ILLIN)13 POLLtJTI3~’1 CONPROL BOARD
February 25, 1988
ALTON PACKAGI~IG CORP.,
Petitioner,
v.
)
PCB 83—49
ILLINOIS ENVIRONMENTAL
)
PROT~CTI3~A~GENCY,
Respondent.
MR. D~WI~LF. ~D’CON~LL ~PPE~RED O.~BEH~LLFOF PETITIONER, ALTO~
PACK~GI~1GCORPORATION;
MR. WILLIAM INGERSOLL PPE~RED ON BEHALF OF R~3PONDENT, ILLIN313
ENVIRONMENTAL PROTECTION AGENCY.
)PI~IOP~IAND ORDER OF THE BOARD (by R. C. Flemal):
This matter comes before the Board upon an amended petition
for variance filed by ~lton Packaging Corporation (“Altori”) on
February 17, 1987. Alton seeks variance from former Rule 204(f)
of Cha?ter 2 of the Boar~’sAir Pollution Rules and Regulations
(now codified as 35 Ill. Adm. Code 214.141) for sulfur dioxide
(SO2) emission3 emanatin~ from boilers 6 and 7 at its paoerboard
mill (“Alton Mill”) located in Alton, Illinois. Variance relief
is requested for a period of three years or until the Board
grants Alton site—specific relief from Section 214.141, whichever
occurs sooner.
For the reasons described below, the Board finds that Alton
has failed to make the requisite showing necessary for the
granting of variaric’? relief. The Board will therefore deny the
variance relief requested by Alton.
BAC
KGRO’:JND
Rule
204 was amended by the Board on February 24, l9~33. ~
new subsection (f) was added at that time which instituted a
sulfur dioxide emission limitation of 1.8 poun3s per million
British thermal units (“mmbtu”) of energy produced. Alton filed
its initial variance petition in this matter, along with a
concurrent petition seeking Board approval of an alternative
standard for the .Adton Mill pursuant to 35 Ill. Mm. Code
214.201, on April 13, 1983. Because Alton filed its variance
petition within 20 days of the effective date of Rule 204(f), it
received an automatic stay, pursuant to Section 38(b) of the
Environmental Protection Act (“Act”), of the emission limitation
pending disposition of its variance petition.
86—289
—2—
The Illinois Environmental Protection Agency (“Agency”)
filed Recomnendations on August 17, 1933, recom~ending that
Alton’s petitions for variance and site—specific relief be
denied.
The gency recom.riended denial due to its belief that
Alton’s air
disoersion modeling failed to show, “under all
foreseeable conditions”, that
~lton’s
requestad level of sulfur
dioxide emissions would not cause or contribute to a violation of
the Na:ional Ambient Air Quality Standard for sulfur dioxide.
After the filing of the Agency’s recommendations, Alton
worked with
the Agency in revising
its modeling study. On June
29, 1984, the Board, noting no activity in the case since August
1983, ordered a hearing to be held on Alton’s petitions within 60
days. On July 1, Alton filed a motion to extend the hearing date
until October 30, because the hearing officer assigned to the
case was unavailable for a hearing within the time set by the
Board. The Board granted Alton’s ~notion. hearing wa~
scheduled for October 25, but was rescheduled to December 7 by
the hearing officer.
At the December hearing, Alton presented the conclusions of
its revised modeling study through the testimony of its
consulting expert. At the end of the hearing, Adton stated it
intended to file within the next thirty days amended petitions
conforming with the testimor~y at the hearing. The Agency noted
that it already had Alton’s modeling results and would file an
amende~ recommendation within 30 days after receiving Alton’s
amended petitions. No amended petitions were ever filed.
In April of 1985, the Agency sent a letter to Alton asking
for clarification of a few technical matters. Alton forwarded
this letter to its consultant, but aooarently no response was
made. On July 19, l985,r the Agency moved to dismiss P.lton’s
petitions for failure tu prosecute th~matter with diligence. On
July 23, the hearing officer scheduled a hearing on Alton’s
petitions for Se~tember 18. On August 1, however, the Board
dismissed Alton’s case. The Board stated in its Order, after
noting no further activity in the case since the December
hearing, that Alton had had sufficient time to present its case
and should not be allowed to extend the automatic stay by filing
an amended petition. The hearing officer accordingly cancelled
the September 18 scheduled hearing. Alton filed a motion for
reconsideration on September 4, 1985, which the Board denied on
Seotember 20, 1985. Z~lton then apoealed the Board’s decision to
the Illinois Appellate Court, Fifth District.
