1. Illinois Pollution Control Board

ILLINOIS POLLUTION CONTROL BOARD
October 25,
1984
CITY
OF PARK RIDGE,
)
)
Petitioner,
)
v~
)
PCB 84—140
)
IL~INOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
)
Respondent.
ORDER OF THE BOARD
(by J. Anderson):
In response to the Board’s October
12,
1984 Order
in this
matter the City of Park Ridge submitted supplemental information
on October 23,
1984 regarding its variance petition.
The
Illinois Environmental Protection Agency (Agency)
filed
a
recommendation that variance be granted,
subject to certain
conditions.
Unfortunately, neither document supplies sufficient
information
for the Board to make
a judgement on the merits.
First,
the Board cannot determine whether variance is
necessary~ Park Ridge states that it “was advised by Illinois
EPA that
a variance would be required.”
The Agency may be
correct, but the present record includes insufficient information
for the Board to make such a determination.
The Agency does note
that “it is unclear whether Petitioner’s existing system is
in
non-compliance.”
If the system is presently in the grant
process, does the exemption contained in 35
Ill. Adm. Code,
306.306(d)(1,2,3,) apply to excuse any present non—compliance?
If the existing system is,
in
fact,
in compliance,
the City must
explain how the act of raising the outfall elevation would result
in non—compliance necessitating variance relief.
The Board
cannot simply presume that such relief is necessary.
Therefore,
information sufficient to prove the necessity of variance is
required.
Second,
as the Board pointed out in its September
20,
1984
Order,
the question
of ultimate compliance
is at issue.
In
response to that Order,
Park Ridge indicated that ultimate corn-
pliance would be achieved sometime between 1995 and 2000 when the
City~sdischarge will ~irportedly be connected to the Tunnel
and
Reservior Project.
The Agency accepted that estimate.
The
Board’s authority to grant variance relief is limited to five
years
(with possible extensions),
and compliance is expected no
earlier than 11 to 16 years in the future.
The Board notes that
procedures have been established under
35
Iii.
Adm. Code
306,
60-375

—2—
Subpart D which allow for exceptions from the combined sewer
overflow rules which are not limited
in duration and
which
may
well
be
a more appropriate mechanism
for
obtaining
the
desired
reliefr
if
such
relief
is,
in
fact,
necessary.
In
such
case
the
City
should
file
a petition
pirsuant
to
those
rules
to
seek
longer term
relief,
Third,
as the Agency points out,
the
City
still
has
not
presented
“any data on the
quality
of
effluent
discharged”
and
only
“a
very
scanty analysis of the environmental impact.”
While
the
City argues that
there
will
be
little
change
in
the
impact
from the present
discharge,
the
Board
is
without
any
information
as to the impact of
the
present
discharge.
For all of these reasons the Board cannot reach a conclusion
on the merits based upon the present record and
is left with only
two alternatives:
to dismiss the proceeding or to attempt to
obtain the relevant information.
The Board chooses the latter
course,
and since requests for further written information have
proven
largely
futile,
the
Board will order this matter to
proceed
to
hearing
at
which
the
Board expects all the issues
raised by the Board to be fully addressed.
The Board again
stresses its concern over the delay involved
in proceeding toward
a
remedy
for
the
basement
sewer
back—ups,
but without adequate
information before
it,
it cannot grant the requested relief.
Finally,
the
Board
notes that the remaining issues which
have
not
been
adequately
discussed
are,
generally,
legal
and
environmental
rather
than
engineering
issues.
The
City
must
provide
sufficient
information
to
establish
that
the
variance
mechanism
:Ls
the
appropriate
one
to
obtain
the
requested
relief
(or choose
an
alternative
mechanism)
and
that any
adverse
environmental
impacts
are heavily outweighed by other
considerations.
Therefore,
the
Board
orders
that
hearing
be scheduled within
15
days
and held within
45
days
of
the
date
of
this
Order.
IT
IS
SO
ORDERED.
Board
Member
~3,Theodore Meyer concurred.
I, Dorothy M. Gunn,
Clerk of the Illinois Pollution Control
Board,
hereby certify that the
above
Order was adopted on
the
___
P~~__day of
,
1984 by a vote
of______
____
~z
Dorothy
~4.
~nn,
Clerk
Illinois
Pollution
Control
Board
60-376

Back to top