ILLINOIS POLLUTION CONTROL BOARD
April
24,
1986
IN THE MATTER OF:
APPLICATiON FOR
LAKE
MICHIGAN
)
PCB 86-60
PERMIT NO.
187 LM FOR THE
CITY OF LAKE FOREST
)
DISSENTING OPINION
(by
B.
Forcade):
I dissent from the majority Order
because
it authorizes an
extremely large quantity of material
to be placed in Lake
Michigan with virtually no information on the pollution
consequences of that action.
Additionally,
I dissent
from the
haste
in which
final action was taken
today.
Action could have
been delayed one week
to secure fundamental
information which the
Board should have and
to provide
an opportunity
for public
comment.
To understand
the full implications
of the majority
order,
and the rationale for my dissent,
it
is necessary
to
review the permitting processes, past dredge and fill activities
reviewed by this Board,
and the factual record presently before
the Board.
The process
for securing Illinois governmental approval for
a fill project
in Lake Michigan generally
involves three steps:
1.
Securing 401 certification from the
Illinois Environmental Protection Agency
(“Agency”);
2.
Securing
a Permit from the Illinois
Department
of Transportation
(“IDOT”)
under I.R.S.,
chapter
19,
and;
3.
Securing Board concurrence on IDOT’s
permit pursuant
to I.R.S.,
chapter 19,
paragraph
65.
The exact role of
the Agency’s 401 certification
in state
review of Lake Michigan fill projects has never been fully
explained to the Board.
Under Section 401
of the Federal Water
Pollution Control Act
(42 U.S.C.
Section 1251, et seq.)
such
a
certification is required prior
to issuance
of
a federal
permit
by the Secretary of the Army (under Section 404
of that Act)
for
discharge of
fill material.
Under State
law,
IDOT may issue Lake
Michigan fill permits only where they determine,
~that the
deposit
or deposition of dredge material will not cause water
pollution as defined
in the Environmental Protection Act”
(IRS,
ch.
19, par.
65).
IDOT may require
a
401 certification letter
as
part
of their procedures.
Whatever legal role the 401
69-275
—2—
certification letter plays
in the state permitting process, there
is nothing
in this record
to indicate what facts were before the
Agency at the time it made its decision
to issue
the letter, nor
is there information on the criteria and procedures by which the
Agency determines whether
or not water quality will be
violated.
The 401 certification letter
(dated April
4,
1986)
contains an introductory paragraph briefly describing this
project.
The remainder
of the certification
is
a standard form
letter seen by the Board
in many other cases~ it states that
the
proposed project
can be completed without causing water pollution
so long as the applicant does
not
(condition
la) cause violation
of water quality standards,
or
(condition
ib) cause water
pollution.
Consequently,
I cannot legally
or factually rely on
this letter as
a reasoned judgment,
based on sound criteria and
adequate facts,
that water pollution will not occur
under
the
proposed project.
The second step
in the state permitting process
is the IDOT
Permit.
There
is
no statement in the Permit or
in the cover
letter
to the Board indicating that IDOT has made determinations
relating to water pollution.
After
review of many IDOT permits
sent
to the Board,
I must agree with the majority that:
-
.the
permit
system
of
the
Waterway’s
Regulation
Act
is
designed
to
utilized
the
expertise
developed
by
IDOT
in
assessing
the
impact
a project may have on the configuration
of
waterways
and
shorelines,
and
to
utilize
the
expertise developed
by
the
Board
and
the
Agency
in
assessing
the
impact
a project may
have
on
the
quality
of
the
waters
contained
within those waterways.”
Consequently,
I cannot rely on IDOT’s process
to perform an
evaluation of the water quality aspects of this project.
That
is
clearly
a function of this Board.
The last step
in the state authorization process
is Board
concurrence with the IDOT permit.
The Board has previously held
that
its role is:
To
determine
whether
the
facts
contained
in
the
record
demonstrate
that
the
proposed
activity
will
not
cause
a
violation
of
the
Environmental
Protection
Act
or
Board
regulations or adverse environmental impact In
Re:
Application
for Lake Michi~ganPermit, N~
114, PCB 85—134, March 14,
1986.
Thus,
under state
law,
this Board
is the last governmental agency
to review and decide whether
a proposed fill project
in Lake
Michigan may proceed without causing water quality problems.
69.276
—3—
Under federal law a Section 404 permit from the Secretary of
the Army
is
required.
However,
the water quality aspects
of that
federal process are
in large part delegated
to the state
in
the
Section
401 certification process.
On April 23,
1986,
the Army
Corps made
a decision
to issue the federal Section 404 permit for
the Lake
Forest project.
Aside
from
a reference
to the state 401
certification,
the Section 404 permit contains no conditions or
limitations which would
indicate
a review of the water quality
impacts of
the project.
