ILLINOIS POLLUTION CONTROL BOARD
    April 1, 1987
    VILLAGE OF LEMONT,
    )
    Petitioner,
    V.
    )
    PCB 86—207
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    Respondent,
    and
    CAROLYN F. PLACEK, KATHERINE
    )
    B. MURPHY AND GEORGE PODREBARAC,
    Intervenors.
    JOHN ANTONOPOULUS, VIRTEL & GROSELAK, P.C., APPEARED ON BEHALF OF
    PETITIONER; AND
    WAYNE L. WIEMERSLACE, STAFF ATTORNEY, APPEARED ON BEHALF OF
    RESPONDENT.
    OPINION OF THE BOARD (by J. Theodore Meyer):
    This matter comes before the Board on a December 3, 1986
    petition filed by the Village of Leinont seeking variance, for a
    period of one year from the provisions of 35 Ill. Adin. Code
    602.105(a), Standards for Isssuance, and from 35 Ill. Adm. Code
    602.106(b), Restricted Status, but only to the extent those rules
    involve 35 Ill. Adm. Code 604.301(a) and (b) (combined radium 226
    and 228 and gross alpha particle activity). The Illinois
    Environmental Protection Agency (Agency) filed its recommendation
    that variance be granted on January 7, 1987. Six objections to
    the variance were filed. Hearing was held in Lemont on February
    9, 1987. At hearing three objectors moved to intervene which
    motion was granted by the hearing officer. The intervenors are
    Carolyn F. Placek, Katherine H. Murphy and George Podrebarac
    (“Intervenors”). This Opinion supports the Board’s Order of
    March 19, 1987 which granted the variance relief requested.
    The Village of Lemont has previously sought and obtained a
    variance for its public water supply. In PCB 80—84, a variance
    from the gross alpha particle activity limitation was granted
    until January 1, 1984. On April 21, 1986 the Village requested
    variance from restricted status for the contaminants in question
    77-51

    —2—
    for a period of five years. This variance request was denied on
    July 31, 1986. In its denial, the Board noted the Village’s lack
    of compliance with the conditions imposed in the prior
    variance. The Board also noted that the Village had failed to
    devise a viable compliance plan over nearly seven years.
    Accordingly, the Board did not look favorably upon •the variance
    request since it essentially amounted to a request to study the
    problem and achieve compliance over an additional five years.
    The Board thus found that denial of the variance would not
    constitute an arbitrary or unreasonable hardship since any
    hardship was largely self—imposed by Leinont’s dilatory approach
    to compliance. Thus, the variance request was denied.
    Subsequently, the Village filed the current petition on December
    3, 1986.
    BACKGROUND
    The Village of Lemont is located in southwestern Cook
    County, Illinois and has a population of approximately 5300
    residents. The Village owns its public water supply which serves
    approximately 5000 residents from its deep and shallow well water
    supply. The Village also maintains a complete public water
    distribution system including deep wells, shallow wells, pumps
    and distribution facilities.
    The Petitioner has three wells with the following depths,
    ages and pumping capacities:
    Placed in
    Gallons
    Well No.
    Depth
    Operation
    Per Minute
    2
    172 ft.
    1955
    400
    3
    1662 ft.
    1969
    940
    4
    1657 ft.
    1978
    940
    By letter dated October 4, 1986, the Village was advised by
    the Agency that the maximum allowable concentration of 5 pCi/i
    for gross alpha activity was exceeded and that the Village was
    going to be placed on Restricted Status. The Agency reported a
    gross alpha activity concentration of 19 pCi/i. By letter dated
    October 4, 1984, the Village was advised by the Agency that the
    maximum allowable concentration of radium was exceeded and that
    the Village was placed on Restricted Status. Pet. at 4. The
    analyses showed a radium—226 count of 12.4 pCi/l and a radium—228
    count of 5.6 pCi/l. The combined radium content of the water was
    thus 18 pCi/l which exceeds the standard of 5 pCi/l.
    The Village states that it attempted to comply with its
    previous variance by establishing a blending program. However,
    this attempt proved unsuccessful since blending of the flows from
    the Village’s one shallow well with either deep well ‘failed to
    meet the Village’s daily capacity requirements. The Village then
    began evaluating the installation of softening equipment. The
    77-52

