ILLINOIS POLLUTION CONTROL BOARD
    September 11, 1986
    IN THE MATTER OF:
    )
    SITE—SPECIFIC RULEMAKING
    )
    R85—7
    FOR CENTRAL ILLINOIS LIGHT
    )
    COMPANY.
    OPINION AND ORDER OF THE BOARD
    (by R.
    C.
    Flemal):
    PROCEDURAL HISTORY
    On March
    6,
    1985, Central Illinois Light Company (“CILCO”)
    filed
    a petition for site—specific rulemaking with the Board.
    Specifically, CILCO requests that
    it be granted exception from
    the total suspended solids
    (“TSS”)
    limitation of
    35 Iii.
    Adm.
    Code 304.124(a)
    and 304.104(a), which presently limit effluent
    discharges from the ash pond at CILCO’s E.D.
    Edwards Station
    (“Station”)
    to 15 milligrams per
    liter
    (mg/i)
    of TSS
    (STORET
    number 00530)
    as
    a monthly average and
    30 mg/i
    as
    a daily
    maximum.
    In place of these
    limits, CILCO proposes that
    it be
    subject
    to Best Practicable Technology
    (“BPT”)
    limitations
    pursuant
    to 40 CFR 423.12
    (b)(4).
    BPT specifies limits on TSS
    discharges from ash ponds
    to
    30 mg/i
    as
    an average of daily
    values
    for
    a calendar month and 100 mg/i as
    a maximum
    for any one
    day.
    Hearing was held in this matter
    September
    11,
    1985,
    at the
    Peoria Public Library.
    Testimony was presented by Mr.
    Steven L.
    Burns, Senior Water Pollution Control Engineer for CILCO, and Mr.
    David Nott,
    Instrument and Chemical Supervisor at the Station.
    At hearing
    the Illinois Environmental Protection Agency
    (“Agency”)
    reserved comment on CILCO’s proposal.
    However, on
    January 21,
    1986,
    the Agency filed
    a recommendation that CILCO’s
    petition be denied.
    On February 19,
    1986, CILCO filed comments
    in response
    to the Agency’s recommendation.
    In its
    recommendation the Agency raised issues not previously addressed
    in the
    record.
    This action caused the Hearing Officer
    in an
    Order dated February 19, 1986,
    to request
    that the Agency and
    CILCO further address these matters.
    Responses
    to the Hearing
    Officer’s Order were filed by the Agency and by CILCO, both on
    April
    2,
    1986.
    No other comment on CILCO’s request have been
    received by the Board, either
    at hearing or
    through filings.
    The Illinois Department
    of Energy and Natural Resources made
    a “Negative Declaration”
    of economic impact
    in this matter on
    December
    5,
    1985, noting that
    the declaration
    is appropriate
    based
    on the statutory criteria
    in
    Ill. Rev.
    Stat.,
    Ch. 92~’
    par. 7404(d)(2)
    (1985).
    The Economic Technical Advisory
    Committee concurred in this determination on December
    6,
    1985.
    72-369

    —2—
    For the reason discussed below,
    the Board declines
    to grant
    the regulatory change requested by CILCO.
    CILCO’s petition will
    therefore be denied.
    OVERVIEW OF ARGUMENTS
    CILCO contends that ash pond discharges such as
    those of its
    Station cannot consistently achieve the TSS limitations imposed
    by Illinois regulations.
    It argues
    that a combination of
    factors,
    including high concentration of influent TSS and algal
    growth within the pond,
    frustrate all efforts
    at attaining
    compliance.
    CILCO additionally believes
    that BPT limitations are
    achievable and are the most appropriate
    from both environmental
    and economic perspectives.
    The Agency alternatively contends that
    it
    is the
    limited
    area and volume of the Station’s ash pond which causes
    it to
    fail
    to consistently meet the Illinois standards.
    The Agency states
    that ash ponds at other facilities
    in the State,
    including those
    which are subject to similar
    influent compositions, do achieve
    consistent compliance.