The Fifth District Court found on Sertember 5, 1986, that
the Board erred in dismissing Alton’s petition without a hearing
and in refusing to reconsider its decision. The Court noted that
a dismissal for failure to prosecute is justified when the party
has been guilty of inexcusable delay in prosecuting the suit.
The Court found, however, that the record did not suoport a
86—290
—3—
finding of inexcusable delay on the part of Alton. The Court
consequently reversed
the Board’s August 1, 1985, decision
dismissing Alton’s petitions and remanded the matter back to the
Board for further proceedings. A new hearing was conducted on
January 15, 1987. An amended petition was filed by Alton on
February 17, 1987. Post hearing briefs from both lton an~the
Agency have also been received by the Board.
TdE ALPO:I F~CILETY
The Alton Mill is one of the larger paperboard mills in the
Midwest. It is located within the city limits of Alton,
Illinois, in Madison County on the Mississippi River immediately
below Alton Lock and Dam No. 26. The Alton Mill employs 60
salaried and 230 union employees.
The Alton Mill site is aporoximately 107 acres, and includes
several buildings comprising a little over 500,000 square feet.
The Alton Mill produces approximately 600 tons of paoerboard per
day and 200,000 tons per year. The paperboard is converted into
manufactu~ingproducts for use in corrugated shipping containers.
R. at 34.
The Alton Mill uses steam both for heating and in the
production of oaperboard. Alton owns five boilers which it can
use to produce steam. Of these, Alton regularly uses only
boilers 6 and 7. Id. These two boilers have adequate capacity
to orovide all the steam needed at the Alton Mill, and at the
same time, provide steam to LaClede Steel Company (“LaClede”)
pursuant to an agreement between the two companies (see pgs. 8—
9).
Boilers 8 and 9 are only used when the main boilers (i.e.
boilers 6 and 7) are unable to operate at their normal
capacity. In such a situation, boilers 8 and 9 are normally
operated on natural gas, but can be operated on oil. Boiler 5
has not been fired in years, but can be fired on an emergency
basis. R. at 34—35.
1 References made to the transcript of the January 15, 1987,
hearing in this matter will be cited as “R. at
______
86—29 1
—4—
The capacity of the five boilers is as follows:
Boiler #
Heat Input BTU/hrs.
Fuel Used
5
114 mmbtu
Gas
125 mmbtu
Oil
6
171 mmbtu
Coal
173 mmbtu
Gas
178 mmbtu
Oil
7
445 mmbtu
Coal
444 mmbtu
Gas
464 mmbtu
Oil
8
182 mrnbtu
Gas
175 mmbtu
Oil
9
182 mmbtu
Gas
175 mmbtu
Oil
R. at 35.
Boilers 6 and 7 are the subject of Alton’s Petition for
Variance. Notwithstanding their rated caoacity, the boilers are
not operated above 138.5 mmbtu per hour for boiler 6 and 365.5
mmbtu per hour for boiler 7, for a combined maximum firing rate
of 504 mmbtu per hour. R at 35. Boilers 6 and 7 are pulverized,
wet bottom boilers. Coal is ground into a fine powder in five
pulverizers and then blown into the boilers. The coal is burned
in the boilers, producing heat; the heat, in turn, is used to
produce steam for heating and process use. The exhaust from each
boiler passes through a mechanical collector known as a “multi—
clone” and then through an electro—static precipitator. These
particulate control devices have a combined collection efficiency
of approximately 99. The boilers vent through separate stacks
which are 54 feet above the Mill roof and 192 feet above grade.
R. at 35—36. The Alton Mill is not equipped with any add—on
control devices to reduce sulfur dioxide emissions. R. at 36.
RELIEF REQUESTED
Alton requests that the Board grant it variance from Section
214.141 for three years or until the Board grants it site—
specific relief from the same section, whichever occurs first.
