ILLINOIS POLLUTION CONTROL BOARD
    July 11,
    1986
    VILLAGE OF LENA,
    )
    Petitioner,
    v.
    )
    PCB 86—101
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    )
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by J.D. Duinelle):
    This provisional variance request comes before the Board
    upon
    a July 11,
    1986 Recommendation of the Illinois Environmental
    Protection Agency (Agency).
    The Agency recommends
    that a 45—day
    provisional variance be granted to
    the Village of Lena
    (Lena)
    from 35 Ill. Adm. Code
    304.124 as
    it pertains
    to biochemical
    oxygen demand
    (BOD) and total suspended solids
    (TSS)
    to allow
    adequate time for the completion of repairs
    to the trickling
    filter at the Petitioner’s wastewater treatment plant.
    (Rec.
    1—
    3).
    The Village of Lena was previously granted a provisional
    variance
    in PCB 85—117 on August
    15,
    1985 to allow the draining
    of
    its polishing pond to facilitate the removal of sludge from
    the lagoon.
    (See:
    Opinion and Order of August
    15,
    1985 in PCB
    85—117, Villa~of Lena v.
    IEPA).
    The Village of Lena owns and operates
    a wastewater treatment
    facility (WWTP) which has a design average flow of 0.20 million
    gallons per day
    (MGD)
    and consists of
    a trickling filter,
    two
    primary clarifiers,
    a final clarifier,
    a polishing lagoon, and
    effluent chlorination.
    The Petitioner’s WWTP discharges its
    effluent to an unnamed tributary of Yellow Creek which
    is
    tributary to the Pecatonica River pursuant to its NPDES
    Permit 11L0024945.
    (Rec 1—2).
    The Petitioner’s NPDES Permit provides that the Village’s
    wastewater treatment facilities must meet interim effluent limits
    of 45 milligrams per liter
    (mg/i) as monthly averages for both
    biochemical oxygen demand and total suspended solids until June
    30,
    1988.
    The Agency has indicated that the Petitioner has
    completed an acceptable Municipal Compliance Plan and
    is
    scheduled to meet the requisite final effluent limits of
    10 mg/i
    for BOD and 12 mg/l for TSS on July
    1,
    1988.
    (Rec.
    2).
    Recent inspections
    of Lena’s WWTP by the Agency have
    disclosed that the sludge collector mechanisms in the
    71-67

    —2—
    Petitioner’s primary clarifiers and the trickling filter
    center
    column were badly in need of repair.
    (Rec.
    1).
    On April
    21,
    1986, contractors hired
    by the village began to repair the sludge
    collectors in the primary clarifiers.
    However, expeditious
    completion of these needed repairs was inadvertently delayed
    because
    of problems involving the shipping and fabrication of the
    requisite replacement parts.
    (Rec.
    2).
    Subsequently,
    on May 27,
    1986,
    the trickling filter distributor failed unexpectedly,
    thereby causing the Petitioner’s wastewater treatment facility to
    exceed the effluent standards set forth in its NPDES Permit.
    At
    the present time,
    the WWTP’s flows are being treated
    in one
    primary clarifier,
    a final clarifier,
    and the polishing lagoon.
    During the past year,
    the Petitioner’s discharge monitoring
    reports
    to the Agency pertaining
    to BOD and TSS in its effluent
    have indicated the following concentrations:
    Month
    F1ow(M(~))
    BCI) (mg/i)
    TSS
    (mg/i)
    April, 1986
    0.322
    22.1
    23.2
    March, 1986
    0.594
    17.7
    15.8
    February, 1986
    0.320
    32.4
    15.8
    January, 1986
    0.200
    25.6
    16.2
    December, 1985
    0.348
    13.4
    10.6
    November, 1985
    0.600
    17.1
    14.4
    October, 1985
    0.317
    34.5
    37.5
    September,
    1985
    0.200
    50
    46.6
    August, 1985
    0.200
    42
    39.6
    July, 1985
    0.192
    40.8
    31.8
    June, 1985
    0.200
    47.2
    32.8
    May, 1985
    0.250
    26
    16
    Average
    0.312
    30.7
    25.0
    (Rec.
    2)
    Additionally,
    the Petitioner has reported
    to the Agency that
    the concentration of BOD in its effluent was 52 mg/l on June 4,
    1986 and was 62.5 mg/i on June
    6,
    1986.
    In reference to the relief requested by the Petitioner,
    the
    Agency has stated that
    it “is not aware of any alternatives
    to
    bring
    the plant
    into compliance other
    than getting the trickling
    filter
    repaired”.
    (Rec.
    3).
    Moreover,
    the Agency believes that
    any adverse environmental impact will be minimized by the
    treatment provided by the Village of Lena.
    The Agency expects
    that, although the receiving stream
    is a zero low flow stream,
    the recent rains
    in the area should help guarantee that there
    will be no long—term adverse environmental impact.
    (Rec.
    3).
    71-68

