ILLINOIS POLLUTION CONTROL BOARD
    May 20, 1999
    PANHANDLE EASTERN PIPE LINE
    COMPANY,
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 98-102
    (Permit Appeal - Air)
    ORDER OF THE BOARD (by K.M. Hennessey):
    This matter comes before the Board on the motion to reconsider (Motion) of petitioner
    Panhandle Eastern Pipe Line Company (Panhandle). Panhandle moves the Board to reconsider
    its decision of January 21, 1999, in which the Board affirmed the Illinois Environmental
    Protection Agency’s (Agency) denial of Panhandle’s application to revise an air permit. See
    Panhandle Eastern Pipe Line Company v. Illinois Environmental Protection Agency
    (January 21, 1999), PCB 98-102 (Opinion). The Board denies the Motion.
    BACKGROUND
    The Board’s findings of fact and conclusions of law are set forth in the Opinion and are
    incorporated by reference. Below, the Board highlights the facts and proceedings relevant to
    the Motion.
    Panhandle is a natural gas pipeline transmission company. It operates a compressor
    station in Glenarm, Sangamon County, Illinois (the Glenarm Station). Compressor engines at
    the Glenarm Station recompress natural gas to ensure it continues to move along the natural
    gas pipeline that Panhandle operates.
    The compressor engines emit nitrogen oxides (NO
    x
    ). NO
    x
    is a pollutant for which the
    United States Environmental Protection Agency (USEPA) has established a National Ambient
    Air Quality Standard (NAAQS) to protect public health and welfare. The area in which the
    Glenarm Station is located meets the NAAQS for NO
    x
    and thus is considered an attainment
    area. Under Section 165 of the federal Clean Air Act, 42 U.S.C. § 7475, sources in
    attainment areas are subject to “Prevention of Significant Deterioration” (PSD) requirements,
    which are intended to prevent the degredation of air quality. The Environmental Protection
    Act (Act), 415 ILCS 5/1
    et seq
    . (1996), requires all sources in Illinois to comply with Section
    165 of the Clean Air Act and the regulations thereunder. See 415 ILCS 5/9.1(d) (1996).

    2
    The PSD program imposes various requirements on sources that construct and operate
    new and modified stationary sources of pollutants. These requirements apply to modifications
    that are “major;” generally, a modification that will increase NO
    x
    emissions by 40 tons per
    year or more is considered major. If an existing major stationary source undertakes a major
    modification, PSD requirements compel it to demonstrate, among other things, that it will use
    the best available control technology (BACT) to control emissions.
    This case arose out of Panhandle’s application to revise a construction permit that the
    Agency issued to it in 1988 (the 1988 construction permit). That permit allowed Panhandle to
    retire twelve compressor engines and to add four compressor engines. Illinois regulations
    required Panhandle to obtain a construction permit for these changes. In order to avoid PSD
    requirements, however, Panhandle sought a “minor source” or “PSD avoidance” permit from
    the Agency. That permit would limit to 39.9 tons per year the increase in NO
    x
    emissions from
    the changes that Panhandle sought to implement.
    To determine the PSD avoidance permit limit, the Agency had to calculate Panhandle’s
    existing or baseline NO
    x
    emissions. The Agency did so on the basis of certain standard
    “emission factors” and Panhandle’s gas usage in 1987, the most recent one year period. The
    1988 construction permit limited Panhandle’s NO
    x
    emissions to its baseline plus 39.9 tons per
    year (a total of 461.3 tons per year). The Agency issued Panhandle an operating permit
    containing the same emission limit in 1988, and renewed that permit in 1989, 1990, and 1991.
    In 1997, Panhandle filed with the Agency an application to revise the 1988 construction
    permit. Panhandle sought to increase the emission limit in its permit and to add emission
    controls to two compressor engines. Panhandle’s application revealed that it had exceeded the
    emission limit in the 1988 construction permit each year between 1989 and 1996.
    In the permit application, Panhandle stated that the emission limit in the 1988
    construction permit should be revised for two reasons. First, Panhandle believed that in
    calculating Panhandle’s baseline, the Agency should have considered more than one year of
    gas usage and should have used data from 1985 and 1986. Panhandle considered those years
    more representative than 1987, the year the Agency used to establish the baseline in the 1988
    construction permit. Second, Panhandle believed that the Agency should use more accurate
    (and now updated) emission factor data to calculate Panhandle’s baseline.
    The Agency denied the application. Panhandle appealed the denial to the Board and
    asked the Board to order the Agency to issue the requested permit. On January 21, 1999, the
    Board affirmed the Agency’s denial of the permit on two grounds. First, the Board found that
    Panhandle was subject to the requirements of the PSD program and that Panhandle’s
    application failed to meet those requirements—in particular, the requirement to show that it
    would use BACT to control emissions. Second, the Board found that Panhandle failed to
    support adequately the revised emission factor data that it proposed for ten of the retired
    engines. The Board also found that the Agency should not be estopped from requiring
    Panhandle to obtain a PSD permit.

