ILLINOIS POWER
COMPANY
(Baldwin Power Plant),
Petitioner,
V.
PCB 84—34
ILLINOIS ENVIRONMENTAL
PROTECTION
AGENCY,
Respondent.
INTERIM ORDER OF THE BOARD (by B..
Forcade):
At the May 10, 1984, hearing in this matter counsel for
both~the petitioner and respondent stated that they have reached
agreement on the matters in dispute and that a joint motion to
dismiss would be filed with the Board as promptly as possible
(R, 3-4). The parties are directed to file any such motions as
soon as possible, hut in no event later than June 11, 1984.