ILLINOIS POLLuTION CONTROL BOARD
APRIL 30, 1987
IN THE MATTER OF:
PROPOSED AMENDMENTS TO
)
R85—20
35 ILL.
ADM.
CODE PART 203
)
FIRST NOTICE
PROPOSED RULE
PROPOSED OPINION AND ORDER OF THE BOARD
(by
3.D.
Dumelle):
On September
4, 1985,
the Illinois Environmental Protection
Agency
(Agency)
filed proposed amendments to
35 Ill. Adm. Code
203:
Major Stationary Source Construction and Modification, more.
commonly referred to
as New Source Review or NSR.
The Agency
amended that proposal on December 19, 1985,
and again on February
5,
1986.
Hearings were held
to consider the proposal on November
13 and December 10, 1985,
and on February 4
and May 28,
1986.
On
~3eptember29,
1986,
the Department of Energy and Natural
Resources (DENR)
filed a negative declaration indicating that no
economic impact study
(EcIS) would
be performed regarding this
proposal,
a determination
in which the Economic and Technical
Advisory Committee concurred by letter filed on October
20, 1986.
The primary purpose of the proposal
is
to enable the State
to obtain approval of
its New Source Review Rules as part of the
Illinois State Implementation Plan
(SIP).
The Clean Air Act
provides that unless
a state has an approved new source review
program as part of its SIP, no major source may be constructed or
modified
in
a non—attainment area.
(See Sections LLL(a)(2)(D),
111
(a)(2)(I) and 173 of the Clean Air Act).
HISTOR’~
OF NEW SOURCE REVIEW RULES
In April,
1979,
the Agency submitted its own NSR rules
to
the United States Environmental Protection Agency
(USEPA)
for
approval as part of the Illinois SIP,
and they were conditionally
approved
in 1980.
(See 45
Fed.
Reg.
11472, Feb.
21, 1980).
However,
in May,
1981,
that conditional
approval was reversed by
the Seventh Circuit in the case of CBE v.
USEPA, 649 F.2d 522
(7th Cir.,
1981).
In turn,
the State became subject to
a
construction moratorium in non—attainment areas.
Thereafter, the
General Assembly adopted Section 9.1(d) of the t~nvironmental
Protection Act (Act) which mandated the Board
to adopt
regulations establishing
a permit program meeting the
requirements of Section 173 of the Clean Air Act
(42 USC Section
7503) by October
1, 1981.
In response
to that directive,
the
Agency submitted an NSR proposal
to the Board
in April,
1980,
which was docketed as R81—16.
Final
rules were adopted under
77-419
that docket
in July,
1983, which were then submitted to USEPA for
approval.
On April
9,
1984, USEPA proposed to approve
in part
and disapprove in part.
(49 Fed. Reg. 13893).
However,
in light
of the Seventh Circuit’s decision in Bethlehem Steel v. Gorsuch,
742 F.2d 1028
(7th Cir,,
1984), USEPA determined that such action
was impermissible, and that it was obligated to disapprove the
rules
in their entirety.
At that point the Agency and USEPA agreed
to jointly develop
draft NSR rules which would be proposed for promulgation by USEPA
and whIch would be filed with the Board
for adoption as state
rules.
As stated by the Agency
Under
the terms of this “parallel processing”
agreement,
were
the
Board
regulations
to
be
finally
adopted
before
USEPA
has
completed
its promulgation, USEPA would review them for
inclusion in the SIP
in lieu of
the Federally
promulgated
rules.
If
USEPA
has
completed
promulgation
before
final
adoption
by
the
Board, upon approval of the Board regulations
for
inclusion
in
the
SIP USEPA will rescind
the Federal
regulations.
Once NSR rules are
in place,
whether ~y Federal promulgation
or
approval of the State rules,
the construction
moratorium will
be
terminated
to
the
extent
that
the
SIP
for
a
particular
area
and
contaminant
is
not
found
to
be deficient
on
other grounds.
(Sept.
4, 1985 Statement of Reasons at 3).
OVERVIEW OF THE PROPOSAL
The proposal before
the Board is
intended to eliminate
deficiencies identified
by USEPA
in the NSR rules,
thereby
allowing expeditious approval as a SIP revision.
It also
includes clarification of certain administrative procedures
contained in the rules, adjustments
to account for changing USEPA
guidelines, adjustments necessitated by the Board’s decision not
to
adopt state Prevention of Significant Deterioration of Air
~uality (PSD)
rules, and minor corrections of the present
:ules.
Finally, the proposal includes some changes which reduce
:he stringency of currently existing rules
to conform to the
federal proposal which is required to impose a program which
is
tinimally required under
the Clean Air Act.
The Agency
ummarizes
the basis
for these changes as follows:
The complexity
of
the present
rulemaking
and
the
desire
to
expedite
the
process
are
certainly
important,
as
is
the
lack of major
projects over
the last few years
to which
35
77-420
—3—
Ill.
Adm.
Code
Part
203
would
apply.
Most
importantly,
however,
IEPA believes
that the
points
of
greater
stringency
in
the
State
rules
would
not
result
in
any
significant
environmental benefits.
(Sept.
4,
1985 Statement of Reasons at 4).
35
Ill. Adm. Code 203 establishes a permit program which
is
designed
to ensure that the construction of a major new source of
air pollution or
a large increase of emissions at an existing
source does not interfere with the attainment demonstration and
does not delay timely achievement of the air quality standards.
The rules specify what projects are “major” and the requirements
which apply to such projects.
There are essentially four such
requirements imposed on owners or operators of such projects.
The first of these
is the imposition of LAER (Lowest
Achievable Emission Rate), which
is
a hardware based
requirement.
LAER is the most stringent of feasible emission
limits for
a particular
source and
is established on
a case—by—
case basis in the permitting process.
In essence,
it
is
to
reflect
the
state—of—the—art
in
process
or
emission
control
technology.
The second requirement
is that a major project must be
accompanied by compensating “emission offsets” from other sources
in the area or by a demonstration that
it is within the allowance
for major projects already contemplated
in the attainment
demonstration.
In other words,
the source must either
demonstrate that emissions of particular pollutants will not be
increased in the general area of the source
or that any increase
falls within the growth allowance which is built
into the
attainment demonstration.
The
third
requirement
is
present
compliance
by
other
sources
in the State which are under common ownership or control.
Unless
this requirement
is met, the new source cannot be constructed.
The final requirement applies only to areas which are not
in
attainment for ozone
and carbon monoxide and for which the
attainment deadline has been extended to December
31,
1987
pursuant
to
Section
172(a)(2)
of
the
Clean
Air
Act,
42
USC
Section 7502(a)(2).
In these
areas, an analysis of alternatives
to a particular major project must be made which demonstrates
that the benefits of the project outweigh the environmental and
social
costs.
The most intricate aspect of
the NSR rules regards
applicability.
A project must be evaluated independently for
each contaminant
for which the area
in which the project
is
located
is designated non—attainment.
There
are several types of
projects to
be considered;
77-421
—4—
1)
The construction of a new major source;
2)
A “significant” modification
to a major source;
3)
A physical change at a non—major source, that by itself
constitutes
a major source, and
4)
Reconstruction of a major source.
Finally, there are specialized applicability provisions concerned
with changes in the status
of projects and the handling of
fugitive emissions.
“SOURCE” DEFINITION AND VESSEL EMISSIONS
Two major issues have arisen during the course of this
proceeding.
The first
is whether the dual definition of source
should
be replaced by
a plant—wide definition.
The other
regards
whether, and to what extent, vessel emissions should be included
in the NSR rules.
The Steel Group has argued that the Board cannot retain the
dual definition of “Source”
absent an economic impact study
addressing that issue.
The argument
is that at the
time the dual
definition was adopted
in R81—l6,
it was
in essence done on a
“pass—through” basis:
that
is, since USEPA would not approve NSR
rules absent inclusion of a dual definition, such a definition
would have
to be adopted regardless of the economic impact,
thereby negating the worth
of an economic analysis of the impact
of adoption of
the dual definition.
The argument continues that
USEPA no longer requires a dual definition,
thereby negating the
“pass—through”
rationale
and
reinstituting
the
necessity
of
an
economic evaluation of that issue.
Therefore,
the argument
concludes,
the
Board
cannot
retain
the
dual
definition absent an
EcIS
analysis.
The
E~oarddisagrees.
The
present
proposal before the Board
does not contain any modification of the existing definition.
While
the
original
proposal
did,
that
has
now been withdrawn.
Furthermore,
no
one
has
contended that the rule was not properly
adopted
in RBl—l6.
To carry the Steel Group’s argument
to its
logical extreme, whenever the economic considerations underlying
a properly adopted existing rule change,
the Board would
be
required
to reconsider that rule.
The Board does not believe
that either the Act or the Administrative Procedure Act requires
such a result.
Furthermore, the Steel Group’s argument
is factually suspect
in that it
is probably fairer
to say that USEPA has taken no
position
on
whether
the
dual definition would
be required
in the
context
of
the
Illinois
rules.