    3
    On February 25, 1999, Panhandle moved the Board to reconsider its Opinion on the
    grounds that the Board misapplied the law. On March 12, 1999, the Agency filed a Response
    to the motion. The Agency opposes the Motion and argues that the Board did not err.
    DISCUSSION
    A motion to reconsider may be brought “to bring to the [Board’s] attention newly
    discovered evidence which was not available at the time of the hearing, changes in the law or
    errors in the [Board’s] previous application of existing law.” Citizens Against Regional
    Landfill v. County Board of Whiteside County (March 11, 1993), PCB 92-156, slip op. at 2,
    citing Korogluyan v. Chicago Title & Trust Co., 213 Ill. App. 3d 622, 627, 572 N.E.2d
    1154, 1158 (lst Dist. 1991). In this case, Panhandle argues that the Board erred in its
    application of existing law. The Board already addressed many of these arguments in the
    Opinion and the Board will not revisit them here. Panhandle raises several arguments,
    however, that warrant further consideration.
    Specifically, the Board will address Panhandle’s arguments that (1) the Board
    misinterpreted Section 39(a) of the Act; (2) the Agency could and should address Panhandle’s
    exceedences of the 1988 construction permit limit through an enforcement action; (3) the
    Agency could revise the permit as requested; (4) the Board’s ruling leaves Panhandle unable to
    defend itself in subsequent enforcement proceedings; (5) the Agency took inconsistent
    positions; and (6) the Agency should be estopped from requiring Panhandle to apply for a PSD
    permit.
    The Applicability of PSD
    Panhandle argues that the Board erred in upholding the Agency’s determination that
    Panhandle was subject to PSD requirements. Before turning to Panhandle’s arguments, the
    Board will reiterate the basis for its conclusion that the Agency properly found Panhandle
    subject to PSD requirements.
    In concluding that Panhandle was subject to PSD requirements, the Board first found
    that the 1988 construction permit was valid and enforceable. Opinion at 13-14. Second, the
    Board found that Panhandle’s application showed that it had exceeded the limit set forth in that
    PSD avoidance permit.
    Id
    . at 15. Third, the Board found that these exceedences showed that
    the changes that Panhandle made in 1988 increased its emissions by 40 tons or more per year,
    and that Panhandle therefore had made a major modification in 1988.
    Id.
    Fourth, the Board
    found that as a result of this major modification, Panhandle had triggered PSD requirements.
    Id
    . Finally, the Board found that the Agency appropriately denied the permit application on
    the grounds that Panhandle had failed to meet PSD requirements, particularly the requirement
    to show that it would use BACT to control emissions.
    Id.
    at 15-16.

