ILLINOIS POLLtJTION CONTROL BOARD
    June
    30,
    1988
    IN THE MATTER OF:
    PARTICULATE EMISSION LIMITATIONS,
    )
    R82—l
    (Docket
    B)
    RULE 203(g)(l)
    AND 202(b) OF
    CHAPTER 2
    ADOPTED RULE.
    FINAL ORDER.
    OPINION AND ORDER OF THE BOARD
    (by J.
    D.
    Dumelle):
    This Opinion and Order brings
    to
    a close
    a long and
    complicated rulemaking proceeding.
    Early procedural activities
    are set forth
    in the Board’s Final Opinion and Order dated July
    2,
    1986
    in R82—l(Docket A):
    Particulates.
    On March
    14,
    1986,
    the Board adopted an Interim Order
    in R82—l separating
    that
    proceeding
    into two dockets: Docket A:
    Particulates and Docket
    B:
    Opacity.
    At that time the Board intended
    to proceed
    to second
    notice on the particulate
    rules while further considering the
    opacity
    rules.
    However,
    the Joint Committee on Administrative
    Rules
    (JCAR)
    refused
    to
    allow the Board
    to proceed
    in that
    manner.
    Therefore,
    on May
    9,
    1986,
    the Board adopted
    a Fourth
    Second Notice order including both the opacity and the
    particulate rules.
    Second notice was received by JCAR on May 16, 1986,
    and was
    considered by JCAR on June
    23,
    1986,
    at which
    time
    it objected
    to
    each of
    the opacity
    rules but none
    of the particulate
    rules.
    In
    response the Board determined
    that it would withdraw the opacity
    rules but proceed
    to adopt and file the particulate rules.
    The
    Board adopted
    a Resolution and Order
    to that effect on July
    2,
    1986,
    and indicated
    that
    a new first notice order would be
    adopted concerning
    the opacity
    rules
    in the near
    future under
    Docket
    B.
    On August 14,
    1986,
    the Board adopted
    a Third First
    Notice Order.
    As more
    than one year passed since
    the date
    of
    that first notice,
    Section
    5.01(d)
    of
    the Illinois ~dministrative
    Procedure Act
    (APA) precluded
    the rule from being adopted,
    or
    from being filed with
    the Secretary of State.
    Therefore,
    the
    Board sent the proposed rules
    to Fourth First Notice on December
    17,
    1987.
    In
    the interest of expediency,
    the Board adopted
    for Fourth
    First Notice the same proposal as was adopted
    for Third First
    Notice
    ——
    but with
    a few amendments.
    First,
    in its comments,
    the
    Agency suggested certain revisions
    to Section 212.124(d),
    the
    defense provision,
    based
    on issues that arose at hearing.
    The
    Agency stated
    its position that
    the record does
    not
    support
    extending
    the Adjusted Opacity Standards Procedures
    to “process
    sources” and offered revised language.
    90—589

    —2—
    Also,
    the Board proposed
    a Subpart
    B
    to
    35 Ill.
    Adm.
    Code
    106 entitled
    “Air Adjusted Standards Procedures”.
    Proposed
    Subpart
    E
    is similar
    to
    35
    Ill.
    Adm.
    Code
    106.
    Subpart
    D, which
    relates to RCRA adjusted standards procedures.
    The sections
    which comprise Subpart
    E are generic
    procedural rules which the
    Board will reference whenever adjusted standards procedures
    are
    provided for
    in the Board’s
    air pollution
    regulations.
    The Board
    believes that
    a separate Subpart
    for air adjusted standard
    procedures
    is appropriate
    to address
    the particular
    requirements
    associated with the air regulations.
    Accordingly,
    those
    provisions previously
    set forth
    in Section
    212.126 which address
    generic procedures are now located
    in 35
    Ill.
    Adm.
    Code
    106.
    Subpart
    E.
    Fourth First Notice was published
    at 12
    Ill.
    Reg.
    1722,
    1729,
    January 15,
    1988.
    The first notice comment period
    concluded
    on March
    2,
    1988.
    The Illinois Environmental
    Protection Agency (Agency) submitted the only comment during the
    Fourth First Notice on February 26,
    1988.
    On March
    21,
    1988,
    the
    Department
    of Commerce and Community Affairs filed
    its Impact
    Analysis
    stating
    that
    the proposed amendments
    will have no
    economic effect on small businesses.
    The Administrative Code
    Division of the Secretary of State’s Office
    filed comments on
    February 11,
    1988.
    Those comments have been incorporated into
    the Second Notice Order.
    Pre—Fourth
    First Notice Comments
    In the Fourth First Notice Order
    the Board stated:
    “The
    Board
    believes
    that
    the
    revisions
    may
    affect
    the
    continued
    applicability
    of
    the
    previously filed
    cormiients and requests further
    comment
    on
    these
    issues.
    For
    the
    sake
    of
    efficiency,
    the Board notes that comments need
    not
    be
    duplicated.
    Previous
    comments,
    if
    still
    applicable,
    may
    be
    incorporated
    by
    reference.”
    As noted above, only the Agency filed comments on the Fourth
    First Notice Order.
    Despite
    the Board’s clear request
    for
    additional comment, none
    of the previous comrnenters opted
    to
    address
    the Fourth First Notice proposal.
    As
    the Board cannot
    and will not second—guess
    those commenters,
    the Board
    can only
    assume that the Fourth First Notice proposal does not meet with
    disapproval
    other than that noted
    by the Agency.
    Third First Notice History
    On August
    14,
    1986 the Board issued
    the Third First Notice
    Order
    in this Docket (R82—l(B)).
    The Board noted
    that several
    issues remained
    from the Fourth Second Notice Order
    and requested
    ‘jo—
    591)

    —3—
    comment
    on
    them.
    On October
    2, 1986,
    the Administrative
    Code
    Division
    of the Secretary of States Office
    filed comments.
    On
    November
    20,
    1986,
    the Agency submitted
    a revised opacity
    proposal.
    The final hearing was held on November
    24, 1986.
    Seven comments were filed between May,
    1986 and February,
    1987.
    In
    the~
    Third First Notice Order,
    the Board asked whether
    “Reasonable Time” in Section 212.124(c)
    (now renumbered
    to
    subsection
    (d))
    should be defined.
    At hearing on November
    24,
    1986,
    the Agency suggested
    the language
    “a reasonable
    time not
    to
    exceed
    60 days.”
    This was the language proposed at Fourth First
    Notice.
    In reviewing previous comments,
    the Board determined
    that this language could be clarified further.
    The Board added
    “after written notification from the Agency
    of
    a violation”
    after
    “60 days.”
    The Board
    takes
    this action consistent with
    the
    expressed intentions
    of
    the Agency.
    (Tr.
    16, November 24,
    1986).
    In Third First Notice,
    the Board asked whether
    “similar
    operating conditions” should be defined.
    At hearing
    on November
    24,
    1986,
    the Agency agreed that “similar
    operating conditions”
    is vague.
    Further,
    the Agency noted that there might be
    similar
    operating conditions
    that would decrease mass emissions but not
    opacity.
    This,
    the Agency noted, could
    be viewed
    as
    a relaxation
    of the State Implementation
    Plan
    (SIP) without
    a demonstration
    that the National Ambient Air Quality Standards would not be
    jeopardized.
    The Agency proposed,
    therefore,
    to amend “similar”
    to “same.”
    The Board did so
    at Fourth First Notice,
    and received
    no comment on
    this action.
    As the Board believes that the “same
    operating conditions”
    at
    the time of the violation
    is more
    definite than “similar operating conditions,”
    the Board will
    retain the language as proposed
    at Fourth First Notice.
    At Third First Notice,
    the Board asked whether levels of
    justification must be established
    under
    then Section 212.126(1)
    regarding how the factors
    of Section 27(a)
    of
    the Environmental
    Protection Act (Act) will be considered
    in deciding whether
    to
    adopt an
    adjusted standard.
    JCAR had indicated that such levels
    of
    justification were necessary.
    The Board notes
    that this
    subsection
    no longer exists
    in Part 212,
    rather
    a similar section
    was proposed
    in the Part 106 procedures
    for an adjusted
    standard.
    Section 106.507, requires the Board
    to adopt an
    opinion and order consistent with Section
    27(a)
    of
    the Act.
    As
    the text of this Section was based
    on Section 106.416, already
    adopted and already past JCAR review,
    the Board does not
    anticipate any further problem with the language proposed
    at
    Fourth First Notice.
    As previously noted,
    after
    Third First Notice, several
    comments were submitted on the proposed rules.
    As
    a result of
    changes made at hearing
    and thereafter,
    the Board believes that
    many concerns raised
    in the comments have been resolved.
    However, one of the commenters,
    the Illinois Power Company,
    took
    the position
    that
    90-59 1

