to
be
taken
in
an
attempt
to alleviate the situation including:
*
What
scanty
history
there
is on the original complaint
and counterclaim in this action
is contained in pleadings
and depositions from 79MR257, which were attached by
the
Agency as exhibits
to
its June
4,
1982 Motion for
Order for Additional Information
in this action.
55-210

—3—
a)
construction of additional
sewage treatment
capacity;
b)
construction of
a stormwater bypass system to
alleviate pressure during heavy rains;
c)
maintenance and repair work on the existing
treatment facilities;
d)
adoption of
a sludge management program;
e)
study
of
infi1tr~tion/inf1owproblems.
The part of
the court’s order which
is most pertinent to
Unity Ventures’ claim
is the allocation system which the court
set up for connections
to the overloaded plant.
This allocatior
system provides for staged addition of
connections
to the
overloaded plant based upon performance of the plant as
represented by discharges to the
waters of the State.
This
order contemplated and provided for additional connections by
all those holding sewer permits
from the Agency for addition to
the Woodridqe—Lisle facilities.
The allocation system was to
have a limited life since additional treatment capacity was to
he added
to the Woodridge plant by the end of
1983.
The
additional plant capacity is
to
he provided by the Green Valley
plant.
Unity entered
the Cor~porate
West
case as an intervening
complainant on October 10,
1980,
seeking
in part a declaratory
iudgment that
the
August
13,
1980 Order did not affect Unity’s
ability to utilize the January
31,
1979 2,392
P.E. permit
relatinq to Hobson’s Greene Unit No.
2.
(While that permit was
included
in
the
court’s overall flow calculations,
Unity had
not been
a party
to
the stipulation creating the Order.)
As
of the time
of Unity’s briefing
of this matter,
it
would appear
that Judge Teschner has not ruled on Unity’s request
(see Unity
Reply Brief
of September 15,
1983,
at p.2—3).
As
of the filing of its original October
9, 1980 petition,
Unity had not begun construction of the Hobson’s Greene Unit
2
development pursuant
to
its January
31,
1979 permit,* and
presented
no proposed construction timetable.
Unity asserted that construction had been delayed
“because
of the slowdown in demand for residential housing
and the uncertainties surrounding the Lisle—Woodridge Sewage
Treatment Plant involving multiple litigation” (Pet.~).
*
Construction had been completed on Hobson’s Greene Unit 1,
a 35 single family dwellings development immediately north of
Unit
2, pursuant to a February,
1979 permit.
A
third phase,
Unit
3,
is also planned,
to consist of 121 single family
dwelling units and 480 multiple family units.
The Units
1
and 3 developments are not here at issue.
55-211

—4-.
Variance was sought
for a
5
year period to allow for
construction of the sewer
at some
time after completion of
the Green Valley plant.
On December 19,
1980,
a majority
of the Board voted to
dismiss the petition as inadequate pursuant to
35
Ill, Mm.
Code 104.125
(formerly Rule 401(h)
of Chapter
1, Procedural
Rules),
upon motion by the Agency.
The majority Order found
that the petition “lacked
a sufficient allegation of hardship”,
and that
it alleged uncertainty
as
to whether
Unity
might
construct the sewers
at all.”
Leave
to refile the petition
was,
however, granted.
Unity appealed the dismissal,
rrhe Appellate Court
for the
Second District reversed the dismissal
in a non—published
decision pursuant to Supreme Court Rule 23 in Unity Ventures v.
IEPA
etal.,
No.
81—59, February
2,
1982.
The Court ruled that
the Agency~smotion
to
dismiss constituted an objection to the
grant of variance such as to trigger a mandatory hearing
pursuant
to Section 37 of the Environmental Protection Act,
therefore finding the Board’s pre—hearing dismissal of the
action improper
(slip op.
at p.3).
The Board received the
remand mandate
of the Appellate Court on May
28,
1982,
and
reinstated the case and directed that hearing be set by
Order ot June
10,
1982.
D
over
and SanCtion
S
On June
4,
1982
the
Agency
asked
the
Board
to r~rd~rUnity
to provide additional information concerning
the legal entity
which
is the petitioner
in this case.
On June
11,
1982 the
Agency filed
its initial discovery including interrogatories
and requests to produce.
The discovery requests sought
information
to support statements
in the Petition,
including
information about Unity’s development plans, the ownership of
the property to be developed,
the holder of the permit for
which an extension was requested, and the expenditure of funds
for development,
improvement and other costs.
The Agency also
asked
for admissions of fact and genuineness of documents
on
June
11,
1982.
In its July
1,
1982 Order, the Board noted
that the information which the Agency sought concerning the
holder of the permit should be forthcoming
in discovery.
Therefore, the Board denied the Agency’s June
4,
1982 request~
Following
five requests by Unity
for extensions of time
to
respond
to
the
Agency’s
interrogatories
and
requests
to
produce
(see
the
Board’s
Order
of
December
2,
1982
and
the
Agency’s
September
21,
1982
Motion
in
Opposition
to
Request
for
Additional
Time),
the
Board
on
October
5,
1982
ordered
Unity
to
respond
by
October
12,
1982.
Unity’s
response
on
October
12,
1982
was
to
move
to
strike
the
Agency’s
inter—
rogatories
as
burdensome
and
beuause
the
iiiformaLioi~
was
55
19