While
USEPA
has
indicated
that
77-422
the rules would not be automatically disapproved
if a plant—wide
definition were adopted,
it is either unwilling or unable to
state that such definition would
be approved.
What USEPA has
indicated is that if the plantwide definition were adopted,
it
would be approvable only
to the extent that the State could
support a certification that the adoption of such definition
would not undermine the State’s attainment demonstration.
The
likelihood that such a showing could be made is uncertain, and
the requirement of making such a demonstration would add
considerable delay in obtaining approval.
Even
if an economic analysis were done (and the DENR has
determined that
it will not perform an EcIS
in this matter),
the
best that could
be hoped
for would be
a range of possible
increased costs from $0 to some upper
limit which would
be based
largely upon conjecture due to the difficulties inherent
in
estimating how many major new sources would be proposed to be
built
in non—attainment areas
of Illinois
in the future.
Not
even the Steel Group, which may well be the industry most
affected
by the choice of definition, has made any attempt
to
quantify the costs associated with that choice,
and there
is
certainly nothing
in the record before
the Board
to
indicate that
such costs,
if any, are unreasonable.
The other major area of contention regards the proposed
rules concerns vessel emissions.
Representatives of the terminal
operators industry have strongly urged that vessel emissions not
be
included
in the NRS program.
Under the Agency’s proposal,
vessels are to
be considered to the extent that they are involved
with “the transfer of materials
...
to or
from a building,
structure,
or facility” and
to the extent that they take place
“at or adjacent
to such building, structure,
or facility
and
are associated with such transfer.”
(See Sections 203.136 and
203.112).
This treatment of vessel emissions was worked out
between the Agency and USEPA in an attempt
to develop an
approvable
rule.
As with the question of the definition of source,
it
is
difficult
to determine how far the State must go in including
such emissions since USEPA,
at present, has adopted
no vessel
emission policy to replace the policy which was overturned
and
remanded
to USEPA
by the Seventh Circuit Appellate Court on
January 17,
1984.
NRDC v.
EPA,
725 F.2d 761.
USPEA has taken
the position that the Agency’s proposal
is sufficiently
conservative to be approvable no matter what policy USEPA finally
adopts, and that any other
treatment may not meet the minimum
requirements and,
in turn, may not be approvable.
if there were a clear vessel emissions policy to which the
Agency proposal could be compared, this would
be an easy issue
to
resolve
in that the Agency has taken the position that all
that
is sought
is the minimum stringency required
for federal
77-423
approval.
This
is
based
on
the
Agency’s
determination
that
áu
to the small amount of vessel emissions in the State, there
should be little impact upon air quality regardless of the vest
emissions rule which
is adopted.
That position has not been
subject to contrary testimony.
In the absence of a clearly articulated policy, the Board
could hope to find guidance
in USEPA’s proposed NSR rules
for
Illinois since those rules are required to be no more or less
stringent than required for approval.
That route to
enlightenment,
is, however, considerably darkened by USEPA’s
sidestepping of the issue.
The USEPA proposal simply includes
“dockside vessel emissions as determined on a case—by—case basis’
by the USEPA.
See
proposed rule,
40 CFR 52.736(b)(l)(i)(O).
All that can really be determined from such a rule
is that USEPA
requires that there be some rule which leaves open the
possibility that some dockside vessel emissions be included
in
the
NSR
program.
The only other guidance, such as
it
is,
comes
from
the
NRDC
case,
above.
In order
to understand the import of that case,
it
is useful
to examine the history of the vessel emissions rules.
In the preamble of the USEPA’s 1980 adoption of NSR rules,
USEPA
indicated
its interpretation that the definition of “Stationary
Source”
included in these
rules encompassed emissions from docked
vessels.
(See
45 Fed.
Reg.
52736).
Furthermore, the emissions
of those vessels coming to and from the terminal
(“to and fro
emissions”)
were determined to be “secondary emissions”
which
were defined as those emissions that “occur as a result of the
construction or operation of
a major ‘stationary source or a major
modification, but do not come from the major stationary source or
major modification itself.”
(See 45
Fed.
Reg.
52737).
Such
emissions are not used
to determine whether the source
is major,
but are used for other purposes such as the
required air quality
impact analysis.
On June 25,
1982, USEPA revoked the vessel emissions
equirements on the basis that dockside vessels are “Mobile
ources”
rather than “Stationary Sources” and,
therefore,
~iissions
from
them
should
not
be
included
under
the
NSR
program
irsuant
to
Section
llO(a)(5)
of
the
Clean Air Act which
ohibits OSEPA (although not the states) from considering
direct
sources under
the NSR program.
The
Court
concluded
that
while
vessels
are
mobile
sources,
.t
does
not
prevent
USEPA
from
attributing
some
of
their
ssions to the terminal.
It,
therefore,
vacated
and
remanded
PA’s revocation of the vessel emission rules
for consideration
thich emissions are properly attributable
to the terminal.
Court
did,
however,
affirm
the
repeal
of
the
“to
and
fro
sions”
rules.
Thus,
the
only
conclusions
that
flow
from
this
are
that
“to
and
fro
emissions”
are
not
to
be
included
in
77.424
—7—
the NSR rules
and that dockside emissions may or may not be
included
to some extent.
This case
is,
if anything, less instructive than USEPA’s
present policy
(if that is an appropriate term to use) that the
NSR rules must include some kind of vessel emissions rule,
in
that the case appears
to leave open the possibility that no
vessel emissions can be attributable to the terminal.
However,
the clear implication
is that some such emissions are
attributable, and USEPA’s position is consistent with that
implication.
The Board concludes that the NSR rules must allow for the
attribution of some vessel emissions to the terminal since the
failure
to do so would result in a very high likelihood
of
running counter
to the mandate of the Clean Air Act and an even
higher likelihood of USEPA disapproval.
Additionally, the record
supports the finding that the proposed rule
is approvable.
The
remaining question,
then,
is whether a rule more restrictive than
the proposed rule is appropriate and approvable.
It is
in this
area that the Board ventures into a regulatory haze.
Under
the proposed rules, only those “pollutant—emitting
activities which belong
to the same industrial grouping, are
located on one or more adjacent properties, and are under control
of
the same person
(or persons under common control)” are
attributable
to the terminal.
The fact that emissions are
attributable only to the extent that the terminal owner controls
the vessels should substantially alleviate the concerns of the
terminal operators that they are at the mercy of the vessels
which dock at their terminals:
to the extent that the operations
of such vessels are beyond
the terminal’s control, they are not
attributable.
The Board construes this to mean that if the
terminal
is determined to be subject to NSR,
LIAER could not be
imposed upon those vessels except
to the extent that they are
controlled by the terminal, and the terminal operator could not
be required
to turn away vessels simply because they do not have
emission controls which represent
LAER.
The question still remains as to what emissions for dockside
vessels will be included.
Clearly, pursuant to proposed Section
203.122(b)(l)
and (2), material transfers and associated
activities are covered
as long as the control and proximity
criteria of subsection
(a)
are met.
It might be argued that
subsection
(a) allows other emissions
to be covered and that
(b)
simply serves
to give examples of some emissions which are
covered.
However,
the Board construes the structure
of the
definition as
it relates to vessels to be limited to those
activities delineated
in subsection
(b).
Comment on this
interpretation is invited, including suggestions as to how the
language
might
be
clarified.
77-425
—8—
As stated above,
it may be that even these limited emissions
go beyond what is necessary for approval.
However, the Board
believes that if any vessel emissions are
to be attributable
to
the terminal,
those resulting from material transfer should be.
This activity of necessity involves some control by the terminal
even if only to specify where the material transfer takes place
and what the materials are transferred into or onto.
In this
activity, the terminal’s facilities and operations will have an
impact upon the emissions and should
be required
to comport with
LAER
requirements.
Therefore,
the Board believes that this
provision should be retained.
The question of whether activities associated with such
transfer, such as the operation of engines,
is less straight-
forward, and the record before the Board sheds little light on
either
the propriety or the necessity of such further
regulation.
However, the Board believes that
the control and
proximity requirements of subsection (a) provide a reasonable
limitation on these associated activities, and will retain the
proposed language.
In making these determinations regarding both the question
of the definition of “Source” and vessel emissions,
the Board is
mindful of the present construction moratorium and the
unfortunate history of these
rules.
The Board has weighed the
very real necessity to adopt approvable rules against the rather
vague and, for the most part,
theoretical arguments in opposition
to these aspects of the proposal
and has concluded that the most
prudent course
is to proceed as proposed by the Agency.
The
Board cannot find that the proposal
is
so unreasonable as to
counter—balance the need for expeditious adoption of approvable
rules.
On the contrary, the Board commends the Agency for the
work
it has done
to fashion approvable rules within an ill—
defined context.
SECTION BY SECTION ANALYSIS
The Board’s proposal
is based upon the Agency’s recommended
changes to
its second amended proposal and a draft of the federal
NSR program for Illinois.