    —4—
    “there
    is
    no
    statutory
    mandate
    that
    the Board
    adopt
    opacity
    as
    an
    independently enforceable
    air emission
    standard.
    Furthermore,
    there
    is
    no federal
    requirement under
    the Clean Air Act
    that
    the
    Illinois
    State
    Implementation
    Plan
    (SiP)
    contain
    an
    independently
    enforceable
    opacity
    standard.
    In
    any
    event,
    the
    Record
    does
    not support
    such
    a
    standard.”
    (P.C.
    No.
    42, filed February
    19,
    1987).
    The Board does not agree.
    By Interim Order dated March
    14,
    1986,
    the Board noted
    that
    a
    letter was filed by Mr. Steve
    Rothblatt of United States Environmental Protection Agency
    (USEPA), indicating USEPA’s position that the rule
    as then
    proposed were unapprovable.
    The Board stated that
    “these communications
    from USEPA place
    a cloud
    over the opacity rules:
    the state
    is required
    to
    comply
    with
    the
    Clean
    Air
    Act
    and
    regulations
    adopted
    thereunder,
    and
    USEPA’s
    interpretation
    of
    its own
    rules must be given
    some deference.”
    Further,
    the Board set another hearing
    and requested
    testimony
    regarding
    the
    “legal
    requirements
    of
    the
    state
    implementation
    plan
    regarding
    visual
    emissions,
    what
    type
    or
    types
    of
    rules
    would
    or
    should
    be
    federally
    approvable,
    the
    adequacy
    of
    the
    present
    record
    to support
    the
    adoption of such rules
    ...
    .“
    (Interim Order,
    March
    14,
    1986,
    p.
    2).
    Hearing was held on April
    28,
    1986,
    at which William L. MacDowell
    testified on behalf
    of USEPA.
    It was Mt. MacDowell’s testimony
    that Federal regulations,
    40 CFR 51.19(c)
    (now codified
    at 40 CFR
    51.212(b))
    require enforceable visible emissions limitations
    in
    order
    to ensure that particulate control equipment
    is properly
    operated and maintained on a continuing
    basis.
    Mr. MacDowell
    offered much testimony to support
    the notion that opacity
    rules
    are federally required.
    Further,
    in its comments on
    the Fourth
    First Notice,
    (P.C.
    No.
    44),
    the Agency submitted
    a letter dated
    November
    6,
    1987,
    from
    Mr.
    Michael
    Hayes,
    Manager
    of the the
    Division
    of Air Pollution Control,
    to Jacob Dumelle, Chairman of
    the
    Pollution
    Control
    Board.
    The
    letter
    notes
    that
    the
    previous
    First
    Notice
    in
    the
    rulemaking,
    R82—l(B),
    expired
    on
    September
    5,
    1987
    and
    urges
    the
    Board
    to promptly promulgate opacity standards
    because
    it
    believes
    that
    such
    standards
    remain
    necessary.
    To
    support
    this
    belief,
    the
    Agency
    also
    submitted
    an
    Agency
    memorandum
    from
    Dan
    D’Auben
    to
    Susan
    Schroeder
    on
    the
    necessity
    issue.
    The
    memo
    states:
    90—592

    —5—
    “The
    State
    of
    Illinois
    will
    be
    submitting
    three
    types
    of
    PM10
    SIP5.
    The
    first,
    for
    Group
    I
    areas,
    may
    include
    new
    process
    and
    fugitive
    emission
    rules
    for
    sources
    in
    SE.
    Chicago,
    S.W.
    Cook
    County,
    Oglesby,
    and
    Granite
    City.
    These
    areas,
    because
    of
    previous
    TSP
    monitoring,
    PM10
    monitoring,
    or
    previous
    studies
    are
    presumed
    to
    not
    be
    in
    compliance
    with
    PM10
    NAAQS.
    The second
    type
    of
    PM10
    SIP
    (Group
    II)
    is
    for
    areas
    the
    compliance
    with
    the
    NAAQS
    is
    uncertain.
    The
    last
    type of PM10 SIP (Group
    III)
    is for areas
    that
    it
    is
    assumed
    that
    the
    TSP
    SIP
    is
    adequate
    to protect the PM10 NAAQS.
    This type
    of
    SIP would
    cover
    the majority
    of
    the
    State
    of
    Illinois.
    A
    major
    SIP
    requirement
    for
    Group
    II
    and
    III
    areas
    is
    that
    the
    TSP
    SIP
    must
    be
    viable
    and
    enforceable.
    This
    is
    required
    because
    it
    is
    assumed
    that
    the
    TSP
    emission
    regulations
    are
    adequate
    to
    protect
    the
    PM10
    NAAQS.
    If
    an
    opacity
    rule
    is
    not
    promulgated
    for
    TSP
    (R82—1)
    we
    feel
    that
    the
    USEPA will
    hold
    that portions
    of
    our TSP SIP
    are
    unenforceable
    and
    therefore
    the
    PM10
    SIP
    is
    not viable.”
    (Agency’s Fourth First Notice
    Comments,
    P.C.
    No.
    44,
    filed
    February
    26,
    1988,
    Attachment
    2).
    The
    Board
    believes
    that
    the
    Record
    is
    sufficient
    to
    support
    the
    adoption
    of
    these
    opacity
    rules.
    Fourth
    First
    Notice Comments and Revisions
    The
    Agency
    commented
    that
    in
    proposed
    Section
    2l2.124(d)(1)
    certain
    words
    were
    “mistakenly
    deleted
    from
    the
    Fourth
    First
    Notice”
    Order.
    The
    Board can only note that
    the language
    proposed
    to
    Section
    2l2.124(d)(l)
    at
    Fourth
    First Notice was
    taken
    verbatim
    from
    the
    Final Agency Comments filed February 11,
    1987,
    at
    page
    5.
    The
    Board
    accepts
    the
    Agency’s
    suggestion
    and
    has
    amended
    “Section
    212.123”
    to
    become
    “Sections
    212.122
    and
    212.123.”
    The
    Agency
    commented
    that
    Section
    2l2.124(d)(2)
    contains
    a
    reference
    to
    Section
    212.110.
    The
    Agency
    noted
    that
    it
    has
    proposed
    to change this particular provision
    in Board rulemaking
    R79—14
    to the procedures
    of 35
    Ill.
    Adrn. Code
    230, Appendix A (40
    CFR 60, Method
    5).
    Because R79—14 has not yet been sent to First
    Notice,
    this proceeding will most
    likely result
    in finalized
    regulations first.
    Therefore,
    the Board will
    include the
    amendment
    in this proceeding.
    However, because
    the Environmental
    Protection Act
    (Act)
    no longer authorizes
    the Board
    to
    90—593

    —6—
    peremptorily amend
    35
    Ill. Adm.
    Code 230 and
    231,
    the Board will
    Cite directly
    to the Code
    of Federal Regulations
    for
    incorporation of procedures therein.
    As a result,
    “Section
    212.110”
    is deleted and the following
    language
    is added
    to
    Sections 212.124(d)(2)(A)
    and
    (B):
    “Method
    5,
    40
    CFR 60,
    incorporated
    by reference
    in Section 212.113.”
    The Agency suggested the following modifications
    of Section
    2l2.126(c)
    and
    (e)
    for clarity:
    “Section
    212.126(c):
    Any
    request
    for
    the
    determination
    of
    the
    average
    opacity
    of
    emissions shall
    be
    made
    in writing,
    including
    the
    time
    and
    place
    of
    the
    performance
    test,
    all
    test
    specifications
    and
    procedures,
    and
    submitted
    to
    the Agency
    at
    least
    thirty days
    before the proposed
    test date.”
    “Section
    212.126(e):
    The
    owner
    or
    operator
    shall
    allow
    Agency
    personnel
    to
    be
    present
    during
    the performance test.”
    The Board accepts
    the Section 212.126(e)
    suggestion.
    However,
    the Board believes that Section 212.126(c)
    requires
    further grammatical clarification.
    The Board
    thus amends Section
    212.126(c)
    as follows:
    “Section
    212.126(c):
    Any
    request
    for
    the
    determination
    of
    the
    average
    opacity
    of
    emissions
    shall
    be
    in
    writing,
    shall
    include
    the time and place
    of the performance
    test and
    all
    test
    specifications
    and
    procedures,
    and
    shall
    be
    submitted
    to
    the
    Agency
    at
    least
    thirty days before the proposed test date.”
    The Agency also noted
    its concerns regarding
    the Board’s
    amendment
    of
    35 Ill.
    Adm.
    Code 106.Subpart
    B:
    Air Adjusted
    Standard Procedures.
    The Agency states that although the general
    idea of
    a standardized procedure has merit,
    there are currently
    at least two regulations other
    than the opacity rules that
    contain important specialized procedures for obtaining
    an
    adjusted air standard.
    The Agency argues that these and all
    other existing specialized procedures should
    take precedence over
    a general
    air adjusted procedure.
    The Board does not dispute
    the
    Agency’s arguments.
    However,
    the Board does believe that the
    general procedures
    for obtaining
    an adjusted standard should be
    located among
    the Board’s procedural
    rules.
    Therefore,
    the Board
    will retain
    the
    35
    Iii.. Mm.
    Code 106 amendments, but will make
    them applicable at this time only
    to the
    35
    Ill.
    Adm. Code
    212.
    Subpart B rules.
    The Board
    is persuaded
    that
    there is
    insufficient information
    in the
    record
    to
    justify utilization of
    these rules
    for other existing specialized procedures.
    As future
    90—59 4

