ILLINOIS POLLUTION CONTROL BOARD
    August 15,
    1985
    M.I.G.
    INVESTMENTS
    ,
    INC.,
    and
    )
    UNITED BANK OF ILLINOIS,
    )
    Petitioners,
    )
    V.
    )
    PCB 8~—6O
    )
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent.
    THOMAS
    3.
    IMMEL
    (IMMEL, ZELLE, TURNER
    & OGREN) APPEARED ON BEHALF
    OF PETITIONERS; AND
    WILLIAM
    3.
    BARZANO, JR.
    (ASSISTANT ATTORNEY GENERAL) APPEARED
    ON
    BEHALF OF RESPONDENT.
    OPINION AND ORDER (by 3. Anderson):
    This matter
    is a permit appeal
    filed May 3, 1985
    by M.I.G.
    Investments,
    Inc. and United Bank of Illinois
    (hereinafter,
    collectively “M.I.G.”).
    M.I.G.
    seeks review of the March
    28,
    1985 decision of the IEPA (“Agency”) denying M.I.G.’S application
    to modify
    the development of
    an existing solid waste management
    facility,
    the Bonus Landfill in Belvidere,
    Boone County,
    Illinois.
    The modification proposed involved
    a re—contouring
    to
    increase the height of the existing site; this would
    not,
    however, extend
    the boundaries of the site from those currently
    permitted.
    The Agency denial letter
    had listed six grounds for denial
    of M.I.G.’s request,
    all
    of which were challenged
    in M.I.G’s May
    3 appeal.
    However, at the hearing held
    in this matter
    on July
    9,
    1985,
    the parties’ presented
    a stipulation stating that they,
    had
    “resolved all differences save one”, and that “Petitioner’s agree
    to withdraw their Permit Appeal concerning
    all issues raised
    in
    the Permit Denial letter
    of March 28,
    1985 except for Paragraph
    1
    thereof.”
    (Joint Exh.
    A, Section 2—3).
    The sole issue before
    the Board
    for resolution,
    therefore,
    is whether the Agency
    correctly determined that Section 39(c)
    of the Act required
    it
    to
    deny
    the requested modification for the reason that:
    “Based upon
    the May 9, 1984 decision of the Circuit court
    (sic)
    of Lake County Illinois
    in the case titled Village
    of
    Antioch
    vs. Richard Carlson, Director of Illinois
    Environmental Protection Agency, and Waste Management of
    Illinois,
    Inc., Number 83—CH—454,
    local siting pursuant
    to
    65-261

    Section 39.2
    of the Act
    also
    known as
    P.
    A.
    82—682
    or
    SB
    172
    is required for
    an increase in disposal capacity due
    either
    to new or different elevations above ground
    or
    trenches below ground.”
    Only minimal testimonial explanations of the parties’
    legal
    positions were made
    at hearing.
    The primary materials for
    the
    Board’s consideration then are
    the Agency record, filed July 10,
    1985,
    as supplemented August 12, M.I.G.’s opening brief of July
    10 and
    response brief of July 30,
    as verified by filing of August
    7,
    and the
    Agency’s
    brief of July 19.
    The Existing Bcnus Landfill
    ‘the site was initially permitted by the Department of Public
    Health
    in 1969 and thereafter was repermitted by the Illinois
    Environmental Protection Agency
    in
    1972.
    The owners
    of the
    facility have been
    the same since 1969,
    and
    a series of operators
    have run
    the site under
    lease.
    Since
    it opened
    in 1969,
    the site
    has been operated
    on an uninterrupted basis,
    taking municipal
    wastes and/or some
    special wastes.
    The special wastes have
    consisted for the most part of sludge from municipal water
    and
    waste water
    treatment facilities.
    The site has never been
    permitted to take hazardous materials,
    nor have such permits ever
    been requested.
    The site map indicated that the existing landfill
    has
    an
    area of roughly 1900 ft.
    by 1300 ft.
    (Agency Rec.
    Item
    3
    and
    Supp.