The Board has reviewed these proposals
and for the most part has based
its proposal on the Agency’s
proposal.
Certain differences between the federal and the Agency
proposal are unavoidable due to the difference
in the format of
the rules and the
federal and state environmental structure.
Such differences are not noted
in the following analysis.
The
Board has, however,
identified some minor differences between the
proposals which may be significant and has noted them in its
analysis.
The Board has also made some changes
to the Agency
proposal for purposes of clarity.
Those changes are not intended
to have any substantive affect,
but
if inadvertent substantive
changes have been made, comment
is requested.
The Board has
further asked some questions about language which it believes may
be questioned by the Joint Committee on Administrative Rules
77-426
—9—
(3CAR)
and comments on these questions are requested.
Finally,
in some instances the Board is uncertain of the intended
substantive meaning
of some rules
or the Board has questioned
whether the rules accurately state the intent.
Comment is also
requested regarding such questions.
Where
“no change”
is
indicated,
the Board means that no change has been made to the
Agency’s latest proposal.
Section 203.103:
No change.
Section 203.104:
In line 3,
the federal language
is “average
annual rate;” Agency proposal
is “average rate.”
Some minor
language changes have been proposed solely for purposes of
clarity.
No substantive change is intended.
Beyond that,
the
Board
reads this section as meaning that actual
emissions are
to
be determined by the average actual emissions for the previous
two years
if the Agency has determined that period
to be
representative of normal operations.
Further,
under subsection
(a)
the Agency must allow the use of an alternative period
if the
applicant demonstrates that the alternative
is more
representative of normal operations.
This appears
to leave a gap
if the Agency has not determined the previous two years
to be
representative and
the applicant has not demonstrated that an
alternative period
is more representative.
The proposed rule
does not appear
to allow the Agency to determine actual emissions
on any basis other than the previous two year average unless the
applicant accepts its burden of demonstrating that an alternative
period is more representative.
Yet,
it
would
seem
that
the
Agency
should
have
the
ability
to
demonstrate
that
some
other
period
is
more
representative and to’make its calculation of
actual emissions on that basis.
The Board would appreciate
comments on these
issues.
It may be that additional language is
needed
to clarify this section.
Section 203.107:
In subsection
(a)
the federal language
is
“allowable emissions
rate.-;” Agency proposal
is simply “emission
rate;” the federal language is “other such enforceable limits;”
Agency language
is simply “other such limits.”
In the first
instance the Board has proposed the federal language, while
in
the
second
instance,
it
has
followed
the
Agency
proposal.
In
subsection
(C)
the Agency language is “Chapter” while the Board
has proposed “Subtitle.”
Sections 203.110 and 203.112:
No change.
Section 203.113:
In subsections
(a)
and (b), what would
constitute a “substantial loss” and what is a “reasonable
time.”
The Board suspects that JCAR will desire some
specification of criteria used to make these determinations.
Sections 203.116 and 203.117:
No change other than
capitalization in Section 203.117.
77-427
—10—
Section 203.123:
Agency’s proposal of “Chapter” has been changed
to
“Subtitle;” capitalization has been changed.
Section 203.126:
Can the words “reasonably pass” be made more
specific?
Section 203.125 and 203.126:
No change.
Section 203.131:
The Board has added the word “adopted”
in the
last line and modified the capitalization.
Section 203.134:
Only change
is deletion of the word “otherwise”
(consistent with the federal language)
which seems redundant.
Can the words “reasonably foreseeable” be made more specific?
Are they necessary?
They are not included
in the federal
language.
Section 203.136:
No change.
-
Section
203.145:
The
Board
has
deleted
the clause “The following
compounds
do
not
constitute volatile
organic
compounds:”
as
redundant.
Section 203.150:
What
is “notice of the same?”
Is
it notice of
an intent to issue or notice of application, or something else?
This appears
to refer
to “permit application” language which has
been deleted.
Could
it be made more specific?
Section 203.201:
No change.
Section 203.202:
No change except deletion of
“B”
after
“Subpart.”
-
Section 203.203:
Wording changes have been made to subsections
(a) and
(ci) which are intended to be non—substantive.
Section 203.205:
No change.
Section 203.206:
In subsection
(c) what does “approximately
half” mean?
Why not simply “half.”
Minor wording changes have
been made
to subsections (a)(2) and
(d)
which should not have any
substantive effect.
Section 203.207:
Minor, non—substantive language changes have
been made to paragraphs (c)(5)
and (c)(6).
The Board notes that
in (c)(5)(A) and
(c)(6),
“40 CFR 52.21” has been deleted, but not
in (c)(5)(B).
Is this intended?
Section 203.208:
In line
1
of the introductory paragraph,
“sum”
has been replaced with “total.”
In the last line of that
paragraph,
what does
it mean that “an increase or áecrease
in
77-428
—11—
emissions
is available.”
That term should be further explained
or rephrased.
Is there any distinction between that term and the
term “creditable”
in subsections
(b) and
(c)
and
in the
introductory paragraph?
If not,
can the final sentence of the
introductory paragraph
be deleted or rephrased?
Paragraph (b)(1)
is confusing and should be reworded.
The proposed replacement of
“in effect” with “permitted” adds to
the confusion.
The essence
of the paragraph (“only if no other permit has been issued
for
the source
...
which relied on the same increase or decrease
in
actual emissions”)
is clear,
but the middle clause, as proposed,
is not.
Must the
“other permit” have been
in effect when the
change occurred, or at the time “credit”
is attempted to be
taken,
or both?
The
tenses are confusing and the sentence does
not appear
to be grammatically correct.
In paragraph (c)(l),
what does “approximately the
same qualitative significance for
public health and welfare” mean?
Would
it be appropriate to
reword this as follows:
“It offsets any threat
to the public
health and welfare which may be attributed to
...“?
Section 203.209:
Federal language includes a significance level
for lead.
The Agency’s proposal does not.
Since lead
is a
criteria
pollutant,
the
Board
has
followed
the federal
language.
Sections
203.110
and
203.111:
The
only
changes
are
that
“this
Part
203”
has
been
replaced
with
“this
Part”
for
consistency of
format
with
other
rules.
This
change has been made at several
points
in
the
proposal.
Sections
203.301
and
203.302:
No
change.
Section
203.303:
In
subsection
(b)
the
same
“qualitative
significance”
language
appears
as
in
Section
203.208(c)
(2)
and
the
same
comment
applies.
In paragraph
(d)(l), what constitutes
an “appropriate analysis”?
Also, how will the Agency determine
whether
to “decline”
to make an analysis?
In paragraph
(d)(3),
could the language “be
in the broad vicinity of the proposed new
or modified source”
be deleted?
How
is
it to be determined which
“other
areas
...
may be contributing to the ozone problem”?
Finally, minor, non—substantive language changes have been made
throughout this section.
Section 203.305:
No change.
Section 203.601:
No change.
Section
203.602,
203.603
and
203.701:
Minor,
non—substantive
language
changes.
The
Board
is
concerned,
however,
that
the
changes
to Section 203.602 may inadvertently affect the
meaning.
Comment is requested on this point.
77-429
—12—
TITLE
35:
ENVIRONMENTAL PROTECTION
SUBTITLE B:
AIR POLLUTION
CHAPTER I:
POLLUTION CONTROL BOARD
SUBCHAPTER a:
PERMITS
AND GENERAL PROVISIONS
PART 203
MAJOR
STATIONARY SOURCES CONSTRUCTION
AND
MODIFICATION
SUBPART
A:
GENERAL
PROVISIONS
Section
203.101
203.103
203.104
203.107
203.110
203.112
203.113
203.116
203.117
203.119
203.122
203.123
203.124
203.125
203
.
126
203.128
203.131
203.134
203.136
203.145
203.150
Section
203. 201
203.202
203.203
203. 205
203.206
203.207
203.208
203.209
203.210
203.211
Definitions
Actual Construction
Actual Emissions
Allowable Emissions
Available Growth Margin
Building, Structure or Facility
Commence
Construction
Dispersion
Enhancement
Techniques
Emission
Baseline
Emission Offset
Emissions Unit
Fugitive Emissions
bAER
Installation
LAER
Potential
to Emit
Reasonable Further Progress
Secondary Emissions
-
Stationary Source
Volatile Organic Compounds
Public Participation
Se~e~eb~~y
SUBPART
B:
MAJOR
STATIONARY
EM~SS~SNS
SOURCES
IN NONATTAINMENT AREAS
Prohibition
Coordination with Preeen
r~e~4ert
Permit
Requirement and Application Pursuant to Part 201
Construction Permit Requirement and Application
~et~en
o?
een8b~et4ert
Per,n4t
Effect
of
Preeenetrt~et~et~end
Construction
Permits
Major
Stationary
En~~es~en
Source
Major Modification of a Source
Net Emission Determination
Significant Emissions Determination
Relaxation of a Source—Specific Limitation
Permit Exemption Based
on Fugitive Emissions
77-430
—13—
SUBPART
C:
REQUIREMENTS
FOR
MAJOR
STATIONARY
SOURCES
IN
NONATTAINMENT
AREAS
Section
203.301
Lowest Achievable Emission Rate
203.302
Maintenance of Reasonable Further Progress and
Emission
Offsets
203.303
Baseline and Emission Offsets Determination
~8~394
Exem~t~en~
?~om
~~ens
e?feet
Reqa~rement
203.305
Compliance by Existing Sources
203.306
Analysis of Alternatives
SUBPART F:
OPERATION OF A MAJOR STATIONARY SOURCE
OR MAJOR MODIFICATION
Section
203.601
Lowest
Achievable
Emission
Rate
Compliance
Requirement
203.602
Emission Offset Maintenance Requirement
Am~,4entMeMter4n~ Re~femen~
SUBPART G:
GENERAL MAINTENANCE OF EMISSION OFFSETS
Section
203.701
General Maintenance of Emission Offsets
AUTHORITY:
Implementing Section 9.1 and authorized by Sections
5
and
27
of
the
Environmental
Protection
Act
(Ill.