    Although allowing that the requested
    relief would be unlikely to pose any significant threat
    to the
    receiving stream,
    the Agency concludes that CILCO has not carried
    the burden of demonstrating that the
    relief
    is either necessary
    or equitable.
    SITE CHARACTERISTICS
    CILCO owns and operates
    a steam—electric generating plant
    known as
    the E.D. Edwards Station located approximately five
    miles south of Peoria,
    Illinois,
    at river mile 154.5 of the
    Illinois River.
    The station has three coal—fired electric
    generating units
    (1,
    2,
    &
    3) with respective net capacities of
    117 megawatts (“MW”),
    266 MW,
    and 361 MW.
    Unit
    1 was installed
    in 1960, Unit
    2
    in 1968, and Unit
    3
    in 1972.
    The three
    units burn pulverized coal and produce ash as
    a
    by—product
    of the coal combustion.
    It
    is estimated that 76
    of
    the
    total
    ash production
    is fly ash collected by electrostatic
    precipitators, 20
    is bottom ash collected
    in bottom ash hoppers,
    and 4
    is ash collected from economizers
    (Ex.
    18,
    p.
    3—15).
    The
    fly ash
    is collected dry and stored
    in silos
    (R.
    at 111—2).
    Subsequently it may be trucked off site,
    or
    it may be mixed with
    water
    and sluiced
    to the ash pond at issue
    in this matter.
    Both
    the bottom ash and the economizer ash are collected wet and
    sluiced directly to the ash pond.
    All sluice water
    is drawn from
    the Illinois River.
    The ash pond
    in question is an 84—acre pond located on—
    site.
    In addition
    to the combustion waste
    ash, the pond also
    receives small
    amounts of coal pile runoff,
    certain sump
    discharges, and the discharge from a holding pond which itself
    72-370

    —3—
    receives yard runoff
    and sump discharges.
    Excess water
    from the
    pond
    is drawn off as an effluent at a standpipe structure located
    on the east side of the pond and discharges through
    a pipe
    directly onto the Illinois River.
    Effluent flows average 4.43
    million gallons per day
    (MGD)
    and
    reach
    a maximum of
    5.99 MGD
    (Ex.
    18,
    P.
    3—17).
    The ash pond began operation
    in 1960 and has been dredged
    several times.
    Dredged ash
    is accumulated within
    the confines of
    the pond.
    The ash pond serves
    to reduce TSS
    in the sluice and
    runoff water
    by the process of sedimentation, primarily in a
    delta located along
    the north and west sides of the pond.
    In its
    present configuration the pond
    is asserted
    to have
    a retention
    period of over
    90 hours for approximately 90 percent
    of the
    sluice water
    and
    a breakthrough time of approximately
    9 hours
    (R.
    at 19), as based on a retention time study conducted by CILCO
    (Ex.
    13).
    Annual deposition
    is approximately 50,000 cubic yards,
    at which rate the pond
    is projected
    to be
    filled by 1999
    (R.
    at
    34).
    PROBLEM
    Effluent from the ash pond has not consistently met the
    15
    mg/i TSS monthly average limitation specified
    in
    35
    Ill. Adm.
    Code 304.124(a)
    nor the 30 mg/l daily maximum limitation
    specified
    in
    35
    Ill. Adm.
    Code 304.104(a).
    Of 74 monthly
    averages during
    the period July,
    1979,
    through June,
    1985,
    27,
    or
    36
    exceeded
    15 mg/I
    (Ex.
    5).
    For the same period,
    16 of 303
    analyses, or
    5
    of the total, have exceeded the
    30 mg/i daily
    maximum TSS concentration
    (R.
    at 17—18).
    There
    is no discernable
    trend
    in the number
    of excursions
    during the 1979—85 period
    of record emphasized by CILCO
    in its
    presentation at hearing and submissions to the record
    (Ex.
    4 and
    5),
    in spite of the efforts undertaken by CILCO
    to reduce
    excursions
    (see below).