    Rec.
    Item D).
    As noted
    in the narrative portion of
    the
    application
    for modification of the existing permit,
    the proposed
    recontouring lies “above existing contour
    800”.
    A maximum
    contour of 872
    feet above mean sea level was proposed,
    as
    indicated
    in bold face on the site map.
    The final contours
    in
    the
    plansheet
    for
    the original permit indicate maximum final
    contours of 827 feet above mean sea level.
    (Supp.
    Rec.
    Items
    C,D.
    The 825
    feet figure listed
    in the Agency permit reviewer’s
    notes appears
    to be an error.
    See Agency Rec.
    Item 8).
    The
    Board notes that the site map indicates that an area of roughly
    600
    feet by 200
    feet just west
    of the center of
    the existing site
    has elevations
    in excess of 830
    ft.
    The site map also depicts
    a proposed extension of the area
    of the existing landfill, addition of which land to the south
    and
    east
    of the existing site would more
    than double the landfill’s
    size.
    Concerning
    this,
    M.I.G,
    stated:
    “A proposed extension of the existing landfill has
    been
    in the mill for more than two
    (2)
    years,
    and has
    now been re—filed with the County.
    Due to SB 172
    machinations by the County, and the long delay
    therefrom~the site is currently running dangerously
    low
    in capacity.
    65-262

    This proposed height increase,
    as well as the
    proposed areal extension,
    is badly needed
    in the
    area.
    Some of the reasons are
    as follows:
    Closure
    of
    the City/County Landfill because
    of financial ~nd
    environmental problems has been seriously discussed
    at recent County Board meetings.
    The distance tothe
    nearest landfill; The practical absence of
    environmentally acceptable landfill site locations in
    the three
    (3)
    county area centered by Boone
    County;..
    .“
    The Antioch Decision and The Parties’ Arguments Here
    The procedural history of the Antioch decision
    is not
    entirely clear to the Board, based on the materials from that
    action submitted to the Board.
    These
    include
    the unreported
    single page Order of May 9, 1984 cited by the Agency
    in its
    denial letter
    (attached hereto as Appendix
    1)
    and
    the
    unreported
    two page Order of April 23,
    1984 (attached hereto as Appendix
    2).
    Additionally, M.I.G.
    in its opening brief
    in this matter
    attached and
    incorporated by reference the Agency’s response to
    a
    motion for summary judgment,
    and a
    12 page brief
    in opposition
    to
    that motion filed by the Attorney General (M.I.G.
    Brief,
    p.
    2 and
    Attach, 1,2).
    As the complaint in this matter was not provided,
    and the Circuit Court’s Orders do not describe the nature of the
    action, the Board must surmise, based on the nature of the relief
    granted,
    that the Village of Antioch sought equitable relief
    in
    the
    form of an injunction order against both the Agency and Waste
    Management of Illinois, Inc.
    (Waste Management).
    Waste
    Management had sought a permit
    to change
    the final contours, by
    way of vertical expansion,
    of the H,00D, Landfill, located within
    the boundaries of the Village
    of Antioch.
    The Agency had issued
    the requested permit on June 15, 1983 without proof
    of Antioch’s
    site location suitability approval pursuant
    to Section 39.2 of
    the Act.
    (Id., Attach.
    2, p. 1—3).
    The Agency explained that it had not denied the permit,
    based on
    its interpretation of Section 3(x)(2)
    of the Act,
    defining “new regional pollution control facility”
    as “the area
    of expansion beyond the boundary of
    a currently permitted
    regional pollution control
    facility.”
    The Agency stated that
    it
    had interpreted this section
    “as not including permit applications under which
    only new space above
    or below ground surface would be
    occupied.
    Operating under this interpretation, the
    Agency has, between July 1, 1981 and June 30, 1983,
    issued at least 99 supplemental permits
    to regional
    pollution control facilities
    in
    which additional
    or
    different space would
    be occupied above or below the
    ground surface
    (this number
    includes the permit
    in
    dispute).