    —7—
    adjusted
    standards provisions
    are adopted,
    these general
    procedures can be referred
    to and utilized.
    In addition
    to providing comments regarding Part 106
    procedures
    in general,
    the Agency commented on certain specific
    aspects of the Part 106 proposal.
    First,
    the Agency opposes
    a
    certain part
    of Section 106.503(b).
    The Agency states that
    it
    has “limited access
    to source
    information and limited procedures
    to enforce information gathering,”
    and that “this section should
    not be construed as requiring the Agency to assist
    in the proof
    of the petition,
    as the Agency has the right
    to prioritize
    its
    use of resources
    to meet its statutory obligations under
    the
    Environmental Protection Act.”
    The Board
    notes
    that Section
    106.503(a)
    clearly and explicitly states
    “the Agency may,
    in
    its
    discretion, act
    as
    a co—petitioner.”
    Thus,
    the Agency will not
    be required
    to assist
    in the proof of
    the petition.
    The Agency further argues that
    “to require written
    notification of
    the Agency’s position regarding whether
    or not
    it
    will
    be
    a co—petitioner and
    its underlying reasons
    is unnecessary
    and places
    an added burden on the Agency.”
    In support
    of its
    argument,
    the Agency states that
    it and potential petitioners are
    “well aware”
    of
    the identity of each other
    and that “the Agency’s
    position
    is
    clear
    from
    its
    pleadings
    and
    hearing
    participation.”
    The Board notes
    that this requirement
    is not new
    to
    adjusted
    standard
    procedures.
    Similar
    requirements
    can
    be
    found
    in
    the
    RCRA
    adjusted
    standard
    procedures
    (35
    Ill.
    Adm.
    Code
    106.412)
    and
    in
    the
    CSO
    exception
    proceeding
    (35
    Ill.
    Adrn.
    Code
    306.352(b)).
    Because
    this decision
    is discretionary (proposed
    Section 106.503(a))
    and not appealable
    to the Board
    (proposed
    Section 106.503(c)),
    and because
    the Agency has expressed
    opposition
    to the requirement in this context,
    the Board
    has
    determined
    that
    a compromise
    is
    in order.
    The Board will retain
    the written notification requirement
    (1)
    to maintain consistency
    with the above—noted regulations and
    (2)
    to ensure that the
    applicant receives
    a prompt response.
    However, the Board
    believes
    that
    it
    is
    perfectly
    appropriate
    for
    the
    Agency
    to
    decline
    to
    co—petition
    in
    the
    event
    that the Agency
    is faced with
    a
    lack
    of
    resources
    with
    which
    to
    investigate
    and
    co—petition.
    Therefore,
    a simple statement
    to that effect
    is
    the minimum that
    would
    be
    required
    by
    Section
    106.503(b).
    The Agency states that in Section l06.504(b)(2)
    the written
    statement should
    be signed by only the petitioner
    and not the
    Agency, even
    if the Agency
    is
    a co—petitioner
    or approves
    of the
    proposed standard.
    The Agency argues
    that
    it cannot,
    from
    its
    own independent knowledge,
    verify all
    of the various elements
    that this written
    statement contemplates.
    The Board appreciates
    the
    Agency’s
    concerns
    and
    has
    revised
    Section
    106.504(b)(2)
    to
    require
    only
    the
    petitioner’s
    signature.
    90—595

    —8—
    As regards
    the Section 106.505 time for response to the
    filing of
    a petition,
    the Agency argued that twenty—one
    (21)
    days
    is too short.
    The Agency believes
    that
    a minimum of
    forty—five
    (45)
    days
    is necessary
    for
    an effective evaluation.
    In the
    absence of any evidence
    to the contrary,
    the Board defers to
    the
    Agency’s
    knowledge
    of
    its internal processes,
    and accepts the
    forty—five
    .i~45) day
    response
    period.
    In
    addition,
    the
    Board
    has
    made
    certain
    clarifications
    to
    the
    text
    of
    the
    proposed
    rules
    on
    its
    own.
    These changes
    are
    in
    no
    way
    intended
    to affect
    the substance
    of
    the proposed rules,
    but
    rather
    are
    intended
    to
    make
    the
    language of
    the
    rules
    more
    precise.
    First,
    in
    Section
    2l2.214(d)(l),
    the
    Board
    removed
    “and
    either”
    and replaced
    it with “but subject to.”
    This action was
    taken
    to correct the internal logic
    of the subsection.
    Second,
    the Board notes that Section 2l2.214(d)(1)
    and
    (2)
    are defense provisions
    for different
    types of sources.
    Section
    2l2.2l4(d)(1)
    is applicable
    to sources
    not subject
    to Sections
    212.201 through 212.204, but subject
    to 212.122 or
    212.123.
    The
    Board has added
    language
    to clarify that Section 212.124(d)(1)
    does not apply
    to sources
    subject to New Source Performance
    Standards,
    i.e.,
    subject
    to Section
    111
    or
    112 of
    the Clean Air
    Act.
    Section 212.124(d)(2)
    is applicable
    to sources subject
    to
    Section 212.201 through 212.204
    and either
    212.122 or 212.123.
    Language was added here also
    to clarify that Section
    2l2.l24(d)(2) does not apply
    to sources subject
    to New Source
    Performance Standards.
    The difference between Section
    2l2.l24(d)(l)
    and
    (2)
    lies
    in the defense mechanism.
    Section
    212.124(d)(2)(A)
    and
    (B) state:
    A)
    An exceedance
    of the limitations of
    Section 212.122 or 212.123 shall
    constitute
    a violation of
    the applicable
    particulate
    limitations
    of this Part.
    It
    shall
    be
    a defense
    to a violation of the
    applicable particulate limitations
    if,
    during a subsequent performance test
    conducted within
    a reasonable time not
    to
    exceed
    60 days,
    under the same operating
    conditions
    for
    the source and the control
    device(s),
    and
    in accordance with Method
    5,
    40 CFR 60, incorporated by reference
    in Section 212.113,
    the owner
    or operator
    shows
    that the source
    is in compliance
    with the particulate emission
    limitations.
    B)
    It shall
    be
    a defense
    to an exceedance
    of
    the opacity limit
    if, during
    a subsequent
    performance test conducted within
    a
    reasonable
    time not
    to exceed
    60 days,
    90—596

    —9—
    under
    the same operating conditions
    of
    the source and the control
    device(s),
    and
    in accordance with Method
    5,
    40 CFR 60,
    incorporated by reference
    in Section
    212.113,
    the owner
    or operator shows
    that
    the source
    is
    in compliance with the
    allowable particulate emissions
    limitation while,
    simultaneously, having
    visible emissions
    equal
    to
    or greater
    than the opacity exceedance
    as originally
    observed.
    Section 212.l24(d)(l) states
    “The opacity limitations of Sections 212.122
    and 212.123 shall
    not apply
    if
    it
    is shown
    that the emission source was,
    at the time
    of
    such emission,
    in compliance with
    the
    applicable particulate emissions limitations
    of this Part.”
    One reason for the different defense provision between
    these two
    subsections
    is
    that the performance test conducted
    in accordance
    with Test Method
    5,
    40 CFR 60, Appendix A,
    is clearly designed
    for accurate measurement
    of stack particulate emissions from
    sources
    subject
    to
    Sections
    212.201
    through
    212.204
    (i.e.
    Section
    212.124(d)(2)),
    while
    for
    other
    sources,
    e.g.,
    process
    emission
    sources, Method
    5
    may
    not
    be
    applicable
    because
    such
    sources
    (1)
    may not have
    a stack
    or
    (2) may be allowed
    to use other methods
    in lieu of the stack
    test
    to show compliance.
    However,
    the lack
    in Section 212.124(d)(1)
    of specific defense requirements,
    i.e.,
    subsequent performance
    test,
    under same operating conditions,
    while having visible emissions greater
    than or equal
    to the
    opacity exceedance originally observed,
    is
    in no way intended
    to
    imply that those showings would
    not be appropriate
    to
    a
    demonstration
    of compliance with the particulate emission
    limitations.
    In fact,
    such showings
    (as prescribed under
    Section
    2l2.124(d)(2)) would be the preferred method
    of demonstrating
    compliance
    under Section 212.l24(d)(l).
    Third, subsection
    212.124(a) was amended
    to include
    exceptions
    for times
    of malfunction and breakdown,
    in addition
    to
    start—up.
    This was suggested
    in comment previously
    received.
    The commentor stated that
    35
    Ill.
    Adm.
    Code
    20l.Subpart
    I
    allows
    for permission
    to be granted
    to operate during any
    of these
    three
    events.
    The commentor pointed out that,
    to be consistent,
    Section
    212.214(a)
    should include exception
    for malfunction and
    breakdown.
    The Board agrees and
    has added
    the exceptions at
    Second Notice.
    Fourth,
    the Board agrees with
    the Agency’s comments and will
    retain the upper
    limit of
    60
    in the adjusted opacity
    90—597