Alton is willing to limit the scope of this relief by complying
with a number of conditions. Specifically, these conditions are
that:
86—292
—,.)—
(1) Alton will operate boilers 6 and 7 using coal
with a maximum average 902 emission rate of 5
lbs per mmbtu;
(2) Alton will limit its firing rate to 138.5 mmbtu
per hour for boiler 6 and 365.5 mmbtu per hour
for boiler 7;
(3) Alton will not operate its boilers 5, 8 and 9 on
oil unless it limits its operation of boilers 6
and 7 to the use of coal with a maximum average
SO2 emission rate of 1.8 lbs per mmbtu; and
(4) Alton will increase the height of the stacks
from boilers 6 and
7 to 234 feet above grade.
The suggested compliance conditions would not inhibit
Alton’s ability to maintain its operations at present levels, and
in fact seem to provide some flexibility
for Alton to exoand
operations.
More specifically,
Alton proposes (oursuant to
condition 1, above) to operate its boilers 6 and 7 solely on coal
having
a maximum average SO2 emission rate of
5 lbs per mmbtu.
Based on a weighted average, the Alton Mill’s 302 emission rate
for 1985 was 4.43 lbs per mmbtu.
R. at 37.
A similar degree of leeway appears
to exist in the requested
condition pertaining to the firing rates of the two boilers.
Under condition 2 (above), Alton proposes to limit the firing
rate of boilers 6 and 7 to 138.5 mmbtu per hour and 365.5 mmbtu
per hour, respectively.
The ~gency contends such a level of
operation would be approximately 24 greater than the level
anticipated for 1987, and the latter assumes an aooroximate 45
increase in the amount of coal burned over 1986 levels.
Agency
Post—searing Brief, o. 6.
ECONOMIC HARDSHIP
Alton states that in order to comply with the 1.8 lbs/mmbtu
limitation,
it would have to purchase low—sulfur coal from out—
of—state sources. R. at 48—49. At time of hearing, Petitioner
indicated its belief that it cou1~ purchase such coal for $37.80
per ton, which Alton states is $9.80 to $12.50 more per ton than
it pays for the coal it currently uses.
R. at 49. Alton
calculates that for 1987 coal purchases, this manner of complying
with the 1.8 lbs/mbtu standard woul~ cost the company an
additional $1.43 million to $1.82 million.
Id. Petitioner
argues that this cost would be economically unreasonable, and
warns that the profitability
of its Alton facility would be
seriously jeooardized if it were forced to increase its operating
costs in this manner.
Alton’s Post—Hearing Brief, p. 22.
According to Petitioner,
“(t)he Comoany’s management would be
86— 293
forced to reconsider the continued economic viability of the
(Alton) Mill”. Id.
The bur3en of proof in a variance proceeding is on the
petitioner (see Ill. Rev. Stat. 1985, ch. lll~-/2, par. 1037(a)),
and the Board concludes that in this instance Petitioner has
failed to adequately demonstrate that denial of the requested
relief woul~ impose an arbitrary or unreasonable hardshio upon
Alton.
Alton has failed to make the requisite showing in several
respects. First, Alton’s projected $1.43 million to $1.82
million increase in annual operating costs (predicted to come
about because of a need to purchase low—sulfur coal from out—of—
state) is subject to some dispute.
These figures were calculated
from a per ton price of $37.80. The Agency questions the manner
in which that figure was determined, as IL is the result of a
“spread sheet check on prices in various mines” (R. at 59), but
is apparently not the result of a bidding process. Agency Post—
Hearing Brief, pgs. 6—7. Competitive bidding might very well
reduce the price per ton of this coal, thereby reducing the
overall cost of compliance and impacting the question of whether
unreasonable economic hardshio exists.
Second, Alton has presented no data concerning the cost(s)
of utilizing any other compliance option(s). The Board is aware
from its past rulemakings that other technologies exist for
sulfur dioxide control. These include lime or limestone
injection into the furnace with the pulverized coal, fluidized
bed furnaces, and wet
arid
dry stack gas scrubbers. Alton
presents no information whatsoever regarding any of these
possible alternatives. It is not clear whether Altori han
investigated any alternative control technologies, or whether
utilizing low—sulfur coal would in fact even be the most
economical way for Petitioner to comply with the 1.8
lbs/nimbtu
limitation. Similarly, Alton has made no mention of whether it
has considered alternative energy sources to coal that might be
used for the production of steam.
In this context it is to be
noted that the boilers
in question
are capable of operating on
fuel other than coal.
