ILLIN)13 POLLtJTI3~’1 CONPROL BOARD
    February 25, 1988
    ALTON PACKAGI~IG CORP.,
    Petitioner,
    v.
    )
    PCB 83—49
    ILLINOIS ENVIRONMENTAL
    )
    PROT~CTI3~A~GENCY,
    Respondent.
    MR. D~WI~LF. ~D’CON~LL ~PPE~RED O.~BEH~LLFOF PETITIONER, ALTO~
    PACK~GI~1GCORPORATION;
    MR. WILLIAM INGERSOLL PPE~RED ON BEHALF OF R~3PONDENT, ILLIN313
    ENVIRONMENTAL PROTECTION AGENCY.
    )PI~IOP~IAND ORDER OF THE BOARD (by R. C. Flemal):
    This matter comes before the Board upon an amended petition
    for variance filed by ~lton Packaging Corporation (“Altori”) on
    February 17, 1987. Alton seeks variance from former Rule 204(f)
    of Cha?ter 2 of the Boar~’sAir Pollution Rules and Regulations
    (now codified as 35 Ill. Adm. Code 214.141) for sulfur dioxide
    (SO2) emission3 emanatin~ from boilers 6 and 7 at its paoerboard
    mill (“Alton Mill”) located in Alton, Illinois. Variance relief
    is requested for a period of three years or until the Board
    grants Alton site—specific relief from Section 214.141, whichever
    occurs sooner.
    For the reasons described below, the Board finds that Alton
    has failed to make the requisite showing necessary for the
    granting of variaric’? relief. The Board will therefore deny the
    variance relief requested by Alton.
    BAC
    KGRO’:JND
    Rule
    204 was amended by the Board on February 24, l9~33. ~
    new subsection (f) was added at that time which instituted a
    sulfur dioxide emission limitation of 1.8 poun3s per million
    British thermal units (“mmbtu”) of energy produced. Alton filed
    its initial variance petition in this matter, along with a
    concurrent petition seeking Board approval of an alternative
    standard for the .Adton Mill pursuant to 35 Ill. Mm. Code
    214.201, on April 13, 1983. Because Alton filed its variance
    petition within 20 days of the effective date of Rule 204(f), it
    received an automatic stay, pursuant to Section 38(b) of the
    Environmental Protection Act (“Act”), of the emission limitation
    pending disposition of its variance petition.
    86—289

    —2—
    The Illinois Environmental Protection Agency (“Agency”)
    filed Recomnendations on August 17, 1933, recom~ending that
    Alton’s petitions for variance and site—specific relief be
    denied.
    The gency recom.riended denial due to its belief that
    Alton’s air
    disoersion modeling failed to show, “under all
    foreseeable conditions”, that
    ~lton’s
    requestad level of sulfur
    dioxide emissions would not cause or contribute to a violation of
    the Na:ional Ambient Air Quality Standard for sulfur dioxide.
    After the filing of the Agency’s recommendations, Alton
    worked with
    the Agency in revising
    its modeling study. On June
    29, 1984, the Board, noting no activity in the case since August
    1983, ordered a hearing to be held on Alton’s petitions within 60
    days. On July 1, Alton filed a motion to extend the hearing date
    until October 30, because the hearing officer assigned to the
    case was unavailable for a hearing within the time set by the
    Board. The Board granted Alton’s ~notion. hearing wa~
    scheduled for October 25, but was rescheduled to December 7 by
    the hearing officer.
    At the December hearing, Alton presented the conclusions of
    its revised modeling study through the testimony of its
    consulting expert. At the end of the hearing, Adton stated it
    intended to file within the next thirty days amended petitions
    conforming with the testimor~y at the hearing. The Agency noted
    that it already had Alton’s modeling results and would file an
    amende~ recommendation within 30 days after receiving Alton’s
    amended petitions. No amended petitions were ever filed.
