1. Respondent.
      2. 58-363
      3. 58-364
      4. ORDER
      5. 58-366
      6. CERTIFICATION

ILLINOIS
POLLUTION CONTROL BOARD
June
14,
1984
ILLINOIS
POWER
COMPANY,
Petitioner,
V.
)
PCB 84—75
ILLINOIS ENVIRONMENTAL
)
PROTECTION
AGENCY,
)
Respondent.
OPINION
AND
ORDER
OF
THE
BOARD
(by W,
3.
Nega):
This provisional
variance request comes before the
Board
upon
a June
14,
1984
Recommendation of the Illinois
Environmental
Protection Agency (Agency).
The Agency recommends that
the Board
grant Illinois Power
Company
(IPC) a 45—day provisional variance,
beginning on June 18,
1984 and lasting until August
2,
1984,
from
the effluent limitations,
monitoring requirements, and special
conditions in its currently
expired NPDES Permit No, 1L0036919*
and from 35
Ill. Adm~
Code 304.124(a)
and 35
Ill.
Adm. Code
3O4.141(a)~
(Rec~4).
The requested provisional variance
would
enable the Clinton
Power Station to:
(1)
bypass
the existing
station flushwater
treatment facilities
so that preoperational
flushwaters
from the
outside ring header of the station fire
protection and safe shutdown
service water systems can be
dis-
charged directly to Clinton
Lake and
(2) to allow it to exceed
the total suspended solids
(TSS)
and total iron effluent standards
for these discharges,
(Rec.
1),
IPC is
in the process
of constructing a nuclear—powered
electrical generating facility
at its Clinton Power Station in
DeWitt County,
Illinois which
will include
a boiling—water reactor
and steam turbine generator,
varied
electrical transmission
facilities, normal operating and
emergency shutdown
heat dissipa-
tion systems, primary water
consumption
systems, a station fire
*phe
Petitioner~s
NPDES Permit No, 1L0036919 e,~iredon
July 31, 1980w
Although
IPC submitted an application
for its
renewal on January 29,
1980,
the NPDES Permit has not yet been
reissueth
On April
ii,
1984, the Agency issued
a
pre—public—notice
draft reissued NPDES
Permit for the Clinton Power Station,
The
Petitioner has requested
that an additional
special condition be
incorporated
in the final
NPDES
Permit which would
authorize
direct discharge to Clinton
Lake such as requested in this
provi—
sional variance~
(Pet.
1
& 2),
58-363

protection system, and a safe
shutdown service water system.
Construction of this station,
which has been designed to generate
933 net megawatts of electricity,
was
begun in October of 1975
and
is expected to be completed around October of
1986,
The
initial
fuel loading has been scheduled for January
of 1986 and
the initial commercial
operation is anticipated
to
begin in
November of 1986.
(Pet,
3—4;
see:
Figure
1),
The fire protection
system
(which
supplies fire
suppression
water throughout the
station) and the safe shutdown service water
system
(which supplies
water to cool safety—related equipment
such as diesel—generator
coolers,
residual
heat
removal heat
exchangers, and other
equipment necessary
for a
safe shutdown of
the reactor)
are designed
to he operated and available as precau-
tionary operational
systems to prevent the potential loss of
life,
personal injury,
and property damage associated with accident
or
emergency situations.
(Pet,
4;
see:
Figures
1,
2,
&
3).
IPC has preliminarily
scheduled the
flushing
of the
ring
header portion of the
station~sfire protection system for
June
18—19, 1984 and anticipates
that about 2.8
million
gallons
of
water will be discharged
during this time
period,
This
flushing
operation will
flush
the service water pumphouse piping,
the
10-inch supply line;
and
the 14—inch loop
line
with water being
discharged from all
29
of the hydrants on the loop header,
(Pet,
8;
Rec.
2),
Similarly,
the
flushing of the division no,
3
subsystem of
the safe shudown service water
system
is tentatively scheduled
for July 1—4,
1984 and is
expected to discharge about
2 million
gallons of water during
this short time
period.
Flushing opera-
tions will involve the flushing piping associated with the ECCS
heat exchangers
1A,
1B,
and 1C as well as with the switch
heat
removal condensing piping and diesel—generator
1C,
(Pet.
8;
Rec,
There appears to be no reasonable alternative to the method
suggested by IPC, since the
flushing water
which will be discharged
is all very far removed from the flushwater treatment system.
To
be able to convey this flushwater to the treatment system,
IPC
would need to either lay ~thousands of feet of hose~which would
improperly block station roadways,
or make
costly modifications
to the piping systems which are
presently
ready
for startup.
If
large quantities of hose were
laid,
safety
hazards from ruptured
or broken hoses might be prevalent,
Similarly,
if costly modifica-
tions to existing piping
systems were made,
these changes might
be contrary to the design and installation specifications of the
Nuclear Regulatory
Commission.
(Rec.
2).
The flushwater treatment
system,
which has a batch treatment
capacity of
2 million gallons and normally receives
flows
of
about 350,000 gallons per
week,
consists of a storage chamber and
58-364

