ILLINOIS POLLUTION CONTROL BOARD
June 10,
1987
JOLIET SAND AND
GRAVEL
COMPANY,
)
)
Petitioner,
)
V.
)
PCB 87—55
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
Respondent.
DISSENTING OPINION
(by J.
Anderson):
The Order
of the majority of the Board dismissed this appeal
of
the denial of a permit.
The grounds were that, since the
Third District Appellate Court is considering
an appeal
of a
prior
(August
26,
1986) Illinois Environmental Protection Agency
(~Agency)denial of an operating permit for
the same operation at
Joliet’s facility, the Board lacks jurisdiction to consider
issues arising
from the Agency’s later March 26,
1987,
decision
to deny.
While
both the March, 1987 denial
letter and the August,
1986 denial letter were essentially based on the fact that the
respective applications as subi~ittedcontained inadequate
information, the March, 1987 letter does not just repeat the
permit denial
reasons of
the August, 1986 letter.
None of the
four reasons
in the earlier letter
is repeated
in the latter
letter; and none of the reasons
in the later letter appears
in
the earlier letter.
I dissent from the majority Order because
I believe that the
petitioner’s statutory and due process rights are being
constrained because,
in order
to prevent multiple appeals, the
Board decision
in essence requires the petitioner to abandon
certain rights
in order
to preserve others.
I also believe that
the Board’s reliance on the Board’s holdings
in Album,
Inc. v.
IEPA,
PCB 81—23, March
19,
1981 and Caterpillar Tractor Co.
v.
IEPA,
PCB 79—180,
July 14, 1983 is misplaced.
Each of these
cases involved purported Agency issuance of a second permit while
appeal of condition of a prior
issued permit was pending before
the Board;
the policy and practical considerations involved
in
this case involving two permit denials are dissimilar.
And
I
further believe that the Board’s decision
is not beneficial
to
the environment.
As background
for my dissent, there are several observations
drawn from my experience as
a member of this Board that might
78-406
—2—
serve
to place
the issues
in perspective.
It
is beneficial
to
the environment as well as to a
facility operator
to have
operating permits renewed
as quickly as possible.
The benefit to
the environment
is that the renewal permit contains conditions
for the facility’s operation which are based
on current data.
The benefit to the operator
is that the facility
is insulated
from enforcement for failure
to have a valid permit.
‘Where the
Agency has either denied a permit or where the permit has been
issued with conditions which are deemed objectionable, it
is not
uncommon for the applicant to reapply
to the Agency as well as
to
file an appeal with the Board.
In addition to preserving
the
right of review of substantive disagreements,
the appeal
to the
Board may also protect the facility’s operating status.
Where
the permit is denied, and the applicant has timely filed
for
renewal of a permit,
the Board
has consistently held that the
facility may lawfully continue its operations pursuant to
the
expired permit, which
is deemed
to continue
in effect during the
pendancy of any appeal.
If the appeal
is dismissed prior
to
issuance of
a permit,
the facility cannot operate lawfully.
Where the conditions of an issued renewal permit are the subject
of challenge,
the facility operates pursuant
to the renewal
permit whose objectionable conditions may be stayed by the Board.
The Act contains
a detailed system for processing permits
and
resolving disputes.
Section 40 of the Illinois Environmental
Protection Act (“Act”)
allows a petitioner
to appeal to the Board
any final permit determination of the Agency, and to appeal
to
the Appellate
Court any final determination of the Board.
This
right of appeal must be exercised within 35 days.
It must be
emphasized
that,
once an application
is filed ‘with
the Agency or
an appeal
is filed with the Board, Sections 39(a)
and 40 of the
Act impose decision deadlines on the Agency and the Board
respectively.
Failure by the Agency or the Board
to timely
decide results
in a deemed approved permit.
There
is nothing
in
the Act that requires the petitioner
to waive these deadlines.
It
is also important to note that Section
39 requires the
Agency to give specific reasons for its denial of a permit.
Agency failure to state a reason
in the denial letter constitutes
a waiver of the right
to rely on the unstated reason; on appeal
the Board may not consider
reasons for denial which were
unstated, even
if those reasons would be valid.
In this instance, all parties had followed their mandates or
exercized their
rights.
The Agency had timely denied
a permit;
the petitioner
had timely appealed
to the Board,
the Board timely
upheld the Agency’s denial and the petitioner had timely appealed
to the appellate court, where jurisdiction of the August, 1986
decision now rests.
Following
the Board’s affirmation of the
Agency’s denial, the petitioner
also reapplied
to the Agency for
a permit.
The Agency again timely denied the permit in March,
1987 for
reasons different from those given
for its denial of the
78-407
—3—
earlier permit application.
The petitioner timely appealed this
denial
to the Board.
As the majority Order
notes,
in Album
the Board held that
where
a permit had been issued,
the Agency lacks authority
to
modify that permit while
it
is the
subject of an appeal.