    In April of 1985, the Agency sent a letter to Alton asking
    for clarification of a few technical matters. Alton forwarded
    this letter to its consultant, but aooarently no response was
    made. On July 19, l985,r the Agency moved to dismiss P.lton’s
    petitions for failure tu prosecute th~matter with diligence. On
    July 23, the hearing officer scheduled a hearing on Alton’s
    petitions for Se~tember 18. On August 1, however, the Board
    dismissed Alton’s case. The Board stated in its Order, after
    noting no further activity in the case since the December
    hearing, that Alton had had sufficient time to present its case
    and should not be allowed to extend the automatic stay by filing
    an amended petition. The hearing officer accordingly cancelled
    the September 18 scheduled hearing. Alton filed a motion for
    reconsideration on September 4, 1985, which the Board denied on
    Seotember 20, 1985. Z~lton then apoealed the Board’s decision to
    the Illinois Appellate Court, Fifth District.
    The Fifth District Court found on Sertember 5, 1986, that
    the Board erred in dismissing Alton’s petition without a hearing
    and in refusing to reconsider its decision. The Court noted that
    a dismissal for failure to prosecute is justified when the party
    has been guilty of inexcusable delay in prosecuting the suit.
    The Court found, however, that the record did not suoport a
    86—290

    —3—
    finding of inexcusable delay on the part of Alton. The Court
    consequently reversed
    the Board’s August 1, 1985, decision
    dismissing Alton’s petitions and remanded the matter back to the
    Board for further proceedings. A new hearing was conducted on
    January 15, 1987. An amended petition was filed by Alton on
    February 17, 1987. Post hearing briefs from both lton an~the
    Agency have also been received by the Board.
    TdE ALPO:I F~CILETY
    The Alton Mill is one of the larger paperboard mills in the
    Midwest. It is located within the city limits of Alton,
    Illinois, in Madison County on the Mississippi River immediately
    below Alton Lock and Dam No. 26. The Alton Mill employs 60
    salaried and 230 union employees.
    The Alton Mill site is aporoximately 107 acres, and includes
    several buildings comprising a little over 500,000 square feet.
    The Alton Mill produces approximately 600 tons of paoerboard per
    day and 200,000 tons per year. The paperboard is converted into
    manufactu~ingproducts for use in corrugated shipping containers.
    R. at 34.
    The Alton Mill uses steam both for heating and in the
    production of oaperboard. Alton owns five boilers which it can
    use to produce steam. Of these, Alton regularly uses only
    boilers 6 and 7. Id. These two boilers have adequate capacity
    to orovide all the steam needed at the Alton Mill, and at the
    same time, provide steam to LaClede Steel Company (“LaClede”)
    pursuant to an agreement between the two companies (see pgs. 8—
    9).
    Boilers 8 and 9 are only used when the main boilers (i.e.
    boilers 6 and 7) are unable to operate at their normal
    capacity. In such a situation, boilers 8 and 9 are normally
    operated on natural gas, but can be operated on oil. Boiler 5
    has not been fired in years, but can be fired on an emergency
    basis. R. at 34—35.
    1 References made to the transcript of the January 15, 1987,
    hearing in this matter will be cited as “R. at
    ______
    86—29 1

    —4—
    The capacity of the five boilers is as follows:
    Boiler #
    Heat Input BTU/hrs.
