1. as recommended.
    2.  

ILLINOIS POLLUTION CONTROL
BOARD
April
18, 1985
CIT~COF O’FALLOL
)
)
Petitioner,
)
PCB 85—48
itd~INOtSENVIRONMENTAL
)
PROTECTION AGENCY,
)
Respondent.
3PINION
AND
ORDER OF THE BOARD
(by J.D. Dumelle):
This provisional variance request comes before
the Board
upon an April
18, 1985 Recommendation of the Illinois Environ-
mental Protection Agency (Agency).*
The Agency recommends that a
45—day provisional variance be granted to the City of O’Fallon
(City) from 35
Ill. Adm.
Code 304.141(a)
to allow removal from
service for repair
and maintenance of
one of
its
wastewater
treatment facility’s two package contact stabilization units, and
to allow the Petitioner
to exceed
its interim NPDES Permit
effluent limitations during the period that the unit
is out of
service,
The
Petitioner was previously granted
a pro~visiona1
variance
in PCB 84—148
(see:
City of O~Fal1onv.
IEPA,
PCB 84—148, Opinion and Order of September
20,
1984),
The
City
of O’Fal~on owns and operates a wastewater treat—
ment facility which includes two 1.5 million gallon
per day
(MGD)
package contact stabilization units followed by a lagoon
system.
Effluent from this facility
is
discharged
to
Silver
Creek pursuant to NPDES Permit No.
1L0021636,
(Rec,
i)*
During September of
1984,
the Petitioner
awarded
a contract
for painting one of
its
stabilization
units
and
subsequently
finisI~edrepair and maintenance work
which
included
the draining
and cleaning of the tank and the
installation
of
new
diffusers
and air drop pipes.
However, weather conditions
were
not
suitab~efor the requisite painting work at
that
time.
To clean
the
tank in preparation for the necessary painting, the
Petitioner wishes to remove the stabilization unit
from
operation
on
May
1,
1985 and anticipates that the painting contractor will
complete the appropriate work by June
15, l985~~ (See:
letter
from City Engineer David J.
Davis to Agency dated April
5,
1985.)
*On April
18,
1985,
the Agency filed
an ~mendment to
the
Agency Recommendation which added
the Agencyes
finding
of~
arbitrary or unreasonable hardship,
83-511

—2—
The Petitioner’s NPDES Permit provides that the City’s
wastewater treatment facilities must meet effluent limitations of
30 mg/i for both BOD and suspended solids,
The
following table
summarizes the relevant information obtained from the
Petitioner’s discharge monitoring reports
to the Agency
pertaining to SOD and suspended solids levels during
the past
year:
Month
Flow
(M~)
B~X~
(n~/l)
55
(i~q/l)
March,
1984
2.8
53
154
April
2.7
81
37
May
1.3
47
30
June
1.3
26
36
July
0.4
32
57
August
1.4
13
29
September
1.1
15
45
October
1.1
13
33
November
2.0
14
21
December
2,0
14
21
January, 1985
1~6
11
18
February
2.6
6
9
Average
1.7
27
41
(See:
Rec.
2)
Although the City of O’Fallon did not request specific
effluent limitations for
the time period of
its requested
provisional
variance,
the
Agency
has
recommended
that effluent
limits of 40 mg/i SOD and 65 mg/i suspended solids are reasonable
and appropriate based on the pre’~,iouslydelineated data derived
from
the
Petitioner’s
discharge
monitoring
reports.
(Rec.
2).
The Petitioner has indicated to the Agency that it wishes to
atart draining the package contact stabilization unit
to be
worked on
in
the
very near future (i.e.,
on May 1,
1985).
The
City intends to complete the necessary repair
and maintenance
work
on
the
stabilization unit and return
it to service by
June 15, 1985.
(Rec.
2).
The Petitioner anticipates that this
repair
and
maintenance
work
will
include
cleaning,
sand
blasting,
and
painting
the
tank.
(Rec,
2).
According to Agency field personnel, the line from the
Petitioner’s activated sludge units to the lagoon cannot handle
the flow during periods of high influent flows,
thereby causing
the flow to backup and flow over the tops of the activated sludge
units.
(Rec.
2).
Although
the Petitioner did not address this
potential problem in its provisional varianca request,
the Agency
has recommended that this line from the activated sludge units to
the lagoon be inspected and,
if necessary,
rodded out to avoid
environmental problems.
(Rec.
2).
The Board agrees with the
Agency’s assessment of this situation, and will mandate that this
corrective action be taken,
63-512