a
treatment
pond
followed
by a
filter,
(Rec,
2—3),
Twelve
days
are
usually
needed
to
treat
and discharge
each
hatch.
IPC
has
stated
that,
if
the
treatment
system
was
expanded
to
accommodate
the
additional
fiushwaters
resulting
from
a
temporary
flushing,
it
would
result
in
the
unnecessary
expenditure
of
funds
(since
the
resultant
additional
capacity
would
be
needed
infrequently)
and
would
necessitate costly delays in the construction of the
generating
station
without any concomitant benefits,
(Rec,
3).
The
Petitioner
has
indicated
that
both
of the
pre—operational
flushes
are
necessary
and
are
critical
path
milestones
on
the
startup
schedule
for
the
Clinton
Power
Station,
IPC has asserted
that
each
day
of
delay
in
the
completion
of
a
~critical
path
item~
is considered
equivalent
to
a
day
of
delay
in
fuel
loading
and
is estimated
to
cost
about
$1,000,000.
(Rec,
3).
Because
IPC
personnel
est.
imate
that
it
would
take
30
days
to
construct
special
facilities
to
convey
and
provide
the requisite treatment
for
the
pre~o~erational
flushwaters,
the
expense
involved
in
such
an
alternative
include
construction costs
plus the substantial
equivalent
of
$30,000,000
due to the
completion
delay.
(Rec,
3).
Data
obtained
from
previous
flushes
indicates
that
TSS
and
total
iron
concentrations
have been well
within
allowable
limits
when
flows
have
been
greater than
1
million gallons.
(Pet.
10;
see:
Table
1;
Rec,
3).
Moreover, because precleaned
pipes will
be
used
in
the
systems
to
be
flushed,
minimal
suspended
solids
and
iron
levels
are
expected
to be present
in
the flushwater.
(Rec.
3)~
Although
the
actual flushing of the two
systems
is
anticipated
to
occur
on
only
six
days,
IPC
has
requested
a
longer
time
period
to allow for adjustment,
if necessary,
of
the
planned
schedule
for the pipe flushing activities,
(Rec,
4).
While the presently
expired NPDES Permit does not
include
a provision to authorize
the discharge of the ring header
and safe
shutdown service water
system,
future flushing activities of a similar nature are expected
to be authorized in the proposed NPDES Permit which is presently
under public notice,
(Rec.
3—4),
IPC has requested this provi-
sional variance in order to maintain its construction schedule
and
control
its costs while discharging the necessary flushwaters.
The
Agency believes that the denial of
the
provisional
variance
would
impose an arbitrary or unreasonable hardship
on
the
Petitioner,
Thus,
the Agency recommends that
the
Board
grant
Illinois
Power
Company
a
45—day provisional variance from Sections
304,124(a)
and 304,141(a) to
begin on June
18,
1984,
subject to
certain
conditions,
Pursuant to Section 35(h) of the Illinois Environmental
Protection Act, the Board hereby grants the provisional variance
as
recommended,
However,
in so granting this provisional variance,
the Board
58-365
—4—
wishes to
alert
the parties
to portions of
the Petition
and
attachment that appear to
suggest that future flushing activities
may violate Board effluent
standards
and that these activities
are to be authorized in
a proposed NPDES permit renewal
(see
Pet.
unnumbered p.
3,
lines 2—5;
p.
4,
lines 4—6; Attach,
p.
3, para.
3
and 4),
It
is,
of course,
unacceptable
to include, without a
Board variance,
a
permit condition that
allows Board effluent
standards to be exceeded,
Also, regarding the ~infrequently”
needed
additional capacity
(Pet,
p,
3,
lines
2-5),
the Board
wishes to alert the parties to the limits on the frequency with
which
provisional variances may be granted
in
Sec.
34(c)
of the
Act.
This Opinion constitutes
the Boardes findings of fact and
conclusions of law
in this matter.
ORDER
Illinois Power
Company is hereby
granted
a 45—day provisional
variance,
beginning
on
June
18, 1984 and
lasting until August
2,
1984,
from
the
effluent
limitations, monitoring requirements,
and
special
conditions
in
its NPDES Permit No,
1L0036919
and
from
35
Ill.
Adm,
Code
304,124(a)
and 35
Ill,
Adin,
Code
304,141(a)
to
enable
the
Clinton
Power Station to
(1)
bypass
the existing
station
flushwater
treatment facilities
so
that pre—operational
flushwaters from the
outside ring header
of
the
station
fire
protection and safe
shutdown service
water systems can be dis-
charged directly
to
Clinton Lake and
(2)
to allow it to exceed
the total suspended
solids and total
iron
effluent
standards
for
these discharges,
subject to
the following conditions:
1.
The
Petitioner shall notify Roger Cruse of
the
Agency~s
Compliance
Assurance
Section by
telephone
at
217/782—9720
when each flushing
event begins
and ends.
2,
The Petitioner
shall
monitor
these
discharges
by
taking
a
24—hour
composite
sample each day
that
discharge
occurs,
These samples shall
be
analyzed
for
pH,
total
suspended
solids and total
iron,
3.
The
Petitioner
shall
monitor
the
lake water used for
these
flushes
prior
to
its
use
by
24
hour
composite
samples.
The waters of
Clinton Lake shall
be analyzed for total
suspended solids, total iron and pH.
4,
The
results
of the above
referenced analyses, along
with
flow data
and dates and
times
of
each
discharge,
shall
be
sent
to
Roger Cruse within
10
days
after
the
last
day
of
each
flushing
event,
The
appropriate
documents
shall
be
sent to
the
following
address:
58-366

