ILLINOIS POLLUTION CONTROL BOARD
December 3, 1987
CITY OF DELAVAN,
Petitioner,
v.
)
PCB 87—137
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD (by J.D. Dumelle):
This matter comes before the Board on Petitioner’s September
18, 1987 Petition seeking a 3 month variance from Illinois NPDES
Effluent Standards. 35 Ill. Mm. Code Section 304.141, Section
304.1201 and IEPA’s Motion To File Agency Recommendation
Instanter, filed November 3, 1987.
Petitioner, the City of Delavan, Tazewell County, illinois
is a municipal corporation with a population of 1,973.
Petitioner provides sewage collection and treatment to 2,000
people, with improvements designed for
2300.
Sewage collection
is provided by a separate sanitary sewer system, and treatment is
currently provided by a single—cell pond system. The small cell
pond, which is designed to handle a design average flow I.DAF of
250,000 gallons/day, is in need of upgrading. The sewer system
tributary to the treatment plant is subject to surcharging and
basement back—ups, causing Petitioner to be placed on restricted
status on December 14, 1979. Agency Rec. pp. 2—3.
The existing, single cell, waste stabilization pond has a
surface area of 15.5 acres and a volume of approximately 17
million gallons. This single cell system is proposed to be
upgraded and augmented by the construction of a four (4) acre
second cell, rock filter, and a chlorine contact tank. Upon
completion of the project, treatment will be by large cell, small
cell, rock filter and chlorination. Petitioner has already
received permits to construct the new, four (4) acre pond.
Construction bids were due before September 17,1987 and awarding
of contracts was expected shortly thereafter. However, as a part
of the project, the existing pond must temporarily be taken out
of service. Pet. p. 3.
During the time when the original pond is out of service,
there will be discharges into nearby Crane Creek. From April 21,
1988 to May 1, 1988, 1 million gallons per day of effluent will
84-45
—2—
be discharged. From May 7, 1988 to May 18, 1988, approximately
700,000 gallons per day will be discharged. This discharge will
consist of 500,000 gallons/day transferred from the larger, older
pond and 200,000 gallons/day of raw sewage; however, prior to
discharge this flow will be treated by the small pond, rock
filter and chlorination. From May 15, 1988 to June 30, 1988,
approximately 200 gallons/day will be discharged. This will also
receive treatment consisting of small pond, rock filter
chlorination. Pet. p. 3.
Petitioner claims that during the construction period
current effluent standards cannot be met because the existing
pond must be taken out of service for repairs. Pet. p. 3, par.
‘E’.
COMPLIANCE PLAN
As noted above, Petitioner’s Compliance Plan includes
construction of a second lagoon cell, rock filter, and a
chlorination unit. when these are completed, raw sewage flows
and water from the dewatering of the first cell will be diverted
to the second cell. IEPA has approved of the proposal Agen?y
Recommendation p. 3 which incorporated the following work
schedule:
September 17, 1987
Construction bids received.
November 1, 1987
Construction of pumping station,
forcemain, small pond, rock
filter and chlorination unit
begins.
April 21, 1988
Drain large pond down 1.4 feet.
May 1, 1988
Construction work completed.
Finish draining large pond down
1.4 feet. Begin transfer from
large pond to small pond.
May 7, 1988
Finish small pond filling.
May 15, 1988
Draining of large pond is
completed. Begin reshaping of
earthen berms on large pond.
June 30, 1988
Completion of earthwork. Begin
filling large pond with raw
sewage. Implace riprap during
ret illing.
Pet. p. 2j.
84--46
—3—
ENVIRONMENTAL
IMPACT
Petitioner is currently authorized to discharge under NPDES
Permit No. IL 0028355, issued on April 4, 1983. Interim limits
are 40/75 mg/l BOD5/TSS monthly average, with final limits of
30/37 mg/i BOD5/TSS (monthly average
1.