    Fuel Used
    5
    114 mmbtu
    Gas
    125 mmbtu
    Oil
    6
    171 mmbtu
    Coal
    173 mmbtu
    Gas
    178 mmbtu
    Oil
    7
    445 mmbtu
    Coal
    444 mmbtu
    Gas
    464 mmbtu
    Oil
    8
    182 mrnbtu
    Gas
    175 mmbtu
    Oil
    9
    182 mmbtu
    Gas
    175 mmbtu
    Oil
    R. at 35.
    Boilers 6 and 7 are the subject of Alton’s Petition for
    Variance. Notwithstanding their rated caoacity, the boilers are
    not operated above 138.5 mmbtu per hour for boiler 6 and 365.5
    mmbtu per hour for boiler 7, for a combined maximum firing rate
    of 504 mmbtu per hour. R at 35. Boilers 6 and 7 are pulverized,
    wet bottom boilers. Coal is ground into a fine powder in five
    pulverizers and then blown into the boilers. The coal is burned
    in the boilers, producing heat; the heat, in turn, is used to
    produce steam for heating and process use. The exhaust from each
    boiler passes through a mechanical collector known as a “multi—
    clone” and then through an electro—static precipitator. These
    particulate control devices have a combined collection efficiency
    of approximately 99. The boilers vent through separate stacks
    which are 54 feet above the Mill roof and 192 feet above grade.
    R. at 35—36. The Alton Mill is not equipped with any add—on
    control devices to reduce sulfur dioxide emissions. R. at 36.
    RELIEF REQUESTED
    Alton requests that the Board grant it variance from Section
    214.141 for three years or until the Board grants it site—
    specific relief from the same section, whichever occurs first.
    Alton is willing to limit the scope of this relief by complying
    with a number of conditions. Specifically, these conditions are
    that:
    86—292

    —,.)—
    (1) Alton will operate boilers 6 and 7 using coal
    with a maximum average 902 emission rate of 5
    lbs per mmbtu;
    (2) Alton will limit its firing rate to 138.5 mmbtu
    per hour for boiler 6 and 365.5 mmbtu per hour
    for boiler 7;
    (3) Alton will not operate its boilers 5, 8 and 9 on
    oil unless it limits its operation of boilers 6
    and 7 to the use of coal with a maximum average
    SO2 emission rate of 1.8 lbs per mmbtu; and
    (4) Alton will increase the height of the stacks
    from boilers 6 and
    7 to 234 feet above grade.
    The suggested compliance conditions would not inhibit
    Alton’s ability to maintain its operations at present levels, and
    in fact seem to provide some flexibility
    for Alton to exoand
    operations.
    More specifically,
    Alton proposes (oursuant to
    condition 1, above) to operate its boilers 6 and 7 solely on coal
    having
    a maximum average SO2 emission rate of
    5 lbs per mmbtu.
    Based on a weighted average, the Alton Mill’s 302 emission rate
    for 1985 was 4.43 lbs per mmbtu.
    R. at 37.
    A similar degree of leeway appears
    to exist in the requested
    condition pertaining to the firing rates of the two boilers.
    Under condition 2 (above), Alton proposes to limit the firing
    rate of boilers 6 and 7 to 138.5 mmbtu per hour and 365.5 mmbtu
    per hour, respectively.
    The ~gency contends such a level of
    operation would be approximately 24 greater than the level
    anticipated for 1987, and the latter assumes an aooroximate 45
    increase in the amount of coal burned over 1986 levels.
    Agency
    Post—searing Brief, o. 6.
    ECONOMIC HARDSHIP
    Alton states that in order to comply with the 1.8 lbs/mmbtu
    limitation,
    it would have to purchase low—sulfur coal from out—
    of—state sources. R. at 48—49. At time of hearing, Petitioner
    indicated its belief that it cou1~ purchase such coal for $37.80
    per ton, which Alton states is $9.80 to $12.50 more per ton than
    it pays for the coal it currently uses.
    R. at 49. Alton
    calculates that for 1987 coal purchases, this manner of complying
    with the 1.8 lbs/mbtu standard woul~ cost the company an
    additional $1.43 million to $1.82 million.
    Id. Petitioner
    argues that this cost would be economically unreasonable, and
    warns that the profitability
    of its Alton facility would be
    seriously jeooardized if it were forced to increase its operating
    costs in this manner.
    Alton’s Post—Hearing Brief, p. 22.
    According to Petitioner,
    “(t)he Comoany’s management would be
    86— 293

    forced to reconsider the continued economic viability of the
    (Alton) Mill”. Id.
