ILLINOIS POLLUTION CONTROL BOARD
April 1, 1987
VILLAGE OF LEMONT,
)
Petitioner,
V.
)
PCB 86—207
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
Respondent,
and
CAROLYN F. PLACEK, KATHERINE
)
B. MURPHY AND GEORGE PODREBARAC,
Intervenors.
JOHN ANTONOPOULUS, VIRTEL & GROSELAK, P.C., APPEARED ON BEHALF OF
PETITIONER; AND
WAYNE L. WIEMERSLACE, STAFF ATTORNEY, APPEARED ON BEHALF OF
RESPONDENT.
OPINION OF THE BOARD (by J. Theodore Meyer):
This matter comes before the Board on a December 3, 1986
petition filed by the Village of Leinont seeking variance, for a
period of one year from the provisions of 35 Ill. Adin. Code
602.105(a), Standards for Isssuance, and from 35 Ill. Adm. Code
602.106(b), Restricted Status, but only to the extent those rules
involve 35 Ill. Adm. Code 604.301(a) and (b) (combined radium 226
and 228 and gross alpha particle activity). The Illinois
Environmental Protection Agency (Agency) filed its recommendation
that variance be granted on January 7, 1987. Six objections to
the variance were filed. Hearing was held in Lemont on February
9, 1987. At hearing three objectors moved to intervene which
motion was granted by the hearing officer. The intervenors are
Carolyn F. Placek, Katherine H. Murphy and George Podrebarac
(“Intervenors”). This Opinion supports the Board’s Order of
March 19, 1987 which granted the variance relief requested.
The Village of Lemont has previously sought and obtained a
variance for its public water supply. In PCB 80—84, a variance
from the gross alpha particle activity limitation was granted
until January 1, 1984. On April 21, 1986 the Village requested
variance from restricted status for the contaminants in question
77-51
—2—
for a period of five years. This variance request was denied on
July 31, 1986. In its denial, the Board noted the Village’s lack
of compliance with the conditions imposed in the prior
variance. The Board also noted that the Village had failed to
devise a viable compliance plan over nearly seven years.
Accordingly, the Board did not look favorably upon •the variance
request since it essentially amounted to a request to study the
problem and achieve compliance over an additional five years.
The Board thus found that denial of the variance would not
constitute an arbitrary or unreasonable hardship since any
hardship was largely self—imposed by Leinont’s dilatory approach
to compliance. Thus, the variance request was denied.
Subsequently, the Village filed the current petition on December
3, 1986.
BACKGROUND
The Village of Lemont is located in southwestern Cook
County, Illinois and has a population of approximately 5300
residents. The Village owns its public water supply which serves
approximately 5000 residents from its deep and shallow well water
supply. The Village also maintains a complete public water
distribution system including deep wells, shallow wells, pumps
and distribution facilities.
The Petitioner has three wells with the following depths,
ages and pumping capacities:
Placed in
Gallons
Well No.
Depth
Operation
Per Minute
2
172 ft.
1955
400
3
1662 ft.
1969
940
4
1657 ft.
1978
940
By letter dated October 4, 1986, the Village was advised by
the Agency that the maximum allowable concentration of 5 pCi/i
for gross alpha activity was exceeded and that the Village was
going to be placed on Restricted Status. The Agency reported a
gross alpha activity concentration of 19 pCi/i. By letter dated
October 4, 1984, the Village was advised by the Agency that the
maximum allowable concentration of radium was exceeded and that
the Village was placed on Restricted Status. Pet. at 4. The
analyses showed a radium—226 count of 12.4 pCi/l and a radium—228
count of 5.6 pCi/l. The combined radium content of the water was
thus 18 pCi/l which exceeds the standard of 5 pCi/l.
The Village states that it attempted to comply with its
previous variance by establishing a blending program. However,
this attempt proved unsuccessful since blending of the flows from
the Village’s one shallow well with either deep well ‘failed to
meet the Village’s daily capacity requirements. The Village then
began evaluating the installation of softening equipment. The
77-52
—3—
Village obtained cost estimates from various consultants but was
unable to determine how to fund the equipment purchase. The
Village states that during 1981 to 1984 it experienced a period
of stagnant growth and an inadequate increase in its assessed
valuation. Since 1985, however, the Village states that it has
experienced substantial growth which will enable it. to finance a
compliance plan. Current projects to be developed are:
a) Amber Shires Planned Unit Development of 225 acres with
approximately 1,100 units and a projected population of
3,500;
b) Windmills of Lemont, a Senior Citizen Development with
200 units and a development cost of $10 million;
C)
Four Winds Hospital, a 30 acre development with
estimated construction costs of $25 million;
d) Hilltop Estates Subdivision of 150 single—family homes;
and
e) Dudek Industrial Park of approximately 20 Industrial
Buildings.