    —10—
    standards.
    The Board also notes
    that sources obtaining
    an
    adjusted opacity
    limit pursuant to 212..121(a)(6)
    are allowed
    to
    exceed
    the standard
    for one six—minute
    averaging period
    in any
    60—minute period rather than pursuant
    to the exception
    in
    existing Sections 212.122 and 212.123.
    The adjusted opacity
    limitation exception contained
    in Section 212.126(a)(4)
    is
    consistent with the measurement methods
    of Method
    9,
    40 CFR 60,
    Appendix
    A.
    Second Notice Review
    The Second Notice Opinion and Order was adopted
    on May
    5,
    1988.
    The Joint Committee on Administrative Rules considered the
    proposed rules
    at its June 14,
    1988 Meeting.
    On that date,
    the
    Joint Committee issued
    a Certificate
    of No Objection
    to the
    proposed amendments
    to
    35 Ill.
    Adm.
    Code
    212.
    Pursuant
    to
    discussions with the Joint Committee,
    the Board agreed
    to make
    certain non—substantive
    language changes
    to clarify
    the intent of
    the rules.
    Those changes
    are noted below.
    Also on June
    14,
    1988,
    the Joint Committee
    issued a Certificate of Objection
    to
    the rules proposed for inclusion into
    35
    Ill. Adm.
    Code
    106.
    By
    separate Resolution and Order,
    also adopted
    today,
    the Board set
    forth
    its formal response
    to the JCAR Objection refusing
    to
    modify or withdraw the proposed
    rules.
    Pursuant
    to second notice review discussions with the Joint
    Committee,
    the Board agreed
    to make the following non-substantive
    modifications
    to the proposed
    rules:
    35
    Ill. Mm.
    Code
    106:
    1.
    To amend Section 1O6.505(a),
    the
    last sentence
    to
    read:
    “This response shall include
    the Agency’s
    recommendations concerning
    the Board’s proposed action
    on the petition.”
    2.
    To add a citation to Section 28.1 of
    the Environmental
    Protection Act
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    111 1/2,
    par.
    1028.1) after
    Sections 106.507(c) and
    (d).
    3.
    To update its statutory citations
    to the 1987 Illinois
    Revised Statutes.
    35
    Ill.
    Mm.
    Code
    212:
    1.
    To insert “Subparts D—T of”
    in Sections
    212.l24(d)(l)
    and 212.l24(d)(2)(A)
    after “applicable particulate
    emission limitations.”
    2.
    To insert “of Sections 212.121—212.125” after “otherwise
    applicable standards”
    in Section 212.126(a).
    90—598

    —11—
    3.
    To replace
    the word “may”
    with “shall”
    in Section
    212.126(b)
    so the last sentence
    of the Section
    reads:
    “The Agency shall
    refuse
    to accept the results of
    emissions tests
    if not conducted pursuant
    to this
    Section which
    are conducted without prior review and
    approval of the test specifications and procedures by
    the
    Agency.”
    4.
    To replace the word “devise(s)” with
    “device(s)”
    in
    Section 212.124(d)(2)(A).
    5.
    To update
    the “Statutory Authority” citation
    to “1987”
    in
    the
    Authority
    Note.
    Economic
    Impact of Proposed Rules
    Finally,
    the Board notes
    that the existing Opacity
    regulations were declared
    invalid as they applied
    to sources
    regulated
    by the Particulate
    rules
    in Celotex
    Corp.
    v.
    Pollution
    Control Board,
    94
    Ill.
    2d
    107,
    445 N.E.2d
    752,
    68
    Ill.
    Dec.
    108
    (1983).
    The basis
    for
    the invalid declaration was that in
    adopting the Opacity regulations,
    the Board had relied on the
    economic reasonableness justification provided
    in the adoption
    of
    the Particulate rules
    formerly
    Rule 203(g)(1).
    Because
    the
    Particulate rules were declared invalid based
    on
    a failure to
    consider economic reasonableness
    in Commonwealth Edison Company
    v.
    Pollution Control Board,
    25
    111.
    App.
    3d
    271,
    323 N.E.2d
    84
    (1975),
    the Supreme Court
    ruled
    in Celotex that the Opacity rules
    were also invalid.
    Subsequent
    to that holding,
    the Board
    revalidated the Particulates
    rules.
    Analysis
    of the economic
    reasonableness
    is set forth
    in the Final Opinion and Order dated
    July
    2,
    1986
    in R82—l (Docket A).
    There
    the Board stated
    in
    part:
    The
    Executive
    Summary
    of
    the
    Economic
    Impact
    Study (EcIS)
    in this matter concludes:
    Because
    so
    few
    sources
    remain out—
    of—compliance,
    repromulgation
    of
    rules
    203(g)(l)
    and
    202(b)
    is
    not
    expected
    to
    impact
    very
    noticeably
    on
    the
    Illinois
    economy.
    Hence
    Board
    approval
    of
    R82—l
    should
    have
    little
    effect
    on
    the
    overall
    availability
    of
    goods
    and
    services
    to
    the
    people
    of
    the
    state,
    nor
    should
    it
    have
    much
    impact
    on
    agriculture,
    local
    government,
    commerce or
    industry.
    Of course,
    if
    the avoidance of
    nearly $400 million
    in
    Clean
    Air
    Act
    penalties
    is
    assumed
    to result from revalidation,
    90—599

    —12—
    then
    it
    follows
    that
    all
    of
    those
    sectors
    will
    experience
    a
    significant
    benefit
    in
    the
    form
    of
    averted
    funding
    losses
    and
    the
    associated
    secondary
    effects.
    (Ex.
    10,
    p.
    vi).
    The
    reason
    for
    such
    widespread
    compliance
    with
    invalid
    Rule
    203(g)(l)
    is
    that
    the
    Agency,
    in
    its
    permitting
    process,
    has
    acted
    almost
    as
    though
    the
    rules
    had
    never
    been
    invalidated.
    Despite
    the
    fact
    that
    the
    Agency
    no
    longer
    had
    valid
    rules
    on
    which
    to base permitted levels
    of
    particulate
    emissions,
    it
    established
    a
    policy,
    which
    it
    filed
    with
    the Secretary
    of
    State’s
    Office
    in
    December
    of
    1977,
    stating
    that
    compliance
    with
    203(g)(l)
    still
    would
    “usually
    be
    deemed
    ...
    sufficient
    to
    assure
    compliance
    with
    air quality provisions
    ...
    of
    the
    Act.”
    According
    to
    these
    guidelines,
    a
    plant
    may
    obtain
    a
    permit
    by
    either
    demonstrating
    compliance
    with
    the
    remanded
    rules
    or
    by
    performing
    comprehensive
    air
    quality
    evaluations
    to
    demonstrate
    that
    alternative
    emissions’
    limitations
    would
    not
    threaten
    air
    quality
    standards.
    Since
    this
    policy
    has
    been
    in
    effect,
    only
    the Winnetka
    Electric Plant has been granted
    an alternative
    standard.
    The
    EcIS
    proceeded
    on
    the
    assumption
    that
    “repromulgation
    is
    assumed
    to
    have
    no
    impact
    on those sources already
    in compliance.”
    (Ex.
    10,
    p.
    14).
    It,
    therefore,
    discusses
    costs
    imposed
    on
    those
    facilities
    which
    have
    not
    achieved compliance,
    those which are presently
    permitted
    to
    emit
    as
    much
    as
    0.2
    lbs/MBtu
    under
    203(g)(1)(C)
    but
    which
    will
    ultimately
    be
    required
    to
    comply
    with
    a
    stricter
    limitation,
    the
    Winnetka
    plant
    which
    is
    operating under
    a relaxed
    limitation,
    and new
    sources.
    (Ex.
    10,
    pp.
    16—18).
    Of
    the
    30
    sources which are not presently
    in compliance,
    12 operate
    routinely,
    9
    are
    used on
    a standby
    basis
    and
    none
    are
    shut
    down.
    (Ex.
    10,
    p.
    53).
    Eleven
    are
    in
    non—attainment
    areas
    for
    particulates;
    five
    are
    in
    attainment
    areas.
    (Ex.
    10, pp.
    53—56).
    The
    authors
    of
    the
    EcIS
    admit
    that
    assigning
    an
    economic
    value
    to
    the
    costs
    and
    benefits
    involved
    in
    this proceeding
    is
    difficult.
    On
    90—600