available from
some
unspecified ‘alternative means.’
Unity also
moved
to strike the document requests on grounds of relevancy.
In its order of
November
12,
1982 the Board noted
that
during the four months following the discovery requests,
Unity
had not raised an objection to the discovery.
The Board also
noted that the petitioner presumably would be the one to
provide
information on its identity, on funds expended on the project
and on the entities expending such funds.
The Board assumed
that
this
information
would
be
forthcoming
from
Unity
and
found
it
to
be
relevant
to
the
proof
of
arbitrary
or
unreasonable
hardship.
The
Board
ordered
responses
from
Unity
by
November
19,
1982
and
warned
Unity
that sanctions would result if
Unity
failed to respond.
Unity did not answer the Agency’s discovery
requests as ordered.
On December 2, 1982, the Board entered sanctions against
Unity for its ‘intentionally dilatorious’ conduct.
Specifically, those sanctions barred Unity from making claims or
introducing
evidence
on
the
issues
of
ownership
of
the
property
in
question;
expenditure
of
funds
for land development and
improvement costs
as
well
as
other
expenses;
identity
of
the
holder of the permit which
is the subject of the extension
request;
and
plans for development.
In addition to precluding
introduction of evidence on these matters at hearing, the Order
struck information on these issues from the petition.
On December 30,
1982, the Board denied Unity’s motion to
reconsider the December 2 sanctions Order.
Unity was, however,
given leave to file an amended petition.
Unity filed its amended petition January 17,
1983.
The
amendment
was
virtually identical to the October, 1980 petition,
and
contained the material stricken December 2.
However, the
petitions
did
differ
in
that
the
amendment
alleged
that
the
‘worst
case
completion
date’
for
the Green Valley plant
was
October,
1983.
The relief requested was also slightly
different,
in that a
two
year variance was requested to begin
‘upon notification by the
Agency
that construction of the Green
Valley plant was complete, or on January 1,
1984, whichever date
is earlier’
(Am.
Pet.,
¶9,10).
This amended petition
was
the subject of a March 1, 1983
motion in limine by the Agency,
which
contended over Unity’s
objections,
that the
December
2 sanctions should apply despite
the filing of an amended petition.
In its order dated March 24,
1983 the Board said:
‘Unity cannot escape sanctions imposed for cause
merely by filing an amended petition.
The Board will
not
allow that which cannot be done directly to be done by
indirection.’

