1. rule with the Secretary of State:

ILLINOIS POLLUTION CONTROL
BOARD
December 20,
1984
IN THE MATTER OF:
CORNELL FORCE, HAMPSHIRE DIVISION
)
R83-26
PETITION FOR A SITE-SPECIFIC
OPERATIONAL LEVEL PURSUANT TO
CHAPTER 8,
RULE 206(d)
OF THE
)
RULE AND REGULATIONS OF THE
ILLINOIS POLLUTION CONTROL BOARD
ADOPTED RULE.
FINAL OPINION
AND
ORDER.
OPINION AND ORDER OF THE BOARD
(by B.
Forcade):
On August
2,
1984,
the Board proposed to adopt a new rule,
35
Iii. Adm. code 901,115, which provides site-specific relief
from the Board’s noise regulations.
First notice
of this proposal
was piblished at 8
Iii.
Reg.
15274,
on August 24, i984~ The first
notice comment period expired on October
8, 1984.
The Administrative
Code
Unit
submitted
a comment
on
September 10,
1984, regarding
Illinois
Register
first notice format.
No other comments were
received.
The
Board
made
a
non-substantive
change
in the wording
of
tI’e
proposed
rule.
By
order
of
the
Board
dated October 10,
1984,
the proposed
rule
was
submitted
to
the Joint Committee
on Administrative Rules
(“JCAR”).
JCAR
second
notice
review
commenced
on October 22,
1984.
JCAR
issued
a
Certification
of
No
Objection
to
this
rulemaking on
November
8,
1984,
ending
the second notice
period,
This
matter
comes
before the Board on
a petition filed
on
November
15,
1983,
by Cornell
Forge,
Hampshire Division (“Cornell”),
for
a site—specific operational
level
for its forging shop as
an
alternative
to
compliance
with
the noise limits contained
in 35
Ill.
Adm.
code
901.105
(old
Rule
206
of
Chapter
8)~,
A
public
hearing
was
held
on
March
29,
1984,
in
Hampshire,
I1:iinois.
Two
members
of
the
piblic,
Robert
Kudlicki,
the
village president and
Frederick
G.
Modde,
the
township supervisor,
testified
in
support
of
the
petition.
No other piblic testimony
or
comments
were
received.
The
Board
appreciates
the contribution of David
G~Mueller
who
assisted
in
drafting this Opinion.

2
The
Department
of
Energy
and
Natural
Resources
Y~DENP~)
issued
a
statement
of
negative
declaration
oi
economic
impact on
April
19,
1984,
obviating
the
need
for
an
economic
impact
state-
ment.
On
July
18,
1984,
the
Economic
and
Technical
Advisory
Committee
concurred
with
the DENR’s finding,
The
regulatory
scheme
for
existing
forging
operations requires
that the Petitioner either
(1) comply with the noise prohibitions
contained
in Table
F of Rule 206(c)
no later
than fifteen months
following the effective date of the Rule,
or
(ii)
seek
a permanent
site-specific operational level
as provided in Rule 206(d),
These rules have been recodified as 35 Ill~Mm,
Code 901,905(c)
and
(d).
The noise prohibitions in §901.905(c) vary for different
classes of receivers and for daytime and nighttime periods,
z~
petition under §901.905(d)
must demonstrate that it is technically
and economically infeasible
for
its shop to meet the numercial
limits of §901.905(c).
A petition must also propose measures to
reduce impilsive noise where possible and assess the consequential
health and welfare impacts on the surrounding commcnity~
Cornell
is located on Walker Road
in Hampshire,
Illinois,
Cornell’s operation occupies six acres and is surrounded on
all
four sides by land zoned
for farming.
The sole noise receiver is
a farmhouse located approximately 1,000 feet northeast of the
Cornell
facility (R. 25).
The farmhouse is
a Class A receiver,
The Cornell
facility was built in 1953 and has beeh in operation
since that time
(R. 25).
The facility consists of three
one-story
buildings.
The forging hammers and furnaces are located in
a
single one-story building that runs north and south of the
property.
The building’s lower levels are composed principai:Iy of
a structural
frame with sheet steel
sides.
The roof is made entirely of sheet
steel.
The
sheet
steel
sides open like garage doors
arid the roof
also can be
opened
(R.
36).
The building houses
seven impact
forge hammers and seven furnaces,
There
are two
I ~50O :b~, hammers
and five 2,000 lbs. hammers
(R. 28).
Cornell
eurrentdLv employs
28 people at its Hampshire facility (R.
41).
The forging process consists of heating cari~onor al~Ioy
steel
in furnaces to approximately 2350 degrees
Fahrenheit.
arid
then forcing the heated pieces between two dies~
The upper die
is attached to a guided
rain and the lower
die
is attached to the
forge.
The metal
is shaped through pressure exerted by the ram
or
forge hammer,
forcing the workpiece into the impression
on the
dies.
The sound produced through this process~is :Lm~uisiveand
originates primarily from the impact between the upper
and lower
die and the workpiece.
There is a constant flow of materials
between the furnace,
forge,
and cooling area
(R~. 49).
Cornell
forges golf club irons and various commercial
and industrial
parts
(R.
33).
The nature of the forge operation creates an extremely hot
work environment.
The furnaces require
a tremendous amount of
oxygen and emit a great deal
of
heat.
The cooling workpieces

