ILLINOIS POLLUTION CONTROL BOARD
May 16, 1985
VILLAGE OF ENERGY AND WILLIAMSON
)
COUNTY HOUSING AUTHORITY,
Petitioners,
v,
)
PCB 84—123
ILLINOIS ENVIRONMEI~TALPROTECTION
AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD (by ~J.Marlin):
This matter comes before the Board upon the August 10, 1984
filing of a variance petition by the Village of Energy (Village)
for relief from 35 Ill. Adm. Code 309.241(a) to permit the
Williamson County Housing Authority (Authority) to connect a 30
unit housing complex for elderly and disabled people to the
Village’s organically overloaded sewer system, which was placed
on restricted status on May 8, 1980. In an August 22, 1984
Order, the Board joined the Authority as a necessary party and
requested additional information. The Village submitted more
information on October 1, 1984 while the respondent Agency filed
a motion to dismiss on November 7, 1984. The Board denied the
motion on November 8, 1984 and ordered the Village to cure all of
the deficiencies noted in the August 22 Board Order within 45
days. An amended petition was filed on February 19, 1985 by the
Village and the Authority. On April 18, 1985, the Board granted
the Agency’s motion to file its recommendation instanter. The
Agency recommends denial of the requested variance. Hearing was
waived and none was held.
The Authority is constructing a 30 unit housing development
for the elderly and/or handicapped which consists of twenty one—
bedroom units, ten two—bedroom units, and a laundry room. The
development is located on East College Street in Energy,
Williamson County, Illinois. An eight inch sanitary sewer
conveyance system.is needed to connect to the Village’s eight
inch sanitary sewer system. A maximum of 60 people is expected
and the wastewater flow, at 100 gallons per person per day, would
not exceed 6,000 gallons daily average.
The Authority applied for and received a U.S. Department of
Housing and Urban Development (HUD) grant for the Village of
Energy housing project. No information has been submitted on the
amount of the grant or whether there is a threat of losing this
grant.
64-57
2
The Village operates a waste water treatment plant (WWTP)
which consists of a single cell lagoon treatment system under
NPDES Permit No. 1L0023566, issued March 30, 1984. The WWTP has
a design average flow (DAF) of 0.10 million gallons per day (MGD)
and a design maximum flow (DMF) of 0.25 MGD. The design organic
load capacity of the WWTP is 1,000 population equivalents (PE).
The order of discharge from the village lagoon is to several
stripmine lakes, to Hurricane Creek, and finally to the Big Muddy
River.
The present facility is organically overloaded. Agency data
from 1980 shows that the organic loading to the facility is 1,181
PE for biochemical oxygen demand (BOD) and 1,262 PE for suspended
solids (SS) (Pet,, IEPA itr). The present interim permit limits
for BOD and SS are 50 mg/i and 60 mg/i respectively. The Village
plans to upgrade the DAF to 0,157 MGD (1570 PE) and the DMF to
0.628 £IGD. Once the upgrading is complete, the final permit
limits will be 30 mg/i BOD and 37 mg/i SS, based on a three—stage
lagoon exemption. The amended Facilities Plan provided for
expanding the existing single cell lagoon to a two cell lagoon
with ultra—violet light disinfectant facilities. However, as the
Agency notes, the amended Facilities Plan is now deficient and
will not qualify for Innovative and Alternative (I/A) grant
funding (Ag. Rec. 3). An agreement to construct spray irrigation
facilities on a local golf course was not reached (Id.). The
Village has asked the Agency to reconsider its old facility plan,
for which there is no funding availabie. While the record makes
clear the Village’s intention to upgrade its WWTP and come into
compliance by July 1, 1988, there is no firm compliance plan
schedule.
The Authority has identified and priced two alternative
plans to treat on—site the wastewater from the housing project if
variance is denied and until the restricted status designation is
removed from the village treatment facilities. The first is a
series of septic tanks, a sand filter and chlorination equipment
for temporary treatment. The cost is approximately $36,900 pius
$1,000 annual maintenance cost (2/19/85 Pet,). The second plan
consists of installation of concrete holding tanks and the daily
hauling of the wastewater to other permanent treatment
facilities. The estimated cost is $225 per day or $82,000 per
year (Id.).
In order to reduce water usage at the housing project, the
Authority is requiring water misers in the water closets and flow
restrictors in the shower heads.
Petitioners did not address the environmental impact to the
waterways but only furnished data estimating the contribution of
60 PE to the village treatment facilities, The Agency states
that the present high BOD and SS discharges will overload the
stripmine lakes with nutrients which in turn will limit the
quality of Hurricane Creek (Ag. Rec. 8). The Agency furnished
data from 1981 on the effluent being colored pea green to light
64-58
3
brown, clarity as being cloudy to cloudy with visible solids, and
odor being foul to slight (Id.)~
HARDSHIP
Petitioners must show that compliance with the Board’s rules
and regulations would impose an arbitrary or unreasonable
hardship~ Ill, Rev. Stat, 1983, ch~ill
1y~
oar, 1035. The
Authority be~anthe HUD grant process for fac~1ities in the
County in ~
However, the application for the Village units
was filed 11! February of 1981 and was the last one acted on by
HUD, Re:~: ted status was imposed by the Agency in 1~8U, The
Agency s~r~~ letter to the Village informing it of this fact on
May 8, 1~4~:iAttach. to Pet.), The Agency states that it gave
notice of ~TeStricted status in the Board~s Environmental Register
#245 as early as October 6, 1981 (Age. Rec, 4)~ Notice was
repeated on a quarterly basis up to the present time (Id.). Site
acqUisit.iC)fl for the housing project was completed on June 1,
1983, The Village and the Authority applied for a construction
permit on April 4, 1984 which was denied on April. 24, 1984 (Ag.