Rev.
Stat.
1985,
ch.
111
1/2,
pars.
1005,
1009.1
and
1027).
SOURCE:
Adopted
and
codified at
7
Ill.
Reg.
9344,
effective
July
22,
1983; codified at
7
Ill.
Reg.
13588,
amended
in R85—20,
Ill. Reg.
_____,
effective
__________
77-431
SUBPART A:
GENERAL PROVISIONS
Section 203.103
Actual Construction
“Actual Construction” means in general, initiation of physical
on—site construction activities
on an emissions unit which are of
a permanent nature.
Such activities include, but are not limited
to, installation of building supports and foundations,
laying of
underground pipework, and erection of permanent storage
structures.
With respect to
a change
in method of operation,
this term refers
to those on—site activities other than
preparatory activities which mark the initiation of the change.
Section 203.104
Actual Emissions
“Actual Eemissions” means
the actual
rate of annual emissions of
a pollutant from an epe
t~ene~emissions eo~ee unit ?or
as of
a
particular date.
Actual emissions are equal
to the meen average
rate at which the emissions ee~reeunit actually emitted the.
pollutant during the two—year period which immediately precedes
the particular date end
if that period
whteh
is determined by the
Illinois Environmental Protection Agency (Agency)
to be
representative of normal e,~iee~onsource operation.
Actual
emissions shall
be calculated using
the unit’s actual operating
hours, production rates, and types of materials processed,
stored
or combusted during the selected time period
however:
a)
The Agency shall allow the use of
a different time perioc
upon a determination by the Agency that
it
is more
representative of normal ern4ee~onsource operation.
The
burden shall be on the applicant to demonstrate that
another time period
is more representative.
Aet~e~
etn~se~ens
ehe~ ~e ee~e~etedt~e~ng
the em4eMen
t~ee~L.e
eet~e~operet4n~het~re7pfod~et~en~etee7 end typee of
~ete~e~e
preeessedy stored7 or eem~ueteddt~r~ng
the
se~eetedt~meper4odT
b~-
~f
the Ageney determ~nee
thet
there 4s 4nedeqtiete
~rtforntet~ento determine eet~e3em5se~onees ~nd~eeted 4n
the preeed~ngperegrephe-, the Agency she~ t~ee
the
potent~e~ to
emit
of
the
er~se5~enseuree~
b)
The Agency may presume
in the absence of reliable data on
actual emissions that the source—specific allowable
emissions for the emissions unit are equivalent to the
actual emissions of the emissions unit.
c)
For any emissions unit which has not begun normal
operations on the particular date, the Agency shall
presume that the potential to emit of the emissions unit
is equivalent
to the actual emissions on that date.
77-432
—15—
Section 203.107
Allowable Emissions
a)
“Allowable Eemissions” means the emission rate of en
en~es4ona stationary source calculated using the
maximum rated capacity of the eM4es~onsource
(unless
the em4se4on source
is subject
to enforceable permit
conditions or other such enforceable limits which
restrict the operating rate, or hours of operation, or
both)
and
the n~eremost stringent of the following:
1)
The applicable standards set forth
in 40 CFR 60
or
40 CFR 61.
~+2) The applicable emission standard or limitation
contained
in the Illinois State Implementation
Plan, as described at 40 CFR 52, Subpart 0, th4s
ehepter
including those with
a future compliance
date
(generally
the
applicable
standards
or
limitations contained
in this Subtitle)
or
~-~3)The emissions rate specified as an enforceable
permit condition including those with a future
compliance
date.
b)
The allowable emissions may be expressed as a permit
condition limiting annual emissions or material or
fuel
throughput.
c-)
A~oweb~eem-i~e4ensehe~ ~ne~de
e reesone~eest4i~tete
of eM~ss4ens~n e~eeseof epp~4eeb~eetenderds dur~ng
etert—~py~ieH~net~ony or ~reekdowny es eppropr~ete7
on’y 4f the prov~e4ensof ~
~
Adm~eede ~
heve
seen eomp~edwtth7
d-)’c)
If
a en e~es4onsource
is not subject to an emission
standard
under
subsection
(a)
and
is
not
conditioned
pursuant
to subsection
(b), the allowable emissions
shall be the
source’s
potential
to
emit.
Section
203.110
Available
Growth
Margin
~Aye~eb~e
growth
rt~erg~&’
teens
the
difference
between
tetei
e~eweb~ee~ee~ons eene~stent
with
reesoneb~e ?~rther
progress
end
pro~eeted
eet~e~e~n
one
4n e nonette4nment eree--
“Available Growth Margin” means
the portion which remains of any
emission allowance for new or modified major stationary sources
expressly
identified
in the attainment demonstration approved by
the U.S. Environmental Protection Agency
(USEPA)
under
Section
172(b) (5)
of the Clean Air Act
(42 USC 702(b)(5)
for a
particular pollutant and area.
-
-
77-433
—16—
Section 203.112
Building, Structure or Facility
~j
The
terms “building”, “structure”, or “facility”
include
all of the pollutant—emitting activities which belong to
the
same
industrial
grouping,
are
located
on
one
or
more
contiguous
or
adjacent properties, and are under
the
control_of_the
same
person
(or
persons
under
common
control).
Pollutant—emitting
activities
shall
be
considered
as
part
of
the
same
“Major
Group”
(i.e.,
which
have
the
same
two—digit
code)
as
described
in
the
Standard
Industrial
Classification
Manual,
1972,
as
amended
by
the
1977
Supplement
(U.S. Government Printing
Office
stock
numbers
4101—0066
and
003—005—00176—0,
respectively).
b)
The
terms
“building”,
“structure”,
or “facility”
shall
also
include
1)
the
transfer
of materials,
including but not
-
limited
to grain,
gasoline, petroleum liquids,
coal, fertilizer,
crushed stone and ore, from
vessels, motor vehicles or other conveyances
to or
from a building, structure,
or facility as defined
in subsection
(a), and
2)
activities at or adjacent
to such building,
structure
or
facility
which
are
associated
with
such
transfer,
including but not limited
to
idling
of
propulsion
engines,
the operation of engines
to
provide
heat,
refrigeration
or
lighting,
operation
of auxiliary engines for pumps or cranes, and
transfer of materials from hold
to hold
or tank to
tank during onloading or offloading operations.
Section 203.113
Commence
As applied
to construction of a major stationary source or major
modification “commence” means that the owner or operator has
obtained all necessary preconstruction approvals or permits and
either
has:
a)
Begun,
or caused to begin,
a continuous program of
actual on—site construction of the source,
to be
completed within e4~ghteenMonths efter the dete the
perM4t 45 grented~a reasonable time
or
b)
Entered into binding agreements or contractual
obligations, which cannot be canceled
or modified
without substantial loss
to the owner or operator,
to
undertake
a program of actual construction of the source
to be completed within
a reasonable time.
77-434
—17—
Section 203.116
Construction
“Construction” means any physical change or change
in the method
of operation,
including but not limited
to fabrication, erection,
installation, demolition,
or modification of an emissions eo~ree
unit, which would result
in a change
in actual emissions.
Section 203.117
Dispersion Enhancement Techniques
“Dispersion Enhancement Techniques” mean so much of the stack
height of any source
as exceeds good engineering practice or any
other dispersion technique, determined by regulations at 40 CFR
51.1 or 51.12 pursuant
to Section 123 of the Clean Air Act
(42
U.S.C.
7423).
Section 203.123
Emissions Unit
“Emissions Unit”
means any part
of stationary source which emits
or
has
the
potential
to
emit
any
pollutant
subject
to
regulation
under
this
Subtitle
or
the
Clean Air Act
(42 U.S.C.
7401
et
seq.).
Section
203.124
Fugitive
Emissions
“Fugitive
Emissions”
means
those
emissions
which
could
not
reasonably
pass
through
a
stack,
chimney,
vent or other
functionally
equivalent
opening.