3
~
so
radiate
heat
into
the
forge
shop.
Consequently,
the
shop
requires
extensive
ventilation
which
is
provided by the garage-
type
side
doors
and
the
ability
of
the
roof
to open.
This system
creates
a
“stack
effect”
whereby
air
flows
through the open
sides
of
the
building
and
is
drawn
up
and
out
through the roof
(R.
67-68).
This natural ventilation system is effective and
widely
utilized
by
the
forging
industry.
The
open
sides of the building
also
facilitate
the
free
movement
of
material
in and out of
the
forge
shop.
Noise escapes through these
roof
and side
openings
(R. 68).
Cornell currently operates from
7:00
a,m,
to 4:30 p.m.,
five
days
per
week
with
daily
and
Saturday
overtime,
Historically,
Cornell has
operated
two shifts from 7:00
a,m,
to 12:00 p.m.
The
Petitioner,
in a post—hearing submittal,
requests
a site-specific
level
that would allow them to operate no
more than seven hammers
at any one time for
a maximum period of 17
hours per day, Monday
through Saturday.
Petitioner proposes to
operate
in two shifts;
one from
7 a.m.
to 3:30 p.m.
and
the other
on
an alternating
basis, either from 3:30 to 12:00 midnight
or from 10:30 p.m.
to 7:00
a.m.
Cornell’s president testified that
the company could
sig-
nificantly reduce its electricity bill
if
it were allowed to
operate a nighttime shift.
Cost savings would
amount to 80
of
Cornell’s $60,000 to $65,000 annual
demand
charge
for electricity
(R.
53).
Production has fluctuated over the last
few years.
Production
levels have declined slightly
since 1981 as
is shown by the
table below.
The volume of production in 1983 is expected
to be
the
same
as
in
1982.
Total
No,
of Forgings
No,
of
Tonnage
of
all
on hammers
-
1980
3,133,000
13,158,000
1,005
1981
3,426,000
14,388,000
1,123
1982
3,352,000
14,079,000
1,011
The
regulations
of
the
Board
define
two methods
of measuring
sound.
The
definition
of dB(A),
or A
weighted sound in decibels,
is
found
in
35
Ill,
Adm.
Code 900.101,
as
is the definition of
Leg,
or
equivalent
continuous
sound
pressure
level
in decibels,
Essentially,
dB(A)
measures
the
noise
level
at
the peaks while
Leg
measures
the
average
noise
level
over
time,
including
peaks
and
background
noise,
Permissible impilsive
sound
levels
for
existing
forge
shops
are found
in
35
Ill.
Adm, Code 901,105.
The
impulsive sound
level emitted to residences (Class A-land)
cannot exceed 58.5
Leg, during the day or 53.5 Leg at night.
Actual measurements
of
sound were taken around
the
Cornell
facility by George
F.
Kamperman,
an
expert
in
the
area
of
noise-control
engineering.
Based on
these measurements, Kamperman predicted that the highest level
at
the
nearest
receiver
would
be
approximately
62 Leg (R,
72),
This
62-45