    —13—
    the
    cost
    side,
    errors
    arise
    from choosing
    an
    emission
    reduction
    strategy.
    The
    study
    assumed
    the use
    of
    fabric
    filters
    or cyclones
    resulting
    in
    an annualized cost
    of control
    for
    the
    affected sources
    of
    about
    $4.4 million
    in
    1982 dollars with
    a range
    of error
    of
    about
    50
    percent.
    However,
    some
    of
    the
    30
    sources
    impacted
    by
    repromulgation
    have
    shut
    down
    within
    the past
    five
    years
    and
    many,
    if
    not
    most,
    may
    never
    operate
    again,
    regardless
    of
    the Board’s
    ruling
    in
    this
    matter.
    Further,
    an
    equal
    number
    of
    sources
    are
    used
    as
    emergency
    standby
    units,
    which
    operators
    may
    choose
    to retire.
    Thus,
    only 12 sources which
    are out—of—compliance
    with
    the
    remanded
    rules
    operate on
    a routine basis, with
    an annualized
    control
    cost
    of
    about
    $4.42 million,
    most
    of
    which
    is
    attributable
    to
    CILO’s
    Wallace
    Station.
    The
    benefits
    of
    repromulgation
    are
    also
    subject
    to
    considerable
    uncertainty,
    especially
    in
    the
    estimation
    of
    reduced
    damages
    to
    health
    and
    welfare.
    Dispersion
    modeling
    indicates
    that
    in
    all
    but
    three
    locations,
    promulgation
    of
    the proposed
    rules
    will reduce a~bientTSP concentrations by less
    than
    1
    ug/m~.
    The
    estimated
    health
    and
    welfare benefits
    are $73,000
    per
    year
    in 1982
    dollars,
    although that figure must be regarded
    as
    a
    lower
    limit
    since
    only
    those
    impacts
    greater
    than
    1 ug were evaluated.
    Significant
    errors
    may
    arise
    for
    uncertainties
    in
    the
    damage coefficients themselves which are based
    on
    the
    work
    of
    Dr.
    Allen
    Cohen
    who
    has
    conceded
    that
    they could
    offer
    no better
    than
    “order
    of
    magnitude”
    accuracy:
    i.e.
    they
    could
    vary
    by
    a
    factor
    of
    ten.
    Potentially
    overriding
    any
    of
    these
    costs
    or
    benefits
    is the impact which would result from
    a
    decision
    by
    the
    Administrator
    of
    USEPA
    to
    impose
    the
    Clean
    Air
    Act’s
    sweeping
    penalties.
    The
    deficiency
    in
    Illinois’
    SIP
    due
    to
    judicial
    remand
    is
    cause
    for
    the
    sanctions.
    Illinois’
    inability
    to
    show
    attainment
    with
    TSP
    air
    quality
    standards
    exposes
    the
    State
    to
    a
    possible
    annual
    loss
    of
    up
    to
    $335
    million
    in
    highway
    funds,
    $35
    million
    in
    sewage
    treatment
    grants,
    and
    nearly
    $12
    million
    in
    Agency
    operating
    funds
    per
    year.
    In
    that
    case
    the
    benefits
    of
    revalidation clearly outweigh
    the costs.
    90—61)1

    —14—
    Based on this analysis and on the absence of any indication
    in
    the
    record
    that
    these
    rules
    are
    not
    economically
    reasonable,
    the
    Board
    concludes
    that
    it
    is
    economically
    reasonable
    to
    comply
    with the underlying Opacity
    rules
    as well as
    today’s adopted
    rules
    ORDER
    The
    Board
    hereby
    adopts
    the
    following
    amendments
    to
    the
    Illinois
    Administrative
    Code:
    TITLE
    35:
    ENVIRONMENTAL PROTECTION
    SUBTITLE
    A:
    GENERAL PROVISIONS
    CHAPTER
    I:
    POLLUTION CONTROL BOARD
    PART 106
    HEARINGS PURSUANT TO SPECIFIC RULES
    SUBPART
    A:
    HEATED EFFLUENT DEMONSTRATIONS
    Section
    106.
    101
    106. 102
    106.
    103
    106.104
    106.105
    106.
    106
    106.107
    Petition
    Requirements
    for Petition
    Parties
    Recommendation
    Notice and Hearing
    Transcripts
    Opinion and Order
    SUBPART
    B:
    ARTIFICIAL COOLING LAKE DEMONSTRATIONS
    Section
    106.201
    106.202
    106.203
    106.204
    Petition
    Notice and Hearing
    Transcripts
    Effective Date
    Section
    106.301
    106.302
    106.303
    106.304
    106.305
    106.
    306
    Section
    Petition
    Requirements
    for
    Petition
    Part ies
    Recommenda tion
    Notice and Hearing
    Transcripts
    SUBPART
    D:
    RCRA ADJUSTED STANDARD PROCEDURES
    106.401
    Petition
    (Repealed)
    SUBPART
    C:
    SULFUR
    DIOXIDE
    DEMONSTRATIONS
    90— 602

    Notice of Petition
    (Repealed)
    Recommendation
    (Repealed)
    Response (Repealed)
    Public Comment
    (Repealed)
    Public Hearings
    (Repealed)
    Decision
    (Repealed)
    Appeal
    (Repealed)
    Scope and Applicability
    Joint
    or Single Petition
    Request
    to Agency to Join as Co—Petitioner
    Contents
    of Petition
    Response and Reply
    Notice and Conduct of Hearing
    Opinions and Orders
    SUBPART
    E:
    AIR ADJUSTED STANDARD PROCEDURES
    Section
    106.
    501
    106.502
    106.503
    106.504
    106.505
    106.506
    106.
    507
    Scope and Applicability
    Joint
    or Single Petition
    Request
    to Agency to Join As Co—Petitioner
    Contents of Petition
    Response and Reply
    Notice and Conduct of Hearing
    Opinions and Orders
    Appendix
    A
    AUTHORITY:
    authorized
    (Ill.
    Rev.
    1028.1
    and
    Old
    Rule Numbers Referenced
    Implementing Sections
    5,
    22.4,
    27,
    28 and 28.1 and
    by
    Section
    26
    of
    the
    Environmental
    Protection
    Act
    Stat.
    1987,
    ch.
    1111/2,
    pars.
    1005,
    1022.4,
    1027,
    1028,
    1026).
    SOURCE:
    Filed with Secretary of
    State January
    1,
    1978; amended
    at
    4
    Ill.
    Reg.
    2,
    page
    186,
    effective
    December
    27,
    1979;
    codified
    at
    6 Ill.
    Reg.
    8357;
    amended
    in R85—22
    at 10
    Ill.
    Reg.
    992,
    effective February
    2,
    1986; amended
    in R86—46 at 11
    Ill.
    Reg.
    13457,
    effective August
    4,
    1987;
    amended
    in R82—1 at ______Ill.
    Reg.
    _______
    ,
    effective
    _________________
    SUBPART
    E:
    AIR ADJUSTED STANDARD PROCEDURES
    Section 106.501
    Scope
    and Applicability
    This
    Subpart applies only whenever
    an adjusted standard,
    as
    provided
    in Section 28.1
    of
    the Environmental Protection Act
    (Act),
    is sought pursuant
    to
    35
    Ill.
    Adm.
    Code 212.126.
    Ill.
    Reg.
    ________
    __________
    Section
    106.502
    Joint
    or
    Single
    Petition
    —15—
    106.402
    106.403
    106.
    404
    106.405
    106.
    406
    106.407
    106.408
    106.410
    106.411
    106.412
    106.413
    106.414
    106.415
    106.416
    (Source:
    Added
    at
    effective
    )
    90—603

