ILLINOIS POLLUTION CONTROL BOARD
    June 10,
    1987
    JOLIET SAND AND
    GRAVEL
    COMPANY,
    )
    )
    Petitioner,
    )
    V.
    )
    PCB 87—55
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent.
    DISSENTING OPINION
    (by J.
    Anderson):
    The Order
    of the majority of the Board dismissed this appeal
    of
    the denial of a permit.
    The grounds were that, since the
    Third District Appellate Court is considering
    an appeal
    of a
    prior
    (August
    26,
    1986) Illinois Environmental Protection Agency
    (~Agency)denial of an operating permit for
    the same operation at
    Joliet’s facility, the Board lacks jurisdiction to consider
    issues arising
    from the Agency’s later March 26,
    1987,
    decision
    to deny.
    While
    both the March, 1987 denial
    letter and the August,
    1986 denial letter were essentially based on the fact that the
    respective applications as subi~ittedcontained inadequate
    information, the March, 1987 letter does not just repeat the
    permit denial
    reasons of
    the August, 1986 letter.
    None of the
    four reasons
    in the earlier letter
    is repeated
    in the latter
    letter; and none of the reasons
    in the later letter appears
    in
    the earlier letter.
    I dissent from the majority Order because
    I believe that the
    petitioner’s statutory and due process rights are being
    constrained because,
    in order
    to prevent multiple appeals, the
    Board decision
    in essence requires the petitioner to abandon
    certain rights
    in order
    to preserve others.
    I also believe that
    the Board’s reliance on the Board’s holdings
    in Album,
    Inc. v.
    IEPA,
    PCB 81—23, March
    19,
    1981 and Caterpillar Tractor Co.
    v.
    IEPA,
    PCB 79—180,
    July 14, 1983 is misplaced.
    Each of these
    cases involved purported Agency issuance of a second permit while
    appeal of condition of a prior
    issued permit was pending before
    the Board;
    the policy and practical considerations involved
    in
    this case involving two permit denials are dissimilar.
    And
    I
    further believe that the Board’s decision
    is not beneficial
    to
    the environment.
    As background
    for my dissent, there are several observations
    drawn from my experience as
    a member of this Board that might
    78-406

    —2—
    serve
    to place
    the issues
    in perspective.
    It
    is beneficial
    to
    the environment as well as to a
    facility operator
    to have
    operating permits renewed
    as quickly as possible.
    The benefit to
    the environment
    is that the renewal permit contains conditions
    for the facility’s operation which are based
    on current data.
    The benefit to the operator
    is that the facility
    is insulated
    from enforcement for failure
    to have a valid permit.
    ‘Where the
    Agency has either denied a permit or where the permit has been
    issued with conditions which are deemed objectionable, it
    is not
    uncommon for the applicant to reapply
    to the Agency as well as
    to
    file an appeal with the Board.
    In addition to preserving
    the
    right of review of substantive disagreements,
    the appeal
    to the
    Board may also protect the facility’s operating status.
    Where
    the permit is denied, and the applicant has timely filed
    for
    renewal of a permit,
    the Board
    has consistently held that the
    facility may lawfully continue its operations pursuant to
    the
    expired permit, which
    is deemed
    to continue
    in effect during the
    pendancy of any appeal.
    If the appeal
    is dismissed prior
    to
    issuance of
    a permit,
    the facility cannot operate lawfully.
    Where the conditions of an issued renewal permit are the subject
    of challenge,
    the facility operates pursuant
    to the renewal
    permit whose objectionable conditions may be stayed by the Board.
    The Act contains
    a detailed system for processing permits
    and
    resolving disputes.
    Section 40 of the Illinois Environmental
    Protection Act (“Act”)
    allows a petitioner
    to appeal to the Board
    any final permit determination of the Agency, and to appeal
    to
    the Appellate
    Court any final determination of the Board.
    This
    right of appeal must be exercised within 35 days.
    It must be
    emphasized
    that,
    once an application
    is filed ‘with
    the Agency or
    an appeal
    is filed with the Board, Sections 39(a)
    and 40 of the
    Act impose decision deadlines on the Agency and the Board
    respectively.
    Failure by the Agency or the Board
    to timely
    decide results
    in a deemed approved permit.
    There
    is nothing
    in
    the Act that requires the petitioner
    to waive these deadlines.
    It
    is also important to note that Section
    39 requires the
    Agency to give specific reasons for its denial of a permit.
    Agency failure to state a reason
    in the denial letter constitutes
    a waiver of the right
    to rely on the unstated reason; on appeal
    the Board may not consider
    reasons for denial which were
    unstated, even
    if those reasons would be valid.
    In this instance, all parties had followed their mandates or
    exercized their
    rights.
    The Agency had timely denied
    a permit;
    the petitioner
    had timely appealed
    to the Board,
    the Board timely
    upheld the Agency’s denial and the petitioner had timely appealed
    to the appellate court, where jurisdiction of the August, 1986
    decision now rests.
    Following
    the Board’s affirmation of the
    Agency’s denial, the petitioner
    also reapplied
    to the Agency for
    a permit.
    The Agency again timely denied the permit in March,
    1987 for
    reasons different from those given
    for its denial of the
    78-407

