1. IT IS SO ORDERED.
    2. Dorothy N. Gunn, Clerk

ILLINOIS POLLUTION CONTROL BOARD
October 10, 1985
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Complainant,
v.
)
PCB 83—61
MISSOURI PORTLAND
CEMENT COMPANY,
)
Respondent.
ORDER OF THE BOARD (by 3. Theodore Meyer):
This matter comes before the Board on a November 3, 1983
complaint filed by the Illinois Environmental Protection Agency
(Agency) against the Missouri Portland Cement Company (Missouri
Portland). The complaint alleges that Missouri Portland caused
the emission of particulate matter into the atmosphere in
violation of Sections 9(a) and 9.1(f) of the Illinois
Environmental Protection Act (Act) and former Air Pollution Rules
203(b), 203(d)(2)(B), 904, 105(a) and 105(d), now recodified at
35 Ill. Adin. Code 212.322, Illustration C; 212.422; 230.160;
201.149; and 201.263 respectively.
A hearing was held on January 11, 1985 at which time the
parties stated their intention to enter
into a settlement
agreement. The Stipulation and Proposal for Settlement was
submitted on June 19, 1985 but was rejected by the Board (4—3)
since the one violation admitted to was statutorily
insufficient
to support the stipulated $20,000 penalty.
In response, the parties filed a revised Stipulation and
Proposal for Settlement on August 15, 1985. As set forth by the
cevised stipulation, Missouri Portland owns and operates a
portland cement manufacturing plant near Joppa, Massac County,
Illinois. The plant uses two dry processing rotary kilns (Kiln
No. 1 and Kiln No. 2). The kiln in question, Kiln No. 1, is
controlled by water sprays, a dust curtain, two simple cyclones
in parallel, a dust chamber, and two electrostatic precipitators,
Clinker generated by Kiln No. 1 is sent to Clinker Cooler No. 2
for cooling. This clinker cooler is controlled by a baghouse or
a gravel bed filter. (Stip, at 2—3),
The violations alleged concern various dates upon which
Agency inspectors observed that Kiln No.
1 was in operation while
one or both of its electrostatic precipitators were
malfunctioning. This is alleged to have caused the emission of
particulate matter into the atmosphere in excess of the allowable
66~O5

—2—
~our1y emission rate as set forth in 35 111. Adm. Code 212.322
(51.20 lbs/hr per 100 tons/hr process weight rate).
Agency
calculations, based on stack tests conducted in 19/5 and 191.1,
~timate that during periods of malfunction emission rat~scouH
range from 102,6 lbs/hr (using the 1975 data) to 267.2 1h~/hr
using the 1981 data).
The Agency also asserts that Clinker Cooler No. 2
wus ~lsu
operated in violation of 35 Ill. Mm. Code 212,422(b)() which
provides for an allowable emission rate of .10 lb/ton of te~dto
the kiln. On various occasions, the Agency has observed bypasses
o~the baghouse control on the clinker cooler caused by operation
at excessive temperatures. During bypass periods particulate
matter is d:Lscharged in excess of the applicable standard. The
\~neydid not receive immediate reports of any of these
ad functions.
Neither Kiln No, 1 nor Clinker Cooler No. 2 was issued
~ermi.tsauthorizing operation during malfunctions or breakdown
until January and October of 1982 respectively. The Agency
asserts that the malfunctions resulted in an unreasonable
interference with the enjoyment of life and property in the
vicinity of the plant by causing 1) the accumulation of cement
dust on homes, cars, and fruit trees; 2) the closure of windows
and doors, even in warm weather, to prevent cement dust from
entering homes; 3) the settling of cement dust on persons~hair
and clothes when outside; 4) additional gutter cleaning due to
cement dust accumulations; and 5) the obstruction of views from
homes by cement dust in the air,
The settlement provides that Missouri Portland admits that
it failed to immediately report a “malfunction” of the air
pollution equipment on its No. 2 Clinkler Cooler and continued to
operate during the malfunctions on two separate occasions. Such
conduct is a violation of Section 9(a) of the Act and 35 111.
Adm, Code 201,263 (failure to repott a malfunction) and 35 111.
Adm. Code 201.149 (operation during malfunction). With the
exception oL these admissions, Missouri Portland denies the
remaining allegations of the Agency’s complaint. Missouri
Portland agrees to pay a stipulated penalty as to the violattonu
admitted
of Twenty Thousand Dollars ($20,000) and also agrees n~u:
to
engage
in any future violations of the Act and Board
regulations. Accordingly, the stipulation addresses the concerns
as expressed in the Board’s order of July 11. However, the
stipulation raises an additional concern.
As part of the settlement, the Board is asked to referee any
disputes connected with programs to be instituted by Missouri
Portland under the settlement agreement. These programs consist
ot a maintenance program to prevent excessive accumulations of
cement dust outside the plant and a program of “periodic visual
observation and recording of stack opacity and precipitator power
levels for both kilns,” (Stip. at 10), These programs are to be
submitted
to the Agency within 30 days after approval of the
66-06

—3—
Settlement Agreement by the Board. The Agency may reject or
modify the programs; in that event Missouri Portland has ten
working days to object. If the objections cannot be resolved
informally within 30 days thereafter then Missouri Portland is
required to petition the Board within 21 days to resolve the
conflict.
Since this process provides that the program be subsequently
incorporated into the settlement agreement, it would require that
the Board retain continuing jurisdiction over this Ratter until
such time as it is notified that the programs have been agreed
to. while the Board certainly has the authority to retain
jurisdiction over matters before it, such action is normally
taken only in special circumstances. In this instance, no
special circumstances exist. The parties have agreed that these
two programs should be instituted
and
have
set
up a timetable for
doing so. It is only the specifics of the programs which remain
to be worked out. No explanation is given as to why the Board
should approve a settlement agreement which has not yet been
‘settled’ in all respects. As there is no apparent impediment to
doing so, the programs should be submitted and approved by the
Board as
‘part
and parcel’ of the settlement approvement
process. To do so will eliminate the need for continuing
jurisdiction
and
promote efficiency for all concerned.
Consequently, the Board hereby rejects the revised
Stipulation Agreement and Proposal for Settlement. The Board
orders that hearing in this matter be scheduled within 90 and
held within 120 days of the date of this order. Should the
parties determine that they wish to file an amended settlement
agreement, they should, according to their agreed—to timetable,
submit the programs as part of a revised stipulation. Should the
parties be unable to agree on the specifics of the programs, they
should submit a statement of reasons for their position on the
disputed term(sJ from which the Board will be able to resolve the
dispute.
IT IS SO ORDERED.
R. C. Flemal dissented.
I, Dorothy N. Gunn, Clerk of the Illinois
Pollution Control
Board, hereby certify that the above
Order was adopted on
the
Joe
day of
_4t~1ttL
,
1985, by a vote
of
6—i
1M~~cL
~.
7
~
-
Dorothy N. Gunn, Clerk
Illinois Pollution Control Board

Back to top