    However, the Agency notes that a
    distinct increase
    in the number of excursions
    is discernable when
    1974—79 data are compared with the 1979—85 data,
    as shown
    in
    Exhibits
    8
    and
    9
    (Figures
    3 and
    4
    of Petition).
    The Agency
    attributes
    this increase
    to a reduction
    in volume and area of the
    pond,
    and
    an attendant reduction
    in settling opportunity.
    CILCO
    does note that there were two operational modifications at the
    Station in
    1979:
    the plant switched to coal from a different
    source, and the present pneumatic fly ash collection system was
    put into operation
    (R. at 87—88).
    However, CILCO has
    not
    supplied supporting evidence to demonstrate how these operational
    changes might have affected TSS
    in the pond discharge nor has it
    addressed the issue
    of why during the earlier 1974—79 period the
    ash pond appears to have functioned with minimal or no
    excursions.
    72.371

    —4—
    CILCO argues that it has attempted
    to identify the cause(s)
    of the more recent TSS excursions and has undertaken numerous
    attempts
    to correct the cause(s).
    Among
    the causes of excursions
    CILCO cites high TSS levels
    in the influent sluice water drawn
    from the Illinois River
    as
    a major contributing factor
    in almost
    all cases
    (R.
    at 37, 59—62).
    CILCO additionally contends,
    and
    is
    supported by its consultants
    (Ex.
    14), that some of the influent
    TSS consists of colloidal solids which cannot effectively be
    removed by settling
    or sedimentation
    in the ash pond.
    TSS concentrations have
    in fact been higher
    in the Illinois
    River
    than in the ash pond effluent
    at all times when synchronous
    samples were available, with Illinois River concentrations
    typically exceeding those of the ash pond discharge by a factor
    of approximately
    5
    (Ex. 10).
    CILCO believes that the high TSS
    levels
    in the Illinois River
    stem from a combination of factors,
    including the large amount of barge traffic
    in the river,
    turbulence
    from which inhibits settling of suspended materials;
    the location of the Station downstream from the Peoria Lock and
    Dam, which promotes local
    turbulence
    and which causes all of the
    easily settleable particles to have been removed above the dam,
    and the upstream entry of Farm and Kickapoo Creeks, both high TSS
    streams
    (R.
    at 63).
    Another regularly occurring causative factor
    identified by
    CILCO is the in—pond growth of algae.
    CILCO argues that algae
    naturally present
    in the influent water propagate in the
    clarified water
    of the ash pond.
    When discharged through the
    pond outfall the algae
    are detected
    as suspended
    solids
    (R.
    at
    38—39).
    CILCO estimates,
    based
    on
    a study of the percent
    volatiles in the effluent
    (EX.
    12), that approximately 30
    of the
    ash pond effluent TSS on the average consists of algae
    (R.
    at
    41)
    CILCO additionally examined each of the
    77
    (out of 303
    total) daily concentrations over 15 mg/i for the period July,
    1979,
    through June,
    1985, and
    identified
    the following causative
    factors contributing
    in part or
    in total
    to the recorded values
    (Ex.
    1):
    algal blooms
    in the ash pond
    (8), inadequate retention
    time
    (14),
    failure
    of fly ash
    to fully wet (10),
    rapid ice melt
    releasing entrapped ash particles (5), flooding
    in the Illinois
    River producing entrained colloids
    in the influent sluice water
    (7), boom malfunction
    (13),
    invalid sampling due
    to contamination
    of the sampling pipe
    (5), river backup into the sampling pipe
    (2),
    high winds carrying ash particles over the outfall boom (4),
    thermal i9version
    in the ash pond (3), propwash from a survey
    crew’s boat
    (1), and various activities associated with
    construction and dredging
    (6).
