ILLINOIS POLLUTION CONTROL BOARD
    September 4, 1987
    REYNOLDS METALS COMPANY,
    Petitioner,
    vs.
    )
    PCB 87—63
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENC’~Y
    Respondent.
    OPINION AND ORDER OF
    THE
    BOARD (by
    3.
    Theodore Meyer):
    This matter is before the Board on a petition for variance
    filed by Reynolds f~ieta1s Company (Reynolds). Reynolds seeks
    relief until July 1, 1988, from 35 Ill. Adm. Code 304.120(c) as
    it relates to the bio—chemical oxygen demand (BOO) effluent
    limitations applicable under its National Pollutant Discharge
    Elimination System (NPDES) permit for its ~1cCook, Illinois,
    aluminum fabricating facility. The Illinois Environmental
    Protection Agency (Agency) has filed its Recommendation in
    support of grant of variance, subject to certain conditions. On
    July 23, 1987, Reynolds filed a motion for expedited
    consideration, in which it stated that it agreed with those
    conditions. On August 6, 1987, the Board granted the motion for
    expedited consideration. Hearing was waived.
    Reynolds1 McCook plant casts and imports alloyed aluminum
    ingots which are then hot and cold rolled into sheet, coil, and
    plate products. Oil and water emulsions are used as lubricants
    in hot rolling the ingots into sheet and plate. These emulsions
    are treated with an emulsion breaking system of steam heat and
    acid treatment. The wastewater from this emulsion treatment
    system is then neutralized with a caustic soda and discharged
    into the plant’s wastewater treatment system. The wastewater
    treatment process consists of oil skimming, chemical
    precipitation, and settling. The treated wastewater is
    subsequently discharged, througn Reynolds’ Outfall 001, into the
    the Summit
    Lyons Ditch and then by siphon to the Chicago
    Sanitary and Ship Canal (Canal). Outtall 001 is the only one of
    Reynolds’ three outfalls which is limited for BOD, and Reynolds
    states that the wastewater from the emulsion breaking system is
    the only major source of BOD.
    Reynolds’ existing NPDES permit provides for BOD load limits
    of 98.2 lbs/day (30
    day average) and 286.9 lbs/day (daily
    maximum), and concentration limits of 10 mg/l (30
    day average)
    81—51

    —2--
    and 20 mg,’l (daily maximum). Reynolds asks that the BOO limits
    be revised to load limits of 150 lbs/day (30
    day average) and
    450 lbs/day (daily maximum), and concentration limits of 20 mg/l
    (30
    aay average) and 40 mg/l (daily maximum). In the fifteen
    month period between January 1986 and March 1987, the maximum
    concentration limits have been exceeded in eight months and the
    average concentration limits have been exceeded in five months.
    The maximum load limit was surpassed once, and the average load
    limits were exceeded twice. With the exception of three of the
    maximum concentration violations, all of the excesses occurred in
    the last five months of that period. Reynolds states that
    changes in quality and production requirements for aluminum
    rolling operations have forced it and other manufacturers to use
    more stable oil and water emulsions. These more stable emulsions
    contain a greater percentage of water—soluble organics, which
    result in more BOD in the treated wastewater.
    Reynolds proposes to eliminate the discharge of the oil and
    water emulsion breaking system from the wastewater treatment
    system by routing it to the sanitary sewer of the Metropolitan
    Sanitary District of Greater Chicago (MSDGC). This would require
    the design and installation of piping to allow the neutralized
    wastewater from the emulsion breaking system to be discharged to
    the sanitary sewer. This proposal is based upon a 1986 report
    prepared by an outside environmental consultant for Reynolds.
    Reynolds anticipates that the applicable permits will be obtained
    and the system designed and installed by July 1, 1988. The
    preliminary estimated cost of re—routing the emulsion breaking
    system wastewater is approximately $100,000.
    An alternative method for handling the present BOD load
    would be to install additional tertiary treatment to remove
    water—soluble organics from the emulsion breaking system
    effluent.. However, Reynolds contends that additional treatment
    systems would be expensive to install and maintain, and would not
    guarantee that the BOD levels would be in compliance with the
    point limits. Reynolds states that MSDGC, on the other hand,
    already has a biological degradation treatment system in place
    which would effectively treat the BOD. Thus, Reynolds asserts
    that routing the emulsion breaking system wastewater to the
    sanitary sewer is the most efficient way to treat the wastewater
    containing the highest concentration of BOD, and would insure
    compliance with existing NPDES permit levels. Reynolds does not
    believe that the requested variance will have any significant
    environmental impact on the quality of the receiving water.
    Reynolds notes that without a variance, it faces the
    likelihood of continued violations of the existing BOO limits
    until the re—routing is completed. Such violations subject
    Reynolds to the possibility of enforcement action by the Agency
    or by citizen suits. Because it has pursued its BOD non-
    81—52