The
Board’s reasoning was that “two permits covering the same process
or
equipment and
issued pursuant
to the same legal authority
cannot have simultaneous legal effect”,
and went on to conclude
that the earliest issued permits have “primacy and that the later
permits, assuming they exist, did not nullify the legal effect of
the prior permits”.
The Album
reasoning was subsequently
refined
in the Caterpillar case,
in response to arguments made by
the litigants regarding practical difficulties encountered
in an
attempt to settle
the appeal.
In Caterpillar,
the Board went on
to state
that the Agency could consider new information and
“issue”
a voidable permit, which could be ratified by the
permittee
to become effective upon dismissal
of the prior
action.
This procedure accommodates the petitioner’s right to
review of issues and affords protection
to its operating status,
while
still fostering problem resolution with the Agency.
Before today’s Order,
the Board had not considered the
ability of the Agency to issue a permit while a denial appeal was
pending before
the Board,
let alone while
a denial appeal was
pending before
an appellate court.
where no permit exists,
as
is the case here, there cannot be
a transfer of jurisdiction of any existing permit from the Agency
to
the Board
tq the Appellate Court.
While
I would agree that
the Appellate Court now has jurisdiction over the Board’s Order
affirming the August,
1986 permit denial,
I fail
to see how
pendancy of that appeal vests any jurisdiction of
a subsequent
application in that Court,
or how the Agency is precluded or
absolved from its statutory duty to issue or deny a permit upon
the basis of the subsequent application.
In short, the Album
and Caterpillar decisions do not apply
to the facts
in this case.
Moreover, this Board decision
violates the rationale
for
the Caterpillar case, which preserved
all
appeal
rights and benefits while allowing
for exercise of the
right of the filing of an application and timely Agency decision
thereon.
Here, the majority would require
an applicant to
abandon some rights in favor
of others.
It
is unclear from the
majority opinion whether
the majority considers that the pendancy
of the court appeal bars one or both of the following acts during
the pendancy of an appeal:
1)
the permitee’s filing
of
a
subsequent application,
or
2)
the Agency’s action on that
application within
the statutory time period.
Caterpillar
assumes that the applicant may file the application, and the
Agency may issue
a “voidable” permit before the applicant
dismisses its prior
appeal.
Ironically,
the rights the Board
78~408
—4—
sought
to preserve pursuant to Caterpillar are now lost
if the
Agency denies the permit.
Whether one or both acts are barred,
it
is clear
that an applicant
is being forced
to choose between
the right of judicial review of a previous administrative action
concerning
a permit application, and the right
to have either one
or both administrative agencies
(i.e. the Agency and/or
the
Board) make timely decisions concerning
the changed factual
situation which
a subsequent application presents.
~hi1e the effect of
the majority holding
is to
reduce
the
number of appeals pending before
the Board and the Courts~an
additional effect may be
to delay bringing
a facility into
the
permit system.
In this case,
for
instance,
if Joliet does not
choose
to dismiss its earlier appeal,
it cannot safely reapply
for
a permit until
that appeal
is finally decided some months
hence.
If the Board’s decision
is upheld, the application
process must begin
again.
Whereas
if a simultaneous appeal and
permit reapplication procedure is allowed to function,
as
I think
it practically and legally must, a permit could issue well before
a final appellate decision
is reached.
I appreciate the Board’s concern about potential for abuse
of
the permitting system through the filing of successive appeals
by an applicant who has filed successive deficient
applications.
However, even assuming that there are several
applicants who choose
to expend the not—inconsiderable monetary
and other
resources necessary to prosecute several simultaneous
appeals
in the courts and before the Board rather than
in
developing data,
the device chosen
by the majority to curtail one
perceived abuse can serve
to foster another.
For example, as aforementioned,
Section 39(a)
of the Act
requires the Agency,
in a permit denial letter, to give
“specific, detailed statements as
to the reasons”.
Thus,
the
Agency cannot later, on a re—review of the same information,
alter or
add
to those reasons.
Notwithstanding,
in a system
where permit applications and reapplications may be processed by
multiple and differing Agency permit reviewers over
time,
it
is
natural that new “afterthought” objections are or can be raised,
in good faith as well
as
in bad.
(See, e.g.,
Illinois Power
Co.
v. IEPA,
PCB 86—154, April
1,
1987,
a third appeal of issues
arising from an application filed
in 1979.)
This tendency to
raise new objections
to previously submitted information could be
encouraged by the majority holding, to the detriment of
the
permit system and the environment.
The Act’s fast—track appeal system was designed
to give
quick answers to all disputes arising between the Agency and the
regulated community,
in the interest of protection and
enhancement of the environment.
I believe that the majority’s
holding
frustrates the intent of this system.
78-409
—5—
For all
of the foregoing reasons,
I respectfully dissent.
~i4~J
~
Aoan G. Anderson
I,
Dorothy M. Gunn,
Clerk of the Illinois Pollution Control
Board, hereby certify that the above Dissenting Opinion was
submitted on the
2Z~
day of
_______________,
1987.
Dorothy M. Gunn,
Clerk
Illinois Pollution Control Board
78.410