ILLINOIS POLLUTION CONTROL BOARD
September
20,
1984
BLACK BEAUTY
COAL
COMPANY~
?
Petitioners
)
PCB 84—109
ILLINNOIS ENVIRONMENTAL PROTECTION
AGENCY
Respondent.
OPINION
AND
ORDER
OP
THE
BOARD
(by J. Marlin):
ThIs matter
comes before the Board upon the July 31,
1984
filing of a petition for variance by the
Black
Beauty Coal
Company
(BBCC)
from the 35 mg/I total suspended
solids
(TSS)
effluent standard of 35 III. Adm, Code 406.106.
BBCC requests
a variance for its Cedar Creek Mine in Brown and
Schuyler
Counties for five years or until and
if there
is a grant of
regulatory change in R84-29.
The Illinois Environmental Pro-
tection Agency
(Agency) on August
31,
1984 filed its recoin—
mendation to grant the variance for eighteen months subject
to conditions0
Filed with the variance petition was a
motion
for expedited consideration which is granted0
BBCC
waived its
ri~ht
to
a
hearing and none was held0
No public cou~ments
in
opposition to BBCC’s request were received0
BBCC
is the owner/operator
of
a proposed surface coal
mining, processing and shipping complex which covers
portions
of 3,548 acres
in
Brown and Schuyler Counties0
BBCC has ap-
plied
to
the Illinois Department of Mines and Minerals
(XDMM)
for development
permits for the Cedar Creek Miner which is
expected to begin production approximately on January
1,
1985.
It will’employ 125 new employees and produce 700,000 clean
tons of bituminous coal
per
year
(Pet0
2,
4).
The mining
program will consist of developing structures to control
run-
off, clearing vegetation where necessary,
removing topsoil,
removin~jroot media where necessary,
and stockpiling soil
for
subsequent reclamation work.
The land will be graded
to
ap-
proximate the original contour.
Topsoil and root media will
be replaced and then revegetated
(Pet.
3).
The
mine itself
it composed of fifteen permit areas
which
are further composed of
twenty~five
subareas
(Pet.
17;
Attach.
1 Hydro. Map).
All
subareas are within a five mile
radius of
the processing complex.
No more than three subareas will
be
mined at a time
(Pet.
5).
The overburden covering the
coal
seam in
the
subareas varies
from twenty to seventy
feet.
The
coal seam is located at shallow depths
on high flat areas but
has been eroded away in the lowlands and ravines.
60437
The fifty~fivesedimentation ponds needed to control
TSS
runoff are located in ravines between steep slopes
(Pet.
12;
Ag.
Rec.
2,
3).
The shallow bedrock in the area has
contributed
to diffiqulties in deepening the ponds.
The ponds will
be built
as needed ar1d then reclaimed.
Associated diversion ditches
will
channel runoff to the ponds.
Detention time in fifty—three
of
the ponds ranges from l~9to 12.5 hours for runoff
from a ten
year twenty~fou~
hour storm event,
Two other ponds have six-
teen and twenty~twohour detention times.
Twenty foot
high
dams could be constructed but are not cost effective
or feasible
considering the short life of each mining subarea
(Pet.
10).
BBCC will have to obtain pond design approval in the
form of an
NPDES permit from the Agency.
In addition, BBCC proposes
to
monitor the discharge from the ponds and submit ~he data
to
the Agency.
BBCC claims that the environmental impact of granting
the
variance will be minimal and that the ponds will reduce the
sediment loading to the area streams
(Pet.
6).
However,
the
Agency contends that the claimed sediment reduction is
un-
founded because BBCC used the less restrictive federal set-
tleable solids standard rather than Illinois~TSS
standard
when initially designing the sediment ponds and determining
the stream sediment loading
(Ag. Rec.
2;
Pet., Attachs,
4,
2).
There is little valid data at this time to support
BBCC~sclaim
of reduced stream sediment loading.
Surface mining for coal in Illinois has traditionally
been
carried out on the flatlands.
The BBCC proposal to mine on
ridges is not often done in Illinois.
This mining project
will
give BECC and the Agency the opportunity to gather data on what
is essentially a new type of mining in Illinois.
The
proposed
sediment control measures can be considered experimental
and
should provide field data which will assist the state in
deciding
whether such projects should be encouraged in
the future.
During mining BBCC proposes, where possible,
to contempor—
aneous1~restore the approximate original contour of the land
by soil replacement andrevegetation
(Pet,
3)..
This contempor-
aneous restoration, combined with the short active life of
the
sedimentation ponds, estimated to be under three
years
(Pet.
8),
should minimize adverse environmental impact.
BBCC must show that compl!ance with the TSS
standard
would
impose an arbitrary or unreasonable hardship.
BBCC asserts
an
arbitrary or unreasonable hardship would exist if the
variance
were denied because the variance is necessary for Agency
issu
-
ance of the needed NPDES permit
(Pet.
14).
