ILLINOIS POLLUTION CONTROL BOARD
September 4, 1987
REYNOLDS METALS COMPANY,
Petitioner,
vs.
)
PCB 87—63
ILLINOIS ENVIRONMENTAL
PROTECTION AGENC’~Y
Respondent.
OPINION AND ORDER OF
THE
BOARD (by
3.
Theodore Meyer):
This matter is before the Board on a petition for variance
filed by Reynolds f~ieta1s Company (Reynolds). Reynolds seeks
relief until July 1, 1988, from 35 Ill. Adm. Code 304.120(c) as
it relates to the bio—chemical oxygen demand (BOO) effluent
limitations applicable under its National Pollutant Discharge
Elimination System (NPDES) permit for its ~1cCook, Illinois,
aluminum fabricating facility. The Illinois Environmental
Protection Agency (Agency) has filed its Recommendation in
support of grant of variance, subject to certain conditions. On
July 23, 1987, Reynolds filed a motion for expedited
consideration, in which it stated that it agreed with those
conditions. On August 6, 1987, the Board granted the motion for
expedited consideration. Hearing was waived.
Reynolds1 McCook plant casts and imports alloyed aluminum
ingots which are then hot and cold rolled into sheet, coil, and
plate products. Oil and water emulsions are used as lubricants
in hot rolling the ingots into sheet and plate. These emulsions
are treated with an emulsion breaking system of steam heat and
acid treatment. The wastewater from this emulsion treatment
system is then neutralized with a caustic soda and discharged
into the plant’s wastewater treatment system. The wastewater
treatment process consists of oil skimming, chemical
precipitation, and settling. The treated wastewater is
subsequently discharged, througn Reynolds’ Outfall 001, into the
the Summit
—
Lyons Ditch and then by siphon to the Chicago
Sanitary and Ship Canal (Canal). Outtall 001 is the only one of
Reynolds’ three outfalls which is limited for BOD, and Reynolds
states that the wastewater from the emulsion breaking system is
the only major source of BOD.
Reynolds’ existing NPDES permit provides for BOD load limits
of 98.2 lbs/day (30
—
day average) and 286.9 lbs/day (daily
maximum), and concentration limits of 10 mg/l (30
—
day average)
81—51
—2--
and 20 mg,’l (daily maximum). Reynolds asks that the BOO limits
be revised to load limits of 150 lbs/day (30
—
day average) and
450 lbs/day (daily maximum), and concentration limits of 20 mg/l
(30
—
aay average) and 40 mg/l (daily maximum). In the fifteen
month period between January 1986 and March 1987, the maximum
concentration limits have been exceeded in eight months and the
average concentration limits have been exceeded in five months.
The maximum load limit was surpassed once, and the average load
limits were exceeded twice. With the exception of three of the
maximum concentration violations, all of the excesses occurred in
the last five months of that period. Reynolds states that
changes in quality and production requirements for aluminum
rolling operations have forced it and other manufacturers to use
more stable oil and water emulsions. These more stable emulsions
contain a greater percentage of water—soluble organics, which
result in more BOD in the treated wastewater.
Reynolds proposes to eliminate the discharge of the oil and
water emulsion breaking system from the wastewater treatment
system by routing it to the sanitary sewer of the Metropolitan
Sanitary District of Greater Chicago (MSDGC). This would require
the design and installation of piping to allow the neutralized
wastewater from the emulsion breaking system to be discharged to
the sanitary sewer. This proposal is based upon a 1986 report
prepared by an outside environmental consultant for Reynolds.
Reynolds anticipates that the applicable permits will be obtained
and the system designed and installed by July 1, 1988. The
preliminary estimated cost of re—routing the emulsion breaking
system wastewater is approximately $100,000.
An alternative method for handling the present BOD load
would be to install additional tertiary treatment to remove
water—soluble organics from the emulsion breaking system
effluent.. However, Reynolds contends that additional treatment
systems would be expensive to install and maintain, and would not
guarantee that the BOD levels would be in compliance with the
point limits. Reynolds states that MSDGC, on the other hand,
already has a biological degradation treatment system in place
which would effectively treat the BOD. Thus, Reynolds asserts
that routing the emulsion breaking system wastewater to the
sanitary sewer is the most efficient way to treat the wastewater
containing the highest concentration of BOD, and would insure
compliance with existing NPDES permit levels. Reynolds does not
believe that the requested variance will have any significant
environmental impact on the quality of the receiving water.
