ILLINOIS POLLUTION CONTROL BOARD
    February 25, 1988
    VILLAGE OF LEMONT,
    Petitioner,
    v.
    )
    PCB 86—207
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent,
    and
    CAROLYN
    F. PLACEK, KATHERINE
    )
    H.
    MURPHY AND GEORGE PODREBARAC,
    )
    )
    Intervenors.
    )
    ORDER OF THE BOARD (by 3. Theodore Meyer):
    This matter is before the Board on a verified motion to
    modify, filed by the Village of Lemont on January 22, 1988.
    Lemont seeks extension of the variance granted in the Board’s
    March 19, 1987 Order. That Order granted Lemont a variance from
    35 Ill. Mm. Code 602.105(a) (Standards of Issuance) and 35 Ill.
    Mm. Code 602.106(b) (Restricted Status), but only as those
    sections relate to combined radium and gross alpha particle
    activity. The variance is to expire on March 19, 1988. The
    Illinois Environmental Protection Agency (Agency) filed its
    response on January 28, 1988. On January 27, 1988, the Board
    received a certificate of service from Lemont stating that
    intervenors Carolyn F. Placek, Katherine H. Murphy, and George
    Podrebarac were served with the motion on January 25, 1988.
    Iritervenors have not responded to the motion.
    In the instant motion, Lemont asks that the variance be
    extended for an additional six months, until September 19,
    1988. Lemont states that it cannot come into compliance by March
    19, 1988 because severe weather and remedial work on its water
    tower have delayed its construction of the treatment system. In
    support of its request, Lemont has attached a letter from its
    contractor asking for an extension until July 9, 1988 in which to
    complete its work. The contractor states that an extension is
    necessary because of a seven week delay in starting construction
    and because of winter conditions. (Motion, ex. 5.) Lemont has
    also included a memo from its consulting engineer, which
    recommends that Lemont request an extension of variance to
    September 19, 1988. (Motion, ex. 6.)
    86—335

    —2—
    In its response, the Agency states that Lemont’s motion
    fails to answer several questions about the delay in
    construction, and that in light of these unanswered questions, it
    cannot venture an opinion as to whether compliance will be
    achieved within the shortest practicable time. However, because
    Lemont appears to be making progress in constructing the
    treatment facility, the Agency states that it has no objection
    to a grant of the motion to modify.
    The Board agrees with the Agency that Lemont’s motion does
    leave several questions unanswered, and that there is some
    question as to whether construction of the treatment facility has
    proceeded as quickly as practical. Nevertheless, Lemont does
    seem to now be on track in achieving compliance. Therefore, the
    motion to modify the Board’s March 19, 1987 Order is granted.
    ORDER
    The Village of Lemont is hereby granted a variance from the
    provisions of 35 Iii. Mm. Code 602.105(a) (Standards of
    Issuance), and 602.106(b) (Restricted Status), but only as they
    relate to combined radium and gross alpha particle activity,
    subject to the following conditions:
    1. This variance expires on September 19, 1988;
    2. Petitioner shall continue its efforts to obtain Lake
    Michigan water through the Joint Action Water Agency.
    3. In consultation with the Agency, Petitioner shall
    continue its sampling program to determine as accurately
    as possible the level of radioactivity in its well and
    finished water. Until this variance expires, Petitioner
    shall collect quarterly samples of its water from its
    distribution system, shall composite and shall analyze
    them annually by a laboratory certified by the State of
    Illinois for radiological analysis so as to determine
    the concentration of the contaminants in question. The
    results of the analyses shall be reported to the Water
    Quality Unit, Division of Public Water Supplies, 2200
    Churchill Road, IEPA, Springfield, Illinois 62706,
    within 30 days of receipt of each analysis. At the
    option of Petitioner, the quarterly samples may be
    analyzed when collected. The running average of the
    most recent four quarterly sample results shall be
    reported to the above address within 30 days of receipt
    of the most recent quarterly sample.
    4. Compliance shall be achieved with the maximum allowable
    concentration in question no later than September 19,
    1988.
    86—336