—3—
The Agency has agreed with the Petitioner that the
maintenance of the contact stabilization unit
is
necessary and
believes that there
is no practical alternative to taking the
unit out of service
to perform the requisite repairs and
maintenance.
(Rec.
3).
Moreover, the Agency has concluded that
the
environmental impact on Silver Creek caused by one
stabilization unit being out of service will
be minimal,
since
the
other lagoons will remain available during the time period
that one of the units
is being repaired.
(Rec.
3).
The Petitioner has asserted that an unreasonable hardship
(due to the ultimate cost of
a new treatment
unit
to replace the
present one) would result
if the necessary repair and maintenance
work
to the contact stabilization unit is not performed.
The
Agency agrees with the Petitioner’s contention
in regard to such
hardship and notes that “failure to maintain the contact
stabilization unit would accelerate deterioration of this
unit”.
(See:
April
18, 1985 Amendment to the Agency
Recommendation).
Accordingly, the Agency has concluded that compliance
on a
short—term basis with the provisions
of
35 Ill. Mm. Code
304.141(a) would impose an arbitrary or unreasonable hardship
upon
the Petitioner.
Therefore, the Agency recommends that the
Board grant
the City of O’Fallon a provisional variance from
Section 304141(a) for
a period of 45 days,
subject to certain
conditions.
Pursuant to Section 35(b)
of the Illinois Environmental
Protection Act, the Board hereby grants
the provisional variance
as
recommended.
This Opinion constitutes the Board’s findings of fact and
conclusions
of law in this matter,
ORDER
The City of O’Fallon is hereby granted
a provisional
variance
from 35
Ill. Mm. Code 304.141(a), subject
to the
following conditions:
1.
This provisional variance shall commence
on May 1,
1985
and shall continue for
45 days,
or until the Petitioner’s contact
stabilization unit
is returned to service, whichever occurs
first.
2.
During
the period of this provisional variance, the
effluent discharged shall be limited
to
40 mg/i BOD and 65 mg/i
suspended solids.
3.
The Petitioner
shall sample
and perform laboratory
analyses as required
in its NPDES Permit No.
1L0021636.
83-513

—4—
4,
The Petitioner
shall notify Mr. Michael Severns of the
Agency’s Compliance Assurance Section via
telephone at
217/782—9720 when dewatering
of the contact stabilization unit
is
begun; when painting and repair work
is begun;
and when the unit
is returned to service,
Written notification confirming the
telephone notification shall be submitted within
5 days
thereof.
This written notification shall
be submitted
to:
Mr. Michael Severns
Illinois Environmental Protection Agency
Division of Water Pollution Control
Compliance Assurance Section
2200 Churchill Road
Springfield,
Illinois
62706
5.
The Petitioner
shall inspect
the line between the
activated sludge units and the lagoon and,
if possible,
shall
perform all necessary maintenance and/or repairs
to
this line
during the provisional variance period
to alleviate the flow
backage during periods of high influent fiows.~
6.
The Petitioner
shall operate and
maintain
the
wastewater treatment facility so as to produce
the
best effluent
practicable.
7.
Within
10 days of the date
of
the Board’s Order,
the
Petitioner shall execute
a Certificate
of Acceptance and
Agreement which
shall be sent
to Mr. 3ames Frost of the Agency at
the address specified
in condition 4,
above, of this Order.
This certification shall have the following form:
I,
(We) ______________________________
___,
having read
the Order
of the Illinois Pollution Control Board
in PCB 85—48
dated April
18,
1985,
understand and accept said Order,
realizing
that such acceptance renders all terms and conditions thereto
binding and enforceable~,
Petitioner
By:
Authorized Agent
Title
Date
83~514

—5—
IT IS SO ORDERED.
I, Dorothy M.
Gunn, Clerk of the Illinois Pollution Control
Boards
hereby
certify
that
the
above
0 iniori and Order was
adopted on the
/~
day of
______________,
1985 by
a vote
of4-O
~
Dorothy M. Gunn~Clerk
Illinois Pollution Control Board
63415

Back to top