    4
    The Board’s Interpretation of Section 39(a) of the Act
    In the Motion, Panhandle argues that under Section 39(a) of the Act, 415 ILCS 5/39(a)
    (1996), the only relevant issue is whether the proposed action will, in the future, violate the
    Act or Board regulations. Motion at 6. Specifically, the Agency is obligated to issue a permit
    (or a revised permit) “upon proof by the applicant that the facility, equipment, vehicle, vessel,
    or aircraft will not cause a violation of this Act or of regulations hereunder.” 415 ILCS
    5/39(a) (1996). Panhandle argues that contrary to Section 39(a), the Agency denied the permit
    application on the basis of past violations. Motion at 7.
    The Board disagrees. Section 9.1(d) of the Act prohibits anyone from operating a
    source in violation of Section 165 of the Clean Air Act. Panhandle’s application showed not
    only that it had exceeded the 1988 construction permit limit in the past, but that it had
    triggered PSD requirements under Section 165 of the Clean Air Act. The application further
    failed to demonstrate that Panhandle would meet PSD requirements, particularly the
    requirement to show that it would use BACT to control emissions in the future. The Agency
    therefore properly denied the permit application.
    These facts also distinguish this case from those cases in which the Board found that the
    Agency improperly substituted permit denial for an enforcement action. See Illinois
    Environmental Protection Agency v. Illinois Pollution Control Board, 252 Ill. App. 3d 828,
    830, 624 N.E.2d 402, 404 (3d Dist. 1993) and Centralia Environmental Services, Inc. v.
    Illinois Environmental Protection Agency
    (October 25, 1990), PCB 89-170, slip op. at 10-13.
    In those cases, the Agency expressly denied a permit application because the applicant had not
    corrected various violations of the Act and regulations. Here, by contrast, the Agency’s denial
    letter did not state that it denied the application on those grounds. More importantly, Panhandle’s
    application showed that it had triggered a different set of requirements—the PSD requirements—
    than those under which it had been operating. Panhandle’s failure to meet those requirements
    precluded the Agency from finding that Panhandle would not cause a violation of the Act if its
    permit were revised. See ESG Watts, Inc. v. Pollution Control Board, 286 Ill. App. 3d 325, 335-
    336, 676 N.E.2d 299, 306 (3d Dist. 1997) (rejecting claim that the Agency impermissibly used
    permitting process as an enforcement tool when the Agency’s denial letter offered sufficient and
    proper reasons for denial).
    The Agency’s Ability to Seek Enforcement
    In the Motion, Panhandle also argues that the Agency could have and should have
    revised the 1988 permit as requested, while addressing Panhandle’s exceedences of the limit in
    that permit through an enforcement action. Motion at 8-13. Panhandle asserts that both the
    consent decree that it attached to its Petitioner’s Reply Brief of November 17, 1998 (Pet.
    Reply Br.), and the USEPA guidance that the Board cited, establish that this would have been
    a permissible course for the Agency to have taken.
    Id
    .
    The Board finds the consent decree unpersuasive. First, the terms of the consent
    decree provide that it is not an “admission of any issue of fact or law,” and therefore it cannot

    5
    be considered USEPA guidance. Pet. Reply Br., Attachment at 2. In any event, it appears to
    involve a situation in which the USEPA alleged that the source had constructed a major source
    without a PSD permit. As part of the settlement, the source agreed to adhere to a limit that
    would render it a minor rather than a major source.
    Id
    . By contrast, Panhandle now seeks a
    permit limit that, given its baseline, would not have allowed Panhandle to avoid PSD if
    Panhandle had sought that limit in 1988.
    The Board also disagrees with Panhandle’s reading of USEPA guidance. USEPA
    guidance discusses what an administering agency may do when a source exceeds an emission
    limit in a minor source permit. The guidance provides that an agency may enforce a minor
    source permit, instead of requiring the source to get a PSD permit, if the source intends to
    adhere to the original permit limit. See 54 Fed. Reg. 27274, 27280 (June 28, 1989). But
    Panhandle does not intend to adhere to the original permit limit; Panhandle seeks to
    substantially increase its permit limit. The portion of the guidance that Panhandle relies upon
    is therefore inapplicable.
    The portion of the USEPA guidance that does apply requires the Agency to apply PSD
    requirements to Panhandle. That guidance provides that when a source has a “belated
    realization that its original plans cannot accommodate the design or operational limitations
    reflected in” its minor source permit, it is proper for the administering agency to “treat the
    source as major by requiring it to obtain a PSD . . . permit” under 40 C.F.R. § 52.21(r)(4).
    See 54 Fed. Reg. 27274, 27280 (June 28, 1989).
    Panhandle argues that this portion of the guidance means that “a source may become a
    major stationary source or major modification solely by virtue of a relaxation in an enforceable
    limit, but is subject to the PSD requirements only after the permit relaxation takes place.”
    Motion at 8-9. It is not clear if Panhandle means to argue that such a source may obtain a
    revised PSD avoidance permit for a relaxation in an enforceable limit and later obtain a PSD
    permit for the same changes; alternatively, Panhandle may be arguing that such a source would
    become subject to PSD requirements only if it undertook a major modification in the future.
    Neither course of action is sensible or permissible. Section 52.21(r)(4) provides that
    “At such time that a particular source or modification becomes a major stationary source or
    major modification solely by virtue of a relaxation in any enforceable limitation . . . then the
    requirements of paragraphs (j) through (s) of this section [
    i.e.
    , PSD requirements] shall apply
    to the source or modification as though construction had not yet commenced.” 40 C.F.R. §
    52.21(r)(4) (emphasis added.) This language requires that the relaxation and the application of
    PSD requirements be simultaneous rather than sequential.
    The Agency’s Ability to Revise the Permit
    Panhandle argues that the Board erroneously concluded that the Agency could not
    revise the permit as requested. Motion at 3-6. Panhandle argues that 35 Ill. Adm. Code
    201.167(a) grants the Agency the ability to revise a permit and does not limit the revisions that
    the Agency may make.
    Id.
    at 4-6.