Section
203.125
Installation
“Installation” means an identifiable piece of equipment.
Section ~
203.126
LAER
“LAER”
is an abbreviation for lowest achievable emission rate.
Section 203.131
Reasonable Further Progress
“Reasonable
F?urther
~progress”
means
the
annual
incremental
reductions
in
the
emissions
of
the
applicable
air
pollutant
sufficient
to
provide
for
attainment
of
the
National
Ambient
Air
Quality
Standards
as
expeditiously as practicable,
in accordance
with
Part
D
of
the
Clean
Air
Act
(42
U.S.C.
7501
et
seq.)
and
40
~
as
amended
at
44 FR ~~69y
May
~0y
~9~97
federal
regulations adopted pursuant thereto.
Section 203.134
Secondary Emissions
“Secondary emissions” means
the emissions which would occur
as
a
result of the construction or operation of
a major stationary
source or major modification,
but do not come from the major
stationary source
or major modification itself.
For the purpose
77-435
—18—
of this Part,
secondary emissions must be specific, well defined,
quantifiable,
and impact the same general area as the stationary
source
or modification which causes the secondary emissions.
Secondary emissions may include, but are not limited
to,
emissions from any reasonably foreseeable off—site support
facility which would not etherw4se be constructed or increase its
emissions except as a result of the construction or operation of
the major stationary source or major modification.
Section 203.136
Stationary Source
“Stationary Source” means any building, structure,
facilit~’or
installation which emits or may emit any air pollutant subject to
regulation under
the Clean Air Act
(42 U.S.C.
7401 et seq.).
Section 203.145
Volatile Organic Compound
“Volatile Organic Compound”
means any chemical compound of
carbon,
released
to or present
in
the atmosphere
in a gaseous
state,
including compounds which are liquids at standard
conditions,
but excluding the following
compounds:
methane,
ethane, carbon monoxide, carbon dioxide, carbonic acid, metallic
carbonic acid, metallic carbide, metallic carbonates,
ammonium
carbonate,
1,1,1 trichloroethane
(methylchloroform), methylene
chloride,
trichlorotrifluorenthane
(Freon
113),
trichlorofluoromethane
(CFC—ll), dichlorodifluoromethane
(CFC—
12), chlorodifluoromethane
(CFC—22), trifluoromethane
(FC—23),
trichiorotrifluoroetnane
(CFC—1l3),
dichlorotetrafluoroethane
(CFC—l14), chioropentafluoroethane (CFC—ll5).
Section 203.150
Public Participation
At the 4n4t4et4on of a perm4t epp~4eat4onPrior to the
initial
issuance of
a permit pursuant to Subpart B,
the Agency shall
provide at
a minimum, notice of the same and a comment period
pursuant to the Agency public participation procedures found
at
35
Ill.
Code 166.
Sect4ert
~9I4S~
Severe~4~4ty(Repealed)
Notw4~thetand4ng35
Adm~eode ~6~~Sy
4f any prev4e4on of
Part ~03 4s stayed or dee~ered4rwa~4d~y a f4na~order-i no
‘onger stt~jeetto eppee~yof any eot~rtof competent ~r4sd4et4on7
then the ent4rety of Part ~93 shaH ~e deemed eteyed or
4n~aHdetedurtt4~the stay 4s Hfted or the Board acts to
revaHdate the Party
77-436
—19—
SUBPART B:
MAJOR STATIONARY EMISSIONS
SOURCES IN NONATTAINMENT AREAS
Section 203.201
Prohibition
In any area designated nonattainment,
as defined at Section
171(2)
of the Clean Air Act
(42 U.S.C.
7501(2)), nNo person shall
cause or
allow the construction of a new major stationary source
or major modification
4rt en area des4gnated as that
is major
for
the pollutant for which the area
is deisgnated nonattainment as
def4ned
at
Seet4on
~-f~-)
of
the
e~ean Mr
Act *4~BTS~0T
~5~7~)
w4th
respect
to
that
poHutent,
except
as
in
compliance
with
this
Part for that pollutant.
Section 203.202
Coordination With Preeortstr~et4enPermit
Requirement and Application Pursuant
to Part
201
For new major sources and major modifications, the fulfillment of
the requirements of Part 201 related
to construction, including
the
permit
requirements
of
35
Ill.
Adm.
Code
201.142,
shall
be
combined
with
the requirements of this Subpart.
a)
AppHeat4ons
for
preconstr~ct4ort
perm4ts
shaH
eonte4n
s~ff4e4ent
4nfermat4en
to
demonstrate
that
the
so~ree
eorist4tt~tes
or
does
not
eonst4tt~tee
a
new
me~or ee~ree
-
or
me~or mod4f4eat4ert
p~rsuent
to
th4e
Subpert--
b-)
A
preeenetrt~ct4on
perm4t
des4gnat4ng
the
proposed
eonstr~et4on
as
a
new
maser
so~ree
or
major
mod4f4eat4or
4s
regt~4red pr4or
to~
~3
Enter4ng
4nte
b4nd4ng
agreements
or
eontreet~a~
obHget4one7
wh4eh
cannot
be
eance~ed or
med4f4ed
w4thet~t et~bstant4ai
ioss
to
the
owner
or
operator7
to
undertake
a
program
of
aet~a~eonstrt~et4en
of
a
source
to
be
comp’eted
w4th4n
a
reesonab~e
t4met
~
~n4t4et4ng
phys4ea~ on-s4te
construet~on
aet4~4t4e~
wh4eh
are
permanent
4n
nature
4nc~ud4ng but
not
Hm4ted
to
4nstaHat4on
of
buHd4ng
supports
end
foundat4ons
iay4ng
underground
p4pewerk
and
eortstruet4on of permanent storage struetureet or
3)
~n4t4at4ng a change 4n eperet4ons wh4eh may be
subject to th4s Subpart or
Subpart
e-~
Section 203.203
Construction Permit Requirement and
Application
a)
A construction permit
is required prior
to hav4ng begun
or hav4ng caused to beg4n a eont4nueus program of actuaJ
77-437
—20—
on—s4te construction of a major new source
or major
modification.
or change 4n eperet4ons -of the soureeT
Such perm4t shaH eente4n en?ereeeb~eeend4t4ens
sat4efy4ng the requ4rements of Subparts B end
e7
b)
Applications for construction permits required under
this
Section
shall
contain
sufficient
information
to
demonstrate
compliance
with
35
Ill.
Adm.
Code
201
and
the requirements of this Subchapter
including, but not
limited to, Subpart C.
c)
The permit shall
include conditions specifying
the
manner
in which
the requirements of Subparts B and C are
satisfied.
d)
No permittee shall violate any condition contained
in a
construction permit issued for
a new major stationary
source or major modification which
is subject
to this
Part.
Seet4on ~63~94
Burat4on of eenstruet4on Perm4t
A perm4t to construct shaH become 4nveHd 4? the perm4ttee has
not commenced censtruct4on w4th4n ~8 months after reee4pt of such
perm4ty censtruet4on 4s d4eeent4nued for a per4od of ~8
eonseeut4~emonths or moreT
However-i th4s prov4s4en does not
epp~yto the
t4nte per4ed between censtruet4en of the approved
phases of a phased construct4on projectt each phase must beg4n
actua’ construct4on w4th4n 3~8months of the dates cente4ned 4n
the perm4t eppHeat4on--
Section 203.205
Effect of Preconstruct4ort and Senstruct4on
Permits
The issuance of ne4ther a preeenstruet4en nor
a conetruct4on
a
permit for
a source subject to the requirements of this Part
shall not relieve any person of the responsibility to comply
fully with applicable provisions of the Environmental Protection
Act (Ill. Rev.
Stat.
l98~5,ch.
1ll~/2, pars.
1001 et seq.),
the
regulations contained
in this ehapter Part,
the Clean Air Act
(42
U.S.C.
7401 et seq.)
and federal regulations adopted thereunder
including the Illinois State Implementation Plan, and
or other
applicable requirements under local, state and federal
law.
through the effeet4~edate of th4s Subpart.
Section 203.206
Major Stationary Em4se4on Source
A major etat4onery em4es4on source that 4s major for organ4e
mater4e3 shaH be cons4dered major for oeone~
a) The
following
constitutes a major stationary em4ss4on source:
77-438
—21—
a-)3~jAny stationary em4ss4on source of air pollutants
which emits, or has the potential to emit, 100 tons
per year or more of any pollutantT subject to
regulation under
the Clean Air Act for which the
area is designated nonattainment pursuant to
Section 107 of the Clean Air Act
(42 U.S.C.
7407).
b-~2)Any physical change that would occur
at a
stationary em4ss4en source not qualifying under
paragraph
1
subseet4on
-~e-) as
a
major
stationary
em4ee4on source,
if the change would constitute
a
major stationary em4ss4on source by itself.
b)
A major stationary scource that
is major
for volatile
organic
compounds
shall
be
considered
major
for
ozone.
c)
The reconstruction of
a stationary em4es4on source will
be treated as the construction of
a new major stationary
source
if the fixed capital cost of new components
exceeds approximately half of the fixed capital cost of
an entirely new stationary source.