    ~
    Under
    these permits, regional
    pollution control facilities have included
    incinerators, waste treatment facilities,
    landfills,
    65-263

    —4—
    and waste storage facilities and the additional
    or
    different space above or below ground has been
    occupied by a variety of objects including berms,
    trenches,
    changed elevation contours,
    equipment,
    monitoring
    wells and buildings.
    A review of supplemental permits
    for
    the current
    fiscal year
    (July 30, 1983 to the current date)
    has
    not yet been made.
    If the rate of applications in
    this year
    is similar
    to
    the two previous fiscal
    years,
    approximately 20
    to 25 supplemental permits
    for
    kegiona.
    pollution control facilities
    in which
    new or different space above or below ground level
    is
    occupied, r~ayhave been issued.
    This could
    be
    a
    totol
    of
    120
    to 125 such supplemental peri~its,fo~
    which proof of local siting approval was not required
    by the Agency.”
    (Id.,
    Attach.
    2,
    P.
    3—4)
    In support of
    its interpretation of Section 3(x)(2)
    of the
    Act,
    the Agency argued that the plain meaning
    of the terms “area”
    and
    “boundary”,
    as commonly understood,
    imply surface area and
    not volume:
    “Black’s Law Distionary (Revised Fourth Edition)
    defines areas as “a surface,
    a territory,
    a region,”
    and defines boundary as “every separation,
    natural
    or
    artificial,
    which marks the confines or line of
    division of two contiguous estates.”
    This common
    usage indicates the words
    “areas” and “boundary”
    imply surface area.
    ~**
    If
    the legislature
    intended new facilities
    to
    include expansion of the shape,
    or three dimensional
    volume occupied by these
    items,
    it would have not
    used the words
    “areas” and “boundary”;
    it would
    rather have used the words “volume” and “shape”
    so
    that the definition
    under Section 3(x)(2)
    would
    read
    “the volume of expansion beyond
    the shape
    or boundary
    of
    a currently permitted facility”.
    However, the
    legislature
    used words pertaining
    to surface area,
    and
    its clear intent was thus not to include contour
    changes
    in the definition of new regional pollution
    control facilities.”
    (Id.,
    Attach.
    2,
    p.
    8).
    The Agency further argued
    that,
    if the court determined that
    two constructions could be placed on Section
    3(x)(2),
    that the
    Court
    could consider the legislative history of P.
    A.
    82—682.
    Specifically,
    the Agency cited
    a comment during debate
    in the
    House
    of Representatives upon House consideration of
    the
    Governor’s September 24, 1981 amendatory veto of the bill as
    passed July 1,
    1981.
    In response
    to a question,
    the sponsor of
    the motion
    to accept the Governorts
    arnenclatory veto had stated
    that
    65-264

    —5—
    “P.
    A.
    82—682
    applies to any new site or old site
    that
    is expanded beyond
    its original bounds.
    If
    landfills
    apply for
    a permit to take in one extra
    acre, this Bill would apply.”
    (Id., Attach.
    2, p.410—
    11.
    Prior
    to the Antioch court’s consideration of these Agency
    arguments,
    the permit holder, Waste Management,
    stipulated
    to the
    April
    23, 1984 entry against
    it
    of an injunction permanently
    prohibiting
    it from “vertical enlargement of the Antioch Landfill
    Site”
    (Appendix
    2,
    p.
    2).
    Upon its consideration
    of the
    arguments presented by the Village and the Agency of the motion
    for summary judgment,
    the Court entered judgment for
    the
    village.
    The June
    15,
    1983 permit was voided,
    and the Agency was
    enjoined
    from again issuing
    any such permit,
    based on
    the
    findings that
    “The increase of volume contemplated by WMI and
    permitted by the IEPA is
    a new regional pollution
    control facility and it was the intent of the
    legislature
    to require local siting hearings for such
    expansion.
    Any other interpretation would make
    the legislation
    a
    nullity.”
    (Appendix 1).