—5—
Illinois Environmental Protection Agency
Division of Water Pollution Control
Compliance
Assurance
Section
2200
Churchill
Road
Springfield,
Illinois
62706
5.
The
Petitioner shall perform the flushes
so
as
to
minimize
any
impact
upon
Clinton
Lake.
6.
Within
10
days
of
the
date
of
the
Board~s Order,
Illinois
Power
Company
shall
execute
a
Certificate
of
Acceptance
and
Apreement.
which
shall
be
sent
to:
Illinois
Environmental
Protection
Agency,
Division
of Water Pollution Control,
Compliance
Assurance
Section,
2200
Churchill
Road,
Spring-
field,
illinois
62706,
This
certification
shall have the
following
form:
CERTIFICATION
I,
(We),
_______________________________having read
the
Order of the
Illinois
Pollution Control
Board in PCB 84~75
dated
June 14,
1984,
understand and accept the said Order, real-
izing
that such
acceptance
renders all terms
and conditions
thereto binding and
enforceable,
Petitioner
By:
Authorized Agent
Date
IT
IS
SO
ORDERED,
I,
Dorothy
M.
Gunn,
Clerk of the
Illinois Pollution Control
Board,
hereby
certif
that the above
Opinion
and
Order was adopted
on
the
~day
~
1984 by a
vote of
____
~
Clerk
Illinois Pollution Control Board
58-367

Back to top