    The bur3en of proof in a variance proceeding is on the
    petitioner (see Ill. Rev. Stat. 1985, ch. lll~-/2, par. 1037(a)),
    and the Board concludes that in this instance Petitioner has
    failed to adequately demonstrate that denial of the requested
    relief woul~ impose an arbitrary or unreasonable hardshio upon
    Alton.
    Alton has failed to make the requisite showing in several
    respects. First, Alton’s projected $1.43 million to $1.82
    million increase in annual operating costs (predicted to come
    about because of a need to purchase low—sulfur coal from out—of—
    state) is subject to some dispute.
    These figures were calculated
    from a per ton price of $37.80. The Agency questions the manner
    in which that figure was determined, as IL is the result of a
    “spread sheet check on prices in various mines” (R. at 59), but
    is apparently not the result of a bidding process. Agency Post—
    Hearing Brief, pgs. 6—7. Competitive bidding might very well
    reduce the price per ton of this coal, thereby reducing the
    overall cost of compliance and impacting the question of whether
    unreasonable economic hardshio exists.
    Second, Alton has presented no data concerning the cost(s)
    of utilizing any other compliance option(s). The Board is aware
    from its past rulemakings that other technologies exist for
    sulfur dioxide control. These include lime or limestone
    injection into the furnace with the pulverized coal, fluidized
    bed furnaces, and wet
    arid
    dry stack gas scrubbers. Alton
    presents no information whatsoever regarding any of these
    possible alternatives. It is not clear whether Altori han
    investigated any alternative control technologies, or whether
    utilizing low—sulfur coal would in fact even be the most
    economical way for Petitioner to comply with the 1.8
    lbs/nimbtu
    limitation. Similarly, Alton has made no mention of whether it
    has considered alternative energy sources to coal that might be
    used for the production of steam.
    In this context it is to be
    noted that the boilers
    in question
    are capable of operating on
    fuel other than coal.
    Finally, Alton has not shown the impact that
    a $1.43 million
    to $1.82 million increase in annual operating expenditures would
    have on Jefferson Smurfit Corporation (“J3C”). Alton is wholly
    owned by JSC, yet Petitioner has not addressed the question of
    whether an increase in costs of the magnitude discussed would
    constitute unreasonable economic hardship to JSC. Alton contends
    that the viability of a JSC plant (of which the Alton Mill is
    one) is evaluated by the corporate parent on the basis of that
    plant’s individual orofitability, and so for that reason argues
    that the projected increase in operating costs should be
    evaluated in light of the Alton Mill’s $3.5 million profit in
    86—294

    —7—
    1986. Alton’s Post—Hearing Brief, p. 23; R. at 63. As an
    illustration
    of the JSC philosophy, an Alton witness testified
    that “(o)nly if (the plant) can show a return do(es) (the plant)
    receive caoital funds for improvement”.
    R. at 61.
    That JSC evaluates each of its plants as individual profit
    centers is well and good, but that is not relevant to the issue
    of whether the Board should look in this instance solely to Alton
    or JSC to determine the true cost of compliance with Section
    214.141. In fact, that the JSC
    plants compete with each other
    for capital improvement funds is telling, but for a different
    reason than that envisioned by Alton. As JSC seemingly views the
    Alton Mill in identical fashion to the way it views its other
    plants, and given that $10 million in capital improvement funds
    is presently committed by JSC to the ~‘\ltonMill (R. at 63), it is
    apparent that Alton does not operate in a manner thoroughly
    independent from JSC. On the contrary, Alton more readily
    appears to function as an arm of JSC. This is further
    exemplified by the fact that at least some percentage of the
    Alton Mill’s output is utilized by JSC for production within the
    latter’s Container Division.
    Exhibit 1, o. 6. JSC is the entity
    against which the projected increase in operating costs must also
    be evaluate~, but Alton did not provide the information which
    would have made such an analysis possible.