The conditions imposed indicate the Army
Corps’
decision
in this case was based on erosion and
navigation.
It
is probable that as
a general rule the Army’s
decision,
like that of
IDOT,
is concerned with navigation and the
configuration
of shorelines or waterways.
While this process
is confusing,
and involves many agencies
of government,
I believe that this Board
is
the last agency of
government
(federal or state)
that
is required to address the
pollution control aspects of
a Lake Michigan fill project.
In
that role,
and considering
the tremendous importance
of Lake
Michigan
to the people of Illinois and the nation, the Board has
a special duty
to ensure that all
of the facts are
in and all
of
the judgments are sound.
When today’s action
is measured against
prior Lake Michigan activities or other dredge and fill projects,
it
is obvious that the special duty has not been fulfilled.
This Board has significant
and recent experience with dredge
and fill activities.
From November
of
1982 through October
of
1984,
it reviewed three variance requests from the Department of
the Army seeking
to do navigational dredging on the Illinois
River
(PCB 82—136, November
19,
1982;
PCB 83—25, July 26,
1983;
and PCB 84—86, October
25, 1984).
In summary,
these proceedings
authorized
a
four-year program
to remove sediment from the river
and place
it on the banks
in a manner
to minimize the amount
of
material entering the water
column.
The record before
the Board
contained substantial background information on
the nature
of the
sediment
to be dredged, flows,
depths,
disposal methods and
character of the area.
In addition, and most importantly,
the
record contained chemical analyses of
a wide variety
of
parameters for sediment
in the areas where dredging was
anticipated and chemical analyses
of water quality in the
affected area.
In granting relief,
the Board adopted an Order
containing
four pages
of conditions relating
to monitoring and
analyses, restrictions on disposal methods,
and similar
conditions designed
to reduce the pollution impact.
An example
of the level
of detail
in the October
25,
1984, Order
is
paragraph 9),
C)
and
1):
(1)
Petitioner
shall
sample
the
following
parameters
at
all sampling points
listed
under
Paragraph
9,
c)
4:
specific
conductance;
turbidity;
oil
and
grease;
dissolved oxygen;
total suspended
solids;
69-277
—4—
total
dissolved
solids;
volatile
suspended
solids;
total
ammonia
nitrogen
as
N;
pH;
water
temperature;
lead
(total);
zinc
(total);
arsenic
(total);
barium (total);
cadmium (total); chromium
(total
hexavalent
and
total
trivalent);
copper
(total);
mercury
(total);
nickel
(total); and selenium (total).
In the Illinois River dredging proceedings,
I believe the Board
exercised sound
judgment based on adequate facts.
In
a similar vein,
the Board has experience with Lake
Michigan projects.
In PCB 84—72
(In Re:
Illinois Department of
Transportation;
Permit for American Toxics Disposal,
Inc., June
14,
1984), Board concurrence was sought
for
a project
to dredge
25 cubic yards
of contaminated sediment from Waukegan Harbor.
The sediment would not be returned
to the waterway but would
be
used on shore
in an experimental process to destroy poly—
chlorinated biphenyls.
The record contained substantial infor-
mation on project protocols and chemical analysis data.
The
project would use silt curtains to contain the contamination
stirred
up during dredging operations.
The only issue
of concern
was whether the silt curtains would contain the contamination for
a sufficient time period.
I dissented, stating:
OMC has claimed that ATD’s operation will stir
up
from
3.2
to
7.5
kilograms
of
PCB’s
which
will
be
resuspended
in
the water
column,
that
large
portions
of
resuspended
materials
may
not
resettle
for
approximately
40
days
and
that
silt
curtains
are
unreliable
beyond
one
or
two
days.
Many
of
these
arguments
cite
USEPA
publications
or
protocols
for
support.
Since
these
factual
arguments
are
of the
type
normally
encountered
in
Board
hearings,
and
since
the
record
before
us
does
not
contain
sufficient
factual
material
for
the
Board
to
reach
an
independent
conclusion
on
the
key
issues,
I
would
postpone
decision
until
a
hearing could be held.
While
I disagreed with the majority that the
life of
silt
curtains and sediment settling rates were adequately proven,
at
least
the theoretical
basis and factual data were present in the
record.
Again,
the Board carried out its required duties with
some semblance of theoretical
and factual underpinning.
More recently,
the Board dealt with
a request to dredge
40,000 cubic yards of
sand from the Waukegan Harbor entrance
channel,
In the matter
of:
Application for Lake Mich~~nPermit
No.
114 LM
for
the Department of
the Army ~orps of Engineers, PCB
69-278
—5—
85-134.
The documents conveyed to
the Board contained
information on the
scope and location of the dredging
as well
as
over
550 separate chemical analyses on the sediments.