Rec. 5). The denial letter informed the petitioners that the
village facilities were on restricted status (Ag. Rec. Exh, B),
The denial letter also informed petitioners of the availability
of a conditional installation permit to allow simultaneous
construction of the project with the treatment facility
upgradi!ng, yet no application was
submitted
•~d.) The Authority
decided to proceed without a construction permit and with
knowledge of restricted status,
The
executive director of the
Authority claims that he did not know of the imposition of
restricted status until the summer of 1984, by which time
construction contracts had
already been awarded (Young Affid,,
attach to 2/19/85 Pete), The petitioners have not submitted to
the Board information on what date(s)
construction contracts were
awarded. Meanwhile, an
Agency inspector discovered unpermitted
construction
in progress on October
:3.?
1984 (hg. Rec. 5).
Petitioners
allege hardship because of four reasons (Pet,
4). They allege that the Authority did not
know about restricted
status prior to site acquisition, “lann:ing” and financial
arrangements While this may be
true, it is clear that the
Village knew. That this situation may
not have been
discovered
by or relayed to the Authority is not sufficient
grounds to grant
a variance. Most construction projects of this type require
sewer permits and the Authority should have checked into this
matter, Any hardship resulting from this oversight is a self—
imposed hardship. Petitioners next allege that they are trying
t~fill a void in the elder:Ly housing market~ yet petitioners do
not
argue that
denia:L of variance will cancel their plans.
Thirdly, they
argue that significant adc~.t~.onalenvironmental
impacts will not occur, yet fail
to supoort
~.hio conclusory
statement,
Indeed,
based
on the data lithe
record, the Board
finds that the environmental ilnDact on ~te receiving waterways
would like~y ~e adversely affected by print, of
var:Lance.
Fourthiy~ i,;,~tioners allege that hiphet
utt~e costs will result
64-59
because the
Authority would have to provide on—site treatment,
This most likely is a true statement, but economic grounds
alone
are
insufficient to support a variance request. The Board
also
notes that the cost of on~sitetreatment does not appear
to be
prohibitive. Lastly, while petitioners state that they are
trying to
fill a
void in
elderly housing, they conclusorily
allege
that permanent financing of the housing project could
be
lost and fail to provide any support for the statement,
The Board has granted prior variances where the need for
public housing has outweighed the adverse environmental impact of
adding to the sewage load of the existing treatment facility,
Herr in and Hous in Aut horit
of Count of Willia
ms on v
IEPA,
57 PCB 341, (PCB 83~-l69, April 5, 1984); Ci~~2n
~
49 PCB 419 (PCB 80-
163, February 5, 1981); ~
al. v, IEPA, 39 PCB 285 (PCB 80-~83, August 7, 1980). However,
the
petitioners in these cases had all started substantial
project
planning before imposition of restricted status and were
in jeopardy of losing federal assistance if variance was
denied.
Contra,
see ~
43 PCB 299 (PCB 8F-67, September 3, 1981),
The Board has denied variance in similar cases where the
petitioner should have known about the imposition of restricted
status, substantial planning was not started until after its
imposition,
and
there
was no evidence of loss of federal
assistance.~
~
al. v, IEPA~,, 59 PCB 263 (PCB 84~32, August 2, 1984), Herein,
restricted ~tatus was imposed in May of 1980, While the housing
project
may~have been in the preliminary planning stages, no
substantial~planning had taken place. This conclusion is
supported b~’ the lack of a submittal of a HUD grant application
by the Authority until 9 months after imposition of restricted
status
(Young Ltr, attach, to 10/1/84 Pet,), Furthermore, site
acquisition was not until three years after its imposition. The
Agency attempted to guide the petitioners by informing them
of
the availability of a conditional installation permit, yet
petitioners ignored the suggestion and failed to submit an
application.
The Board finds that denial of the variance would not impose
an arbitrary or unreasonable hardship, in any event, any
economic impact does not outweigh the adverse environmental
effect
of adding further discharge to an already overburdened
treatment
facility and likely adverse effect on the receiving
waterways.
This Opinion constitutes the Board’s findings of fact and
conclusions of law in this matter,
64-80
5
ORDER
The Village of Energy and Williamson County Housing
Authority are hereby denied variance from 35 Ill. Adm. Code
309. 241.
IT IS SO ORDERED,
I, Dorothy ~ Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the above Opinion and Order was
adopted on the
~
day of
____________________,
1985
by a vote of
(~—o
.
Dorothy M. dunn, Clerk
Illinois Pollution Control Board
64-61