Reynolds notes that without a variance, it faces the
likelihood of continued violations of the existing BOO limits
until the re—routing is completed. Such violations subject
Reynolds to the possibility of enforcement action by the Agency
or by citizen suits. Because it has pursued its BOD non-
81—52
—3—
compliance problem and has specific actions underway to achieve
compliance, Reynolds asserts that the prospect of such liability
during the construction period constitutes an arbitrary and
unreasonable hardship.
The
Agency recommends that
the requested variance be
granted, subject to conditions.
The Agency believes that the re-
routing is the best way to handle Reynolds’ discharge. The
Agency also agrees that Reynolds has an arbitrary and
unreasonable hardship, since Reynolds cannot meet its SOD limits
even with good operation. As to the environmental impact of the
variance, the Agency states that the increased BOO in the
discharge should not significantly reduce dissolved oxygen (DO)
in the aitch or in the Canal. The Agency notes, however, that
its water quality sampling program has shown DO violations in the
Canal at Lockport, downstream from Reynolds’ discharge.
Furthermore, the Agency points out that the Board may grant the
variance consistent with tederal requirements, since the
regulation for the aluminum forming subcategory provides no
guidance or restriction on BOD. The Agency does express doubts
as to whether Reynolds’ compliance schedule is accurate. Since
it is in no better position to determine wkiat the schedule should
be, however, the Agency states that it accepts Reynolds’
compliance schedule as the most reasonable available.
Based on all of the facts and circumstances presented here,
the Board finds that denial of the variance would impose an
arbitrary or unreasonable hardship. Therefore, the Board will
grant the requested variance until July 1, 1988, or until the
emulsion breaking system wastewater is re—routed to the MSDGC
sewer system, whichever occurs first.
This Opinion constitutes the Board’s findings of fact and
conclusions of law in this matter.
ORDER
1. Petitioner, Reynolds Metals Company, is hereby granted a
variance from 35 Ill. Adm. Code 304.120(c) as it relates to
bio—chemical oxygen demand (BOD) and from 35 Ill. Adm. Code
304.14l(a) for Outfall 001 only, subject to the following
conditions:
a) This variance will expire on July 1, 1988, or upon the
re—routing of the emulsion breaking system wastewater to
the MSDGC sewer system, whichever occurs first.
b) Petitioner shall operate its facilities so as to meet the
SOD load limits of 150 lbs/day for the 30— day average
and 450 lbs/day for the daily maximum;
81—53
—‘~ —
c) Petitioner shall operate its facilities so as to produce
the best effluent possible and meet the BOD effluent
limits of 20 mg/l for the 30
—
day average and 40 mg/l
for the daily maximum;
d) Petitioner shall apply for all applicable permits in a
timely manner; and
e) Petitioner shall complete the re—routing of the emulsion
breaking system wastewater to the MSDGC sewer system by
July 1, 1988
2. ~ithin forty—five days of the date of this Order, Petitioner
shall execute and forward to Jose Gonzalez, Jr., Enforcement
Programs, Illinois Environmental Protection Agency, 2200
Churchill Road, Springfield, Illinois 62706, a certificate of
Acceptance and Agreement to be bound to all terms and
conditions of the variance. This forty—five day period shall
be held in abeyance during any period that this matter is
being appealed. The form of said Certification shall be as
follows:
CERTIFICATION
I, (ge), _______________________, having read the Order of
the Illinois Pollution Control Board in PCB 87—63, dated
September 4, 1987, understand and accept the said Order,
realizing that such acceptance renders all terms and conditions
thereto binding and enforceable.
Petitioner
By: Authorized Agent
Title
Date
IT IS SO ORDERED.
81—54
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the aboye Opinion and Order was
aoopted on tne ~
day of
~
1987.~ by a
vote of
a—C
-
/-
C
~
Dorothy M. Gu’nn, Clerk
Illinois Pollution Control Board
8 1—55