    —3—
    earlier permit application.
    The petitioner timely appealed this
    denial
    to the Board.
    As the majority Order
    notes,
    in Album
    the Board held that
    where
    a permit had been issued,
    the Agency lacks authority
    to
    modify that permit while
    it
    is the
    subject of an appeal.
    The
    Board’s reasoning was that “two permits covering the same process
    or
    equipment and
    issued pursuant
    to the same legal authority
    cannot have simultaneous legal effect”,
    and went on to conclude
    that the earliest issued permits have “primacy and that the later
    permits, assuming they exist, did not nullify the legal effect of
    the prior permits”.
    The Album
    reasoning was subsequently
    refined
    in the Caterpillar case,
    in response to arguments made by
    the litigants regarding practical difficulties encountered
    in an
    attempt to settle
    the appeal.
    In Caterpillar,
    the Board went on
    to state
    that the Agency could consider new information and
    “issue”
    a voidable permit, which could be ratified by the
    permittee
    to become effective upon dismissal
    of the prior
    action.
    This procedure accommodates the petitioner’s right to
    review of issues and affords protection
    to its operating status,
    while
    still fostering problem resolution with the Agency.
    Before today’s Order,
    the Board had not considered the
    ability of the Agency to issue a permit while a denial appeal was
    pending before
    the Board,
    let alone while
    a denial appeal was
    pending before
    an appellate court.
    where no permit exists,
    as
    is the case here, there cannot be
    a transfer of jurisdiction of any existing permit from the Agency
    to
    the Board
    tq the Appellate Court.
    While
    I would agree that
    the Appellate Court now has jurisdiction over the Board’s Order
    affirming the August,
    1986 permit denial,
    I fail
    to see how
    pendancy of that appeal vests any jurisdiction of
    a subsequent
    application in that Court,
    or how the Agency is precluded or
    absolved from its statutory duty to issue or deny a permit upon
    the basis of the subsequent application.
    In short, the Album
    and Caterpillar decisions do not apply
    to the facts
    in this case.
    Moreover, this Board decision
    violates the rationale
    for
    the Caterpillar case, which preserved
    all
    appeal
    rights and benefits while allowing
    for exercise of the
    right of the filing of an application and timely Agency decision
    thereon.
    Here, the majority would require
    an applicant to
    abandon some rights in favor
    of others.
    It
    is unclear from the
    majority opinion whether
    the majority considers that the pendancy
    of the court appeal bars one or both of the following acts during
    the pendancy of an appeal:
    1)
    the permitee’s filing
    of
    a
    subsequent application,
    or
    2)
    the Agency’s action on that
    application within
    the statutory time period.
    Caterpillar
    assumes that the applicant may file the application, and the
    Agency may issue
    a “voidable” permit before the applicant
    dismisses its prior
    appeal.
    Ironically,
    the rights the Board
    78~408

    —4—
    sought
    to preserve pursuant to Caterpillar are now lost
    if the
    Agency denies the permit.
    Whether one or both acts are barred,
    it
    is clear
    that an applicant
    is being forced
    to choose between
    the right of judicial review of a previous administrative action
    concerning
    a permit application, and the right
    to have either one
    or both administrative agencies
    (i.e. the Agency and/or
    the
    Board) make timely decisions concerning
    the changed factual
    situation which
    a subsequent application presents.
    ~hi1e the effect of
    the majority holding
    is to
    reduce
    the
    number of appeals pending before
    the Board and the Courts~an
    additional effect may be
    to delay bringing
    a facility into
    the
    permit system.
    In this case,
    for
    instance,
    if Joliet does not
    choose
    to dismiss its earlier appeal,
    it cannot safely reapply
    for
    a permit until
    that appeal
    is finally decided some months
    hence.
    If the Board’s decision
    is upheld, the application
    process must begin
    again.
    Whereas
    if a simultaneous appeal and
    permit reapplication procedure is allowed to function,
    as
    I think
    it practically and legally must, a permit could issue well before
    a final appellate decision
    is reached.
    I appreciate the Board’s concern about potential for abuse
    of
    the permitting system through the filing of successive appeals
    by an applicant who has filed successive deficient
    applications.
    However, even assuming that there are several
    applicants who choose
    to expend the not—inconsiderable monetary
    and other
    resources necessary to prosecute several simultaneous
    appeals
    in the courts and before the Board rather than
    in
    developing data,
    the device chosen
    by the majority to curtail one
    perceived abuse can serve
    to foster another.
    For example, as aforementioned,
    Section 39(a)
    of the Act
    requires the Agency,
    in a permit denial letter, to give
    “specific, detailed statements as
    to the reasons”.
    Thus,
    the
    Agency cannot later, on a re—review of the same information,
    alter or
    add
    to those reasons.
    Notwithstanding,
    in a system
    where permit applications and reapplications may be processed by
    multiple and differing Agency permit reviewers over
    time,
    it
    is
    natural that new “afterthought” objections are or can be raised,
    in good faith as well
    as
    in bad.
    (See, e.g.,
    Illinois Power
    Co.
    v. IEPA,
    PCB 86—154, April
    1,
    1987,
    a third appeal of issues
    arising from an application filed
    in 1979.)
    This tendency to
    raise new objections
    to previously submitted information could be
    encouraged by the majority holding, to the detriment of
    the
    permit system and the environment.
    The Act’s fast—track appeal system was designed
    to give
    quick answers to all disputes arising between the Agency and the
    regulated community,
    in the interest of protection and
    enhancement of the environment.
    I believe that the majority’s
    holding
    frustrates the intent of this system.
    78-409

    —5—
    For all
    of the foregoing reasons,
    I respectfully dissent.
    ~i4~J
    ~
    Aoan G. Anderson
    I,
    Dorothy M. Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Dissenting Opinion was
    submitted on the
    2Z~
    day of
    _______________,
    1987.
    Dorothy M. Gunn,
    Clerk
    Illinois Pollution Control Board
    78.410

    Back to top