    6
    The Board expressly held that the Agency may revise permits. Opinion at 14. Its
    ability to do so, however, is not unlimited. As noted earlier, Section 39(a) obligates the
    Agency to issue or revise a permit “upon proof by the applicant that the facility, equipment,
    vehicle, vessel, or aircraft will not cause a violation of this Act or of regulations hereunder.”
    415 ILCS 5/39(a) (1996). As noted earlier, the Agency properly found that proof lacking in
    this case.
    The situation is analogous to that in Hawaiian Electric Company v. United States
    Environmental Protection Agency, 723 F.2d 1440 (9th Cir. 1984). In that case, the USEPA
    had issued Hawaiian Electric Company (Hawaiian Electric) a PSD permit that required
    Hawaiian Electric to burn oil with a 0.5% sulfur content. Hawaiian Electric later realized that
    the model upon which the original permit was based was faulty. It then petitioned the USEPA
    to reconsider this provision and allow Hawaiian Electric to use a fuel with a higher sulfur
    content. The USEPA stated that while Hawaiian Electric could use such fuel without
    adversely affecting air quality, the change in fuel would be a major modification requiring a
    PSD permit. The USEPA denied Hawaiian Electric’s petition because it did not meet PSD
    requirements.
    Id.
    at 1441-1442.
    Hawaiian Electric argued “that it is challenging the premises under which the permit
    was originally granted and that therefore application of the major modification definition in
    particular and PSD review in general is incorrect.” Hawaiian Electric, 723 F.2d at 1445. The
    court rejected this argument, holding that Hawaiian Electric’s challenge to the original permit
    was untimely.
    Id
    . at 1445.
    Panhandle argues that Hawaiian Electric is distinguishable because “no statutory or
    regulatory provision existed which might allow the [USEPA] to reconsider its original
    position” and the Hawaiian Electric court therefore rejected such reconsideration on “public
    policy grounds.” Motion at 6. Here, Panhandle argues, the Board’s regulations do allow the
    Agency to revise a permit and it is inappropriate to disallow that revision on public policy
    grounds.
    Id
    . at 6.
    Panhandle misconstrues both Hawaiian Electric and the Board’s ruling. If Panhandle
    had demonstrated compliance with PSD requirements, it would have been entitled to a revised
    permit, just as Hawaiian Electric would have been entitled to a new PSD permit for the change
    it sought to implement had its petition met PSD requirements.
    1
    What neither the USEPA nor
    the Agency can do, however, is ignore PSD requirements when they are plainly triggered.
    Furthermore, the Agency cannot ignore PSD requirements on the grounds that they
    were triggered, in part, as a result of an alleged defect in a permit that is final and valid. That
    would amount to a reconsideration of its original decision, which the Act does not allow.
    1
    Similarly, a source that has complied with a PSD avoidance permit may seek revision of a
    condition of the permit without meeting PSD requirements, provided that revision will not trigger
    PSD requirements.