Determining whether
reconstruction will occur
is based on the following:
1)
Fixed capital cost shall mean the capital needed
to
provide all the depreciable components;
2)
The
fixed capital cost for the replacements
in
comparison to the fixed capital cost that would be
required
to construct a comparable entirely new
source;
3)
The estimated life of the source after
the
replacements compared to the life of a comparable
entirely new source;
and
4)
The extent. to which the components being replaced
cause
or contribute to the emissions from the
-
source.
d)
For purposes of this Part, the fugitive emissions of
a
stationary source shall not be
included
in determining
whether
it
is
a major stationary source,
unless the
source belongs to one of the following categories of
stationary
sources:
1)
Coal cleaning plants
(with thermal dryers);
2)
Kraft pulp mills;
3)
Portland cement plants;
4)
Primary zinc smelters;
5)
Iron and
steel mills;
6)
Primary aluminum ore reduction plants;
7)
Primary copper smelters
77-439
—22—
8)
Municipal incinerators capable of charging more
than 250 tons of refuse per day;
9)
Hydrofluoric, sulfuric, or nitric acid plants;
10)
Petroleum refineries;
-
11)
Lime plants;
12)
Phosphate
rock processing plants;
13)
Coke oven batteries
-
14)
Sulfur recovery plants;
15)
Carbon black plants
(furnace process);
16)
Primary lead smelters;
17)
Fuel conversion plants;
16)
Sintering plants;
19)
Secondary metal production plants;
20)
Chemical process plants
-
21)
Fossil—fuel boilers
(or combination thereof)
totaling more than 250 million Btu per hour heat
input;
22)
Petroleum storage and transfer
units with a total
storage capacity exceeding 300,000 barrels
-
23)
Taconite ore processing plants;
24)
Glass
fiber processing plants;
25)
Charcoal production plants;
26)
Fossil
fuel—fired steam electric plants of more
than 250 million Btu per hour heat input;
27)
Any other
stationary source category which
is being
regulated,
as
of August
7,
1980,
under Section 111
or 112 of the Clean Air Act
(42 USC 7411,
7412).
Section 203.207
Major Modification of a Source
a)
Any physical change, or change
in the method of
operation of
a major
stationary em4ss4on source that
would result
in a significant net emissions increase of
any pollutant,
for which the
area
is designated
nonattainment pursuant
to Section 107 of the Clean Air
Act
(42 U.S.C.
7407), except as provided
in subsection
(c). that a phys4ce~change or change 4n the method of
operat4on shaH not 4rie~udeany act4v4ty 34sted be~ow-
b)
Any net emissions increase that
is significant for
volatile organic compounds organ4c mater4a~shall
be
considered significant for ozone.
c)
A physical change
or change
in the method
of operation
shall not include:
a-)-
1)
Routine maintenance,
repair, and replacement of
components which does not constitute reconstruction
pursuant
to Section 203.206(c).
2)
Use of an alternative fuel or
raw material
by
reason of any order
under Sections 2(a)
and
(b)
of
77-440
—23—
the Energy Supply and Environmental Coordination
Act of 1974
(15 U.S.C.
791),
the Power Plant and
Industrial Fuel Use Act of 1978
(42 U.S.C.
8301)
(or any superseding legislation)
or by reason of
a
natural gas curtailment plan pursuant
to the
Federal Power Act
(16 U.S.C. 791, et seq.)
c-)
3)
Use of an alternative fuel by reason of an order
or
rule under Section 125 of the Clean Air Act
(42
U.S.C.
7425).
d-)-
4)
Use of an alternative fuel at a steam generating
unit to the extent that the fuel is generated from
municipal solid waste.
e+
5)
Use of an alternative fuel or raw material
by a
stationary source which:
3-)-
A)
~t Was capable of accommodating such
alternative fuel or raw material before
December 21,
1976 and has continuously
remained capable of accommodating such fuels
or materials unless such change would
be
prohibited under any enforceable permit
condition which was established after that
date pursuant to
49
CPR ~
as amended at
45
FR S~357August ~
~989 or this Part or
35
Ill Adm. Code 201.142
or
201.143.
i-)-
,B
Is approved for use under any permit issued
pursuant
to
40
CFR
52.21,
as
amended
at
4S
FR
5~35 August
~,
~989 or this chapter Part or
35
Ill. Adm. Code 201.142 or 201.143..
f-)
6)
An increase
in the hours of operation or
in the
production rate, unless such change wou’d be
is
prohibited under any enforceable permit condition
which was established after December
21,
1976
pursuant
to 48 ~FR
S~T~3~7
as amended at 4S FR
~~357
August ~
3~980-, this Part,
35
Ill.
AcIm.
Code
201.142
or 201.143.
or th4s Chapter
g3-
Any 4ncrease 4n em4ss4ons of ergan4c mater4a~due to the
temporary shutdown of a eontre~dev4ee dur4ng seasona’
per4ods
as
aHowed
by
35
fl~
AdMT
Cede
~
h-)
7)
Any change
in ownership at
a stationary source.
Section 203.208
Net Emission Determination
A net emissions
increase
is the amount by which the sum total
of
any increase
in actual emissions from
a particular physical
77-441
—24—
change or
change in method of operation at a en em4ss4en source,
and any other
increases and decreases in actual emissions at the
em4es4en source that are contemporaneous with the particular
change and are otherwise creditable,
exceeds zero. The following
steps determine whether
the increase or decrease
in emissions is
available.
a)
An increase- or decrease in actual emissions
is contem-
poraneous only if
it occurs between the date that an
increase from a particular
change occurs and
the date
five years before a timely and complete application is
submitted
for the particular change.
~n the case of en
4ncrease
i~tmust also occur after either April
24,
-
1979 or the date the area
is designated by the United
States Environmental Protection Agency (USEPA)
as a
nonattainment area for
the pollutant, whichever is more
recent;
b)
An increase or decrease
in actual emissions is credit-
able:
1)
Only if no other permit has been issued
end for
the source, which
is still 4n effect permitted when
the particular change occurs, which relied on the
same increase
or decrease
in actual emissions;
and
~n the case of a shutdown of an em4ss4ort source-,
on~yto the extent that
tt
4s be4ng rep3aced by
a
s4m4iar eource~end
3+2) Only to the extent the new and old levels differ.
c)
A decrease
in actual emissions is creditable
to the
extent that:
1)
It
is enforceable at and after the time that actual
construction on the particular change begins;
2)
It has approximately the same qualitative
significance for public health and welfare as that
attributed
to the increase from the particular
change;
3)
That Tthe old level of actual emissions or the old
level of allowable emissions, whichever is lower,
exceeds the new level
of actual emissions;
and
4)
It
is demonstrated by the Agency not
to have been
previously relied on
in issuing any permit pursuant
-
to this Part
or
35 Ill. Adm. Code 201.142
or
201.143
or
for demonstrating attainment on or
reasonable further progress
in the nonattainment
77-442
—25—
area which the phys4ca~particular change will
impact.
d)
An increase
that results from a physical change at a
source occurs when the emissions unit on which
construction occurred becomes operational and begins to
emit a particular pollutant.
Any replacement unit that
requires shakedown becomes operational only after a
reasonable shakedown period, not
to exceed 180 days.
Section 203.209
Significant Emissions Determination
A net emission increase
in the pollutant emitted
is significant
if the rate of emission is equal
to or
in excess of the
following:
a)
Carbon monoxide:
100 tons per year
(tpy)
b)
Nitrogen oxides:
40
tpy
c)
Sulfur dioxide:
40 tpy
d)
Particulate matter:
25 tpy
e)
Ozone:
40
tpy of organ4c mater4a~volatile organic
compounds
f)
Lead:
0.6 tpy
g-)-
Asbe~tos~9--98~tpy
-
h+
BeryH4um~ 9~9684tpy
4-)
Mereury~ G~ tpy
~-)
V4ny3
ch~er4de~-.-3~tpy
k~3-
Per4des-
3 tpy
3~)-
Su~fur4cec4d m4sti
~ tpy
in-)
Hydrogen su~f4de*H~S+i~38 tpy
rt+
Pota~reduced su~fur-~4ne~ud4ng
H25+i
~9 tpy
0+
Reduced su~furcompounds -~4nc~ud4ng
H~S-)-~- ~8 tpy
Section 203.210
Relaxation of a Source—Specific Limitation
Bxcept those mod4f4eat4ons exempted pursuant to Sect4on ~83~8~7
at such t4me that a part4eu~arsource or mod4f4cat4on becomes
a
major stet4onary source
or major mod4f4cat4on by ,4rtue of a
77-443
—26—
re~axat4on4n any enforeeeb~eHm4tat4on wh4ch estabHshes
a
spee4f4c standard for that source to em4t a peHutant-, th4s
Subpart shaH app’y to the source or mod4f4eet4en as though
construct4en had net yet commenced~
-
a)
No person shall
cause or allow the operation of a source
-
so as
to exceed any enforceable limitation which affects
or defines the applicability of the requirements of this
Part to
a stationary source or modification,
by
specifying
the permissible emission rate, operating
hours, the type or amount of material processed!
stored
or combusted,
or other aspects of source operation.
b)
At such time that a particular source or modification
becomes a major stationary source or major modification•
solely by virtue of a relaxation
in, or expiration of,
any enforceable limitation which was established after
-
August
7,
1980, on the capacity of the source or
modification otherwise to emit a pollutant, such as
a
restriction on hours
of operation,
then the requirements
of this Part
shall apply as though construction had not
yet commenced on the source or modification.