Because of
difficulties determining which sediment analyses correlated with
which dredging area,
the Board set the matter
for hearing
(Order
of September
20, 1985):
This
matter
will
be
set
for
hearing.
At
hearing,
the Department
of Transportation will
be expected
to provide evidence
on:
1.
The
exact
locations
at
which
dredging and disposal will
occur.
2.
The
level
of
sediment
contamination
at each dredging location.
3.
Whether the anticipated dredging and
disposal
activity
will
cause
violations
of
Board
regulations
or
the Environmental Protection Act.
After hearing, comments filed by the Office
of the Attorney
General raised concerns that contamination levels listed
in the
data might cause subsequent water quality levels
to rise at the
disposal location.
The Board ultimately dismissed the Petition
on procedural issues
(the Army Corps
had proceeded with the
project, without Board
knowledge,
prior
to the scheduled
hearing).
However,
the Board was proceeding
to evaluate the
extensive factual record
on chemical contamination against
numerical standards existing
in our regulations.
In other words,
the Board was again performing the appropriate function.
The purpose
of this lengthy discussion of prior proceedings
is
to provide
a benchmark on the size of
the projects,
the wealth
of factual detail,
and
the depth
of Board scrutiny.
When the
present project
is measured against that benchmark,
the shortfall
is obvious.
The project contemplated under this permit
is
reasonably
described
in the record
(Environmental Assessment 14 February
1986).
Lake Forest
has approximately 3,400 feet of shoreline
that has suffered severe erosion.
To correct the problem, Lake
Forest will first construct offshore breakwaters and shoreline
revetments.
Second, Lake Forest will replenish the lost beach
area with approximately 200,000 cubic yards of
fill material.
Also,
Lake Forest will dredge about
1,500 cubic yards from the
Boat Launch harbor;
that material will
be used as shoreline
fill.
The shoreline protection aspect will utilize approximately
80,000 tons of armor stone
and 10,000 tons of
rock.
The majority
of this material will be placed 100
to 400 feet offshore.
The
69.279
—6—
shoreline replenishment is less well described, but appears
to
involve placing 150,000 cubic yards
of sand and 50,000 cubic
yards
of earth
fill in the area enclosed
by the breakwaters
for
the purpose
of building up and extending
the beach.
Most
of this
material would
appear
to be placed near or below the present
highwater mark.
Thus,
any contaminants in this beach nourishment
fill would appear potentially available
for
release
to the Lake
Michigan water
column.
The actual amount of contaminants that
would
be released
to the water column depends on many factors not
present
in this
record.
My primary concern
is not with the
shoreline protection material, my concern
is the beach
nourishment fill,
and the levels of contaminants
it may
contain.
While the record
in this proceeding
is voluminous,
information on contamination levels
in the fill material
is
virtually non—existent.
That limited
information
is reproduced
here
in
its entirety:
Temporary
water
quality
impacts
may
result
from the small
amount
of
dredging
(1500 cubic
yards)
for
the boat launch harbor.
This small
staging
area
of
protected
water
will
be
dredged to
a
uniform depth
of approximately
6
feet.
It
is currently
5 feet deep Lake Forest
datum
so
a
small
amount
will
be
required
if
any at
all.
The dredge spoil will consist
of
compact clay and will
be removed by
a dragline
or
clamshell
type
operation.
Hydraulic
dredging
is
not
anticipated.
The
dredged
spoil
will
be
used
as
fill
for
shoreline
facilities
and
will
be
placed
behind
the
southern
shoreline
revetment
after
the
revetment has been installed.
Chemical
impacts
to
water
quality
are
not
anticipated
because
the
fill material
will
be
clean,
and
existing
near—shore
sediment
analysis shows
insignificant concentrations of
pesticides
or
PCB’s.
Therefore,
sediment
resuspension
will
not
contain
significant
levels
of
pollutants.
(Environmental
Assessment,
p.
57).
This information
is inadequate
for two reasons:
first,
it
only addresses the 1500 cubic yards
to be dredged
from the launch
harbor
(less than 1
of the total
fill) not the 200,000 cubic
yards from some other
location, and second, statements of
“clean”
fill and “insignificant concentrations”
of contamination can
hardly
replace actual numbers.
In PCB 85—134,
the Board had over
500 chemical
analyses, covering many parameters,
representing the
entire material,
to
a level
of detection of parts per million.
69.280
—7—
find the
two narrative statements,
covering less than 1
of
the
material,
an alarming shortage
of data.
One possible reason
for the data shortage came from Lake
Forest’s April
23 filing at page
5,
where they explained the
consequences of delayed action
by this Board:
The City will
be unable
to benefit from a U.S.
Army
Corps
of
Engineers
dredging
project
scheduled for Waukegan Harbor this summer
from
which
the
City
is
currently
negotiating
the
receipt
of
$250,000
worth
of
sand
fill
material.