    —3—
    5. Within three months of the grant of the variance, the
    Petitioner shall prepare a detailed compliance report
    showing how compliance shall be achieved within the
    shortest practicable time, but no later than September
    19, 1988.
    6. This Compliance Report shall be submitted within three
    months of the grant of this variance to IEPA, DPWS.
    7. Within four months of grant of the variance Petitioner
    shall apply to IEPA, DPWS, Permit Section, for all
    permits necessary for construction of installations,
    changes or additions to the Petitioner’s public water
    supply needed for achieving compliance with the maximum
    allowable concentration for the standards in question.
    8. Within three months after each construction permit is
    issued by IEPA, DPWS, the Petitioner shall advertise for
    bids, to be submitted within 60 days, from contractors
    to do the necessary work described in the construction
    permit. The petitioner shall accept appropriate bids
    within a reasonable time. Petitioner shall notify IEPA,
    DPWS, within 30 days of each action, of: 1)
    advertisements for bids, 2) names of successful bidders,
    and 3) whether Petitioner accepted the bids.
    9. Construction allowed on said construction permits shall
    begin within a reasonable time of bids being accepted,
    but in any case, construction of all installations,
    changes or additions necessary to achieve compliance
    with the maximum allowable concentrations in question
    shall be completed no later than September 19, 1988.
    10. Pursuant to 35 Ill. Mm. Code 606.201, in its first set
    of water bills or within three months after the date of
    this Variance Order, whichever occurs first, and every
    three months thereafter, Petitioner will send to each
    user of its public water supply a written notice to the
    effect that Petitioner has been granted by the Pollution
    Control Board a variance from 35 Ill. Mm. Code
    602.105(a) Standards of Issuance and 35 Ill. Adm. Code
    602.106(b) Restricted Status, as it relates to the MAC
    Standard in question.
    11. Pursuant to 35 Ill. Mm. Code 606.201, in its first set
    of water bills or within three months after the date of
    this Order, whichever occurs first, and every three
    months thereafter, Petitioner will send to each user of
    its public water supply a written notice to the effect
    that Petitioner is not in compliance with the standard
    in question. The notice shall state the average content
    86-337

    —4—
    of the contaminant in question in samples taken the last
    notice period during which samples were taken.
    12. The Petitioner shall take all reasonable measures with
    its existing equipment to minimize the level of
    contaminant in question in its finished water.
    13. The Petitioner shall provide written progress reports to
    IEPA, DPWS, for every six months concerning steps taken
    to comply with paragraphs 2, 8, 9 and 12. Progress
    reports shall quote each of said paragraphs and
    immediately below each paragraph state what steps have
    been taken to comply with each paragraph.
    14. That within 45 days of the date of this Order,
    Petitioner shall execute and forward to Scott 0.
    Phillips, Enforcement Programs, Illinois Environmental
    Protection Agency, 2200 Churchill Road, Springfield,
    Illinois 62706, a Certificate of Acceptance and
    Agreement to be bound to all terms and conditions of
    this variance. This variance will be void if Petitioner
    fails to execute and forward the certificate within the
    45 day period. This 45 day period shall be held in
    abeyance for any period this matter is appealed.
    CERTIFICATION
    I, (We), ____________________________, having read the
    Order of the Illinois Pollution Control Board in PCB 86—207,
    dated February 25, 1988, understand and accept the said Order,
    realizing that such acceptance renders all terms and conditions
    thereto binding and enforceable.
    Petitioner
    By: Authorized Agent
    Title
    Date
    IT IS SO ORDERED.
    86—3 38

    —5—
    J. D. Dumelle and B. Forcade dissented.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify ~at the above Order was adopted on
    the
    ,~$ZZ
    day of
    ~
    ,
    1988, by a vote of
    6 ~
    Illino
    Control Board
    86—339

    Back to top