Section 203.211
Permit Exemption Based
on Fugutive Emissions
The provisions of this Part shall not apply to a source or
modification that would be
a major stationary source or major
modification only if fugitive emissions,
to
the extent
quantifiable, are considered
in calculating
the potential to emit
of the stationary source or modification and the source does not
belong
to
any
of
the
categories
enumerated
in
Subsection
203.206(c).
SUBPART C:
REQUIREMENTS FOR MAJOR STATIONARY
SOURCES
IN NONATTAINMENT AREAS
Section 203.301
Lowest Achievable Emission Rate
a)
For any source,
lowest achievable emission rate
(LAER)
will
be
the
more
most
stringent
rate
of
emissions
based
on the following:
1)
The ~owest most stringent emission limitation which
is contained in the implementation plan of any
state for such class or category of stationary
source,
unless
it
is demonstrated that such
limitation
is not achievable;
or
2)
The ~owest most stringent emission limitation which
is achieved
in practice or 4s ach4evab~eby such
a
class or category of stationary source.
~ or
This
limitation, when applied to a modification, means
77-444
—27—
the lowest achievable emissions
rate for the new or
modified emissions units within the stationary
source.
In no event
shall
the application of this
term permit
a proposed new or modified stationary
source to emit any pollutant in excess of the
amount allowable under an applicable new source
performance standard.
3+
The appHeab~enew source performance standard
eonta4ned 4n 35 H~
Adm-- Code 338~
b)
The owner or operator of a new major stationary source
shall demonstrate that the control equipment and process
measures
applied
to
the
source
will
produce
LAER.
C)
The owner
or operator of a major modification shall
demonstrate that the control equipment and process
measures applied
to the major modification will produce
LAER.
This requirement applies to at each emissions
source unit at which
a net e4gn4f4cent increase
in
emissions of the pollutant has occurred
or would occur
as
a result of
a physical change or change
in the method
of operation.
d)
The owner
or operator shall provide a detailed showing
-
that the proposed emission limitations constitute
LAER.
Such demonstration shall
include:
1)
A description of the manner
in which the proposed
emission limitation was selected, including
a
detailed listing of information resources,
2)
Alternative emission limitations,
and
3)
Such other reasonable
information as the Agency may
request as--necessary to determine whether the
proposed emission limitation
is LAER.
Section 203.302
Maintenance of Reasonable Further Progress and
Emission Offsets
a)
For part4cu~atematter~su~furd4ox4dey notrogen ox4deey
or carbon monex4de em4ss4ons tThe owner
or operator of a
new major source or major modification shall provide
emission offsets equal
to or greater than the allowable
emissions from the source or the net increase
in
emissions from the modification sufficient
to allow the
Agency to determine demonstrate that the source
or
modification will not interfere with reasonable further
progress.
-
77-445
—28—
3~+
Prov4d4ng equai
or greater em4ss4on offsets for the
aHowaHe
em4ss4ons from the source or the net
4nereese
4rt ein4es4ens from the mod4f4cat4on-y and
demenstrat4ng that actua~eve~agea4r quaHty
w4H
be 4mproved 4n the nonatta4nment area and that at
no ioeat4en w4H the 4mpaet exceed the e4gn4f4cant
a4r quaHty 4mpact ieveis eenta4ned 4n Seet4on
~837394~d+t
2-)
Bemonstrat4ng that a4r quaHty 4n the nenatta4nment
area wtH be 4mproved at every ~eeat4on affected by
the new major source or mod4f4cat4on
barr4ng the
use of d4spers4en enhancement techn4quest or
3+
Prov4d4ng 4n the 4mmed4ate v4e4n4ty of the source
or mod4f4cat4on aetua~em4es4on offsets at a rat4o
of ~-25i4 or greater ~
for each ton of new
aHowab~e em4ss4ons
there
shaH
be
at
~eest
~25
tons of aetua~em4ss4on offsets+ prov4ded that.
stack or em4ss4on parameters do not 4nd4eate a
s4gn4f4eant adverse effect on a4r quaHty 4n
accordance w4th Seet4on ~93i-304-~d-)due to the
operat4ort of the source or mod4f4eat4on~-
b-)
For organ4c mater4a~em4ss4ons-, the owner or operator of
a new major source or major mod4f4cat4on shaH
demonstrate that 4t does not 4nterfere w4th reaeonab~e
further progress by prov4d1ng actua~em4ss4on offsets 4n
excess of the aHowab~eem4se4ons from the new source or
the net 4ncrease 4n em4ss4àns from the mod4f4eat4ort-
b)
The Agency shall allow the use of all or
some portion of
the available growth margin
to satisfy subsection
(a)
if
the owner
or operator can show that the possible sources
of emission offsets were investigated and none were
reasonably available at that time.
Section 203.303
Baseline and Emission Offsets Determination
a)
An emission offset must be obtained from a source
in
operation prior
to the permit application for the new or
modified source.
Bm4es4on offsets can be obta4ned from
stat4onary or fug4t4ve sourees~- Emission offsets must
be effective prior
to start—up of the new or modified
source.
b)
The emission offsets provided must:
1)
Must B be of the same pollutant and further
be of
a
type with approximately the same qualitative
significance for public health and welfare as that
attributed
to the increase from
4rt a particular
change;
77-446
—29—
2+
~n the case of a shutdown~have occurred s4nce
Apr4~
~4,
~9~9
or the date the area 4e dee4gnated
by the USEPA as a nonatta4nment area for the
poHutant
wh4ehever
4s
more
reeent7
and
the
shutdown source 4s be4ng rep~aeedby a s4mHar new
sourcet and Must,
in the case of a fuel combustion
source,_be_based on the
type of fuel being burned
at the time the permit application
is filed,
and,
if offset
is to be produced by a future switch to a
cleaner fuel, be accompanied
by a demonstration
that_long—term supplies of the clean
fuel are
available and
a commitment
to a specified
alternative control measure which would achieve the
same degree of emission reduction if return of the
dirtier fuel
is proposed
3)
Must,
in the case of
a shutdown of
a
source or
permanent curtailment of production
or operating
hours
occurring
on
or
after
the
date
a
permit
application
is filed for
a new or modified source,
have
been
made
known
to
the
affected
work
force
4)
Must,
in the case of a past shutdown of a source or
permanent curtailment of production or operating
hours, have occurred since April
24,
1979 or the
date the area
is designated by the U.S.
Environmental Protection Agency (USEPA)
as
a
nonattainment area for the pollutant, whichever
is
~more recent, and the proposed new or modified
source must
be replaced for the shutdown or
curtailment
-~+5)Must, Bbe enforceable by permit--
;
and
6)
Must not have been previous1~relied on,
as
demonstrated by the Agency,
in issuing any permit
pursuant
to 35
Ill.
Adm. Code 201.142
or 201.143
or
this Part,
or for demonstrating attainment or
reasonable further progress.
c)
The baselines for determining emission offsets are
as
follows:
~+
For part4cu~atematter *~SP~ysu’fur d4ox4de
*se
+7
n4trogen
ox4de
*NOM+
and
carbon
monox4de
-eeC-,
the appHcab~eem4ss4on Hm4t conta4ned 4n th4s
?hapter--
~f th4s rate 4s greater than the
uncontroHed em4es4on ratey the beseHne shaH be
the uneontroHed rateT
-
-
77-447
—30—
2+
Except for organ4c mater4a~ 4?
no em4ss4on rate 4s
conta4ned 4n th4s ehapter-, the beseHne shaH be
the eetue~em4se4on rater
-
1)
The baseline for determining the extent to which
emission reductions are creditable as offsets shall
be the actual emissions of the source from which
the offset is to be obtained!
to the extent they
are within any applicable emissions limitations of
this Subtitle or
40 CFR 60
and 40 CFR 61, except as
provided
in subsection
(2).
2)
If the demonstration of reasonable further progress
and attainment of ambient air quality standards
approved by the U.S. Environmental Protection
Agency (USEPA)
as part of the Illinois SIP
is based
on the applicable emission limitations this
Subtitle or
40 CFR
60 and 40 CFR 61,
for sources
within an area, and the source from which the
offset
is to
be obtained
is subject to such
limitations,
the baseline for offsets shall
be
the
lesser
of such limitation or the potential to emit
of the source.