    —16—
    A person may initiate
    an adjusted standard proceeding either by
    filing
    a petition
    jointly with the Illinois Environmental
    Protection Agency
    (Agency),
    or by filing a petition singly.
    (Source:
    Added
    at
    Ill.
    Reg.
    ,
    effective
    Section 106.503
    Request
    to Agency
    to Join As Co—Petitioner
    a)
    The Agency may,
    in its discretion,
    act as
    a co—
    petitioner
    in any adjusted standard proceeding.
    b)
    Any person may request Agency assistance
    in initiating a
    petition for adjusted standard.
    The Agency may require
    the person
    to submit
    to the Agency any background
    information
    in the person’s possession relevant
    to the
    adjusted standard which
    is sought.
    The Agency shall
    promptly notify the person
    in writing of
    its
    determination either
    to join as
    a co—petitioner,
    or
    to
    decline
    to join as a co—petitioner.
    If the Agency
    declines
    to join as
    a co—petitioner,
    the Agency shall
    state
    the basis for
    this decision.
    c)
    Discretionary decisions made by the Agency pursuant
    to
    this
    Section
    are
    not
    appealable
    to
    the
    Board.
    (Source:
    Added
    at
    Ill.
    Reg.
    ,
    effective
    Section 106.504
    Contents
    of Petition
    a)
    The petitioner
    shall
    file ten copies
    of the petition for
    adjusted standard with the Clerk of
    the Pollution
    Control Board
    (Board),
    and
    shall
    serve one copy upon the
    Agency.
    b)
    The petition shall
    contain the following information:
    1)
    Identification
    of the regulation of general
    applicability
    for which an adjusted standard is
    sought
    2)
    A written statement, signed by the petitioner,
    or
    an
    authorized
    representative, outlining
    the scope
    of
    the evaluation,
    the nature
    of,
    the reasons
    for and
    the basis
    of the adjusted
    standard, consistent with
    the level
    of justification contained
    in the
    regulation
    of general applicability
    3)
    The nature of the petitioner’s operations and
    control equipment;
    and
    4)
    Any additional
    information which may be required
    in
    the regulation
    of general applicability.
    90—604

    —17-
    (Source:
    Added at
    Ill.
    Reg.
    ,
    effective
    Section 106.505
    Response and Reply
    a)
    Within
    45 days after
    the filing of
    a petition,
    the
    Agency shall
    file
    a response
    to any petition in which it
    has not joined as
    a co—petitioner.
    This response shall
    include
    the Agency’s recommendations concerning
    the
    Board’s proposed action on the petition.
    b)
    The petitioner may file
    a reply within 14 days after
    the
    filing of any Agency response.
    (Source:
    Added at
    Ill.
    Reg.
    effective
    Section 106.506
    Notice and Conduct
    of Hearing
    a)
    The Board will hold
    at least one public hearing prior
    to
    granting an adjusted standard.
    b)
    The hearing officer will schedule the hearing.
    The
    Clerk will give notice of hearing
    in accordance with 35
    Ill.
    Adm.
    Code 102.122.
    c)
    The proceedings
    will be
    in accordance with
    35
    Ti!. Mm.
    Code 102.160
    through 102.164.
    (Source:
    Added at
    Ill.
    Reg.
    effective
    __________)
    Section 106.507
    Opinions and Orders
    a)
    The Board will adopt an order
    and opinion stating
    the
    facts
    and reasons leading to the final Board
    determination,
    consistent with any considerations which
    may be specified
    in the regulation
    of general
    applicability or Section 27(a)
    of
    the Act.
    b)
    The Board will issue such other orders as the Board
    deems appropriate,
    including,
    but not limited
    to,
    accepting or
    rejecting
    the petition,
    requiring
    the
    submission
    of further
    information or directing that
    further hearings be held.
    c)
    SUCH BOARD ORDERS AND OPINIONS WILL
    BE MAINTAINED
    FOR
    PUBLIC INSPECTION
    BY THE CLERK OF THE BOARD AND A
    LISTING OF ALL DETERMINATIONS MADE PURSUANT TO THIS
    SUBPART WILL
    BE PUBLISHED
    IN THE ILLINOIS REGISTER AND
    THE ENVIRONMENTAL REGISTER AT THE END OF EACH FISCAL
    YEAR.
    (Ill.
    Rev.
    Stat.
    ch.
    111 1/2 par.
    1028.1).
    90—60 5

    —18—
    d)
    A FINAL BOARD DETERMINATION MADE UNDER THIS SUBPART MAY
    BE
    APPEALED
    PURSUANT
    TO
    SECTION
    41
    OF
    THE
    ACT.
    (Ill.
    Rev.
    Stat.
    ch.
    111
    1/2
    par.
    1028.1).
    (Source:
    Added at
    Ill.
    Reg
    ,
    effective
    TITLE
    35:
    ENVIRONMENTAL
    PROTECTION
    SUBTITLE
    B:
    AIR
    POLLUTION
    CHAPTER
    I:
    POLLUTION CONTROL BOARD
    SUBCHAPTER c:
    EMISSION STANDARDS AND LIMITATIONS
    FOR
    STATIONARY
    SOURCES
    PART
    212
    V~SE~M~
    VISIBLE AND PARTICULATE MATTER EMISSIONS
    SUBPART
    A:
    GENERAL
    Section
    212.121
    212.122
    212.123
    212.124
    212.125
    212.126
    Opacity
    Standards
    Limitations
    for
    Certain
    New
    Sources
    Limitations
    for
    All
    Other
    Sources
    Exceptions
    Determination of Violations
    Adjusted Opacity Standards Procedures
    SUBPART
    D:
    PARTICULATE
    MATTER
    EMISSIONS
    FROM
    INCINERATORS
    Section
    212.181
    212.182
    212.183
    212.184
    Limitations
    for
    Incinerators
    Aqueous Waste Incinerators
    Certain Wood Waste Incinerators
    Explosive
    Waste
    Incinerators
    SUBPART
    E:
    PARTICULATE
    MATTER
    EMISSIONS
    FROM
    FUEL
    COMBUSTION
    EMISSION
    SOURCES
    Section
    212.201
    Existing
    Sources
    Using
    Solid
    Fuel
    Exclusively
    Located
    in
    the
    Chicago
    Area
    212.202
    Existing Sources Using Solid
    Fuel Exclusively Located
    Outside
    the
    Chicago
    Area
    212.203
    Existing
    Controlled
    Sources
    Using
    Solid
    Fuel
    Exclusively
    Section
    212.100
    212.110
    212.111
    212.112
    212.113
    Scope
    and Organization
    Measurement Methods
    Abbreviations and Units
    Definitions
    Incorporations by Reference
    SUBPART
    B:
    V~SUAE~VISIBLE EMISSIONS
    90—606

    —19—
    212.204
    New Sources Using Solid Fuel Exclusively
    212.205
    Existing Coal—fired Industrial Boilers Equipped with
    Flue
    Gas
    Desulfurization
    Systems
    212.206
    Sources Using Liquid Fuel Exclusively
    212.207
    Sources
    Using
    More
    Than
    One
    Type
    of
    Fuel
    212.208
    Aggregation of Existing Sources
    SUBPART
    K:
    FUGITIVE PARTICULATE MATTER
    Section
    212.301
    Fugitive Particulate Matter
    212.302
    Geographical Areas
    of Application
    212.304
    Storage Piles
    212.305
    Conveyor Loading Operations
    212.306
    Traffic Areas
    212.307
    Materials Collected by Pollution Control Equipment
    212.308
    Spraying or Choke—Feeding Required
    212.309
    Operating Program
    212.310
    Minimum Operating Program
    212.312
    Amendment
    to Operating Program
    212.313
    Emission Standard for Particulate Collection Equipment
    212.314
    Exception
    for Excess Wind Speed
    212.315
    Covering for Vehicles
    SUBPART
    L:
    PARTICULATE MATTER EMISSIONS
    FROM PROCESS EMISSION SOURCES
    Section
    212.321
    New Process Sources
    212.322
    Existing Process Sources
    212.323
    Stock
    Piles
    SUBPART N:
    FOOD MANUFACTURING
    Section
    212.361
    Corn Wet Milling Processes
    SUBPART
    0:
    PETROLEUM REFINING,
    PETROCHEMICAL
    AND CHEMICAL MANUFACTURING
    Section
    212.381
    Catalyst Regenerators of Fluidized Catalytic Converters
    SUBPART
    Q:
    STONE, CLAY, GLASS
    AND CONCRETE MANUFACTURING
    Section
    212.421
    New Portland Cement Processes
    212.422
    Portland Cement Manufacturing Processes
    SUBPART R:
    PRIMARY
    AND
    FABRICATED METAL
    PRODUCTS AND MACHINERY MANUFACTURE
    90-607

