ILLINOIS POLLUTION CONTROL BOARD
January
8,
1987
CITIZENS OF BURBANK,
Complainants,
v.
)
PCB 84—124
OVERNITE TRUCKING,
Respondents.
INTERIM ORDER OF THE BOARD
(by
B. Forcade):
On August 1,
1985,
the Board entered an Interim Opinion and
Order
in this matter which found that Overnite Transportation
Company (“Overnite”) had violated 35 Ill. Adm. Code 900.102 and
201.141,
as well
as Section 24 and 9 of the Illinois
Environmental Protection Act (“Act”).
That Opinion and Order
found unreasonable noise emissions and unreasonable odor
emissions
from Overnite’s facility and found that those emissions
constituted
a
substantial
interference
with
enjoyment
of
life
for
complainants.
After
making
this
finding
of
a
noise
and
odor
public nuisance violation, the Board retained jurisdiction and
ordered Overnite to prepare and submit a report on the methods,
cost and timing of pollution reduction options.
Overnite filed
reports on June 16,
1986, and July 3,
1986.
Citizens of Burbank
(“Citizens”)
filed collective comments regarding the report on
July 28,
1986.
On January 7,
1987, Overnite filed a response to
the complainant’s comments.
By today’s Interim Order,
the Board
will command implementation of several pollution reduction
concepts identified
in the report.
The Board will also require
monitoring after
those improvements are made and will retain
jurisdiction
pending
receipt
of
a
final
report
demonstrating
completion
of
the
required
activities.
NOISE
The Board’s August
1,
1985, findings of noise emission
violations were based on a public nuisance legal theory applied
to
the
citizen testimony
in this proceeding.
Subsequent to that
finding, Overnite retained ETA, Incorporated
to evaluate the
noise and odor problem (“Noise and Odor Analysis for Overnite
Transportation Company, filed June 16, 1986,
hereinafter Report
No.
1)
and to investigate mitigation measures (“Addendum Number
1
to
Noise
Level
and
Odor
Analysis
for
Overnite
Transportation
Company,
filed July 3,
1986, hereinafter Report No.
2).
Report
No.
I included results of a survey of area residents and included
results
of
noise
monitoring
in
the
affected
area.
The
residen-
tial survey identified the yard horses, trucks at the pump area,
74-344
—2—
truck repairs and noise by workers as the predominant sources.
The primary time for noise complaints was from 10:00 p.m. until
early morning.
The noise monitoring portions of Report No.
1
evaluated noise impacts at four locations along the southern
perimeter of Overriite,
at various times.
In evaluating the
monitoring results, ETA concluded (Report No.
1,
p.
10):
“Examination
of
these
figures
shows
that
the
allowable
night noise
levels
are
exceeded
at
most frequencies.
The majority of the daytime
events
only
exceed
the
allowable
levels
for
certain frequencies.
The degree of exceedance
is
considerably
less
than
for
the night con-
dition.
Events
recorded
during
north
winds
showed slightly higher noise levels than those
recorded
with
south
winds.
Monitoring loca-
tions
at
a
further
distance
from
Overnite
produced
lower
sound
levels;
although
peak
values in excess of the allowable levels were
recorded at all locations.”
Report No.
2 described two technologically feasible and
effective methods for reducing noise levels.
The first is to
permanently reduce the maximum
RPM
of the yard tractor,
presumably by some form of mechanical alteration to the engine.
The second method
is to construct a twelve foot tall solid wall
across the southern perimeter
of the property and the southern
400 feet of the east property line.
ETA estimated that
implementation of these measures could result
in a 10 dB(A)
reduction in noise (which represents a 90
reduction
in energy
and approximately a 50
reduction in perceived noise).
The Board
believes that the approach outlined represents a viable approach
to minimize noise impacts
in the affected area.
The Board cannot
determine,
on the record presented by ETA, that these measures
will be sufficient
to reduce noise impacts to levels below
“unreasonable interference.”
The Board will order that the
RPM
reduction and the twelve
foot tall noise barrier options be implemented.
Because the ETA
reports do not specify the amount of RPM reduction or the design
materials for the noise barriers, these matters will be left to
Overnite’s discretion.
Instead of specifying the noise reduction
modifications in detail,
the Board will require Overnite to
conduct post—modification noise monitoring.
This monitoring
should be conducted
in a manner that will allow comparison with
the pre—modification testing done by ETA and allow estimates of
the noise reduction achieved by the modifications.
The Board
will also set
a June 1,
1987, deadline for completion of the
modifications.
74-345
—3—
The Board notes some discrepancy between Overnite’s January
7,
1987,
comments and the ETA reports concerning site
geography.
The ETA reports urge
a 400—foot wall along the east
property line and describe that property line as adjoining
a
flood basin used for storm water retention.