    —3—
    Village obtained cost estimates from various consultants but was
    unable to determine how to fund the equipment purchase. The
    Village states that during 1981 to 1984 it experienced a period
    of stagnant growth and an inadequate increase in its assessed
    valuation. Since 1985, however, the Village states that it has
    experienced substantial growth which will enable it. to finance a
    compliance plan. Current projects to be developed are:
    a) Amber Shires Planned Unit Development of 225 acres with
    approximately 1,100 units and a projected population of
    3,500;
    b) Windmills of Lemont, a Senior Citizen Development with
    200 units and a development cost of $10 million;
    C)
    Four Winds Hospital, a 30 acre development with
    estimated construction costs of $25 million;
    d) Hilltop Estates Subdivision of 150 single—family homes;
    and
    e) Dudek Industrial Park of approximately 20 Industrial
    Buildings.
    Pet, at 6.
    All of the projects are contingent upon water main
    extensions and when built will generate substantial increases in
    assessed valuation and income to the community.
    The Village notes that since its previous variance request
    it has retained the services of a professional engineering firm
    for the purpose of preparing a preliminary water treatment
    design. The firm has recommended that the Village install an ion
    exchange system for its two deep wells. Accordingly, the Village
    has determined to install the ion exchange system and has
    authorized final engineering and the purchase of the necessary
    equipment. The total capital cost for the system is projected to
    be $650,000 with an annual cost of $158,696. The monthly cost to
    each water user is projected to be $7.35. See Attachment to
    Petition. The Village will finance this obligation with a
    donation of $100,000 from Four Winds Hospital and has contacted a
    municipal financial consultant concerning appropriate funding for
    the remaining cost.
    The Village states that it intends to obtain final
    engineering drawings and to complete the installation of the
    system as soon as practicable. The Village believes that the
    system can be installed and functioning in approximately 12
    months.
    77.53

    —4—
    INTERVENORS
    I
    OBJECTIONS
    The Intervenors object to the grant of this variance on
    numerous grounds. In particular, the Intervenors doubt the
    sincerity of the Village to pursue the proffered compliance plan
    and in support of their contention they question a number of the
    Village’s assertions.
    Mr. Podrebarac and Ms. Placek question whether the Village
    sincerely attempted to establish a blending program and whether
    the conclusion that such is infeasible is really valid. (R. at
    108—111, 203—228). They provided some calculations to support
    their position. (Exh. 15). In rebuttal, however, the City’s
    engineer explained that although at a pumping capacity of 400 gpm
    the shallow well could blend successfully with the deep wells in
    terms of complying with the radiological standards, good
    engineering practice would dictate a number of expenditures
    before blending would really become a long—term viable
    solution. The capacity of the shallow well would have to be
    doubled to provide for increases in population and to provide for
    the contingency of failure of the existing well. This would
    necessitate digging an additional well at a very rough cost of
    $200,000. The piping necessary to effectuate the blending would
    also require a large expense. In addition, the shallow well
    presently used is high in iron and using a large amount of this
    water would necessitate the installation of an ion exchange
    softener to maintain water quality. Thus, the cost of blending
    would be greater than the cost of simply installing the softener
    for radionuclide removal. R. at 273—78. The Board believes that
    Mr. Schaeffer adequately explained why blending was not a viable
    long—term solution. Although the Board appreciates the
    Intervenors concerns, the Board must remind the Intervenors that
    under the Environmental Protection Act, a variance petitioner is
    to submit a compliance plan which will lead to compliance at the
    expiration of the variance. The determination of what compliance
    plan to pursue is uniquely within the discretion of each variance
    petitioner, as long as compliance is achieved. Lemont has
    demonstrated that the installation of softeners will result in
    compliance, and while other means might also lead to compliance
    this fact alone provides no basis for denial of the variance.
    The proper place for the Intervenors to have voiced their
    objections concerning the instant compliance plan was in the
    Village Board room. The Board finds, however, that based on the
    Village’s own testimony blending is currently a feasible way to
    achieve some reductions in the contaminant levels over the short
    time frame that this variance is in effect without significant
    expenditures. Accordingly, a condition of this variance will
    require that the Petitioner take all reasonable measures with its
    existing equipment to minimize the levels of radiological
    contaminants in its finished water. (See Order, Par. 12).
    77.54