Pet, at 6.
All of the projects are contingent upon water main
extensions and when built will generate substantial increases in
assessed valuation and income to the community.
The Village notes that since its previous variance request
it has retained the services of a professional engineering firm
for the purpose of preparing a preliminary water treatment
design. The firm has recommended that the Village install an ion
exchange system for its two deep wells. Accordingly, the Village
has determined to install the ion exchange system and has
authorized final engineering and the purchase of the necessary
equipment. The total capital cost for the system is projected to
be $650,000 with an annual cost of $158,696. The monthly cost to
each water user is projected to be $7.35. See Attachment to
Petition. The Village will finance this obligation with a
donation of $100,000 from Four Winds Hospital and has contacted a
municipal financial consultant concerning appropriate funding for
the remaining cost.
The Village states that it intends to obtain final
engineering drawings and to complete the installation of the
system as soon as practicable. The Village believes that the
system can be installed and functioning in approximately 12
months.
77.53
—4—
INTERVENORS
I
OBJECTIONS
The Intervenors object to the grant of this variance on
numerous grounds. In particular, the Intervenors doubt the
sincerity of the Village to pursue the proffered compliance plan
and in support of their contention they question a number of the
Village’s assertions.
Mr. Podrebarac and Ms. Placek question whether the Village
sincerely attempted to establish a blending program and whether
the conclusion that such is infeasible is really valid. (R. at
108—111, 203—228). They provided some calculations to support
their position. (Exh. 15). In rebuttal, however, the City’s
engineer explained that although at a pumping capacity of 400 gpm
the shallow well could blend successfully with the deep wells in
terms of complying with the radiological standards, good
engineering practice would dictate a number of expenditures
before blending would really become a long—term viable
solution. The capacity of the shallow well would have to be
doubled to provide for increases in population and to provide for
the contingency of failure of the existing well. This would
necessitate digging an additional well at a very rough cost of
$200,000. The piping necessary to effectuate the blending would
also require a large expense. In addition, the shallow well
presently used is high in iron and using a large amount of this
water would necessitate the installation of an ion exchange
softener to maintain water quality. Thus, the cost of blending
would be greater than the cost of simply installing the softener
for radionuclide removal. R. at 273—78. The Board believes that
Mr. Schaeffer adequately explained why blending was not a viable
long—term solution. Although the Board appreciates the
Intervenors concerns, the Board must remind the Intervenors that
under the Environmental Protection Act, a variance petitioner is
to submit a compliance plan which will lead to compliance at the
expiration of the variance. The determination of what compliance
plan to pursue is uniquely within the discretion of each variance
petitioner, as long as compliance is achieved. Lemont has
demonstrated that the installation of softeners will result in
compliance, and while other means might also lead to compliance
this fact alone provides no basis for denial of the variance.
The proper place for the Intervenors to have voiced their
objections concerning the instant compliance plan was in the
Village Board room. The Board finds, however, that based on the
Village’s own testimony blending is currently a feasible way to
achieve some reductions in the contaminant levels over the short
time frame that this variance is in effect without significant
expenditures. Accordingly, a condition of this variance will
require that the Petitioner take all reasonable measures with its
existing equipment to minimize the levels of radiological
contaminants in its finished water. (See Order, Par. 12).
77.54
—5—
The Intervenors also object to grant of the variance on the
basis that 35 Ill. Adm. Code 104.121 was not strictly complied
with.
Section 104.121 lists the information to be included in a
variance petition “where applicable.” The Intervenors allege
that for numerous subsections no or minimal information was
provided.
The Intervenors urge the Board to dismiss the petition
as inadequate under 35 Ill. Adm. Code 104.125. However, the
Board notes that failure to strictly comply with the requirements
of Section
104.121 is not an automatic grounds for dismissal.
The informational requirements of Section 104.121 are somewhat
loose by their nature and not all subsections will be applicable
in every situation.
Just how much information is to be provided
for a petition to be deemed “adequate” is a matter of great
discretion left to the Board.