    ENVIRONMENTAL IMPACT
    Alton presented the findings of two modeling studies, both
    undertaken by contractors hired by Petitioner, in support of its
    contention that ambient air quality will be protected during the
    term of the requested variance.
    Ronald L. Petersen of Cermak/Peterka arid Associates, Inc.
    testified at hearing regarding the fluid modeling study that
    company performed for Alton.
    This study was done to demonstrate
    that the increase in height Alton proposes for the stacks of its
    boilers 6 and 7 (from the existing 192 feet to 234 feet) is
    necessary in order to avoid “excessive concentrations” of SO2 due
    to downwash effects. Such a demonstration must be made before a
    facility may receive credit in its air dispersion modeling for
    certain stack height increases. R. at 21—22.
    Federal regulations define “excessive concentrations” as
    those occurring where maximum ground level concentrations are 40
    higher because of downwash effects caused by nearby structures
    than the concentration would be with these effects removed, and
    those maximum ground level concentrations are in excess of
    National Ambient Air Quality Standard (“NAAQS”). R at 22. The
    modeling study showed that both conditions are satisfied in this
    instance. That is,
    at the operating parameters requested by
    Alton (SO2 emission rate of 5 lbs/mmbtu and operating rates of
    86—295

    —8—
    138.5 and 365.5 mmbtu per hour for boilers 6 and 7,
    respectively), the maximum hourly groun~ level concentrations
    would be 40 higher because
    o~ the structures presen~, and these
    concentrations would be expectel to exceed the NAAQS
    .
    R. at 25—
    27.
    John Paul Bradley of Murray and Trettel,
    Inc. presented
    testimony on the air dispersion modeling study completed by that
    company for lton. The study consists of two components. The
    first involved an analysis of what operating parameters at the
    Alton Mill would assure maintenance of the N.AAQS for SO2 after
    the planned increase in stack height, without reliance on
    LaClede’s reduced SO2 emissions pursuant t the steam
    agreement. R. at 75—76. The second component addressed the
    questions of what combination of operating parameters and other
    arrangements would ensure that the NAAQS for SO2 would be
    maintained prior to the completion of the stack height
    increase. R. at 76.
    The modeling used a grid of 79 receptors, arranged on a
    roughly rectangular grid. R. at 83. Receptors were located in
    areas expected to receive the most significant impact, and in
    areas of expected interaction between Alton and other modeled
    sources. Id.
    All 79 receptors were modeled using 1973 meteorological
    data. R. at 86. Seven receptors showed second highest
    concen~rations exceeding 85 of the 365 microgram per cubic meter
    (“ug/m
    “)
    24—hour standard. Id. These seven receptors were then
    modeled using 1974—1977 meteorological data. The highest s~cond
    highest concentration re~orded by a receptor was 358.6 ug/m3.
    Id.; Alton Gr•ouo Exhibit 5(h). The modeling therefore
    demonstrated no modeled violations of 35 Ill. Adm. Code 243.122
    (Sulfur Oxides). Based on these results, Mr. Bradley opined that
    at the operating parameters requested by Alton, emissions from
    the Alto-i Mill boilers will not result in any violations of the
    SO2 NAAQS. R. at 87.
    The second component of the air dispersion mo9eling
    consisted of an analysis of how Alton might provide for th~
    maintenance of ambient air quality during the period prior to
    accomplishment of the stack height increase. The modeling done
    for this question showed that no violations of the NA~Q3for 302
    2 In fact, Dr. Petersen testified that even if the SO2 emission
    rate was 1.8 lbs/mmbtu, the fluid modeling study predicted that
    the NAAQS for SD2 would be violated.
    3 Hereinafter references to Alton’s Exhibits will appear as
    “Alton Ex.
    86—296

    —9—
    would occur as a result of Alton’s emissions during this interim
    ocriod, orovided that Petitioner operates within the parameters
    it requests and LaClede complies with the provisions of the
    agreements reached between Alton and itself. R. at 91—92. A
    description of these agreements is appropriate this time.
