ILLINOIS POLLUTION CONTROL BOARD
April 30, 1987
CITY OF CARTERVILLE,
)
)
Petitioner,
)
v.
)
PCB 87—22
)
THE ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
)
Respondent.
OPINION AND ORDER OF THE BOARD (by J.D. Dumelle):
This matter comes before the Board on the petition for
variance filed by the City of Carterville (Carterville) on March
2, 1987. Carterville seeks a variance from the provisions of 35
Ill. Adm. Code 309.241(a). Because Carterville has been placed
on Restricted Status, it seeks the variance to complete the hook
up of approximately 66 homes to a recently constructed sanitary
sewer extension. Carterville waived hearing and none was held.
On April 13, 1987, the Illinois Environmental Protection Agency
(Agency) filed its Recommendation with a motion to file
instanter, which is hereby granted. The Agency recommends grant
of variance subject to certain conditions.
The City of Carterville was placed on Restricted Status by
the Illinois Sanitary Water Board August 19, 1964 (Rec. 1).
Carterville, a city of 3,445 population, owns and operates sewage
treatment and collection facilities for its residents. The
treatment facilities currently consist of a bar screen, primary
clarifiers, three aeration tanks, a final clarifier, a storm
water holding lagoon and a chlorine contact pond. Sludge is
anaerobically digested and dried (Pet. 7—8; Rec. 1). Effluent
from the facilities is discharged into Pin Oak Creek, which is
tributary to Crab Orchard Lake. Crab Orchard Lake is used as a
public water supply. (Rec. 1).
Carterville was issued an NPDES Permit (1L0025178) on June
30, 1983, effective July 30, 1983 and expiring on June 1, 1988.
The permit allows interim limitations of 40 mg/i BOD and 50 mg/l
TSS on a monthly average (Pet. 6; Rec. 1). Final limits are
10/12 BOD/TSS (Pet. 6; Rec. 1). The compliance schedule in this
Permit stated that construction of a new treatment facility was
to have been started in September, 1983 and completed on August
24, 1984. Petitioner is not in compliance with the schedule.
(Rec. 1).
On April 2, 1985 Carterville received a Permit to construct
and own (Permit No. 1985—HC—l86l) the Pea Ridge sewage treatment
plant and sanitary sewer extension to serve 66 single family
77-265
—2—
dwellings* subject to certain conditions (See: Exhibit A of the
Petition). In the fall of 1985 and the Spring of 1986
Carterville undertook and completed construction of the sewer
mains and lift stations. The cost of construction was $212,467
(Pet. 2). Approximately $255,000 of the project cost
(construction and engineering) was from a CDAP grant of $278,000
(Pet. 2). Construction of sewer services to the low and moderate
income homes in the area serviced by the new sewer extension
remains to be completed, at a cost of approximately $60,000.
Construction started in September, 1986 and the plant is
expected to be completed and operational in September or October,
1987 (Pet. 8; Rec. 3). The Agency noted that construction was
delayed for two reasons, First, the sewage treatment plant was
originally designed to be a regional facility serving the Village
of Crainville as well as Carterville. Crainville, however,
withdrew from the regional proposal (Rec. p. 3). Second, the low
bid received for construction of the project was approximately
1.5 million dollars above the anticipated budget (Pet. 2, Rec.
3). Design changes were completed in June, 1986, and the revised
bids were within project budget (Pet, 3). Construction has
started and is approximately 15—20 complete (Pet. 8, Rec. 3).
The project appears to be meeting its current construction
schedule (Rec. 3). Upon completion the new facility will consist
of a flow equalization lagoon, a grit chamber, mechanical bar
screen, two oxidation ditches, two final clarifiers, three high
rate filters, two aerobic digesters, conversion of an anaerobic
digester to an aerated sludge holding tank, two vacuum assisted
drying beds and chlorination facilities (Pet. 8; Rec. 3). The
discharge will be diverted from Pin Oak Creek into Hurricane
Creek, a tributary of the Big Muddy River (Pet. 7; Rec. 3). The
Agency notes that this diversion also relieves Carterville of a
phosphorus effluent limitation (Rec. 3).
In September, 1986, Carterville applied to the Agency for a
permit to operate the already completed sewer extension. The
Agency denied the permit, (Pet, 3), reciting the incorporation,
in Special Condition 5 of the construction permit, which
precludes the Agency from granting a permit to operate until the
Agency has determined that the upgraded facilities are actually
operating successfully as designed. (See: Exhibit B of
Petition). Unable to obtain the operating permit, Carterville
Statements in the Variance Petition regarding the number of
homes involved in this project were ambiguous. No. 1(a) of the
Petition sought relief to hook up “approximately 66 homes” to the
sewer extension, No, 2(a) requested variance to allow
construction of sewer services to “approximately 60” homes, And
No. 2(j)(l) stated that variance was requested for “60 homes” and
that construction to “the remaining 60 homes” would take another
60 days, suggesting the possibility that perhaps as many as 120
homes are here involved, The Board assumes that this variance
petition seeks relief for 66 homes only.