    —20—
    Section
    212.441
    212.442
    212.443
    212.444
    212.445
    212.446
    212.447
    212.448
    212.449
    212.
    450
    212.451
    212.452
    212.455
    212.456
    212.457
    Steel
    Manufacturing
    Processes
    Beehive Coke Ovens
    By—Product
    Coke Plants
    Sinter Processes
    Blast Furnace Cast Houses
    Basic Oxygen Furnaces
    Hot Metal Desulfurization Not Located
    in the BOF
    Electric Arc Furnaces
    Argon—Oxygen
    Decarbu
    r ization
    Vessels
    Liquid Steel Charging
    Hot Scarf ing Machines
    Measurement Methods
    Highlines on Steel Mills
    Certain Small Foundries
    Certain Small Iron—melting Air Furnaces
    SUBPART
    5:
    AGRICULTURE
    Grain Handling and Drying
    in General
    Grain Handling Operations
    Grain Drying Operations
    SUBPART
    T:
    CONSTRUCTION
    AND
    WOOD
    PRODUCTS
    Section
    212.681
    Grinding, Woodworking, Sandblasting and
    Shotbiasting
    Allowable
    Emissions
    from
    Solid
    Fuel
    Combustion
    Emission
    Sources
    Outside
    Chicago
    Limitations
    for
    all
    New
    Process
    Emission
    Sources
    Limitations
    for
    all
    Existing
    Process
    Emission
    Sources
    AUTHORITY:
    Implementing
    Section
    10
    and
    authorized
    by
    Section
    27
    of
    the
    Environmental Protection Act
    (Ill.
    Rev.
    Stat.
    1987,
    ch.
    111
    1/2,
    pars.
    1010
    and
    1027)
    SOURCE:
    Adopted
    as Chapter
    2:
    Air Pollution, Rules
    202 and
    203:
    Visual and Particulate Emission Standards and Limitations,
    R7l—23,
    4 PCB 191,
    filed
    and effective April
    14,
    1972; amended
    in
    R77—l5,
    32 PCB 403, at
    3
    Ill.
    Reg.
    5,
    p.
    798, effective
    February
    3, 1979;
    amended
    in R78—lO,
    35 PCB 347,
    at
    3
    Ill.
    Reg.
    39,
    p.
    184, effective September
    28,
    1979;
    amended
    in R78—l1,
    35
    PCB 505, at
    3
    Ill.
    Reg.
    45,
    p.
    100, effective October
    26,
    1979;
    amended
    in R78—9,
    38 PCB 411, at
    4
    Ill. Reg.
    24,
    p.
    514,
    Section
    212.461
    212.462
    212.463
    Appendix
    A
    Appendix
    B
    Appendix
    C
    Illustration
    A
    Illustration
    B
    Illustration
    C
    Rule
    into Section Table
    Section
    into Rule Table
    Past Compliance Dates
    90—608

    —21—
    effective June
    4,
    1980;
    amended
    in R79—ll,
    43 PCB 481,
    at
    5
    111.
    Reg.
    11590, effective October
    19,
    1981;
    codified at
    7
    Ill.
    Reg.
    13591;
    amended
    in R82—l (Docket
    A)
    at
    10
    Ill.
    Reg.
    12637,
    effective July
    9,
    1986; amended
    in R85—33 at 10
    Ill.
    Reg.
    18030,
    effective October
    7,
    1986;
    amended in R84—48 at 10
    Ill.
    Reg.
    691,
    effective December
    18,
    1986; amended
    in R84—42 at
    11
    Ill.
    Reg.
    1410,
    effec~tiveDecember
    30,
    1986; amended
    in R82—l(Docket
    B)
    at
    _____
    Ill.
    Reg.
    _________,
    effective
    ______________________
    Section
    212.113
    Incorporations
    by
    Reference
    The
    following
    materials are incorporated by reference:
    a)
    ASME
    Power
    Test Code 27—1957, Determining Dust
    Concentration
    in
    a
    Gas
    Stream,
    American Society
    of
    Mechanical
    Engineers,
    United
    Engineering
    Center,
    345
    E.
    47th
    Street,
    New
    York,
    NY 10017.
    b)
    Ringelmann
    Chart,
    Information
    Circular
    833
    (Revision
    of
    IC77l8), Bureau of Mines, U.S.
    Department
    of Interior,
    May 1,
    1967.
    c)
    40 CFR 607 A~per~&~x
    A7 4~Fed~Reg~-4~7~54~
    ~8T
    ~973-~- (1987)
    d)
    ASAE
    Standard
    248.2,
    Section
    9,
    Basis
    for
    Stating
    Drying
    Capacity
    of
    Batch
    and
    Continuous—Flow
    Grain
    Dryers,
    American Society
    of Agricultural
    Engineers,
    2950 Niles
    Road,
    St.
    Joseph,
    MI 49085.
    e)
    U.S.
    Sieve Series, ASTM—Ell, American Society of Testing
    Materials,
    1916 Race Street,
    Philadelphia,
    PA 19103.
    f)
    This Part
    incorporates
    no future editions
    or amendments.
    (Source:
    Amended
    at
    Ill.
    Reg.
    effective
    ____________)
    Section 212.121
    Opacity Standards
    For the purposes
    of this Subpart, all
    ~ta~r
    visible emission
    opacity standards and limitations shall
    be considered equivalent
    to corresponding Ringelmann Chart readings,
    as described under
    the definition
    of opacity
    (35
    Ill.
    Adm.
    Code 211.122).
    +Be~~Ne4~e~Th5~Stthpa~as ~
    app~es ~e se~eee ~egt~a~ed
    by
    l~asbeer~~
    ~
    by the
    4~o5~sSttp~eMe
    eo~~7
    ?e3o~exv~~P?B e~a~ 68 fl~ Beer ~88~
    445 HE~
    ~5~+
    (Source:
    Amended at
    ____
    Ill.
    Reg.
    _________
    effective
    ____________
    90—609

    —22—
    Section 212.123
    Limitations for All Other
    Sources
    a)
    No person shall cause or
    allow the emission of smoke or
    other particulate matter, ?f~om
    arty
    ether em~ss~ei’~
    seti~ee
    ~
    the a
    esp~e~ee~with an opacity greater
    than
    30
    percent,
    into the atmosphere
    from any emission source
    other
    than those sources subject
    to Section 212.122.
    b)
    Exception:
    The emission of
    smoke or other particulate
    matter
    from any such emission source may have an opacity
    greater
    than 30 percent but not greater
    than
    60 percent
    for
    a period or
    periods aggregating
    8 minutes
    in any
    60
    minute period provided
    that such more opaque emissions
    permitted during any 60 minute period shall occur
    from
    only one such emission source located within a 305 m
    (1000
    ft) radius from the center point of any other
    such
    emission source owned
    or operated by such person,
    and
    provided further that such more opaque emissions
    permitted from each such emission source shall
    be
    limited
    to
    3 times
    in any 24 hour period.
    (Source:
    Amended
    at
    Ill.
    Reg.
    _________
    effective
    ____________)
    Section 212.124 Exceptions
    a)
    Startup, Malfunction and Breakdown.
    Sections 212.122
    and 212.123 shall apply during times
    of startup,
    malfunction
    and
    breakdown
    except
    as provided
    in the
    operating permit granted
    in accordance with
    35
    Ill.
    Adm.
    Code
    201.
    b)
    Emissions
    of water
    and water vapor.
    Sections 212.122
    and 212.123 shall
    not apply to emissions
    of water or
    water vapor
    from an emission source.
    c)
    Adjusted standards.
    An emission source which has
    obtained
    an adjusted opacity standard pursuant to
    Section 212.126 shall be subject
    to that standard rather
    than the limitations
    of Section 212.122 or 212.123.
    de)
    Compliance with the particulate
    regulations of this Part
    shall constitute
    a defense.
    1)
    For all emission sources which are not subject
    to
    Chapters
    111
    or 112
    of the Clean
    Air Act and
    Sections 212.201, 212.202,
    212.203 or
    212.204 but
    which
    are subject to Sections 212.122 or 212.123:
    The opacity limitations
    of
    Sections 212.122
    and
    212.123
    shall
    not apply if
    it
    is shown
    that the emission source was,
    at the time of
    9 0—6 10

    —23—
    such emission,
    in compliance with
    the
    applicable particulate
    emissions limitations
    of
    Subparts
    D—T
    of
    this
    Part.
    2)
    For all emission sources which are not subject to
    Chapters
    111
    or
    112
    of
    the
    Clean
    Air
    Act
    but
    which
    are
    subject
    to
    Sections
    212.201,
    212.202,
    212.203
    or 212.204 and either Section
    212.122
    or 212.123:
    A)
    An exceedance
    of the limitations
    of Section
    212.122
    or 212.123 shall constitute
    a
    violation of the applicable particulate
    limitations
    of
    Subparts D—T
    of
    this Part.
    It
    shall
    be
    a defense
    to
    a violation of the
    applicable particulate limitations
    if, during
    a
    subsequent
    performance
    test
    conducted
    within
    a
    reasonable
    time not
    to exceed
    60 days, under
    the same operating
    conditions for the source
    and the control device(s),
    and
    in accordance
    with Method
    5,
    40 CFR 60, incorporated by
    reference
    in Section 212.113, the owner
    or
    operator shows
    that the source
    is
    in
    compliance with
    the particulate emission
    limitations.
    B)
    It shall
    be
    a defense
    to
    an exceedance
    of the
    opacity limit
    if, during
    a subsequent
    performance test conducted within
    a reasonable
    time not
    to exceed
    60 days,
    under
    the same
    operating conditions
    of the source and the
    control device(s),
    and
    in accordance with
    Method
    5,
    40
    CFR 60, Appendix A,
    incorporated
    by reference
    in Section 212.113,
    the owner
    or
    operator shows
    that
    the source
    is
    in
    compliance with the allowable particulate
    emissions limitation while, simultaneously,
    having visible emissions equal
    to or greater
    than the opacity exceedance
    as originally
    observed.
    (Source:
    Amended
    at
    Ill.
    Reg.
    effective
    ___________
    Section 212.126
    Adjusted Opacity Standards Procedures
    a)
    Pursuant
    to Section
    28.1
    of the Act,
    and
    in accordance
    with
    35 ill.
    Adm.
    Code 106.Subpart
    E,
    adjusted visible
    emissions standards
    for emission sources subject
    to
    Sections
    212.201,
    212.202,
    212.203,
    or
    212.204
    and
    either
    Section
    212.122
    or
    212.123
    shall
    be
    granted
    by
    the Board to the extent consistent
    with federal
    law
    based upon
    a demonstration by such
    a source that the
    90—6 11