Finally, Alton has not shown the impact that
a $1.43 million
to $1.82 million increase in annual operating expenditures would
have on Jefferson Smurfit Corporation (“J3C”). Alton is wholly
owned by JSC, yet Petitioner has not addressed the question of
whether an increase in costs of the magnitude discussed would
constitute unreasonable economic hardship to JSC. Alton contends
that the viability of a JSC plant (of which the Alton Mill is
one) is evaluated by the corporate parent on the basis of that
plant’s individual orofitability, and so for that reason argues
that the projected increase in operating costs should be
evaluated in light of the Alton Mill’s $3.5 million profit in
86—294
—7—
1986. Alton’s Post—Hearing Brief, p. 23; R. at 63. As an
illustration
of the JSC philosophy, an Alton witness testified
that “(o)nly if (the plant) can show a return do(es) (the plant)
receive caoital funds for improvement”.
R. at 61.
That JSC evaluates each of its plants as individual profit
centers is well and good, but that is not relevant to the issue
of whether the Board should look in this instance solely to Alton
or JSC to determine the true cost of compliance with Section
214.141. In fact, that the JSC
plants compete with each other
for capital improvement funds is telling, but for a different
reason than that envisioned by Alton. As JSC seemingly views the
Alton Mill in identical fashion to the way it views its other
plants, and given that $10 million in capital improvement funds
is presently committed by JSC to the ~‘\ltonMill (R. at 63), it is
apparent that Alton does not operate in a manner thoroughly
independent from JSC. On the contrary, Alton more readily
appears to function as an arm of JSC. This is further
exemplified by the fact that at least some percentage of the
Alton Mill’s output is utilized by JSC for production within the
latter’s Container Division.
Exhibit 1, o. 6. JSC is the entity
against which the projected increase in operating costs must also
be evaluate~, but Alton did not provide the information which
would have made such an analysis possible.
ENVIRONMENTAL IMPACT
Alton presented the findings of two modeling studies, both
undertaken by contractors hired by Petitioner, in support of its
contention that ambient air quality will be protected during the
term of the requested variance.
Ronald L. Petersen of Cermak/Peterka arid Associates, Inc.
testified at hearing regarding the fluid modeling study that
company performed for Alton.
This study was done to demonstrate
that the increase in height Alton proposes for the stacks of its
boilers 6 and 7 (from the existing 192 feet to 234 feet) is
necessary in order to avoid “excessive concentrations” of SO2 due
to downwash effects. Such a demonstration must be made before a
facility may receive credit in its air dispersion modeling for
certain stack height increases. R. at 21—22.
Federal regulations define “excessive concentrations” as
those occurring where maximum ground level concentrations are 40
higher because of downwash effects caused by nearby structures
than the concentration would be with these effects removed, and
those maximum ground level concentrations are in excess of
National Ambient Air Quality Standard (“NAAQS”). R at 22. The
modeling study showed that both conditions are satisfied in this
instance. That is,
at the operating parameters requested by
Alton (SO2 emission rate of 5 lbs/mmbtu and operating rates of
86—295
—8—
138.5 and 365.5 mmbtu per hour for boilers 6 and 7,
respectively), the maximum hourly groun~ level concentrations
would be 40 higher because
o~ the structures presen~, and these
concentrations would be expectel to exceed the NAAQS
.
R. at 25—
27.
John Paul Bradley of Murray and Trettel,
Inc. presented
testimony on the air dispersion modeling study completed by that
company for lton. The study consists of two components. The
first involved an analysis of what operating parameters at the
Alton Mill would assure maintenance of the N.AAQS for SO2 after
the planned increase in stack height, without reliance on
LaClede’s reduced SO2 emissions pursuant t the steam
agreement. R. at 75—76. The second component addressed the
questions of what combination of operating parameters and other
arrangements would ensure that the NAAQS for SO2 would be
maintained prior to the completion of the stack height
increase. R. at 76.
The modeling used a grid of 79 receptors, arranged on a
roughly rectangular grid. R. at 83. Receptors were located in
areas expected to receive the most significant impact, and in
areas of expected interaction between Alton and other modeled
sources. Id.
All 79 receptors were modeled using 1973 meteorological
data. R. at 86. Seven receptors showed second highest
concen~rations exceeding 85 of the 365 microgram per cubic meter
(“ug/m
“)
24—hour standard. Id. These seven receptors were then
modeled using 1974—1977 meteorological data. The highest s~cond
highest concentration re~orded by a receptor was 358.6 ug/m3.
