ILLINOIS POLLUTION CONTROL BOARD
    May 6, 1999
    GENERAL ELECTRIC COMPANY,
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 99-115
    (Permit Appeal - Air)
    ORDER OF THE BOARD (by C.A. Manning):
    On February 22, 1999, the Illinois Environmental Protection Agency (Agency) and
    petitioner filed a request for extension of the 35-day appeal period pursuant to Section 40 of
    the Environmental Protection Act (Act) (415 ILCS 5/40(a)(1) (1996)), relating to a
    January 26, 1999 Agency determination. On April 26, 1999, the Board received petitioner’s
    petition for review. The final determination concerns petitioner’s site located in Ottawa,
    LaSalle County, Illinois. The Board accepts this matter for hearing.
    The Board’s rules require that the Agency file the entire Agency record of the permit
    application within 14 days of notice of the petition. See 35 Ill. Adm. Code 105.102. Hearing
    must be scheduled and completed in a timely manner, pursuant to the applicable statutory
    decision deadline, or the decision deadline as extended by a waiver. See 35 Ill. Adm. Code
    101.105. The assigned hearing officer shall inform the Clerk of the Board of the time and
    location of hearing at least 40 days in advance of hearing so that a 30-day public notice of
    hearing may be published.
    Absent any future waivers of the decision deadline, the statutory decision deadline is
    now August 24, 1999 (120 days from April 26, 1999); a Board meeting is scheduled for
    August 19, 1999.
    IT IS SO ORDERED.

    2
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
    the above order was adopted on the 6th day of May 1999 by a vote of 6-0.
    Dorothy M. Gunn, Clerk
    Illinois Pollution Control Board