ILLINOIS POLLUTION CONTROL BOARD
November 2, 2000
EQUILON ENTERPRISES L.L.C,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL PROTECTION
AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 01-38
(Permit Appeal - Air)
ORDER OF THE BOARD (by C.A. Manning):
On
August 25
, 2000, the Illinois Environmental Protection Agency (Agency) and petitioner filed a
request for extension of the 35-day appeal period pursuant to Section 40 of the Environmental Protection Act
(Act) (415 ILCS 5/40(a)(1) (1998)). On October 25, 2000, the Board received petitioner’s request that the Board
review certain provisions of the Clean Air Act Permit Program (CAAPP) permit that the Agency issued on
July 27, 2000, to Equilon Enterprises L.L.C, for its facility located at 1605 E. Algonquin Road, Arlington
Heights, Cook County, Illinois. The Board accepts this matter for hearing.
Hearings shall be scheduled and completed in a timely manner pursuant to the applicable statutory
decision deadline or as extended by waiver. The assigned hearing officer shall inform the Clerk of the Board
of the time and location of hearing at least 40 days in advance of hearing so that a 30-day public notice of
hearing may be published. Unless otherwise ordered by the hearing officer, the Agency shall file the record
of its review of the CAAPP permit application within 30 days after service of the petition. See 35 Ill. Adm.
Code 105.102(c)(7).
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that the above order
was adopted on the 2nd day of November 2000 by a vote of 7-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board