ILLINOIS POLLUTION CONTROL BOARD
June 10,
1987
JOLIET SAND AND
 GRAVEL
 COMPANY,
 )
)
Petitioner,
)
V.
 )
 PCB 87—55
ILLINOIS ENVIRONMENTAL
 )
PROTECTION AGENCY,
 )
Respondent.
DISSENTING OPINION
 (by J.
Anderson):
The Order
 of the majority of the Board dismissed this appeal
of
 the denial of a permit.
 The grounds were that, since the
Third District Appellate Court is considering
 an appeal
 of a
prior
 (August
 26,
 1986) Illinois Environmental Protection Agency
(~Agency)denial of an operating permit for
 the same operation at
Joliet’s facility, the Board lacks jurisdiction to consider
issues arising
 from the Agency’s later March 26,
 1987,
 decision
to deny.
While
 both the March, 1987 denial
 letter and the August,
1986 denial letter were essentially based on the fact that the
respective applications as subi~ittedcontained inadequate
information, the March, 1987 letter does not just repeat the
permit denial
 reasons of
 the August, 1986 letter.
 None of the
four reasons
 in the earlier letter
 is repeated
 in the latter
letter; and none of the reasons
 in the later letter appears
 in
the earlier letter.
I dissent from the majority Order because
 I believe that the
petitioner’s statutory and due process rights are being
constrained because,
 in order
 to prevent multiple appeals, the
Board decision
 in essence requires the petitioner to abandon
certain rights
 in order
 to preserve others.
 I also believe that
the Board’s reliance on the Board’s holdings
 in Album,
 Inc. v.
IEPA,
 PCB 81—23, March
 19,
 1981 and Caterpillar Tractor Co.
 v.
IEPA,
 PCB 79—180,
 July 14, 1983 is misplaced.
 Each of these
cases involved purported Agency issuance of a second permit while
appeal of condition of a prior
 issued permit was pending before
the Board;
 the policy and practical considerations involved
 in
this case involving two permit denials are dissimilar.
 And
 I
further believe that the Board’s decision
 is not beneficial
 to
the environment.
As background
 for my dissent, there are several observations
drawn from my experience as
 a member of this Board that might
78-406
—2—
serve
 to place
 the issues
 in perspective.
 It
 is beneficial
 to
the environment as well as to a
 facility operator
 to have
operating permits renewed
 as quickly as possible.
 The benefit to
the environment
 is that the renewal permit contains conditions
for the facility’s operation which are based
 on current data.
The benefit to the operator
 is that the facility
 is insulated
from enforcement for failure
 to have a valid permit.
 ‘Where the
Agency has either denied a permit or where the permit has been
issued with conditions which are deemed objectionable, it
 is not
uncommon for the applicant to reapply
 to the Agency as well as
 to
file an appeal with the Board.
 In addition to preserving
 the
right of review of substantive disagreements,
 the appeal
 to the
Board may also protect the facility’s operating status.
 Where
the permit is denied, and the applicant has timely filed
 for
renewal of a permit,
 the Board
 has consistently held that the
facility may lawfully continue its operations pursuant to
 the
expired permit, which
 is deemed
 to continue
 in effect during the
pendancy of any appeal.
 If the appeal
 is dismissed prior
 to
issuance of
 a permit,
 the facility cannot operate lawfully.
Where the conditions of an issued renewal permit are the subject
 of challenge,
 the facility operates pursuant
 to the renewal
permit whose objectionable conditions may be stayed by the Board.
The Act contains
 a detailed system for processing permits
and
 resolving disputes.
 Section 40 of the Illinois Environmental
Protection Act (“Act”)
 allows a petitioner
 to appeal to the Board
any final permit determination of the Agency, and to appeal
 to
the Appellate
 Court any final determination of the Board.
 This
right of appeal must be exercised within 35 days.
 It must be
emphasized
 that,
 once an application
 is filed ‘with
 the Agency or
an appeal
 is filed with the Board, Sections 39(a)
 and 40 of the
Act impose decision deadlines on the Agency and the Board
respectively.
 Failure by the Agency or the Board
 to timely
decide results
 in a deemed approved permit.
 There
 is nothing
 in
the Act that requires the petitioner
 to waive these deadlines.
It
 is also important to note that Section
 39 requires the
Agency to give specific reasons for its denial of a permit.
Agency failure to state a reason
 in the denial letter constitutes
a waiver of the right
 to rely on the unstated reason; on appeal
the Board may not consider
 reasons for denial which were
unstated, even
 if those reasons would be valid.
In this instance, all parties had followed their mandates or
exercized their
 rights.
 The Agency had timely denied
 a permit;
the petitioner
 had timely appealed
 to the Board,
 the Board timely
upheld the Agency’s denial and the petitioner had timely appealed
to the appellate court, where jurisdiction of the August, 1986
decision now rests.
 Following
 the Board’s affirmation of the
Agency’s denial, the petitioner
 also reapplied
 to the Agency for
a permit.
 The Agency again timely denied the permit in March,
1987 for
 reasons different from those given
 for its denial of the
78-407
—3—
earlier permit application.
 The petitioner timely appealed this
denial
 to the Board.
As the majority Order
 notes,
 in Album
 the Board held that
where
 a permit had been issued,
 the Agency lacks authority
 to
modify that permit while
 it
 is the
 subject of an appeal.