As the data below
demonstrates, the current facility is incapable of producing
consistently acceptable effluent levels. The following data was
reported by Petitioner on its discharge monitoring reports ~DMRsj
for the previous year:
Average
Average
Average
Month
Flow—MGD
BOD5 mg/l
TSS mg/i
8/87
0.15
43
190
7/87
0.17
28
210
6/87
0.17
20
130
5/87
0.17
45
110
4/87
0.14
36
77
3/87
0.13
42
64
2/87
0.13
24
60
1/87
0.13
11
9
12/86
0.18
20
35
11/86
0.18
13
32
10/86
0.18
11
67
9/86
0.14
30
180
Average Limit:
0.155
27.0
97.0
40
75
There is no reason to believe these conditions have
improved. In the Agency Recommendation prepared for submission
in PCB 82—86, Petitioner was discharging 28/52 mg/l BODc~/TSS. In
reviewing the receiving streams the Agency said the following:
“Concerning Crane Creek, this investigation found unbalanced
conditions upstream from Petitioner, while downstream from
Petitioner’s outfall, polluted and “semi—polluted” conditions
were found. Stream quality improved to “unbalanced” within 2
miles from the outfall.” Agency Rec. p. 5.
Crane Creek, the receiving stream, is intermittent and
tributary to several ctiannelized drainage ditches. Diversity in
such streams is extremely limited. Crane Creek is unchannelized
for approximately 3 miles downstream of Petitioner’s discharge.
According to the terms of the proposed variance, altnouyh
BOD5 would be raised, the TSS level would remain at its current
level. Agency Rec. p. 5. Discharge of effluent from this
treatment plant is to an intermittent stream which does not
support fish life; there should be minimal effects on human,
animal and plant life. Pet. p. 4. The IEPA has stated that the
proposed variance will result in little additional adverse impact
84-47
—4—
on the receiving streams owing to the, short duration of the
variance. Agency Rec. p. 6.
HARDSHIP
Petitioner stated that construction of temporary holding
pond would cost approximately $207,000. Pet. p. 4. $2,092,681
is the projected cost of the proposed upgrading of the plant and
sewer system, of which $1,471,932 will be funded by grants.
Agency Rec. p. 6. Thus, Petitioner must pay $620,749 from its
own sources of funds. Requiring Petitioner to construct the
temporary holding ponds would be unreasonable, especially since a
temporary holding pond is unnecessary and not needed for final
operation.
CONCLUSION
For the foregoing reasons, and in consideration of the small
adverse environmental impact, the Board finds that denial of the
requested variance would impose an arbitrary or unreasonable
hardship.
This Opinion and Order constitutes the Board’s findings of
fact and conclusions of law in this matter.
ORDER
The Agency’s Motion To File Recommendation Instanter is
granted.
Petitioner, City of Delavan, is hereby granted a variance
from Illinois NPDES Effluent Standards 35 Ill. Adm. Code Section
304.141 Section 304.1201 subject to the following conditions:
1. Variance shall begin when the old pond is removed from
service.
2. Variance shall expire July 1, 1988.
3. While dewatering the old pond, Petitioner shall not
discharge sludges or bottom deposits to either the new
pond or the receiving stream.
4. Petitioner shall notify IEPA of the dewatering of the
old pond at least 24 hours prior to commencement of
dewatering. Petitioner shall contact IEPA’s Regional
Office at (309) 693—5463.
5. Follow—up, written notification of the dewatering shall
be submitted within 5 days to:
84--43
—5—
Illinois Environmental Protection Agency
DWPC, Region II
5415 N. University Avenue
Peoria, Illinois 61614
7. During the time the variance is in effect, Petitioner
shall monitor its effluent for BOD5 and TSS every two
weeks. These results shall be reported on Petitioner’s
DMRs.
8. Petitioner shall operate its sewer treatment facilities
so as to produce the best treatment possible.
9. During the term of the variance, Petitioner shall meet
the following effluent limits:
BOD5
50 mg/i Monthly Average
TSS
100 mg/l Monthly Average
10. Within 45 days of the granting of the variance by the
Board, Petitioner shall execute and submit a
Certificate of Acceptance agreeing to be bound to the
terms and conditions of the variance and shall mail it
to:
Illinois Environmental Protection Agency
Division of Water Pollution Control
Compliance Assurance Section
2200 Churchill Road
P.O. Box 19276
Springfield, Illinois 62794—9276.
I, (We), The City of Delavan, having read the Order of the
Ilrinois Pollution Control Board in PCi3 87—137, dated December 3,
1987, understand and accept said Order, realizing that such
acceptance renders all terms and conditions thereto binding and
enforceable.
Petitioner
Title
By: Authorized Agent
Date
IT IS SO ORDERED.
84 49
—6—
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the above Op~nion~nd Order was
adopted on the
______________
day of
~
,
1987 by a vote
of
_______________.
~
.
dorothy M.~éunn, Clerk
Illinois Pollution Control Board
8 4—50