    —24—
    results of
    a performance test
    conducted pursuant
    to
    this
    Section,
    Section 212.110,
    and Methods
    5 and 9 of
    40 CFR
    60, Appendix A,
    incorporated by reference
    in Section
    212.113, show
    that the source meets the applicable
    particulate emission limitations
    at the same
    time that
    the visible emissions exceed
    the otherwise applicable
    standards of
    Sections 212.121—212.125.
    Such adjusted
    opacity limitations:
    1)
    Shall be specified
    as
    a condition
    in operating
    permits
    issued pursuant
    to
    35
    Ill. Mm.
    Code 201
    2)
    Shall
    substitute for that limitation otherwise
    applicable
    3)
    Shall
    not allow an opacity greater
    than 60 percent
    at any time;
    and
    4)
    Shall allow opacity for one six—minute averaging
    period
    in any 60 minute period
    to exceed
    the
    adjusted
    opacity standard.
    b)
    For
    the purpose of establishing
    an adjusted opacity
    standard,
    any owner
    or
    operator of
    an emission source
    which meets
    the requirements
    of subsection
    (a)
    ,
    above,
    may request the Agency
    to determine the average opacity
    of
    the emissions from the emission source during any
    performance test(s)
    conducted pursuant
    to Section
    212.110 and Methods
    5 and
    9 of
    40 CFR 60, Appendix A,
    incorporated
    by reference
    in Section 212.113.
    The
    Agency shall refuse
    to accept the results
    of emissions
    tests
    if not conducted pursuant
    to this Section.
    C)
    Any request
    for
    the determination of
    the average opacity
    of emissions shall
    be made
    in writing,
    shall
    include the
    time and place
    of
    the performance test and test
    specifications and procedures,
    and shall be submitted
    to
    the Agency at least thirty days before the proposed test
    date.
    d)
    The Agency will advise the owner
    or operator
    of
    an
    emission source which has requested an opacity
    determination
    of
    any
    deficiencies
    in
    the
    proposed
    test
    specifications
    and procedures
    as expeditiously as
    practicable but no
    later
    than
    10 days prior
    to the
    proposed test date
    so as
    to minimize any disruption of
    the proposed testing schedule.
    e)
    The owner
    or operator shall allow Agency personnel
    to be
    present during the performance test.
    90—612

    —25—
    f)
    The method for determining
    an adjusted opacity standard
    is
    as
    follows:
    1)
    A minimum of
    60 consecutive minutes
    of opacity
    readings obtained
    in accordance with USEPA Test
    Method
    9,
    40 CFR 60, Appendix A,
    incorporated
    by
    reference in Section 212.113, sha~.1be taken during
    each sampling
    run.
    Therefore,
    for each performance
    test
    (which normally consists
    of three sampling
    runs),
    a total
    of three sets of opacity readings
    totaling
    three hours
    or more shall
    be obtained.
    Concurrently,
    the particulate emissions
    data from
    three sampling runs obtained
    in accordance with
    USEPA Test Method
    5,
    40 CFR 60, Appendix
    A,
    incorporated by reference
    in Section 212.113, shall
    also be obtained.
    2)
    After
    the results
    of the performance tests
    are
    received from the emission source,
    the status of
    compliance with the applicable particulate
    emissions limitation shall
    be determined by the
    Agency.
    In accordance
    with tJSEPA Test
    Method
    5,
    40
    CFR 60, Appendix A,
    incorporated by
    reference
    in
    Section 212.113,
    the average
    of the
    results of the
    three sampling runs must
    be less
    than the allowable
    particulate emission rate
    in order for the source
    to be considered
    in compliance.
    If compliance is
    demonstrated, then only those
    test runs with
    results which are
    less than the allowable
    particulate emission rate
    shall be considered as
    acceptable
    test
    runs for
    the purpose of
    establishing
    an adjusted opacity standard.
    3)
    The opacity readings for each acceptable sampling
    run shall be divided
    into sets of
    24 consecutive
    readings.
    The 6—minute average
    opacity
    for each
    set shall be determined
    by dividing
    the sum of the
    24 readings within each set
    by
    24.
    4)
    The second highest six—minute average opacity
    obtained
    in
    (f)(3) above
    shall
    be selected as the
    adjusted opacity standard.
    ~j
    The owner
    or operator shall submit
    a written report
    of
    the results of
    the performance
    test
    to the Agency at
    least
    30 days prior
    to filing
    a petition for
    an
    adjusted
    standard with the Board.
    h)
    If,
    upon review of such owner’s
    or operator’s written
    report of the results of
    the performance test(s),
    the
    Agency determines
    that the emission source
    is
    in
    compliance with all applicable emission limitations
    for
    90—613

    —26—
    which the performance
    tests were conducted,
    but fails
    to
    comply with the requirements
    of Section 212.122
    or
    212.123,
    the Agency shall notify the owner
    or operator
    as expeditiously as practicable,
    but no
    later than
    20
    days after
    receiving the written report of any
    deficiencies
    in the results
    of
    the performance
    tests.
    i)
    The owner
    or operator may petition the Board for an
    adjusted visible emission standard pursuant
    to
    35
    Ill.
    Mm.
    Code 106.Subpart
    E.
    In
    addition to the
    requirements of
    35
    Ill.
    Adm.
    Code
    l06.Supart
    E
    the
    petition shall
    include
    the following information:
    1)
    A description of
    the business
    or activity
    of the
    petitioner,
    including
    its location and relevant
    pollution control equipment
    2)
    The quantity and type
    of materials discharged from
    the source
    or control equipment for which
    the
    adjusted standard
    is requested
    3)
    A copy
    of
    any correspondence between the petitioner
    and the Agency regarding
    the performance test(s)
    which form the basis
    of the adjusted standard
    request
    4)
    A copy
    of the written report submitted
    to the
    Agency pursuant
    to subsection
    (g) above
    5)
    A statement that the performance test(s) were
    conducted
    in accordance with
    this Section
    and the
    conditions
    and procedures accepted by the Agency
    pursuant to Section 212.110
    6)
    A statement regarding the specific limitation
    requested; and
    7)
    A
    statement
    as
    to
    whether
    the
    Agency
    has
    sent
    notice
    of
    deficiencies
    in
    the
    results
    of
    the
    performance test pursuant
    to subsection
    (h)
    above
    and
    a
    copy
    of
    said
    notice.
    jj~
    In order
    to qualify
    for
    an adjusted standard the owner
    or operator must justify
    as follows:
    1)
    That the performance test(s) were conducted
    in
    accordance with USEPA Test Methods
    5 and 9,
    40 CFR
    60, Appendix
    A,
    incorporated by reference
    in
    Section
    212.113,
    and
    the
    conditions
    and
    procedures
    accepted
    by
    the
    Agency pursuant
    to Section 212.110
    2)
    That
    the
    emission source and associated
    air
    pollution
    control
    equipment
    were
    operated
    and
    maintained
    in
    a
    manner
    so
    as
    to
    minimize
    the
    90—6 14

    —27—
    opacity of the emissions during the performance
    test(s);
    and
    ~J
    That the proposed adjusted opacity standard was
    determined
    in accordance with subsection
    (f).
    k)
    Nothing in this Section shall prevent any person from
    initiating or participating
    in
    a rulemaking, variance,
    or permit appeal proceeding before the Board.
    (Source:
    Added
    at
    Ill. Reg.
    ,
    effective
    )
    IT
    IS SO ORDERED.
    Board Member
    B.
    Forcade concurred.
    I, Dorothy M.
    Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Op).~nionand Order was
    adopted on the
    ______________
    day of
    y_~c..
    ,
    1988 by a vote
    of
    7-0
    .
    Dorothy M./Gunn, Clerk
    Illinois Eollution Control Board
    90—615

    Back to top