    —3—
    compliance problem and has specific actions underway to achieve
    compliance, Reynolds asserts that the prospect of such liability
    during the construction period constitutes an arbitrary and
    unreasonable hardship.
    The
    Agency recommends that
    the requested variance be
    granted, subject to conditions.
    The Agency believes that the re-
    routing is the best way to handle Reynolds’ discharge. The
    Agency also agrees that Reynolds has an arbitrary and
    unreasonable hardship, since Reynolds cannot meet its SOD limits
    even with good operation. As to the environmental impact of the
    variance, the Agency states that the increased BOO in the
    discharge should not significantly reduce dissolved oxygen (DO)
    in the aitch or in the Canal. The Agency notes, however, that
    its water quality sampling program has shown DO violations in the
    Canal at Lockport, downstream from Reynolds’ discharge.
    Furthermore, the Agency points out that the Board may grant the
    variance consistent with tederal requirements, since the
    regulation for the aluminum forming subcategory provides no
    guidance or restriction on BOD. The Agency does express doubts
    as to whether Reynolds’ compliance schedule is accurate. Since
    it is in no better position to determine wkiat the schedule should
    be, however, the Agency states that it accepts Reynolds’
    compliance schedule as the most reasonable available.
    Based on all of the facts and circumstances presented here,
    the Board finds that denial of the variance would impose an
    arbitrary or unreasonable hardship. Therefore, the Board will
    grant the requested variance until July 1, 1988, or until the
    emulsion breaking system wastewater is re—routed to the MSDGC
    sewer system, whichever occurs first.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    1. Petitioner, Reynolds Metals Company, is hereby granted a
    variance from 35 Ill. Adm. Code 304.120(c) as it relates to
    bio—chemical oxygen demand (BOD) and from 35 Ill. Adm. Code
    304.14l(a) for Outfall 001 only, subject to the following
    conditions:
    a) This variance will expire on July 1, 1988, or upon the
    re—routing of the emulsion breaking system wastewater to
    the MSDGC sewer system, whichever occurs first.
    b) Petitioner shall operate its facilities so as to meet the
    SOD load limits of 150 lbs/day for the 30— day average
    and 450 lbs/day for the daily maximum;
    81—53

    —‘~ —
    c) Petitioner shall operate its facilities so as to produce
    the best effluent possible and meet the BOD effluent
    limits of 20 mg/l for the 30
    day average and 40 mg/l
    for the daily maximum;
    d) Petitioner shall apply for all applicable permits in a
    timely manner; and
    e) Petitioner shall complete the re—routing of the emulsion
    breaking system wastewater to the MSDGC sewer system by
    July 1, 1988
    2. ~ithin forty—five days of the date of this Order, Petitioner
    shall execute and forward to Jose Gonzalez, Jr., Enforcement
    Programs, Illinois Environmental Protection Agency, 2200
    Churchill Road, Springfield, Illinois 62706, a certificate of
    Acceptance and Agreement to be bound to all terms and
    conditions of the variance. This forty—five day period shall
    be held in abeyance during any period that this matter is
    being appealed. The form of said Certification shall be as
    follows:
    CERTIFICATION
    I, (ge), _______________________, having read the Order of
    the Illinois Pollution Control Board in PCB 87—63, dated
    September 4, 1987, understand and accept the said Order,
    realizing that such acceptance renders all terms and conditions
    thereto binding and enforceable.
    Petitioner
    By: Authorized Agent
    Title
    Date
    IT IS SO ORDERED.
    81—54

    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the aboye Opinion and Order was
    aoopted on tne ~
    day of
    ~
    1987.~ by a
    vote of
    a—C
    -
    /-
    C
    ~
    Dorothy M. Gu’nn, Clerk
    Illinois Pollution Control Board
    8 1—55

    Back to top