—6—
Upon
reconsideration of this unanimous decision
the Board once
again reaffirmed the earlier sanctions in an orAer dated
May
5,
1983.
In the same order the Board directed the heating officer
to set the hearing on the Amended Petition within a specified
time,
and
prohibited any continuance of the date to be set.
This order was based on the Board’s acknowledgement of ‘Unity’s
listory of delay in this case.’
(Order of
May
5, 1983 at p.3).
At this juncture,
it should also be noted that the
Agency
had filed a Recommendation that variance be denied June 28,
1982,
and
an Amended Recommendation favoring denial on February
14, 1983.
The Agency recommended
that
vdriance
be
denied
on
two
basic grounds.
The first was that there was no valid permit
whose term could be extended, as the
permit
was issued in
January,
1979 to ‘Unity Ventures’, a corporation defunct as ot
June 21,
1979,
and
no
transfer had been made to the ‘Unity
Ventures’ partership which came into existence
on
~1une1, 1979.
The second ground was that Unity’s petition failed to allege
arbitrary or unreasonable hardship.
The Agency alternatively
requested, however, that if variance were to be granted that
sewer construction not begin until the Green-Valley-Woodridge
Complex demonstrated ability to comply
with
its NPDES
permit
for
three consecutive months.
The County adopted the Agency Amended Recommendation as its
own
on February 17,
1983, adding only an affidavit prolecting
completion of the Green Valley plant between August and October,
1983.
The Hea4flj
The hearing on the Amended Petitiun
was
held on June 30,
1983.
Over objection,
Unity presented the testimony of one
witness, James Huff, on the issue of the environmental effect of
grant of variance.
It also presented
two
exhibits, the
application for the permit at issue and the
permit
itself. Again
over objection, Unity presented an offer of proof reiterating
the allegations of the amended petition.
Neither the Agency nor the County presented witnesses at
hearing, although the Agency presented opening remarks.
Pursuant to schedule, the Agency and Unity submitted simul-
taneous briefs on August 30,
1983, and reply briefs on September
15—16,
1983.
The County has not briefed the matter.
THE
ISSUES
Pending Motions
In addition to objections preserved in its briefs on August
30, the Agency made separate motions to strike the testimony of
James Huff, and to strike Unity’s offer of proof.
Unity
filed
responses on September 15.
CC
014

—7—
The basis
for the motion
to strike the Huff testimony
(R.24-38),
i.n
essence revolves about unfair surprise, and
inadequate opportunity for rebuttal and
cross—examination.
Unity
advised the Agency that
it intended to call
Mr.
Huff as
a
witness on June 2~J, 1983,
ies3 than 24 hourn before
the June 30
hearing;
the County was never informed
(R.14).
Unity asserts
that the decision to use Mr.
Huff
as an expert was not made
until
June 28-29
(Reply at 2).
The Agency asserts
that
it had
been attempting
to learn the identity of Unity’s witness(es)
since July 22,
1982,
and that as
late as June
22,
1983,
Unity
objected that
it was “oppressive
and
burdensome
to ask that the
experts he disclosed at this time”
(Motion at 2).
In reviewing the hearing record, the Board
notes that,
under
the
circumstances,
it
was inappropriate on the part of the
hearing officer to
deny
the Agency’s requests to allow a
pre—testimony
interview,
or a one—halF hour recess to enable the
Agency
to call
a technical expert to he present during Huff’s
10
minute testimony
(R.20,
23—24).
Yet the Board also notes that
the Agency
did
not exercise the option offered both by the
hearing officer
(R.21) and by counsel
for Unity (R.38—39) to
make the witne~~savailable ~
ctoss—examination on another day.
Thus,
while the Board cannot condone Unity’s last minute
decision or approve the actions of
its hearing officer, the
Board will accept the Huff testimony.
The Agency has also moved to strike the Unity offer of
proof reintroducing into the record information thrice—stricken
by the Board in sanctions Orders.
This offer was also objected
to
by
the
County
at
hearing
(R.4~).
The Board
linds
that:
the
offer
of
proof
was
properly
accepted,
but
will
not
consider
the
information
as
evidence.
The Board will allow the offer
to remain
in the record.
Unity
has
raised
two
other
sanctions—related
questions
in
its brief.
Unity reserves and renews its prior arguments that
the sanctions Orders of December
2,
1982,
March
24,
1983,
and
May
5,
1983
were
“arbitrarily, capriciously, and
unlawfully
imposed”
(Brief at 2).
These arguments are rejected for all of
the reasons exhaustively detailed
in the Orders
of those dates.
Finally,
Unity has argued that the Agency has somehow
“waived” the sanctions Orders by addressing the issues on which
Unity had silenced itself by delay
(Brief at 2—3).
The
practical, and ludicrous, effect of acceptance
of this argument
is
to invite variance petitioners to rewrite the Act by
1)
withholding
information
which
the
Act
charges
them
to
give,
so as
2)
to trigger sanctions on particular issues,
so as
3)
to
prevent
the
~geney
from
present
i ng
evidence
so
as
4)
to
prevent
the Board from deliberating
the full range of
issues.