4
receiver,
the
farmhouse,
is
the
only
relevant
noise
receiver
in
terms
of the regulations.
But for the existence
of this farmhouse,
no petition
for site—specific relief would be reouired,
No
citizen complaints have
been
received
about
the noise
from
Cornell’s
facility
(R. 46).
Cornell
has investigated several methods of compliance with
the
Board’s noise regulations.
Cornell’s consultant and expert
witness testified that the most economical
and efficient method
of compliance would require closing
all roof vents,
rebuilding
the north entrance of the building to make
a sound lock-type
vestibule, replacing the present fiberglass
wall
panels
with
more
substantial glass or cement asbestos board,
and
sealing
the
roof
vent system with thick cement asbestos board.
A
mechanical
ventilation
system would then have
to
be
installed
to
exhaust
the
heated
air
from
the
building
(R.
47-48).
These
modifications
would
result
in
an
approximate
10dB
reduction
(R. 97)
and would
achieve
compliance
with
the
regulations.
The
capital cost for
these modifications are $225,000.
The building itself would
require structural
strengthening to support the new vent system
and
roof silencers at
a cost of $88,000.
Electric power
for the
new vent system would cost $14,000
for one
year
(Ri. 99—100).
Cornell’s expert testified that other types of control methods
such as external grade-level
sound barriers would be acoustically
ineffective
and would impede the flow of materials into the forge
shop
(R
69—70).
The
proposed
changes
also
affect
the
flow
of
materials
and
would
create
an
undesirable
“closed-in”
feeling
for
the employees (P97-98).
Cornell has not implemented any control measures at this
time.
Cornell’s president testified that denial
of
site-specific
relief would not result in the immediate closing
of
the
Hampshire
facility.
Eventually,
however, the facility would he phased out
of operation
(R. 54).
The Illinois Environmental Protection Agency (“Agency9),
in
their written comments on the proposal
filed January 18,
1984,
did not challenge Cornell’s qualification for site-specific
relief on the basis that it is an “existing impact
forging
aer-
ation,” nor did they question the fact that the
Petitioner
was
violating
Rule
206(c).
The
Agency
stated
that
while
technolog-
ically
feasible
noise
reduction
measures
existed
for
forge
shops,
these
measures
were
not
technically
feasible
or
economically
reasonable
for
Cornell.
The
Agency
also
stated
that
granting
the
proposal
site-specific
operational
level
would
not endanger the
hearing
of
area
residents.
The
Board
will
grant
the
site-specific
operational
level
requested
by
Cornell.
Cornell
is
an
existing
impact
forging
operation
which
is
presently
in
violation
of
901,105(c).
While
compliance
is
technically
possible,
its
extremely
high cost
makes
it
economically
unreasonable
for
Cornell
at
this
time,
On
a
practical
level, compliance measures would decrease production by
impeding the flow of materials within the forge
shop,
create
an
62-46

5
unacceptable work environment for the employees and
result
in
the
eventual closing
of the facility.
The record
indicates
that
there have been no citizen complaints about the
noise
from
the
forging operation and that there
is no danger
of
hearing loss to
area residents.
The site-specific operational
level will be
limited to seven hammers that may operate a total
of 17 hours
per
day,
Monday
through
Saturday.
Two
shifts
will be allowed;
one
from
7:00
a.m.
to
3:30
p.m.
and
the
other
from
either
3:30
to
12:00
midnight
or
from
10:30
to
7:00
a,m,
No
specific
numerical
noise
level
limitations are
being
imposed,
although
it
is
assumed
that
noise
levels
will
approximate
those testified to by Cornell
and its witness.
Cornell
should
make
efforts
to
lessen
noise
levels
in
the
future
as
equipment
is
replaced and new technology for
noise
suppression becomes available.
In
the
event
that
noise
levels from the forge shop
become
excessive,
citizens have the right to initiate proceedings to change the
rule which accompanies this opinion.
The operational plan set out
in this Order will
be incor-
porated into 35
Ill,
Adm,
Code 901.115.
Cornell will
be required
to
comply
upon
the
filing
of the rule with the Secretary of State
of
Illinois.
ORD ER
The Board hereby adopts
the following rule, to be codified
as 35
Ill.
Adm, Code 901.115,
and instructs the Clerk to file
this
rule with the Secretary of State:
TITLE 35:
ENVIRONMENTAL PROTECTION
SUBTITLE
H:
NOISE
CHAPTER
I:
POLLUTION CONTROL
BOARD
PART 901
SOUND ~4ISSION STANDARDS AND LIMITATIONS
FOR PROPERTY LINE-NOISE-SOURCES
Section
901
.
115
~
~Level
llFor~,j!arn~hireDivisionandfutureownersofthe
~~n~cilitl
ocatedat~~o~,Hamshir~Il1inois,
shall ~
level:
a)
~
~y~one
time;
and
~
~
~hSathrdabetweenthehoursof7:00a,m.
~30
,m,
wi
th an
additional
S
hift
that
ma
her
3: 30
,
m.
to 12: 00
m.
or
fr om
~0,m.to7:00a.m,
62-47

6
IT
IS
SO
ORDERED.
I, Dorothy M. Gunn,
Clerk of the Illinois Pollution Control
nion and
Order
was
adopted
Board,
hereby certify t
on the
~
day
of
~~bove~pi
,
1984
by
a
vote
of
.
Dorothy M.
~nn,
Clerk
Illinois Poilution Control
Board
R2~.4R

Back to top