If
the
City
does
not
have
a
protected
beach
area
prepared
by
August
1,
1986,
we
will
be
unable
to
acquire
this
material and will increase our projected costs
by
$250,000.
A
30—day
delay
will
not
even
allow the City
to
be considered as a potential
recipient of
this resource.
If Lake Forest
is currently negotiating
for
a source
of sand fill
then presumably the actual source
is not yet finally determined,
and the contaminant levels
in that source are also unknown.
There
is
no information
in the record to contradict this
conclusion,
all
of the information supports it.
If the source
of
the materials and contamination levels
are unknown,
then
I find
any conclusions on water quality impacts to
be seriously flawed,
whether those
conclusions are made by the Agency in their
401
certification letter
or
by the majority
of this Board.
In effect,
today’s action by the majority authorized
placement
of 200,000 cubic yards
(over
500 million pounds*)
of
unknown material
in the project area.
If the contaminant level
for some parameter
of that material were
as low as one part per
million,
then the Board has authorized over
500 pounds
of that
contaminant
as potentially available for release
to the water
column.
The only available
information on the source
of the fill is
that
it may come from Waukegan Harbor entrance channel
dredging.
The Board
has some information within its public files
on Waukegan Harbor entrance channel contaminant levels from PCB
85—134.
While drawing conclusions
in this proceeding from data
in the last harbor dredging
is highly speculative,
it does
represent the best information available
to me:
*Using
the conversion on page
56
of the Environmental Assessment.
69.281
—8—
Pounds Potentially
Available for Re—
Concentration
in
lease at Lake Forest
Parts per million
Beach Based on 150,000 yd3
Parameter
from PCB 85—134
(409 million pounds)*
Lead
5
—
69
2,000
—
28,000 pounds
Arsenic
1
—
19
409
—
7,700 pounds
Chromium
5
—
103
2,000
—
42,000 pounds
PCB’s
.004
—
.278
1.6
—
113 pounds
With
the exception of the PCB’s,
each of the above chemicals is
subject
to Board regulation
in one or more media because
of its
potential
for adverse effects
on human health or
the environ-
ment.
PCB’s are regulated predominantly by the federal
government.
Whatever contaminants may
be present
in the fill material
actually used,
those contaminants will
be placed
in
a
5.7 acre
beach area that is utilized by approximately 25,000 men, women
and children annually for swimming and recreational purposes
(Environmental Assessment,
pp.
2,
50).
I believe
in such
circumstances this Board should undertake
a critical review of
the facts and that today’s action by the majority does not
represent such
a review.
Because of
the factual deficiencies
in the record,
I made
a
motion at
the Board meeting
to amend the majority order,
allowing
a short schedule for briefing and comments
on the critical
issues.
The key portion of that amendment
is
as follows:
Consequently,
the
Board will
establish an
expedited schedule
for the filing
of briefs or
public
comments
by
any
participant.
These
filings
should
be
restricted
to
the pollution
issues
over
which
the
Board
has
juris-
diction.
Additionally,
these
filings
should
attempt
to
provide
as
much
information
as
possible on the following concerns:
1.
Whether
quantities
of
material
from
Waukegan Harbor will be used as fill
material
and
what are
the
levels
of
contamination
in that material?
2.
What
are
the
sources
of
fill
material
other
than Waukegan Harbor
sand
fill,
and what are
the
levels
of contamination in that material?
*Using the conversion on page
56 of the Environmental Assessment.
69.282
—9—
3.
What
is
the
impact
on
water quality
and
water
quality
standards
of
placement
of
the material
described
in Nos.
1 and 2?
4.
In
the
absence
of
information
on
questions
Nos.
1
and
3,
can
the
Board
place
meaningful
restrictions
on the activity
or
on
the levels
of
contamination
in
the materials
used
such
that
it
will
not
cause
pollution,
and
what
would
those
restrictions be?
5.
Whether
the
proposed
activity
will
cause
a
violation
of
the
Environ-
mental
Protection
Act
or
Board
regulations
or
cause
environmental
harm?
6.
Is
the
record
before
the
Board
adequate
to make
a
decision,
and
if
not, what
types of information could
be
produced
at
a
public
hearing
on
this matter?
The amendment would have allowed approximately one week for
comments and Board decision,
leaving ample
time for the May
5
bond sale to proceed.
The amendment failed
to carry.
I can only
conclude that the majority chose not
to inquire
into these
issues.
In summary,
I find today’s majority action premature and
factually unsupportable;
accordingly,
I dissent.
I,
Dorothy M.
Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the above Dissenting Opinion was
submitted on the
___________
day of
______________,
1986.
Dorothy
M.
G.~inn, Clerk
Illinois Pollution Control Board
Member
of the Board
69.283