    —5—
    The Intervenors also object to grant of the variance on the
    basis that 35 Ill. Adm. Code 104.121 was not strictly complied
    with.
    Section 104.121 lists the information to be included in a
    variance petition “where applicable.” The Intervenors allege
    that for numerous subsections no or minimal information was
    provided.
    The Intervenors urge the Board to dismiss the petition
    as inadequate under 35 Ill. Adm. Code 104.125. However, the
    Board notes that failure to strictly comply with the requirements
    of Section
    104.121 is not an automatic grounds for dismissal.
    The informational requirements of Section 104.121 are somewhat
    loose by their nature and not all subsections will be applicable
    in every situation.
    Just how much information is to be provided
    for a petition to be deemed “adequate” is a matter of great
    discretion left to the Board.
    In the normal course of events
    this determination is made upon filing of the petition and where
    minimally adequate a petition is allowed to proceed to hearing
    where normally more information will be brought out. In this
    instance, although the information provided in the petition was
    not as detailed as the Intervenors would have liked, the Board
    finds that the petition and hearing provided sufficient
    information to enable the Board to determine whether an arbitrary
    or unreasonable hardship had been demonstrated.
    The Intervenors also allege that the petition should be
    dismissed as inconsistent with federal law. However, this
    contention misapprehends the request for relief made by the
    Village in its variance petition.
    The variance requested is from
    a state
    requirement that when a public water supply is in
    violation of any maximum
    contaminant level that it
    be placed on
    restricted status. Since there is no such requirement imposed by
    federal law, to grant a variance from the state imposed
    “restricted status” is thus, not inconsistent with federal law.
    The Board commends the intervenors efforts to insure that a
    safe drinking water supply is made available to the users in
    Lemont and appreciates th.eir concerns that the Village has not
    acted quickly, decisively and forthrightly in the past. The
    Village’s failure to comply with the terms of its previous
    variance and its lack of a concrete compliance plan were the
    major reasons for the Board’s denial of its previous variance
    request in PCB 86—54. However, the Board believes that the
    testimony in this proceeding demonstrates that the Village is
    extremely committed to achieve compliance within 12 months.
    Final engineering specifications have been authorized, the
    availability of softening equipment has been investigated,
    partial financing has materialized and a consultant has been
    contacted to help arrange the remaining financing. The variance
    time frame is rather tight and requires total compliance within
    one year. The Board believes that to grant the variance and have
    the Village under an enforceable Board Order is preferable to
    denying the variance and have no order to force compliance.
    During the variance period, the Village is admonished to strictly
    77-55

    —6—
    comply with the conditions of this variance.
    The Board wishes to
    note that its Order is enforceable by the Intervenors who may
    bring an action on their own behalf, without an attorney, before
    the Circuit Court to require compliance with the Order or before
    the Board for recission of the variance for failure to comply.
    Such an enforcement action may also result in the payment of
    fines if non—compliance is established.
    ENVIRONMENTAL IMPACT
    The Agency states that while radiation at any level creates
    some risk, the risk associated with this level is very low and
    cites the testimony of Dr. Richard Toohey in PCB 85—84 and P85—
    14. The Agency believes that an incremental increase in the
    allowable concentration for these
    contaminants even up to a
    maximum of four times the allowable level should cause no
    significant health risk for the limited
    population served by new
    water main extensions for the time period of the recommended
    variance, the Agency also notes that compliance will be
    achieved
    at the end of the variance period and that the variance is for a
    relatively short period of time.
    Rec. at 8—10.
    Concerning ion exchange water softening, the Agency states
    that
    it is capable of removing more than 90 of the radium.
    However, a significant health risk may result if the softener is
    regenerated with salt
    since this will significantly increase the
    sodium content of the water.
    Increased sodium is a health risk
    for persons who are hypertensive or who have heart problems.
    Pet. 9—10. The Agency also points out that waste from routine
    softening is high in total dissolved solids and may be difficult
    to dispose of legally. The softening process concentrates the
    radioactivity which may be more of a hazard in the waste stream
    than in the drinking water. In addition, some of the
    radioactivity remains in the ion exchange material posing a
    hazard to maintenance workers. Thus, the Agency actively
    discourages the use of the ion exchange process for radionuclide
    removal unless it is the best treatment method for a particular
    supply.
    CONCLUS IONS
    The Agency recommends that the Board grant the variance for
    the period requested. The Board finds that denial of the
    variance would impose an arbitrary or unreasonable hardship as it
    would impose a moratorium on the very economic growth necessary
    to fund the proposed improvements to bring the Village’s water
    system into compliance. In addition, the Board finds that grant
    of the requested variance will impose no significant injury on
    the public or on the environment for the limited time of the
    requested variance and will actually help to hasten ultimate
    compliance. The Board notes that since the variance only lifts
    the effects of being on restricted status, it only affects those
    77-56

    —7—
    users who consume water drawn from any newly extended water
    lines. The variance does not alter the status of the population
    who draws from existing water lines except insofar as the
    variance helps to expedite the ultimate compliance date.
    Accordingly, the variance relief requested will be granted
    subject to conditions as proposed by the Agency.
    This Opinion constitutes the Board’s conclusions of law and
    findings of fact in this matter.
    IT IS SO ORDERED.
    B. Forcade dissented and J. D. Durnelle concurred.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify ~4~at the above Opinion was adopted on
    the
    /~~Q~4
    day of
    _________________,
    1987, by a vote of ~5—/
    ~~
    Dorothy M. ,R~unn, Clerk
    Illinois Pollution Control Board
    77-57

    Back to top