    The Agency asserts that it appealed this Order, but withdrew the
    appeal (Agency Brief; p.
    6)
    (but see M.I.G. Reply Brief,
    p.
    8).
    In
    the instant action, the Agency states that “not
    only
    has the Agency abandoned the position
    it advanced in Antioch,
    but
    it
    has further
    now adopted that decision as its own and applied
    it accordingly”
    (Agency Brief,
    p.
    2).
    In response
    to an argument
    by M.I.G.
    that the Antioch interpretation should not be applied
    to it because
    it was not a party to that proceeding,
    the Agency
    asserted that the precedent should
    be followed
    to avoid chaos and
    continual reinvention of the “wheel
    (legal precedent)”, although
    admitting that the “precedential nature of
    the Antioch decision
    is not equivalent
    to that of a Supreme Court decision”
    (Id.,
    p.
    1).
    As noted by M.I.G.,
    the Agency’s brief did not ther~fter
    address
    its earlier arguments, as adopted by M.I.G..
    Instead,
    the balance of the brief contains an
    review of the case law
    concerning interpretation of the six criteria of Section 39.2.
    M.I.G.’s final
    argument for rejection of the Antioch
    interpretation of Section 3(x)(2)
    is one of policy,
    relating
    to
    the 120
    odd permits issued by the Agency prior
    to Antioch.
    M.I.G. asserts,
    in essence,
    that the validity of these permits
    is
    uncertain, because of their issuance without
    local approval
    pursuant
    to Section 39.2 of the Act (M.I.G.
    Reply Brief,
    p.
    2).
    Application
    of Stare Decisis
    The threshold question
    is to what extent the Board
    is bound
    61-265

    —6—
    to adhere
    to the holding
    in Antioch
    of
    the Circuit Court
    of the
    Nineteenth Judicial Circuit
    in Lake County,
    based on
    the doctrine
    of stare decisis.
    This doctrine may apply
    ——
    as
    res judicata and
    collateral estoppel may not
    ——
    when
    a second action i~between
    different parties and from a different occurrence, yet the facts
    of the second case are substantially the same as the first
    case.
    American Emp.
    Ins.
    CO.
    V.
    Yellow Cab Co.,
    49
    Ill. App.
    3d
    275,
    364 N.E.2d 948
    (1977).
    Here, as in Antioch,
    the issue is
    whether Section 3(x)(2)
    of the Act, defining
    “new regional
    pollution control facility” by
    its terms encompasses
    the vertical
    landfill expansion proposed by petitoner, therefore precluding
    i~gencypermit issuance until local site location suitability
    approval
    is obtained pursuant to Section 39.2.
    j-ts noted by the Appellate Court
    for
    the Fifth District
    in
    Marathon Petroleum v.
    Briceland,
    75 Ill.
    App.
    3d
    189,
    394 N.E.2d
    44
    (1979):
    “As the Illinois Supreme Court said
    in Neff
    v.
    George
    (1936),
    364 Ill.
    306,
    4 N.E.2d 388
    ***
    The doctrine has more
    or less force, according
    to the nature of
    the question decided.
    Stated
    in
    its
    general
    and simplest terms,
    the doctrine of stare
    decisis expresses the policy of the courts
    to stand
    by precedents and not to disturb settled points.
    ~
    But
    where
    it
    is clear
    that the court has made a
    mistake,
    it will not decline
    to correct it, although
    it may have been reasserted and acquiesced in
    for
    a
    long number
    of years, especially if the
    former
    decisions are injurious and unjust
    in their operation
    (364 Ill,
    at 308—309, A N.E,2d
    at 390—391;
    for more
    recent discussions of the doctrine of stare decisis
    by the Supreme Court,
    see Maki
    v.
    Frelk
    (1968),
    40
    Ill.2d 198, 239 N.E.2d 445,
    and Molitor
    v.
    Kaneland
    Community Unit District No.