Id.; Alton Gr•ouo Exhibit 5(h). The modeling therefore
demonstrated no modeled violations of 35 Ill. Adm. Code 243.122
(Sulfur Oxides). Based on these results, Mr. Bradley opined that
at the operating parameters requested by Alton, emissions from
the Alto-i Mill boilers will not result in any violations of the
SO2 NAAQS. R. at 87.
The second component of the air dispersion mo9eling
consisted of an analysis of how Alton might provide for th~
maintenance of ambient air quality during the period prior to
accomplishment of the stack height increase. The modeling done
for this question showed that no violations of the NA~Q3for 302
2 In fact, Dr. Petersen testified that even if the SO2 emission
rate was 1.8 lbs/mmbtu, the fluid modeling study predicted that
the NAAQS for SD2 would be violated.
3 Hereinafter references to Alton’s Exhibits will appear as
“Alton Ex.
86—296
—9—
would occur as a result of Alton’s emissions during this interim
ocriod, orovided that Petitioner operates within the parameters
it requests and LaClede complies with the provisions of the
agreements reached between Alton and itself. R. at 91—92. A
description of these agreements is appropriate this time.
An agreement involving the sale of steam from Alton to
LaClede was entered into by those two entities in 1984. Alton
Ex. 4(a); R. at 42. Under the terms of the contract, steam is
provided via a line constructed from the Alton Mill to LaClede.
The steam is sold at an agreed once, and is used by LaClele in
its operations. As a consequence of the contract, LaClede has
not operate5 its steam boilers 1 and 2 for the last few years.
Id. The contract provides that it can only be terminated after
six months written notice (Amended Petition for Variance,
0.
10)
and will exoire in 1989 (R. at 43).
Altori’s air dispersion modeling predicted violations of the
NAAQS for SO2 prior to the stack height increase if Alton
operates within its requested oarameters and LaClede operates its
boiler 2 at its maximum permitted level using oil. R. at 88—
89. Alton is therefore relying, in making its case, on LaClede
to adhere to the terms of the steam sales agreement and
consequently riot operate its boilers. Alton asserts that LaClede
and itself will “almost undoubtedly maintain this agreement
throughout the period of the variance prior to Alton raising its
stacks (because)
...
the economies for both parties will provide
a strong incentive to maintain the arrangement”. R. at 43.
Alton has also entered into a “notification” agreement with
LaClede for the purpose of allowing Alton to avoid violations of
the SO2 NAAQS should LaClede decide to operate its process
sources on oil. Under the terms of the agreement, LaClede would
provide Alton written notification seven days prior to operating
in this manner. LaClede’s process sources are presently operated
on natural gas, but are permitted to operate on oil.
Alton has stated that it would accept the following
operating restrictions as conditions to the granting of the
shouldrequestedanyvariance,of the followingin
order
scenariosto
preventarise.NAAQS
violationsThese
conditionsof
SO2
would apply to the period prior to the completion of the stack
height increase. Alton’s modeling predicts that in the following
situations, Petitioner could operate at the stated levels and not
cause 302 violations:
86— 297
—to—
AllowableEmissions302
EmissionCoal
SO2Rate
Firing Rate
(lbs/hr)
(lbs/mmbtu)
(mmbtu/hr)
Scenar io
Status Quo
2,520
5
Boiler 6: 138.5
(steam contract
or 1.8 if
Boiler 7: 365.5
is observed and
Boilers
Total: 504.0
LaClede operated
5, 8 and 9
its process sources
are operated
on natural gas)
using oil
LaClede operates
2,403
5
Boiler 6: 137.0
Boilers 1 and 2
Boiler 7: 361.6
on oil and pro—
Total:
499
cess sources on
natural gas
Steam Contract
1,049
5
Boiler 6: 112.6
continues, but
Boiler 7: 297.0
LaClede operates
Total: 409.6
its process
sources on oil
LaCle3e operates
1,925
5
Boiler 6: 105.8
Boilers 1 or 2
Boiler 7: 279.2
and process
Total: 385.0
sources on oil
COMPLIANCE PLAN
It is axiomatic that a variance does not grant permanent
relief from compliance with a regulatory requirement. One
necessary aspect of a variance petition is that it describe how
and when a facility will come into compliance. This concept is
articulated at 35 Iii. Adm. Code 104.121(f):
A detailed description of the existing and proposed
undertakenequipment
orto proposedachieve methodfull
complianceof
controlwithto
theb2 Act
arid regulations, including a time schedule for
implementation of all phases of the control program
from initiation of design to program completion and
the estimated costs involved for each phase and the
total cost to achieve compliance.