    72-372

    —5—
    COMPLIANCE EFFORTS AND ALTERNATIVES
    Actions undertaken by CILCO to correct these causes include:
    in 1979,
    installation of
    an outflow boom and two dredging
    operations;
    in 1980,
    installation of an additional
    boom,
    modification of the outfall structure, lengthening of the ash
    sluice line,
    and two additional dredging operations;
    in 1981,
    installation of
    a diversion boom to reduce floating particles and
    further dredging;
    in 1982,
    repair
    of
    the boom system and
    additional dredging;
    in 1983, dredging;
    in 1984, further
    repair
    and modification of the boom system and additional dredging;
    in
    1985, additional dredging
    (Ex. 2).
    In addition to
    increasing
    pond capacity, dredging operations, which usually have been
    conducted twice each year,
    have also focused on construction of
    channelways
    and “pond—within—pond”
    structures
    to increase both
    retention and settling time
    (R.
    at 31—33).
    Several boom
    configurations have been utilized, with the present and
    apparently most successful consisting
    of three separate booms
    in
    combination with
    a silt curtain and float collar.
    CILCO contends that the various surveys and corrective
    activities undertaken through mid—1985 on the ash pond and
    its
    outfall structure have cost approximately $486,700.00
    (R. at 18),
    and are still not adequate
    to assure that the ash pond effluent
    will consistently meet
    the 15/30 mg/i standards.
    CILCO further
    contends that there
    is little assurance that additional
    remedial
    actions
    undertaken to the ash pond and/or its outfall
    structure
    will reduce
    the TSS
    in the effluent to comply with
    the 15/30 mg/i
    limits
    (R.
    at 59).
    As alternative compliance programs, CILCO has considered
    a
    physiochemical treatment program, expansion of the present pond,
    and partial
    or complete abandonment of the ash pond
    in favor of
    an alternative ash disposal system.
    The physiochemical treatment
    process investigated consists of chemical coagulation,
    flocculation,
    and precipitation followed by filtration.
    CILCO’s
    engineering consultant,
    with CILCO’s concurrence
    (R.
    at 59),
    believes that physiochernical treatment
    is the only method by
    which
    the frequency of TSS effluent excursions beyond the present
    standards could be
    further decreased
    (Ex.
    14).
    However based
    on
    a
    1983 consultant’s report CILCO contends that such
    a system
    is
    unreasonably expensive.
    Estimated capital expenditure
    in 1985
    dollars
    is $4,610,000
    (R.
    at 20), with first year operation and
    maintenance costs of $204,000; CILCO contends that the operating
    cost alone
    is approximately 17 percent of the entire 1985
    operation and maintenance budget for all pollution control
    programs at the Station
    (R.
    at 20).
    The total expense equates to
    a levelized annual cost of $550,000
    (1985 dollars)
    over the
    twenty—five year
    life span of the system
    (R.
    at 20).
    72-373

    —6—
    CILCO has considered
    and rejected the alternative of
    development of a new or enlarged on—site ash pond.
    CILCO argues
    that there
    is presently insufficient land available on the
    grounds of the Station
    (R. at 61).
    Moreover,
    recent construction
    of a similar pond
    at CILCO’s Duck Creek Generating Station
    is
    asserted
    to have cost $11 million, exclusive of land acquisition
    (R.
    at 61).
    Finally, CILCO believes that the present Illinois
    TSS limitations could not be met with a new or enlarged pond
    (R.
    at 60).
    CILCO has considered several alternatives to on—site
    disposal of
    its waste ash.
    Among these
    are active marketing and
    sale of the waste
    ash, giving away the waste ash, and landfilling
    part or all of the ash.
    Some sale and/or give—away of ash
    presently occurs, but not
    at a rate sufficient to accommodate
    the
    volumes of ash which are produced.
    CILCO has indicated a desire
    to increase this method
    of ash disposal
    (R.
    at 36), but has not
    placed on record an evaluation of possible success.
    Landfilling of
    the ash, assuming
    a suitable site could be
    found or developed,
    is estimated by CILCO to cost roughly $10
    to
    $14 per
    ton
    (R.
    at 62), which would
    involve an annual cost
    generally comparable to physiochemical treatment.