    302
    (1959),
    18 Ill.2d
    11,
    168 N.E.2d 89.)” 394 N.E.2d at 46.
    It
    is well settled Illinois law that each trial court
    is
    bound by decisions of all Illinois Appellate Courts (except
    in
    cases of conflict between Appellate Districts
    in which
    case
    a
    trial court
    is bound by decisions
    in its own district),
    and that
    Appellate Courts are bound by decisions of the Supreme Court;
    this
    is the case even
    if the
    inferior tribunal believes the
    superior one has made “bad
    law”, ~
    People v.
    Thorpe,
    52
    Ill.
    App.3d 576 376 N.E.2d 960 (1977), People
    v. O’Neal 40
    Ill. App.
    3d 448
    352 N.E.2d 282
    (1976).
    However, as MI.G.
    points out,
    courts are not bound to follow decisions of equal
    or inferior
    courts,
    e.g. Village of Northbrook
    v.
    Cannon,
    61
    Ill. App.3d 315,
    377 N.E.2d 1208
    (1978), although the rationale used by such
    courts may be awarded deference.
    In
    the
    context of this proceeding,
    the Board
    finds the
    circuit court
    to be
    an equal, rather than a superior,
    tribunal.
    65-266

    The Act has vested
    in the Board
    and the circuit court concurrent
    jurisdiction
    to hear enforcement actions, People ex
    rel,
    WJS et
    al.
    v.
    Charles Janson,
    57
    Ill.
    2d 451, 312 N.E.2d 62
    (1974), but
    Section 41(a)
    has vested jurisdiction to review Board~actions
    exclusively in the Appellate Court,
    The Board need not,
    therefore adhere
    to Antioch as a matter
    of law.
    what the Agency’s position was
    in 1983
    is not on point
    because
    the Board was not presented with the issue
    at that time.
    However,
    there are policies which militate against
    disturbance of
    a precedent which has served as the basis
    for
    Agency permit review in the two past years,
    nothwithstanding
    the
    Antioch decision’s lack to detailed examination of the arguments
    Li~eLt~
    ~
    A
    number of these were articulated
    by
    the
    Fifth
    District Appellate Court in
    its consideration of the arguments
    presented in Marathon Oil Co.
    V.
    Briceland, supra.
    In that case
    Marathon sought a declaratory judgment, requesting
    the court
    to
    reverse its interpretation of Rule 302(k)
    of the Board’s Chapter
    3: Water Pollution regulations as announced by the Court
    in Olin,
    Corp.
    v.
    IEPA,
    54
    ill. App. 3d 480, 370 N.E.2d
    3
    (1977).
    The
    court declined
    to do
    so, stating
    “Even if we were convinced that our prior
    interpretation of Rule 302(k) was erroneous,
    which we
    are not, we would
    be slow to change
    it where, as
    here,
    it has been adhered
    to since our decision by
    the administrative agency charged with its
    enforcement,
    and
    is urged before us now by that
    agency as the proper interpretation.
    ~
    Becatise,
    like legislation,
    administrative
    rules and
    regulations can be amended, their
    judicial
    construction should not be lightly changed.
    (See
    Illinbis Brick Company
    v.
    Illinois m(1977), 481 U.S.
    720,
    97 S,Ct. 2061,
    52 L.Ed2d
    707, where the court
    speaks of the “presumption of adherence to
    ~
    prior
    decisions construing legislative enactments
    ***.~)
    ~
    For
    us
    to reconsider
    the rule here would only
    lead to new confusion
    in an area of law once confused
    and now settled, ~
    As Mr. Justice Brandeis stated,
    dissenting
    in Burnet
    v. Coronado Oil and Gas Company
    (1932), 285 U.S.
    393, 406, 52 S.Ct,
    443, 447, 76
    L.Ed.
    815:
    ‘Stare decisis is usually the wise policy,
    because
    in most matters
    it
    is more important that the
    applicable rule of law be settled than that it be
    settled right
    Citations,
    This
    is commonly true
    even where
    the error
    is a matter of serious concern,
    provided correction can be had by legislation.’” 394
    N,E.2d 46—47.