~+
The baseHne for orgen4c mater4e~shaH be the
‘esser of the actua3 or aHowab3e em4ss4on rate~-
d)
The location of em4ss4on sources providing the emission
offsets:
~+
For ~SP7 S&~-,
NO~i
or
ee7
must be s-4gn4f4eant
contr4butors to or ~oeated 4n the nenette4nment
area affected by the new or mod4f4ed sourcet or
1)
Must,
for particulate matter,
sulfur dioxide and
carbon monoxide, be such that,
relative to the site
of the proposed new or modified source, the
location of the offset,
together with its effective
stack height,
ensures
a positive net air quality
benefit.
This shall
be demonstrated by atmospheric
simulation modeling, unless the sources providing
the offset are on the same premisses or
in the
immediate vicinity of the new or modified source
and
the pollutants disperse
from substantially the
same effective stack height.
In determining
effective stack height, credit shall not be given
for dispersion enhancement techniques.
The owner
or operator
of
a proposed new
or moáified source
shall perform the appropriate analysis
to
demonstrate the acceptability of the location of an
offset,
if the Agency declines
to make such
analysis.
77-448
—31—
2+
Per organ4c mater4aFy must be ~oeated w4th4n ~98
m4&es of the new or med4f4ed source7
~f the
appHeant can demonstrate us4ng generaHy accepted
a4r quaHty mode~e-,that the effect of the proposed
offsets on a4r quaHty 4e at ~east as great as 4?
the source of the offsets was w4th4n the ~99 m4~e
rad4ue7 these offsets shaH be aeceptab~eT Must,
for nitrogen oxides,
be in the general vicinity of
the proposed new or modified source.
3)
Must,
for volatile organic compounds,
be
in the
broad vicinity of the proposed new or modified
source;
that
is, offsets must be obtained from
within
the
Air
ç.~uality Control
Region
of
the
new
or
modified source,
or
from other
areas which may
be
contributing
to the ozone problem at the site of
the new or modified source.
~)
Replacement of one volatile organic compound with
another
of lesser
reactivity does not constitute an
emission reduction.
Seet4en 2937304
Bxempt4ons from Em-iss4ons 9ffset Regu4rewtent
(Repealed)
e+
The Agency shaH aHow the use of aH
or some port4on o~
the aveHab~egrowth marg4n to sat4sfy Seet4on 2937392
4fi-
~+
The owner or operator can show that poss4b~e
sources of em4ss4on offsets were 4nvest4gated and
none were reesoneb~yavaHab~eat that tmey and
2)-
The
owner operator agrees to accept perm4t
eond4t4ons on aH future perm4ts for the source or
mod4f4cat4on
des4gned
to
prov4de
the
requ4red
em4ss4on effset at the earHest future t4me such
offsets become reasonab’y ava4~ab~e7
b-3~
Seet4on 2837392 shaH not epp~yto a major stat4onary
source
or
major
mod4f4cat4en
4?
the
em4ss4ons
from
the
seuree
or the net em4se4one 4nerease from the
mod4f4cet4on weu~dbe temporary7 that
4s-, ex4st4ng for
per4od of t4me ieee than two years7
e4
Sect4on 2837382*a-)- shaH not app’y to a major stat4onar
source or major mod4f4cat4on 4?
en a4r guaHty ane~ys4s
shows 4t 4s ~oeated 4n a port4on of a g4ven
nonatta4nment area where the a4r guaHty standards are
not be4ng v4o~etedand 4t wH
not cause an 4mpect 4n
the area
4rt wh4ch a4r queHty standards are be-mg
v4e~etedgreater than the s4gn4f4cant a4r quaHty 4mpec~
77-449
~eve~s 4n subsect4on
*d-)T
Such an ana4ye4s shaH be
based upon d4epere4on modeHng and a4r -gueHty
mon4tor4ng performed
by
the Agency or 4n accordance w4th
Agency procedures pursuant to ~Ru~es for the Performance
of Mr euaHty impact Ana~yeeeto be used 4n Support of
Perm4t AppHcat4en~and ~Ru~ee Regerd4ng Subm4ee4en of
Amb4ent Mr euaHty ~nformat4en ebte4ned from Amb4ent
Mr QuaHty Mon4ters under the Centre~of Perm4t
AppHeants~as f4~edw4th the Secretary of State
-4n
Becember-,
~9~7
The date when the em4ee4en offset
requ4rements may be reetr4eted to a Hm4ted pert of the
nonatte4nment area 4s the date that such ena~ys4z4s
eompieted by the Agency or the date such ene~ye4s4s
approved by the Ageney
end redes4gnet4on of the area
where the major source or major mod4f4eat~on4s to be
~oeated 4s under federe~rev4ew7
~f the em4ss4ons from a major stat4onary source or major
mod4f4eat4on are demonstrated to be greater than the
feHew4rtg
&eve~ey
exempt4on pursuant to sttbsect4on
*e-)-
4s not eva4~ab3efor the major stet4onary source or
major mod4f4eat4ori7
S~6N~F~CANCB
~BVE~S
PoHute&e
Annue~ 24—Hour
9—Hour
3—Hour
~—Heur
S92
~-9 ug~’m3 S
ug,’m3
25
TSP
~-9 ug,/m
S ug~’m3
NCx
~78 ug7’m3
9~5mg,”m3
2
e+
Sect4on 2937392-~e+shaH not app~yto a major stat4onery
source or major med4f4cet4en for part4cu~atematter 4f
4t w4H be ~eceted 4n an area wh4ch Meets the foHow4ng
cr4ter4e-
i-)-
The area
te
en
atta4nment area for the pr*mary
teta~suspended part4cu~etee4r quaHty ~tanderd~
2-)
The area te 3ack4ng reesonab~yevaHeb~eem4ss4en
offsetet
3+
The a4r gueHty of the area 4s dom4neted by egr4-
eu~ture~and re~atedfug4t4ve peHutant sourcee~
4+
The area ~ecks major 4ndustr4ai~deve~epment~end
5-)-
The area 4s of a ~ow urban pepu~et4en~4er~e4ty7
77-450
—33—
Section 203.305
Compliance by Existing Sources
The owner
or operator shall demonstrate that all major stationary
sources which he or she owns or operates
(or which are owned or
operated by any entity controlling
or controlled
by, or
under
common control~with the owner
or operator)
in Illinois are
in
compliance,
or on a schedule for compliance, with all applicable
state and federal air pollution control
requirements.
For
purposes of
this Section,
a schedule for compliance must be
federal~yenforceableor contained
in an order of the Illinois
Pollution Control Board or
a court decree.
Section 203.306
Analysis of Alternatives
For emission of volatile organic compounds ergan4e mater4a~or
carbon monoxide, the owner or operator shall demonstrate that
benefits
of the new major source or major modification
significantly outweigh the environmental and social costs imposed
as
a result of its location, construction,
or modification, based
upon an analysis of alternative sites,
sizes, production
processes, and environmental control techniques for such proposed
source.
SUB~ARTF:
OPERATION OF A MAJOR STATIONARY SOURCE
OR MAJOR MODIFICATION
Section 203.6ul
Laowest Achievable Emission Rate Compliance
Requirement
No person shall cause
or allow the operation of
a new major
stationary source or major modification subject
to the
eonstruct4on requirements of Subpart C,
except as
in compliance
with applicable LAER provisions established pursuant
to Section
203.301
for
such
source
or
modification.
Section 203.602
Emission Offset Maintenance Requirement
No person shall cause
or
allow the operation of
a new major
stationary source or major modification where the owner or
operator has wh4ch 4s reqa4red to demonstrated that
it would not
interfere with reasonable
further progress
by providing,
or
wi’x4ch must 4nc~udeemission offsets 4n a demonstrat4on pursuant
to Sections 203.302, and 2937393 without maintaining those
emission offsets or other equivalent offsets.
&ect4en 2937693
Amb4ent Mon4tor4rtg Regu4rement (Repealed)
The owner or operator of a new stat4onary source or major
mod4f~eat4onshaH conduct such amb4ent men4ter4ng as the Agency
deter~t-ines4s reasenab~ynecessary to estabHsh the effect of the
em4sMons from the source or mod4f4eet4on en emb4ent e4r que~4ty
4n the areaT
77-451
—34—
SUBPART
G:
GENERAL MAINTENANCE OF
EMISSION OFFSETS
Section 203.701
General Maintenance of Emission Offsets
No person shall cease
to maintain emission offsets which were
provided for
a source
or modification which is subject to this
Part.
IT
IS SO ORDERED.
I, Dorothy
M.
Gunn, Clerk of
the Illinois Pollution Control
Board,
hereby certify that the above Propos~dOpinion and Order
was adopted
on the
_____________
day of
___________,
1987 by a
vote of
_____________
/
~ (~~-~/
~
/~(
__
Dorothy M. dunn, Clerk
Illinois Pollution Control Board
77-452