    An agreement involving the sale of steam from Alton to
    LaClede was entered into by those two entities in 1984. Alton
    Ex. 4(a); R. at 42. Under the terms of the contract, steam is
    provided via a line constructed from the Alton Mill to LaClede.
    The steam is sold at an agreed once, and is used by LaClele in
    its operations. As a consequence of the contract, LaClede has
    not operate5 its steam boilers 1 and 2 for the last few years.
    Id. The contract provides that it can only be terminated after
    six months written notice (Amended Petition for Variance,
    0.
    10)
    and will exoire in 1989 (R. at 43).
    Altori’s air dispersion modeling predicted violations of the
    NAAQS for SO2 prior to the stack height increase if Alton
    operates within its requested oarameters and LaClede operates its
    boiler 2 at its maximum permitted level using oil. R. at 88—
    89. Alton is therefore relying, in making its case, on LaClede
    to adhere to the terms of the steam sales agreement and
    consequently riot operate its boilers. Alton asserts that LaClede
    and itself will “almost undoubtedly maintain this agreement
    throughout the period of the variance prior to Alton raising its
    stacks (because)
    ...
    the economies for both parties will provide
    a strong incentive to maintain the arrangement”. R. at 43.
    Alton has also entered into a “notification” agreement with
    LaClede for the purpose of allowing Alton to avoid violations of
    the SO2 NAAQS should LaClede decide to operate its process
    sources on oil. Under the terms of the agreement, LaClede would
    provide Alton written notification seven days prior to operating
    in this manner. LaClede’s process sources are presently operated
    on natural gas, but are permitted to operate on oil.
    Alton has stated that it would accept the following
    operating restrictions as conditions to the granting of the
    shouldrequestedanyvariance,of the followingin
    order
    scenariosto
    preventarise.NAAQS
    violationsThese
    conditionsof
    SO2
    would apply to the period prior to the completion of the stack
    height increase. Alton’s modeling predicts that in the following
    situations, Petitioner could operate at the stated levels and not
    cause 302 violations:
    86— 297

    —to—
    AllowableEmissions302
    EmissionCoal
    SO2Rate
    Firing Rate
    (lbs/hr)
    (lbs/mmbtu)
    (mmbtu/hr)
    Scenar io
    Status Quo
    2,520
    5
    Boiler 6: 138.5
    (steam contract
    or 1.8 if
    Boiler 7: 365.5
    is observed and
    Boilers
    Total: 504.0
    LaClede operated
    5, 8 and 9
    its process sources
    are operated
    on natural gas)
    using oil
    LaClede operates
    2,403
    5
    Boiler 6: 137.0
    Boilers 1 and 2
    Boiler 7: 361.6
    on oil and pro—
    Total:
    499
    cess sources on
    natural gas
    Steam Contract
    1,049
    5
    Boiler 6: 112.6
    continues, but
    Boiler 7: 297.0
    LaClede operates
    Total: 409.6
    its process
    sources on oil
    LaCle3e operates
    1,925
    5
    Boiler 6: 105.8
    Boilers 1 or 2
    Boiler 7: 279.2
    and process
    Total: 385.0
    sources on oil
    COMPLIANCE PLAN
    It is axiomatic that a variance does not grant permanent
    relief from compliance with a regulatory requirement. One
    necessary aspect of a variance petition is that it describe how
    and when a facility will come into compliance. This concept is
    articulated at 35 Iii. Adm. Code 104.121(f):
    A detailed description of the existing and proposed
    undertakenequipment
    orto proposedachieve methodfull
    complianceof
    controlwithto
    theb2 Act
    arid regulations, including a time schedule for
    implementation of all phases of the control program
    from initiation of design to program completion and
    the estimated costs involved for each phase and the
    total cost to achieve compliance.
    Alton has not presented a compliance plan in the proper
    sense of that term.