    —3—
    The Village of Lena contends that denial of
    its requested
    provisional variance would create an arbitrary or unreasonable
    hardship and
    the Agency
    is
    in agreement with the Petitioner’s
    contention.
    On page three of its Recommendation,
    the Agency
    states the situation as follows:
    “...The Agency believes
    that
    an arbitrary and
    unreasonable
    hardship
    exists
    in
    that
    the
    center
    column
    on
    the
    trickling
    filter
    has
    already
    failed.
    While
    some
    blame
    must
    be
    placed
    on
    Petitioner
    for not having fixed
    the
    column
    sooner
    even
    though
    warned
    about
    its
    condition
    by
    the
    Agency...the
    fact
    remains
    that it has failed and Petitioner does have an
    emergency with which to cope.”
    For the previously mentioned reasons, the Agency agrees with
    the Petitioner’s assessment of hardship and has therefore
    concluded that immediate compliance with the requisite NPDES
    Permit standards pertaining
    to BOD and TSS levels would impose an
    arbitrary or unreasonable hardship upon the Village of Lena.
    (Rec.
    1—3).
    The Agency has indicated that there are no federal
    laws,
    rules or regulations which would preclude the granting
    of
    the requested provisional variance.
    (Rec.
    3).
    Accordingly,
    the
    Agency has recommended that the Board grant the Petitioner
    a
    provisional variance from 35 Ill.
    Adin. Code 304.124
    as
    it
    pertains to BOD and TSS, subject to various specified conditions.
    Pursuant
    to Section 35(b)
    of the Illinois Environmental
    Protection Act, the Board hereby grants
    the provisional variance
    as recommended.
    This Opinion constitutes
    the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    The Petitioner,
    the Village of Lena,
    is hereby granted
    a
    provisional variance from 35 Ill. Adm. Code 304.124 as
    it
    pertains to biochemical oxygen demand
    (BOD)
    and total suspended
    solids
    (TSS)
    to allow adequate time for the completion of repairs
    to the trickling filter at
    its wastewater treatment plant,
    subject
    to the following conditions:
    1.
    This provisional variance shall commence on May 27, 1986
    and shall expire on July 11,
    1986,
    or upon completion of
    repairs to the trickling filter, whichever occurs first.
    2.
    During the term of this provisional variance, the
    effluent from the Petitioner’s wastewater treatment
    plant shall meet
    a standard of 75 mg/i for both BOD and
    TSS as
    a monthly average.
    71.69

    —4—
    3.
    The Petitioner
    shall continue
    to monitor its effluent as
    specified in its NPDES Permit No. 1L0024945.
    4.
    The Petitioner
    shall complete repairs to the trickling
    filter as expeditiously as possible.
    5.
    The Petitioner
    shall operate its remaining treatment
    units as efficiently as possible so as
    to produce the
    best effluent possible.
    6.
    Within 10 days of the date of the Board’s Order,
    the
    Petitioner shall execute a Certificate of Acceptance and
    Agreement which shall be
    sent to Mr. James Frost of the
    Agency at the following address:
    Mr. James Frost
    Illinois Environmental Protection Agency
    Division of Water Pollution Control
    Compliance Assurance Section
    2200 Churchill Road
    Springfield, Illinois 62706
    This certification shall have the following form:
    I,
    (We)
    ___
    ____________________________
    ,
    having read
    the Order
    of
    tfiiTrflnois
    Pollution Con?rR5l Board
    in PCB 86—101
    dated July 11,
    1986, understand
    and accept said Order,
    realizing
    that such acceptance renders all terms and conditions thereto
    binding and enforceable.
    Petitioner
    ~
    Authorized Agent
    Date
    IT IS SO ORDERED.
    71-70

    —5—
    I, Dorothy M.
    Gunn, Clerk
    of the Illinois Pollution Control
    Board, hereby certify that the above Opinion and Order was
    adopted on the
    //~
    day of
    -
    ,
    1986 by a
    voteof
    ______.
    7
    I~orothyM. Gunn,CleiEk
    Illinois Pollution Control Board
    71-71

    Back to top