    The Board believes that
    the
    situation here
    is best resolved
    by deference
    to the Antioch interpretation for the reasons
    articulated by the Marathon court,
    The Agency has been
    65-267

    —8—
    implementing that interpretation for
    the past two years,
    and has
    “adopted
    it as its own”.
    The area of law is now settled.
    The
    legislature has been free
    to change
    the Antioch court’s
    interpretation,
    and the Agency’s implementation,
    of Section
    3(x)(2)
    for two years and has not done
    so, although amendments
    have been made
    to P.A.
    82—682 during that period,
    e.g4
    P.A.
    83—
    1522, effective July 1, 1985 and amending Section
    39, 39.2,
    39.3
    and 40.1 of
    the Act, and S.B.1l3, currently awaiting action by
    the Governor, amending Section 39.2.
    M.I.G.’S arguments are not
    so compelling as
    to overcome the
    Illinois Brick “presumption of adherence”
    to the Antioch
    interpretation.
    The vertical expansion of some 40—odd feet
    proposed by M.I.G.
    is not
    a de minimum one,
    While the Board
    takes notice that the site location suitability process can be
    time consuming, particularly in the event of appeals from the
    initial decision by local government, and that a landfill’s
    disposal capacity might well be exhausted before such process can
    be completed, there are the natural consequences of the
    legislature’s bifurcation of the siting and permit review
    functions formerly in the sole province of the Agency.
    As to
    M,I,G.’s argument concerning
    the pre—Antioch permits issued by
    the Agency,
    the Board would question whether the decision would
    or should
    be given retroactive effect,
    Furthermore, the Board’s holding
    is highly compatable with
    Section 39.2 criteria.
    Several
    of the criteria which,
    from the
    basis of local review,
    are as much impacted by vertical as areal
    expansion.
    Section 39.2(a)(l)
    clearly contemplates
    a volume
    rather than areal consideration in determining the necessity of
    the site to accommadate
    the waste needs
    of the area intended
    to
    be
    served.
    So too are the considerations of protection of the
    public health and welfare under Section 39.2(a)(2),
    the question
    of minimizing incompatibility with the character of the
    surrounding
    area and the effect on property values
    under Section
    39.2(a)(3),
    as well
    as the consideration of traffic patterns
    under Section 39.2(a)(6).
    Not only can these factors be
    impacted by vertical
    expansion,
    but such expansion could potentially have much greater
    impact than areal expansion;
    an increase
    of volume by vertical
    expansion could well have more effect than areal expansion by one
    acre.
    For all
    of the foregoing reasons,
    the Board
    finds that the
    Agency correctly denied M,I,G.’s application for modification of
    its 1972 development permit to allow for vertical expansion of
    the Bonus Landfill by reason of M,I.G.’s lack of compliance with
    Section 39.2 of the Act,
    The Board wishes
    to emphasize
    that this result
    is not
    to be
    construed as a finding that the procedures of Section 39.2 must
    be utilized for every proposal
    to alter
    the contours of
    a
    landfill; Section 39.2 is triggered by a proposal
    to increase the
    65-268

    —9—
    waste disposal capacity of a site by expansion in any direction
    beyond the dimensions contemplated by permits issued prior
    to
    July 1,
    1981.
    This Opinion constitutes the Board’s findings oftfact and
    conclusions of law in this matter.
    ORDER
    The Agency’s March 28, 1985 denial of the January 24,
    1985
    application of M.I.G.
    Investments, Inc.
    and United Bank of
    Illinois
    for
    a permit to modify the final contours of the Bonus
    Landfill, Boone County,
    is sustained,
    for the
    reasons expressed
    in the foregoing Opinion
    IT IS SO ORDERED.
    J.
    Theodore Meyer dissented.
    I, Dorothy M.
    Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Order was adopted on
    the
    /5~3~day of
    c~Z._~—~yc_,4,
    ,
    1985, by a vote
    of
    ~~---/
    Ill
    Control Board
    65-269

    Back to top