BBCC asserts
this
would force it to construct larger ponds which would be
either
unreasonably expensive and/or impossible
(id.)
due to the
unique topography of the land
(Pet.
15).
The only other option
would be not starting mining operations (Id.)~
The
Agency
asserts that BBCC knew of the strict Illinois TSS
standard
early in the permit application process
(Ag. Rec.
2),
BBcC,
however, contends in its motion for expedited decision that
it only recently became aware that a variance would be re-
quired.
Although BBCC has not included the planning and
design
costs of the project, to the Board it is evident
that
sub-
stantial amounts of time and money have been expended
given
the advanced state of the project and fact that BBCC
has a
contract to deliver coal from the mine.
The Board finds that even though the hardship is
to a
certain extent self~imposed,to deny BBCC a variance
would
impose an arbitrary or unreasonable hardship.
At this time,
there remains a question whether an economically
feasible
means of complying exists given the topography of the
area,
If the variance were not granted, hardship would
include loss
of the substantial amount of money already expended,
the ter-
mination of the mining project, and the loss of
the value of
contracts to furnish coal.
The Board notes that this
project
will have minimal adverse environmental impact
and will pro-
vide data
on
the impact of
a
mining method new
to Illinois.
By limiting the period of variance to eighteen
months and
requiring BBCC, inter alia, to monitor its mine
discharges,
the Board allows collection of necessary data on
sediment
loading and pond efficiency while maintaining controls to
minimize adverse environmental effect.
The Agency has some concerns which it believes can be
addressed by granting the variance for eighteen
months and
requiring additional collection of data.
Soil
boring and
bedrock elevation data would be used to determine whether
ponds could be enlarged by excavating behind the dams,
Data
on the use of flocculating agents to aid in
sediment control
would also be
required.
The Board will impose
these require-
ments as conditions to the grant of this variance.
Black Beauty Coal Company is granted a variance
from
the
total suspended solids effluent standard of
35
Ill.
Adm. Code
406.106 for a period of eighteen months for its~da~?re~
Mine subject to the conditions below.
Although the
Agency
claims that BBCC may exceed the total iron mining
effluent
standard
(Ag. Rec.
2).
BBCC has not requested variance
from
this standard.
This Opinion constitutes the Board~sfindings of
fact and
conclusions of law in this matter.
4
ORDER
Black Beauty
Coal
Company
is hereby granted a variance
from the total suspended solids effluent standard of 35
lii.
Ada. Code 406.106 for its Cedar Creek Mine in Brown
and
Schuyler Counties, Illinois, subject to the following con-
ditions:
1.
This variance expires on March 20, 1986.
2.
This variance is only to apply to the first set
of sediment ponds necessary to start this mining
operation
(an estimated 6 to 10 ponds)
and
only
for the life of those ponds.
No additional ponds
are to be installed under this variance
beyond
March 20, 1986
and
no pond enlargement to ac-
comodate expanded mining operations is to occur
after initial pond installation.
3.
Petitioner is to implement an intensive sampling
program,
after
consultation
with
the
Agency,
sufficient
to
determine
the
efficiency
of
the
first
set
of
ponds.
This
program
is
to
be
car-
ried out by Petitioner during the variance
period,
with
the
results
submitted to
the
Agency
as they are obtained.
4.
Petitioner is to implement a program, after con-
sultation with the Agency, for adding flocculating
agents to the ponds sufficient to
aid
in sediment
control.
5.
Any
further request
for
variance
submitted
by
Petitioner is to include results of the sampling
program described above, as well as evidence, in-
cluding soil borings and bedrock elevations, to
show
if
the
balance
of
the
ponds
can
be
enlarged
by
such
means
as
excavating
deeper
behind
the
dams.
6.
Within forty-five days of the adoption of the Board
Order in this proceeding, Petitioner shall execute
and forward to the Illinois Environmental. Protection
Agency, Mine Pollution Control Program, 2200 ChurchUt
Road, Springfield, Illinois
62706, a Certificate
of
Acceptance
and
Agreement
to
be
bound
by
all
terms
and
conditions
of
this
variance.
This
forty—five
day
period
shall
be
held
in
abeyance
for
any
period
this
matter
is
being
appealed.
The
form
of
the
certificate
shall
be
as
follows:
5
CERTIFICATE
I,
(We).
___
___
____
___
hereby accept(s)
and
agree(s) t~S
bound
by
all
terms and conditions
o~the
Order of
the Pollution Control Board
in PCB 84-109, dated Sep-
tember
,
1984.
Petitioner
By;
Authorized Agent
Title
Date
IT IS
SO ORDERED.
I,
Dorothy M. Gunn, Clerk of the Illinois
Pollution Control
Board, hereby certify that~,the above
Opinion and Order was adopted
on the
~
day
of ~
1984 by a vote of
-
~‘C,
)7~.
~
Dorothy M, ,tunn, Clerk
Illinois
Pollution Control Board