    If only the
    fly ash were
    to be landfilled
    and the bottom continued
    to be
    disposed
    in the ash pond, CILCO believes that the effluent would
    still exceed
    standards due
    to the high content of influent TSS
    and algal growth within the pond
    (R.
    at 62).
    FEDERAL GUIDELINES
    TSS limitations for effluent from ash ponds are more
    stringent under Illinois law than under federal BPT guidelines.
    Specifically, the United States Environmental Protection Agency
    (“USEPA”)
    has promulgated BPT ash pond effluent limitations,
    set
    forth
    in 47 Fed.
    Reg. 52,290
    (November 19, 1982)
    (codified
    in 40
    CFR 423.l2(b)(4)), specifying that the avera.ge daily TSS for
    thirty consecutive days shall not exceed
    30 mg/i and that the
    maximum for any one day shall not exceed 100 mg/l;
    it
    is this
    level of limitation that is requested by CILCO.
    The BPT
    guidelines were established after USEPA studied fuel types,
    equipment, age and size of plants, water usage, and waste water
    constituents involved
    in the steam electric power
    industry.
    The
    USEPA additionally considered
    the type, performance, and cost of
    control and treatment technologies available for potential use
    in
    this industry.
    In contrast, the Illinois standards are based upon accepted
    performance levels
    for removing suspended solids in industrial
    waste streams in general.
    CILCO contends that the USEPA’s
    concentration limits are much more reflective of the nature of,
    conditions experienced by,
    and control and treatment technologies
    72.374

    —7—
    available
    to,
    the steam electric power
    industry than are those
    contained
    in the Illinois regulations.
    The Agency argues
    to
    the contrary.
    Specifically,
    the Agency
    asserts that the steam electric generating industry generally is
    capable of complying with
    the Illinois limitations as based on
    actual compliance records.
    Specifically, the Agency notes
    that,
    in a review of its permit and compliance
    files,
    it found no
    examples of power plant ash ponds which were incapable of
    achieving consistent compliance with the applicable effluent
    limits for TSS
    (Agency Response
    to Hearing Officer Order,
    p.
    4).
    The Agency additionally asserts, that the “USEPA’s BPT
    levels are the minimum effluent limitations which the Agency can
    enforce within its NPDES permitting authority”
    (Reponse
    to
    Hearing Officer Order,
    p.
    9; emphasis
    in original),
    and hence are
    not necessarily identical
    in purpose
    to the Illinois standards.
    The Agency further notes that the USEPA has not yet proceeded
    beyond
    its BPT guidelines to
    the next step of promulgating Best
    Conventional Pollutant Control Technology (“BCT”).
    Given these
    circumstances, the Agency argues that CILCO bears the obligation
    of demonstrating that the federal guidelines are more appropriate
    than the State standard, an obligation which the Agency asserts
    has not been met.
    ENVIRONMENTAL IMPACT
    CILCO contends that
    its present ash pond discharge has no
    adverse environmental impact on the receiving stream, the
    Illinois River
    (R.
    at 64).
    It points out that the reach of river
    adjacent
    to the plant
    is a very productive fishery for
    shad and
    freshwater
    drum,
    and that many fishermen utilize the stream,
    particularly congregating around the condensor discharge
    structure and below the ash pond discharge
    (R.
    at 64).
    CILCO
    further contends that if
    30 mg/i monthly average and 100 mg/i
    daily maximum standards were
    in place, the TSS discharge from the
    ash pond would
    still normally be below that of the river,
    and
    hence that the ash pond effluent would continue
    to
    be cleaner
    than the water of the
    Illinois River
    (R.
    at 65).
    The Agency agrees that the requested relief would be
    unlikely to pose any significant threat
    to the receiving stream
    water quality,
    noting
    that the discharge is
    to a relatively
    turbid stretch of
    a major river
    (Rec.
    p.5).
    CONCLUSIONS
    The Board
    finds it difficult to give weight
    to CILCO’s
    contention that the elevated TSS levels
    in
    its effluent are
    attributable
    in major part to elevated levels
    in the influent
    water.
