ILLINOIS POLLUTION CONTROL BOARD
    October 23, 1986
    ILLINOIS ENVIRONMENTAL PROTECTION
    )
    AGENCY AND PEOPLE OF THE STATE
    )
    OF ILLINOIS,
    )
    Complainants,
    )
    vs.
    )
    PCB 80—21
    )
    INTERSTATE POLLUTION CONTROL, INC.,
    )
    LaVERNE F. ANDERSON,
    LUCILLE D. ANDERSON,
    AND
    )
    MARGARET J. JOHNSON,
    )
    Respondents.
    INTERIM ORDER OF THE BOARD (by J. Anderson):
    On September 2, 1986, the Parties submitted a stipulated
    settlement agreement.
    It appears that either the issuance of a RCRA permit or the
    equivalent of a federal RCRA ~delayed compliance orders may be
    necessary to effectuate the agreement. In any event, it appears
    that this proceeding is subject to the procedural requirements of
    the Board’s RCRA procedural rules 35 Ill. Adm. Code 103.260—
    103.268. Pursuant to these rules and Federal RCRA authorization
    requirements, the proposed agreement is defective.
    The parties are directed to address these issues.
    Alternatively, the parties are directed to inform the Board as to
    a) why these procedures do not apply and b) whether this
    agreement is consistent with the closure and post—closure
    requirements of 35 Ill. Adm. Code Parts 724 and 725.
    If no response to this Order is received within 60 days, the
    stipulation will be rejected and this matter will be set for
    hearing.
    IT IS SO ORDERED.
    73.349

    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the a ove Interim Order was adopted on
    the
    -~
    day of _______________________, 1986 by a vote
    of
    (a-p
    .
    Dorothy M. G n, Clerk
    Illinois Pollution Control Board
    73-350