77.266
—3—
seeks variance from 35 Ill. Adm. Code 309.241(a) to allow the
construction of sewer services to the approximately 66 homes and
to allow those homes to hook up to the sanitary sewer system.
The Agency has indicated that it agrees with Petitioner that
denial of the requested variance would constitute an arbitrary or
unreasonable hardship on
Carterville.
Construction of the sewer
extension serving the Pea Ridge area was funded by a CDAP grant
from the Department of Commerce and Community Affairs (DCCA).
DCCA has expressed concern over why these sewers are not yet in
use (Pet. 3; Rec. 3). If the original purpose of this CDAP grant
is frustrated, DCCA could request that the grant be repaid (Rec.
3) and could deny consideration on further grants (Pet. 11; Rec.
3). As Carterville has many additional needs, including
additional sewer extensions and a fire station, (Pet. 11), denial
of the variance may impose the hardship of preventing Carterville
from receiving the additional grants.
The City of Carterville has incurred great expense in
undertaking this project. In addition to construction of the
sewer extension pursuant to the CDAP grant of $2B,000,
Carterville also expended $120,000 to complete rehabilitation of
its sewer system to reduce infiltration and inflow (Rec. 3). The
total project cost is $2,900,000. For a City of only 3,445
population and a median household income of $14,118, this is a
substantial burden (Rec. 3).
Furthermore, the 6 homes to be served by this extension are
currently served by individual septic tank systems. Carterville
alleges that of these existing septic tanks, some are undersized
and some are served by poorly functioning, or non—functioning,
tile fields (Pet. 9). The Agency found that because of the soil
type found in the region, it is a frequent occurrence that septic
tank wastes stand in roadside ditches or pools in lower areas
(Rec. 3). The Agency notes that the existence of such waste
constitutes a public health hazard, and that beginning
construction now would eliminate the wastes during this
construction season (Rec. 3).
The environmental impact of granting variance appears to be
minimal. Because Carterville rehabilitated its sewer system and
thereby reduced its flow by 0.235 mgd since completion of the
inflow—infiltration removal program and because the 66 homes
sought to be included add only 0.034 mgd to the receiving stream,
the net result remains a decreased impact on the receiving
stream. Moreover, the connections are not to be made until
summer, a period of historically low flow to the plant (See: Rec.
2). The Agency notes that at most the added flow of 0.0345 mgd
will increase the present low flow of 0.19 mgd by 18 or the
design flow by 8.6~(Rec. 4). Even if the BOL/TSS in the added
effluent were untreated, an 8.6 increase in loading would not
cause the current average effluent to exceed the interim limits.
77-267
—4—
Pin Oak Creek, the current receiving stream, is tributary to
Crab Orchard Lake, a surface impoundment used partially as a
public water supply. The Agency does not anticipate that the
additional flows caused by adding the 66 homes will have a
detectable adverse impact on Crab Orchard Lake as Carterville’s
facilities discharge into Pin Oak Creek about 1/2 mile upstream
from the Lake (Rec. 4). Further, the Agency notes that the water
supply intake for the City of Marion, which is infrequently used,
is separated from the creek discharge by a road crossway which
reduces the water circulation (Rec. 4).
In concurrence with the Agency’s assessment, the Board finds
that denial of variance would impose an arbitrary and
unreasonable hardship upon the Petitioner and will grant the
requested relief, subject to the conditions delineated in the
Order.
This Opinion constitutes the Board’s findings of facts and
conclusions of law in this matter.
ORDER
The Petitioner, City of Carterville, is hereby granted a
variance from 35 Ill. Adm. Code 309.241(a) insofar as it relates
to the hookup of the 6# homes, which otherwise woulo be
prohibited under this provision and Restricted Status, for its
Pea Ridge sewer extension, subject to the following conditions:
1. This variance shall commence on the date of the Board
Order.
2. This variance shall expire when the construction of the
sewage treatment plant is completed, but not later than
December 31, 1987.
3. Petitioner, City of Carterville, shall apply for and
obtain an operational permit from the Agency prior to
connecting the 66 to the sewer system.
4. Within 45 days of the date of this Order, the City of
Carterville shall execute and send to:
Mr. James Frost
Compliance Assurance Section
Division of Water Pollution Control
Illinois Environmental Protection Agency
2200 Churchill Road
P.O. Box 19276
Springfield, IL 62794—9276
a certificate of acceptance of this variance by which
it agrees to be bound by its terms and conditions.
77-268
—5—
5. This 45 day period will be held in abeyance for any
period during which this matter is being appealed.
The
form of the certification
shall be as follows.
CERTIFICATION
The City of Carterville hereby accepts and agrees to be
bound by all terms and conditions of the Order of the Illinois
Pollution Control Board in PCB 87—22, dated April 30, 1987.
Petitioner
BY: Authorized Agent
Title
Date
IT
IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify~that the above O~,inion~andOrder was
adopted on the
_______________
day of
~
~
,
1967 by a vote
of
________________.
I
Dorothy M. ~unn, Clerk
Illinois Pollution Control Board
77.269