    Admittedly,
    the waters of the Illinois River are often
    turbid, and TSS concentrations of several hundreds of milligrams
    72-375

    —8—
    per liter
    are not uncommon.
    However,
    in the sluicing process
    employed by CILCO this influent water
    is mixed with large volumes
    of ash, thereby increasing
    its TSS concentration
    to very much
    higher levels than those of the raw influent water.
    It
    is at
    this stage, after CILCO has received the water,
    that the water
    achieves its maximum concentration of TSS, and
    it
    is this highly
    charged sluiced water which
    is required
    to be cleansed
    to the
    point of becoming
    an acceptable effluent.
    It
    is inescapable that
    even
    if CILCO had available
    to
    it an influent which was totally
    devoid
    of TSS,
    it would
    still be required
    to operate an ash pond
    which would function
    to
    a high degree of efficiency to remove the
    sluiced
    ash.
    Moreover,
    it
    is undemonstrated by CILCO that the
    non—organic TSS which occur
    in the effluent consist of the
    same
    solids which where derived from the river, as opposed to solids
    which were added
    as
    a consequence of using
    the water
    to sluice
    ash.
    The Board believes that CILCO has failed
    to adequately
    address why the ash pond was capable of performing
    to standard
    in
    the past, but
    is apparently incapabale of doing
    so now.
    If,
    indeed,
    it
    is the character of the influent water which
    is
    responsible for the present excursions,
    it would seem that
    similar excursions would have occurred
    in the past;
    there
    is no
    reason to believe, nor
    is
    it contended, that the character of the
    influent water has altered
    to a state which now causes higher
    excursion levels.
    The Agency has expressed
    the belief that the fundamental
    cause of the present excursions
    is that the ash pond
    is too full
    to provide the necessary settling opportunity.
    CILCO has
    countered only with assertions that plant modifications and/or
    increases
    in the level
    of TSS
    in the influent water
    are possible
    causative factors.
    While
    the record does not allow the Board
    to
    determine which
    of these perspectives
    is correct, we do note that
    CILCO has
    failed
    to counter
    the arguments of the Agency.
    The Board similarly believes that CILCO has failed
    to
    adequately address the
    issue of equitable and fair treatment.
    The Agency contention that the electric stream generation
    industry
    in Illinois can and does comply with existing TSS
    standards at facilities
    other than the Station has not been
    refuted.
    The Board believes that,
    in the absence of evidence
    to
    the contrary, granting
    of the requested relief
    to CILCO could
    conflict with the goals of equitable and
    fair treatment.
    Finally, the Board
    notes that CILCO has not demonstrated
    that compliance is technically infeasible.
    Compliance was
    clearly feasible at the Station between 1974
    and 1979,
    and
    it is
    unrefuted that other electrical generating facilities
    in Illinois
    are presently able
    to maintain ash ponds
    in compliance with
    Illinois regulations.
    Similarly,
    CILCO has not made a
    demonstration that compliance
    is economically unreasonable.
    72-376

    —9—
    Again,
    other facilities have achieved
    compliance, and CILCO has
    not demonstrated any special conditions existent at the Station
    which would allow the Board
    to determine
    that the Station
    is
    in
    an economic position distinct from these facilities.
    In view of the above considerations, the Board determines
    that the site—specific relief requested by CILCO must be denied.
    ORDER
    The March
    6,
    1985, petition for site—specific exception to
    effluent standards
    for Central
    Illinois Light Company
    is hereby
    denied.
    IT
    IS SO ORDERED.
    Board Members Jacob D.
    Dumelle and Bill Forcade concurred.
    I,
    Dorothy M.
    Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the abçwe Opinion and Order was
    adopted on the
    //t7~
    day of
    ~
    ~
    ,
    1986, by a vote
    of
    ~,-o
    ~
    ~.
    Dorothy
    M.
    Gu’nn,
    Clerk
    Illinois Pollution Control Board
    72.377

    Back to top