In the normal course of events
this determination is made upon filing of the petition and where
minimally adequate a petition is allowed to proceed to hearing
where normally more information will be brought out. In this
instance, although the information provided in the petition was
not as detailed as the Intervenors would have liked, the Board
finds that the petition and hearing provided sufficient
information to enable the Board to determine whether an arbitrary
or unreasonable hardship had been demonstrated.
The Intervenors also allege that the petition should be
dismissed as inconsistent with federal law. However, this
contention misapprehends the request for relief made by the
Village in its variance petition.
The variance requested is from
a state
requirement that when a public water supply is in
violation of any maximum
contaminant level that it
be placed on
restricted status. Since there is no such requirement imposed by
federal law, to grant a variance from the state imposed
“restricted status” is thus, not inconsistent with federal law.
The Board commends the intervenors efforts to insure that a
safe drinking water supply is made available to the users in
Lemont and appreciates th.eir concerns that the Village has not
acted quickly, decisively and forthrightly in the past. The
Village’s failure to comply with the terms of its previous
variance and its lack of a concrete compliance plan were the
major reasons for the Board’s denial of its previous variance
request in PCB 86—54. However, the Board believes that the
testimony in this proceeding demonstrates that the Village is
extremely committed to achieve compliance within 12 months.
Final engineering specifications have been authorized, the
availability of softening equipment has been investigated,
partial financing has materialized and a consultant has been
contacted to help arrange the remaining financing. The variance
time frame is rather tight and requires total compliance within
one year. The Board believes that to grant the variance and have
the Village under an enforceable Board Order is preferable to
denying the variance and have no order to force compliance.
During the variance period, the Village is admonished to strictly
77-55
—6—
comply with the conditions of this variance.
The Board wishes to
note that its Order is enforceable by the Intervenors who may
bring an action on their own behalf, without an attorney, before
the Circuit Court to require compliance with the Order or before
the Board for recission of the variance for failure to comply.
Such an enforcement action may also result in the payment of
fines if non—compliance is established.
ENVIRONMENTAL IMPACT
The Agency states that while radiation at any level creates
some risk, the risk associated with this level is very low and
cites the testimony of Dr. Richard Toohey in PCB 85—84 and P85—
14. The Agency believes that an incremental increase in the
allowable concentration for these
contaminants even up to a
maximum of four times the allowable level should cause no
significant health risk for the limited
population served by new
water main extensions for the time period of the recommended
variance, the Agency also notes that compliance will be
achieved
at the end of the variance period and that the variance is for a
relatively short period of time.
Rec. at 8—10.
Concerning ion exchange water softening, the Agency states
that
it is capable of removing more than 90 of the radium.
However, a significant health risk may result if the softener is
regenerated with salt
since this will significantly increase the
sodium content of the water.
Increased sodium is a health risk
for persons who are hypertensive or who have heart problems.
Pet. 9—10. The Agency also points out that waste from routine
softening is high in total dissolved solids and may be difficult
to dispose of legally. The softening process concentrates the
radioactivity which may be more of a hazard in the waste stream
than in the drinking water. In addition, some of the
radioactivity remains in the ion exchange material posing a
hazard to maintenance workers. Thus, the Agency actively
discourages the use of the ion exchange process for radionuclide
removal unless it is the best treatment method for a particular
supply.
CONCLUS IONS
The Agency recommends that the Board grant the variance for
the period requested. The Board finds that denial of the
variance would impose an arbitrary or unreasonable hardship as it
would impose a moratorium on the very economic growth necessary
to fund the proposed improvements to bring the Village’s water
system into compliance. In addition, the Board finds that grant
of the requested variance will impose no significant injury on
the public or on the environment for the limited time of the
requested variance and will actually help to hasten ultimate
compliance. The Board notes that since the variance only lifts
the effects of being on restricted status, it only affects those
77-56
—7—
users who consume water drawn from any newly extended water
lines. The variance does not alter the status of the population
who draws from existing water lines except insofar as the
variance helps to expedite the ultimate compliance date.
Accordingly, the variance relief requested will be granted
subject to conditions as proposed by the Agency.
This Opinion constitutes the Board’s conclusions of law and
findings of fact in this matter.
IT IS SO ORDERED.
B. Forcade dissented and J. D. Durnelle concurred.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify ~4~at the above Opinion was adopted on
the
/~~Q~4
day of
_________________,
1987, by a vote of ~5—/
~~
Dorothy M. ,R~unn, Clerk
Illinois Pollution Control Board
77-57