    Alton has offered no plan under which the
    boilers at the Alton Mill would ever be brought into compliance
    with the Act and regulations. Rather, Alton requests a three—
    86—298

    —11—
    year variance so that it may pursue permanent relief from the 1.8
    lbs/mmbtu standard of Section 2l4.lfl. by attempting to secure,
    pursuant to 35 Ill. Adm. Code 214.201, an alternative standard
    for the Alton Mill.
    Moreover, Alton’s Amended Petition for
    Variance does not include a commitment from Petitioner that it
    will bring the Alton Mill into compliance by a date certain
    should the Board
    deny Alton the relief it requests under Section
    214.201.
    The absence of a compliance plan in this matter is one of
    the factors
    upon which the Agency bases
    its recommendation that
    variance relief be denied Petitioner. The Agency opines that
    “(p)ursuit of a site—specific limitation is not a compliance plan
    to support a variance petition”. Agency Post—Hearing Brief, p.
    11. Conversely, Alton contends that Citizens Utilities Co. v.
    Pollution Control Board, 152 Ill. Acm. 3d 122 (3rd Dist. 1997),
    is controlling and cites it for the proposition that it is
    reversible error for the Board to refuse to grant a variance,
    pending resolution of an ongoing related rulemaking proceeding,
    if granting the variance would prevent the expenditure of what
    might
    become needless compliance costs.
    The Board finds that Citizens Utilities is readily
    distinguishable from the matter at hand. ~itizens Utilities
    concernel an ongoing rulemaking in which the Agency was proposing
    amendments to rules which, if promulgated, would arguably have
    negated the need for that petitioner or for any other similarly
    located entities to undertake any compliance effort. In the
    instant matter, the “ongoing rulemaking”, PCB 83—55, is a
    creation of Petitioner itself, and consists entirely of a
    proposal which would remove Petitioner alone from the need to
    comply with existing regulations. The Board does not believe
    that such actions on the part of a petitioner can or should be
    allowed to serve the end of avoiding compliance or deflecting
    enforcement.
    Moreover, the Board believes that it
    has never been
    the
    intent of the General Assembly to require the granting of
    variance whenever a regulatory standard is under review. tn
    support thereof, the Board looks to the action of the General
    Assembly in its most recent general session. There the Illinois
    House passed by a vote of 114—1 and the Illinois Senate passed by
    a vote of 37—7 the following amendment to Section 35(a) of the
    Act:
    (a) The Board may grant individual variances beyond
    the limitations prescribed in this Act, whenever it
    is found upon presentation of adequate proof, that
    compliance with any rule or regulation, requirement
    or order of the Boarl would impose an arbitrary or
    unreasonable hardship. However, the Board is not
    required to find that an arbitrary or unreasonable
    86—299

    —12—
    hardship exists exclusively because the regulatory
    standard is under review and the costs of compliance
    are substantial and certain...
    The omnibus bill containing this amendment also contained
    certain provisions totally unrelated to the amendment.
    Controversial provisions regarding landfill fee caps were added
    to the bill in a conference committee report by a vote of 91—31
    in the House and 35—20 in the Senate. The Governor then
    amendatorily vetoed the bill regarding the fee cap and other
    provisions having to do with the Solid waste Management Act, all
    of which was unrelated to the amendnent of concern in the instant
    case. Although the total bill failed to gain passage during the
    following veto session of the General Assembly, the Board
    believes that the strong vote of both Houses of the original bill
    containing the amendment and the absence of the Governor’s veto
    of the particular provision in question stands as a public record
    of legislative intent to not require granting of variances
    whenever there is review of an underlying regulation.