    7
    Panhandle argues that the decision that sets forth this principle, Reichhold Chemicals, Inc. v.
    Pollution Control Board, 204 Ill. App. 3d 674, 561 N.E.2d 1343 (3d Dist. 1990), is
    distinguishable because in that case the Agency sought to reconsider its decision on a permit
    application even though the source had not filed a revised application. Motion at 5.
    Panhandle further argues that Reichhold “merely clarified when the Agency has authority to
    consider a matter and when the Board has such authority.”
    Id
    .
    The Board does not agree; Reichhold addresses the Agency’s authority to reconsider
    decisions, and concludes that it does not have that power. See Reichhold, 204 Ill. App. 3d at
    678, 561 N.E.2d at 1345 (“In view of the case law denying administrative agencies the
    authority to change or modify decisions once announced, we conclude that the Agency here
    had no authority to reconsider or modify the decision . . . .”); see also Waste Management of
    Illinois, Inc. v. Pollution Control Board, 231 Ill. App. 278, 299, 595 N.E.2d 1171, 1184-
    1185 (1st Dist. 1992) (striking down a Board rule that would have allowed the Agency to
    reconsider permit decisions, noting that Reichhold held that “the Act does not grant the
    Agency any authority to modify or reconsider its decisions.”). It follows, therefore, that while
    the Agency may revise a permit, it cannot ignore the consequences that flow from the original
    permit—in this case, the PSD requirements that Panhandle triggered when it exceeded the
    emission limit in its minor source permit.
    The Effect of This Ruling on Subsequent Enforcement Proceedings
    Panhandle argues that it will now be unable to defend itself in a subsequent
    enforcement action because the Board “has already concluded that past violations have
    occurred.” Motion at 11. Panhandle also argues that before the Board can find Panhandle in
    violation of the Act, the Board must take into consideration all the facts and circumstances
    bearing upon the reasonableness of the emissions, including the factors listed in Section 33[(c)]
    of the Act.
    Id
    . at 11-12. Panhandle argues that the Board failed to do so.
    Id
    .
    Panhandle’s concerns are unfounded. First, the Board found only that Panhandle’s
    permit application showed that it had exceeded the limit in the 1988 construction permit. The
    Board did not find, however, that Panhandle violated its permit.
    Furthermore, the Board’s decision in this case will not be
    res judicata
    in a subsequent
    enforcement case. The doctrine of
    res judicata
    provides that once a cause of action is
    adjudicated, it cannot be retried between the same parties or their privies in a new proceeding.
    See Burke v. Village of Glenview, 257 Ill. App. 3d 63, 69, 628 N.E.2d 465, 469 (1st Dist.
    1993). As the Board has previously held, a permit appeal and an enforcement action are not
    the same cause of action, and therefore a decision in a permit appeal has no binding effect in a
    subsequent enforcement action. See ESG Watts, Inc. v. Illinois Environmental Protection
    Agency (July 23, 1998), PCB 96-181, slip op. at 2. Therefore, the Board’s finding that
    Panhandle’s application showed that it exceeded the limit in the 1988 construction permit will
    not be
    res judicata
    in any subsequent enforcement action. If the State or any other complainant
    brings such a proceeding, Panhandle remains free to assert whatever defenses it may have to a
    claim that it has violated its permit.

    8
    The Consistency of the Agency’s Positions
    Panhandle asserts that the Agency’s denial letter never articulated why the Agency
    believed PSD requirements were triggered, and that Agency witnesses offered three
    inconsistent reasons for this conclusion at the hearing. Motion at 12. Panhandle argues that
    the Agency had no reason to list more than one ground for the denial of the permit if revision
    of the NO
    x
    limit was not possible.
    Id
    . Panhandle also argues that if PSD requirements were
    triggered once Panhandle exceeded the 1988 construction permit limit, then supplementing the
    record with the permit history of the 1988 permit application would not have been necessary.
    Id
    .
    While Agency witnesses focused on several different reasons for applying PSD
    requirements, the Agency’s denial letter clearly put Panhandle on notice that the Agency
    believed PSD requirements were triggered. It further put Panhandle on notice that Panhandle
    had to demonstrate that it would use BACT to control its emissions. In this appeal, it is
    Panhandle’s burden to show why those requirements were not triggered. Panhandle failed to
    meet that burden, and the Board is therefore required to affirm the Agency’s permit denial.
    Estoppel
    Panhandle argues that the Board incorrectly relied upon its decision in People v.
    Chemetco, Inc. (February 19, 1998), PCB 96-76, when it rejected Panhandle’s claim that the
    Agency should be estopped from subjecting Panhandle to PSD requirements. Motion at 13.
    Panhandle argues that Chemetco is distinguishable because in that case the petitioner sought
    estoppel on the basis of oral statements that the Agency later contradicted in writing.
    Id
    . In
    this case, Panhandle notes that the oral statements that it relied upon followed, rather than
    preceded, Agency letters. Accordingly, Panhandle argues, estoppel should apply.
    Id
    .
    The Board disagrees. First of all, Panhandle did not prove that the Agency ever
    retracted the statements made in its letters of March 20, 1997, and June 18, 1997, in which the
    Agency stated that Panhandle must satisfy PSD requirements. Two Panhandle witnesses
    agreed that the Agency never specifically informed Panhandle that a PSD application would
    not be required. See Transcript of October 21, 1998 Hearing at 75-76, 148-149. In light of
    the letters and this testimony, Panhandle’s reliance on any inconsistent statements by Agency
    staff was not reasonable.
    CONCLUSION
    The Board denies Panhandle’s motion to reconsider.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that the
    above order was adopted on the 20th day of May 1999 by a vote of 7-0.

    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board

    Back to top