ILLINOIS POLLUTION CONTROL BOARD
    May 16, 1985
    VILLAGE OF ENERGY AND WILLIAMSON
    )
    COUNTY HOUSING AUTHORITY,
    Petitioners,
    v,
    )
    PCB 84—123
    ILLINOIS ENVIRONMEI~TALPROTECTION
    AGENCY,
    Respondent.
    OPINION AND ORDER OF THE BOARD (by ~J.Marlin):
    This matter comes before the Board upon the August 10, 1984
    filing of a variance petition by the Village of Energy (Village)
    for relief from 35 Ill. Adm. Code 309.241(a) to permit the
    Williamson County Housing Authority (Authority) to connect a 30
    unit housing complex for elderly and disabled people to the
    Village’s organically overloaded sewer system, which was placed
    on restricted status on May 8, 1980. In an August 22, 1984
    Order, the Board joined the Authority as a necessary party and
    requested additional information. The Village submitted more
    information on October 1, 1984 while the respondent Agency filed
    a motion to dismiss on November 7, 1984. The Board denied the
    motion on November 8, 1984 and ordered the Village to cure all of
    the deficiencies noted in the August 22 Board Order within 45
    days. An amended petition was filed on February 19, 1985 by the
    Village and the Authority. On April 18, 1985, the Board granted
    the Agency’s motion to file its recommendation instanter. The
    Agency recommends denial of the requested variance. Hearing was
    waived and none was held.
    The Authority is constructing a 30 unit housing development
    for the elderly and/or handicapped which consists of twenty one—
    bedroom units, ten two—bedroom units, and a laundry room. The
    development is located on East College Street in Energy,
    Williamson County, Illinois. An eight inch sanitary sewer
    conveyance system.is needed to connect to the Village’s eight
    inch sanitary sewer system. A maximum of 60 people is expected
    and the wastewater flow, at 100 gallons per person per day, would
    not exceed 6,000 gallons daily average.
    The Authority applied for and received a U.S. Department of
    Housing and Urban Development (HUD) grant for the Village of
    Energy housing project. No information has been submitted on the
    amount of the grant or whether there is a threat of losing this
    grant.
    64-57

    2
    The Village operates a waste water treatment plant (WWTP)
    which consists of a single cell lagoon treatment system under
    NPDES Permit No. 1L0023566, issued March 30, 1984. The WWTP has
    a design average flow (DAF) of 0.10 million gallons per day (MGD)
    and a design maximum flow (DMF) of 0.25 MGD. The design organic
    load capacity of the WWTP is 1,000 population equivalents (PE).
    The order of discharge from the village lagoon is to several
    stripmine lakes, to Hurricane Creek, and finally to the Big Muddy
    River.
    The present facility is organically overloaded. Agency data
    from 1980 shows that the organic loading to the facility is 1,181
    PE for biochemical oxygen demand (BOD) and 1,262 PE for suspended
    solids (SS) (Pet,, IEPA itr). The present interim permit limits
    for BOD and SS are 50 mg/i and 60 mg/i respectively. The Village
    plans to upgrade the DAF to 0,157 MGD (1570 PE) and the DMF to
    0.628 £IGD. Once the upgrading is complete, the final permit
    limits will be 30 mg/i BOD and 37 mg/i SS, based on a three—stage
    lagoon exemption. The amended Facilities Plan provided for
    expanding the existing single cell lagoon to a two cell lagoon
    with ultra—violet light disinfectant facilities. However, as the
    Agency notes, the amended Facilities Plan is now deficient and
    will not qualify for Innovative and Alternative (I/A) grant
    funding (Ag. Rec. 3). An agreement to construct spray irrigation
    facilities on a local golf course was not reached (Id.). The
    Village has asked the Agency to reconsider its old facility plan,
    for which there is no funding availabie. While the record makes
    clear the Village’s intention to upgrade its WWTP and come into
    compliance by July 1, 1988, there is no firm compliance plan
    schedule.
    The Authority has identified and priced two alternative
    plans to treat on—site the wastewater from the housing project if
    variance is denied and until the restricted status designation is
    removed from the village treatment facilities. The first is a
    series of septic tanks, a sand filter and chlorination equipment
    for temporary treatment. The cost is approximately $36,900 pius
    $1,000 annual maintenance cost (2/19/85 Pet,). The second plan
    consists of installation of concrete holding tanks and the daily
    hauling of the wastewater to other permanent treatment
    facilities. The estimated cost is $225 per day or $82,000 per
    year (Id.).
    In order to reduce water usage at the housing project, the
    Authority is requiring water misers in the water closets and flow
    restrictors in the shower heads.
    Petitioners did not address the environmental impact to the
    waterways but only furnished data estimating the contribution of
    60 PE to the village treatment facilities, The Agency states
    that the present high BOD and SS discharges will overload the
    stripmine lakes with nutrients which in turn will limit the
    quality of Hurricane Creek (Ag. Rec. 8). The Agency furnished
    data from 1981 on the effluent being colored pea green to light
    64-58