 The
Board’s reasoning was that “two permits covering the same process
or
 equipment and
 issued pursuant
 to the same legal authority
cannot have simultaneous legal effect”,
 and went on to conclude
that the earliest issued permits have “primacy and that the later
permits, assuming they exist, did not nullify the legal effect of
 the prior permits”.
 The Album
 reasoning was subsequently
refined
 in the Caterpillar case,
 in response to arguments made by
the litigants regarding practical difficulties encountered
 in an
attempt to settle
 the appeal.
 In Caterpillar,
 the Board went on
to state
 that the Agency could consider new information and
“issue”
 a voidable permit, which could be ratified by the
permittee
 to become effective upon dismissal
 of the prior
action.
 This procedure accommodates the petitioner’s right to
review of issues and affords protection
 to its operating status,
while
 still fostering problem resolution with the Agency.
Before today’s Order,
 the Board had not considered the
ability of the Agency to issue a permit while a denial appeal was
pending before
 the Board,
 let alone while
 a denial appeal was
pending before
 an appellate court.
where no permit exists,
 as
 is the case here, there cannot be
a transfer of jurisdiction of any existing permit from the Agency
to
 the Board
 tq the Appellate Court.
 While
 I would agree that
the Appellate Court now has jurisdiction over the Board’s Order
affirming the August,
 1986 permit denial,
 I fail
 to see how
pendancy of that appeal vests any jurisdiction of
 a subsequent
application in that Court,
 or how the Agency is precluded or
absolved from its statutory duty to issue or deny a permit upon
the basis of the subsequent application.
In short, the Album
 and Caterpillar decisions do not apply
to the facts
 in this case.
 Moreover, this Board decision
violates the rationale
 for
 the Caterpillar case, which preserved
all
 appeal
 rights and benefits while allowing
 for exercise of the
right of the filing of an application and timely Agency decision
thereon.
 Here, the majority would require
 an applicant to
abandon some rights in favor
 of others.
 It
 is unclear from the
majority opinion whether
 the majority considers that the pendancy
of the court appeal bars one or both of the following acts during
the pendancy of an appeal:
 1)
 the permitee’s filing
 of
 a
subsequent application,
 or
 2)
 the Agency’s action on that
application within
 the statutory time period.
 Caterpillar
assumes that the applicant may file the application, and the
Agency may issue
 a “voidable” permit before the applicant
dismisses its prior
 appeal.
 Ironically,
 the rights the Board
78~408
—4—
sought
 to preserve pursuant to Caterpillar are now lost
 if the
 Agency denies the permit.
 Whether one or both acts are barred,
it
 is clear
 that an applicant
 is being forced
 to choose between
the right of judicial review of a previous administrative action
concerning
 a permit application, and the right
 to have either one
or both administrative agencies
 (i.e. the Agency and/or
 the
Board) make timely decisions concerning
 the changed factual
situation which
 a subsequent application presents.
~hi1e the effect of
 the majority holding
 is to
 reduce
 the
number of appeals pending before
 the Board and the Courts~an
additional effect may be
 to delay bringing
 a facility into
 the
permit system.
 In this case,
 for
 instance,
 if Joliet does not
choose
 to dismiss its earlier appeal,
 it cannot safely reapply
for
 a permit until
 that appeal
 is finally decided some months
hence.
 If the Board’s decision
 is upheld, the application
process must begin
 again.
 Whereas
 if a simultaneous appeal and
permit reapplication procedure is allowed to function,
 as
 I think
it practically and legally must, a permit could issue well before
a final appellate decision
 is reached.
I appreciate the Board’s concern about potential for abuse
of
 the permitting system through the filing of successive appeals
by an applicant who has filed successive deficient
applications.
 However, even assuming that there are several
applicants who choose
 to expend the not—inconsiderable monetary
and other
 resources necessary to prosecute several simultaneous
appeals
 in the courts and before the Board rather than
 in
developing data,
 the device chosen
 by the majority to curtail one
perceived abuse can serve
 to foster another.
For example, as aforementioned,
 Section 39(a)
 of the Act
requires the Agency,
 in a permit denial letter, to give
“specific, detailed statements as
 to the reasons”.
 Thus,
 the
Agency cannot later, on a re—review of the same information,
alter or
 add
 to those reasons.
 Notwithstanding,
 in a system
where permit applications and reapplications may be processed by
multiple and differing Agency permit reviewers over
 time,
 it
 is
natural that new “afterthought” objections are or can be raised,
in good faith as well
 as
 in bad.
 (See, e.g.,
 Illinois Power
 Co.
v. IEPA,
 PCB 86—154, April
 1,
 1987,
 a third appeal of issues
arising from an application filed
 in 1979.)
 This tendency to
raise new objections
 to previously submitted information could be
 encouraged by the majority holding, to the detriment of
 the
permit system and the environment.
The Act’s fast—track appeal system was designed
 to give
quick answers to all disputes arising between the Agency and the
regulated community,
 in the interest of protection and
enhancement of the environment.
 I believe that the majority’s
holding
 frustrates the intent of this system.
78-409
—5—
For all
 of the foregoing reasons,
 I respectfully dissent.
~i4~J
 ~
Aoan G. Anderson
I,
 Dorothy M. Gunn,
 Clerk of the Illinois Pollution Control
Board, hereby certify that the above Dissenting Opinion was
submitted on the
2Z~
day of
_______________,
 1987.
Dorothy M. Gunn,
 Clerk
Illinois Pollution Control Board
78.410