The Overnite
comments of January 7,
1987, urge the Board
to allow engineering
discretion
in determining the length of the wall along the west
fenceline which abuts the vacant land used for stormwater
retention.
The Board is unable to determine whether the
perimeter subject to fencing
is east or west of the facility.
ODORS
The Board’s August 1,
1985, findings of odor emission
violations were based on a public nuisance legal theory that was
supported by the citizen testimony in this proceeding.
In ETA’s
Report No.
1, the residents survey identified the odor as “oily
and smokey” and “a heavy diesel smell.”
ETA personnel detected
noticeable diesel odors on one occasion during on—site
monitoring.
Because of the difficulties
in ascribing numerical
values or analytical testing
to odors, ETA chose to evaluate a
surrogate,
hydrocarbons.
ETA modelled hydrocarbon levels at several receptors sited
to represent the residential area directly south of the facility
under worst case meteorology.
This effort utilized the USEPA
Intergrated Puff dispersion model with assumptions about
Overnite’s operations and emissions data from the standard 13—
mode federal diesel emission cycle testing conducted in 1979.
Using this approach, ETA was able to estimate the reduction in
ambient hydrocarbon concentrations that could be achieved by
changes
in Overnite’s operational procedures.
Under current
operating practices,
idling trucks awaiting fuel line—up at the
fuel bay (the lines may be 100
to 200
feet long).
Also,
drivers
will start their trucks and then return to the office to secure
paperwork and delivery instructions
(this may result in 12 to 24
trucks idling at one time).
When the maximum ambient
concentrations calculated with these operational practices were
compared with maximum calculated concentrations using different
operational practices,
the reductions were significant
(Report
No.
1, pp.
19,
21):
74.346
—4—
M~thunc~trati~
c~a1x~flata3
fran
cj~erath~E
at cX’er~itEThx~kirg
(ge)
100’ reftElirg*
a)0’ reft~.lirg~ 6 tr~x~s 12 tnx~ 24 tr~x~
q.~e
q~
at idle
at
idle
at idle
Orrait
45
77
45
74
Af~
c~ratia~1
OaT~s
II
23
~e:
AU reftz?lir~g
~
frdhr~
BTfl5
~E
frantiu~idlirg inref~th~
t~.
The operational changes involve reducing or eliminating the
current practice
of having trucks await refueling immediately
adjacent to the fuel bay on the south end of the property.
Instead,
trucks would line up for fueling north of the main
terminal and only move south
to the fuel bay when it was free.
The second operational change would be to provide drivers all
relevant paperwork and instructions for daily activities prior to
allowing access to the trucks for start—up.
This would,
in
theory,
reduce
the start—up time and
reduce the number of trucks
at idle to no more than six at one time.
The Board believes the operational changes described have
the potential
to reduce odor emissions below the level of
“unreasonable interference” and will order
their implementa-
tion.
Because the operational changes appear capable of rapid
implementation,
the Board will set a deadline of 30 days from the
date of this Order.
Today’s Order will also require that Overnight prepare a
final report after completion of the modifications to minimize
noise and operational changes to minimize odor.
This report must
list the actual modifications made, type of material employed,
and date of completion.
After modifications are completed,
Overnight must monitor noise levels in the area in a manner that
will allow the final report to compare post—modification noise
levels with the results obtained
in Report No.
1.
This report
must be served on the parties and filed with the Board within 90
days of completion of
the modifications.
Unless the Complainants
request
a hearing to present evidence that the modifications and
changes did not reduce noise and odor to reasonable levels,
the
Board will proceed to close this docket.
Any such request must
be made within
30 days after
the final report
is served on
Complainants.
74.347
—5--
To summarize today’s Order, Overnight
is required:
1.
To adopt operational changes, not later than February
8,
1987,
that prohibit more than one truck awaiting fuel south
of the north edge of the terminal building and that prohibit
drivers from starting trucks in the morning prior
to
receiving
all schedules and paperwork.
2.
To
implement modifications, not later than June
1,
1987,
which:
a)
permanently reduce maximum yard tractor RPM; and
b)
construct a twelve
foot tall solid noise barrier along
the southern perimeter of the facility and
so much of
the eastern or western perimeter as is necessary to
reduce noise emissions
to compliant levels.
3.
Prepare
a final report within
90 days of the completion of
items No.
1 and No.
2,
but
in no event
later
than September
1, 1987, which explains the changes made and attempts
to
quantify the noise reductions achieved.
This report shall
be
served on complainants and filed with the Board.
4.
The
Board
retains
jurisdiction
in
this
matter
pending
final
disposition.
IT
IS
SO
ORDERED.
I,
Dorothy
M.
Gunn,
Clerk
of
the
Illinois
Pollution
Control
Board, hereby certify tha
the above Interim Order was adopted n
the
~
day
of
____________________,
1987, by a vote
Dorothy
M.
Gu?n,
Clerk
Illinois
Poll1ution
Control
Board
74.348