    3
    brown, clarity as being cloudy to cloudy with visible solids, and
    odor being foul to slight (Id.)~
    HARDSHIP
    Petitioners must show that compliance with the Board’s rules
    and regulations would impose an arbitrary or unreasonable
    hardship~ Ill, Rev. Stat, 1983, ch~ill
    1y~
    oar, 1035. The
    Authority be~anthe HUD grant process for fac~1ities in the
    County in ~
    However, the application for the Village units
    was filed 11! February of 1981 and was the last one acted on by
    HUD, Re:~: ted status was imposed by the Agency in 1~8U, The
    Agency s~r~~ letter to the Village informing it of this fact on
    May 8, 1~4~:iAttach. to Pet.), The Agency states that it gave
    notice of ~TeStricted status in the Board~s Environmental Register
    #245 as early as October 6, 1981 (Age. Rec, 4)~ Notice was
    repeated on a quarterly basis up to the present time (Id.). Site
    acqUisit.iC)fl for the housing project was completed on June 1,
    1983, The Village and the Authority applied for a construction
    permit on April 4, 1984 which was denied on April. 24, 1984 (Ag.
    Rec. 5). The denial letter informed the petitioners that the
    village facilities were on restricted status (Ag. Rec. Exh, B),
    The denial letter also informed petitioners of the availability
    of a conditional installation permit to allow simultaneous
    construction of the project with the treatment facility
    upgradi!ng, yet no application was
    submitted
    •~d.) The Authority
    decided to proceed without a construction permit and with
    knowledge of restricted status,
    The
    executive director of the
    Authority claims that he did not know of the imposition of
    restricted status until the summer of 1984, by which time
    construction contracts had
    already been awarded (Young Affid,,
    attach to 2/19/85 Pete), The petitioners have not submitted to
    the Board information on what date(s)
    construction contracts were
    awarded. Meanwhile, an
    Agency inspector discovered unpermitted
    construction
    in progress on October
    :3.?
    1984 (hg. Rec. 5).
    Petitioners
    allege hardship because of four reasons (Pet,
    4). They allege that the Authority did not
    know about restricted
    status prior to site acquisition, “lann:ing” and financial
    arrangements While this may be
    true, it is clear that the
    Village knew. That this situation may
    not have been
    discovered
    by or relayed to the Authority is not sufficient
    grounds to grant
    a variance. Most construction projects of this type require
    sewer permits and the Authority should have checked into this
    matter, Any hardship resulting from this oversight is a self—
    imposed hardship. Petitioners next allege that they are trying
    t~fill a void in the elder:Ly housing market~ yet petitioners do
    not
    argue that
    denia:L of variance will cancel their plans.
    Thirdly, they
    argue that significant adc~.t~.onalenvironmental
    impacts will not occur, yet fail
    to supoort
    ~.hio conclusory
    statement,
    Indeed,
    based
    on the data lithe
    record, the Board
    finds that the environmental ilnDact on ~te receiving waterways
    would like~y ~e adversely affected by print, of
    var:Lance.
    Fourthiy~ i,;,~tioners allege that hiphet
    utt~e costs will result
    64-59

    because the
    Authority would have to provide on—site treatment,
    This most likely is a true statement, but economic grounds
    alone
    are
    insufficient to support a variance request. The Board
    also
    notes that the cost of on~sitetreatment does not appear
    to be
    prohibitive. Lastly, while petitioners state that they are
    trying to
    fill a
    void in
    elderly housing, they conclusorily
    allege
    that permanent financing of the housing project could
    be
    lost and fail to provide any support for the statement,
    The Board has granted prior variances where the need for
    public housing has outweighed the adverse environmental impact of
    adding to the sewage load of the existing treatment facility,
    Herr in and Hous in Aut horit
    of Count of Willia
    ms on v
    IEPA,
    57 PCB 341, (PCB 83~-l69, April 5, 1984); Ci~~2n
    ~
    49 PCB 419 (PCB 80-
    163, February 5, 1981); ~
    al. v, IEPA, 39 PCB 285 (PCB 80-~83, August 7, 1980). However,
    the
    petitioners in these cases had all started substantial
    project
    planning before imposition of restricted status and were
    in jeopardy of losing federal assistance if variance was
    denied.
    Contra,
    see ~
    43 PCB 299 (PCB 8F-67, September 3, 1981),
    The Board has denied variance in similar cases where the
    petitioner should have known about the imposition of restricted
    status, substantial planning was not started until after its
    imposition,
    and
    there
    was no evidence of loss of federal
    assistance.~
    ~
    al. v, IEPA~,, 59 PCB 263 (PCB 84~32, August 2, 1984), Herein,
    restricted ~tatus was imposed in May of 1980, While the housing
    project
    may~have been in the preliminary planning stages, no
    substantial~planning had taken place. This conclusion is
    supported b~’ the lack of a submittal of a HUD grant application
    by the Authority until 9 months after imposition of restricted
    status
    (Young Ltr, attach, to 10/1/84 Pet,), Furthermore, site
    acquisition was not until three years after its imposition. The
    Agency attempted to guide the petitioners by informing them
    of
    the availability of a conditional installation permit, yet
    petitioners ignored the suggestion and failed to submit an
    application.
    The Board finds that denial of the variance would not impose
    an arbitrary or unreasonable hardship, in any event, any
    economic impact does not outweigh the adverse environmental
    effect
    of adding further discharge to an already overburdened
    treatment
    facility and likely adverse effect on the receiving
    waterways.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter,
    64-80

    5
    ORDER
    The Village of Energy and Williamson County Housing
    Authority are hereby denied variance from 35 Ill. Adm. Code
    309. 241.
    IT IS SO ORDERED,
    I, Dorothy ~ Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Opinion and Order was
    adopted on the
    ~
    day of
    ____________________,
    1985
    by a vote of
    (~—o
    .
    Dorothy M. dunn, Clerk
    Illinois Pollution Control Board
    64-61

    Back to top