—8—
.lit’
Special
Condition 7 of the permit issued January 31,
1979
provides
that
“This permit may not be assigned or transferred without a
new
permit
from
the
Environmental
Protection
agency.”
(Unity
Ex.
2, p.2).
The “Unity
Ventures”
here appearing as a petitioner and claiming
to own this permit
has
admitted
that
it
“was
formed
pursuant
to
an agreement 01 Partnership dated June 1,
1979”
(Unity Response
to Requests for Admissions oE Facts No.
1. and 2).
In
its
Amended Recommendation,
the Agency states that
“This permit was issued to a different legal
entity,
a
corporation, which withdrew from doing business in Illinois
on June
21, 1979.***There is no record
of any transfer of
this permit
from the corporation to the
petitioner—partnership.”
(A!n.
Rev. ¶4)
The Board
finds that the permit here at issue,
Unity Ex.
2,
expired by its own terms
on or about June 21,
1979, when the
entity to which it was issued ceased
to exist.
The Board wishes
to note that this
is not,
in its opinion,
an issue
in which form
is elevated over substance.
As afore—mentioned, the
badly—overloaded Lisle-Woodridge plant was placed
on
restricted
status May 31,
1979.
Based on imposition of restricted status,
the Board questions whether
the
Agency
would have had legal
authority on June 1,
1979 to issue,
or to transfer from one
“Unity”
to the other, the “new” permit specified by Special
Condition
7 absent prior grant of
a variance by the Board
from
3S
Ill. Mm.
Code 309..24L
Arb~~r
or_Unreasonable_Hardsh4~
and
Environmental Effect
Even had the Board not concluded that the permit here at
issue had not expired
long before this action ever reached the
Board, based on
the
evidence here presented,
the
Board could not
find that grant of variance would be lustified.
Consistently, but particularly
in its reply
brief,
Unity
has characterized this action as one in which no environmental
harm would occur if its request were granted,
so that hardship
need not be proven.
The basis for this argument,
as explicated
by portions of the testimony of James
Huff,
is that once the
Green Valley plant comes on line,
about 1.5
mgd
will
be
diverted
from
the
Woodr±dge plant
to
Green
Valley.
The
diversion
is
expected
to cause the effluent quality from both the existing
Lisle and Woodridge plants
to
improve.
Once the 1.5 mgd is
taken out of the Woodridge system,
it.
was stated that
introduction ot
a new wastestream of 240,000 gpd “would not he
detrimental——the effluent quality would be better still than
it
would have been historically”
(R.33).
55-216

—9—
However,
this ignores the fact that the Lisle—Woodridge
tlants have been unable to meet. effluent standards, even given
their improved performance in the past two years.
As the Agency
suggests,
the Green Valley system can be expected
to have an
inconsistent performance
whil.e the usual,
initial “debugging”
process occurs.
The system is still on restricted status, and
will doubtless remain so until both the Woodridge and Green
Valley plants are operating properly.
Unity has therefore
proven that a
less adverse environmental effect would occur b~
~i
connection after Green Valley
is operational than before,
but
not
that none will occur.
Hardship therefore must he proven.
Unity has not,
in
three
years, once alleged that
it was
ready,
willing,
and able to build Hobson’s Greene Unit
2.
It
has,
on the other hand, consistently stated that
it had made
a
business decision not to build during
the time period when its
purported “permit” was valid,
and has resisted revealing any
building plans whatsoever.
Based on the entire complex and
convoluted history of
this action,
the Board has become
convlnced that Unity has pursued variance before
the
Board
merely
to keep the 1979 permit arguably in effect for specu-
lative purposes.
Unity’s proposed 2,392
P.E. was figured into plant capacity
under Judge Teschner’s Order.
Despite Unity’s arguments to the
contrary, denial of variance does not automatically foreclose
Unity’s ability to build when and
if it has actual plans to
proceed.
Once Green Valley becomes fully operational and the
Woodridge
portion
of
the
facility
is
removed
from
restricted
status,
Unity may “get in line” with other prospective
developers and apply for a new permit.
In the event that Unity
wishes to commence construction prior to lifting of restricted
status,
it may petition for variance from Section 309.241,
presenting
a construction schedule and proof of hardship.
This Opinion consttbites the Board’s findings of fact and
conclusions of
law in this matter.
ORDER
Unity Venture’s petition for variance from 35
Ill. Mm.
Code 309.242(a)
is hereby denied.
Fi5-~l7

—10—
IT
IS
SO ORDERED.
I,
Christan
L. Moffett,
Clerk of the Illinois Pollution
Control Board, hereby c~çtifythat t~eabove Opinion and Order
were adopted on the
L~1~
day of~J~—~,
1983
by a vote of
J~.
Christan L. Mof~e
‘,
Clerk
Illinois Pollution
ontrol Board
55-218

Back to top