    The Illinois Supreme Court recently addressed a similar
    interpretation of legislative action in Central Illinois Public
    Service Company v. Illinois Pollution Control Board, 116 Ill.2d
    397, 507 N.E. 2d 819
    ,
    in which it noted:
    Subsequent enactments may be used to help determine
    the legislature’s original intent (In re Marriage of
    Semmler (1995), 137 Ill. 2d 130, 137), particularly
    where the amendment is enacted shortly after the
    interpretation of the statute it amends comes into
    dispute (People v. Rink (1983), 97 Ill. 2d 533,540—
    541). This amendment is additional evidence that the
    legislature did not intend to do away with site—
    specific rulemaking pursuant to section 27 when it
    originally enacted section 28.1.
    The Board therefore finds that it is not now, nor has it
    been, the legislative intent of the variance process in Illinois
    to require granting of variances for the reasons here advocated
    by Alton. Moreover, the Board affirms that pursuit of a site—
    soecific limitation does not of itself constitute a compliance
    plan sufficient to meet the requirements for granting of a
    variance. See
    Modine
    Manufacturing v. I~PA, PCB 71—112, August
    18, 1982; Modine Manufacturing v. IEPA, PCB 85—59, May 16, 1985;
    City of Mendota v. IEPA, PCB 85—182, July 11, 1986; Borden
    Chemical v. IEPA, PCB 82—82, December 5, 1985; Schro~k7~E~appan
    Division v. I~PA,PC~385—205, March 5, 1997.
    86—300

    —13—
    CONCLUSION
    The Board finds that Alton has not persuasively shown that
    it would sffer arbitrary or unreaso~ab1e har ship if denied
    variance relief in this matter.
    Petitioner has not proven that
    it or its parent company,
    390,
    would be faced with economic
    hardship if required to comply with Section 214.141 (see pgs. 5—
    7). In addition, .Alton has failed to meet another necessary
    prerequisite to the granting of variance relief. That
    orerequisite
    is a commitment to the imposition of a compliance
    plan which ensures that compliance will be achieved by a date
    certain.
    For either reason the Board mu3t deny the relief
    requested.
    The Board does note that Altos has presen~eda great deal of
    modeling data, which Petitioner has provided for its own purpose
    of showing that the requested variance relief will not cause a
    violation of the SO2 NAAQS.
    Alton has also presented testimony
    regarding
    the “steam sales” and “notification” agreements it has
    entered into with LaClede. These agreements, from Pilton’s
    perspective, also serve the purpose of showing that the requested
    relief would not cause a violation of the NAAQS for SO2.
    Notwithstanding the volume of information presented on these
    points, the fact is that this evidence only meets the threshhold
    condition here, since under federal law the Board cannot grant a
    variance where a NAAQS violation would result. Even the mounds
    of modeling data presented by Petitioner cannot overcome the
    basic inadequacy of its case.
    That is, it has failed to show
    that it would suffer arbitrary or unreasonable hardship if
    required to comply with Section 214.141.
    However, Alton’s modeling data is quite relevant to the
    showing it must make in the ongoing proceeding in which it seeks
    an alternative standard for the ~lton Mill pursuant to Section
    214.201 (PCB 83—55). The Board’s determination in this matter is
    in no way premised on a belief that Altos’s modeling data is
    inaccurate or invalid. Moreover, the Board’s decision today does
    not indicate any predisposition in the pending PCB 83—55
    proceeding.
    This Opinion constitutes
    the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    The February 17, 1987, amended petition filed by Alton
    Packaging Corporation for variance from 35 Ill. Adrn. Code 214.141
    is hereby denied.
    Section 41 of the Environmental Protection Act, Ill. Rev.
    Stat. 1985 ch. 1111/2 par. 1041, provides for appeal of final
    86—30 1

    —14—
    Orders of the Board within 35 days. The Rules of the Supreme
    Court of Illinois establish filing requirements.
    IT IS SO ORDERED.
    Board Member J. Theodore Meyer concurred.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above ppiiion and Order was
    adopted on the ~Z
    day of
    ~
    ,
    1988, by a
    vote of
    7-
    p
    .
    Dorothy M. 9~nn, Clerk
    Illinois Pollution Control Board
    86—302

    Back to top