Alton has not presented a compliance plan in the proper
sense of that term.
Alton has offered no plan under which the
boilers at the Alton Mill would ever be brought into compliance
with the Act and regulations. Rather, Alton requests a three—
86—298
—11—
year variance so that it may pursue permanent relief from the 1.8
lbs/mmbtu standard of Section 2l4.lfl. by attempting to secure,
pursuant to 35 Ill. Adm. Code 214.201, an alternative standard
for the Alton Mill.
Moreover, Alton’s Amended Petition for
Variance does not include a commitment from Petitioner that it
will bring the Alton Mill into compliance by a date certain
should the Board
deny Alton the relief it requests under Section
214.201.
The absence of a compliance plan in this matter is one of
the factors
upon which the Agency bases
its recommendation that
variance relief be denied Petitioner. The Agency opines that
“(p)ursuit of a site—specific limitation is not a compliance plan
to support a variance petition”. Agency Post—Hearing Brief, p.
11. Conversely, Alton contends that Citizens Utilities Co. v.
Pollution Control Board, 152 Ill. Acm. 3d 122 (3rd Dist. 1997),
is controlling and cites it for the proposition that it is
reversible error for the Board to refuse to grant a variance,
pending resolution of an ongoing related rulemaking proceeding,
if granting the variance would prevent the expenditure of what
might
become needless compliance costs.
The Board finds that Citizens Utilities is readily
distinguishable from the matter at hand. ~itizens Utilities
concernel an ongoing rulemaking in which the Agency was proposing
amendments to rules which, if promulgated, would arguably have
negated the need for that petitioner or for any other similarly
located entities to undertake any compliance effort. In the
instant matter, the “ongoing rulemaking”, PCB 83—55, is a
creation of Petitioner itself, and consists entirely of a
proposal which would remove Petitioner alone from the need to
comply with existing regulations. The Board does not believe
that such actions on the part of a petitioner can or should be
allowed to serve the end of avoiding compliance or deflecting
enforcement.
Moreover, the Board believes that it
has never been
the
intent of the General Assembly to require the granting of
variance whenever a regulatory standard is under review. tn
support thereof, the Board looks to the action of the General
Assembly in its most recent general session. There the Illinois
House passed by a vote of 114—1 and the Illinois Senate passed by
a vote of 37—7 the following amendment to Section 35(a) of the
Act:
(a) The Board may grant individual variances beyond
the limitations prescribed in this Act, whenever it
is found upon presentation of adequate proof, that
compliance with any rule or regulation, requirement
or order of the Boarl would impose an arbitrary or
unreasonable hardship. However, the Board is not
required to find that an arbitrary or unreasonable
86—299
—12—
hardship exists exclusively because the regulatory
standard is under review and the costs of compliance
are substantial and certain...
The omnibus bill containing this amendment also contained
certain provisions totally unrelated to the amendment.
Controversial provisions regarding landfill fee caps were added
to the bill in a conference committee report by a vote of 91—31
in the House and 35—20 in the Senate. The Governor then
amendatorily vetoed the bill regarding the fee cap and other
provisions having to do with the Solid waste Management Act, all
of which was unrelated to the amendnent of concern in the instant
case. Although the total bill failed to gain passage during the
following veto session of the General Assembly, the Board
believes that the strong vote of both Houses of the original bill
containing the amendment and the absence of the Governor’s veto
of the particular provision in question stands as a public record
of legislative intent to not require granting of variances
whenever there is review of an underlying regulation.
The Illinois Supreme Court recently addressed a similar
interpretation of legislative action in Central Illinois Public
Service Company v. Illinois Pollution Control Board, 116 Ill.2d
397, 507 N.E. 2d 819
,
in which it noted:
Subsequent enactments may be used to help determine
the legislature’s original intent (In re Marriage of
Semmler (1995), 137 Ill. 2d 130, 137), particularly
where the amendment is enacted shortly after the
interpretation of the statute it amends comes into
dispute (People v. Rink (1983), 97 Ill. 2d 533,540—
541). This amendment is additional evidence that the
legislature did not intend to do away with site—
specific rulemaking pursuant to section 27 when it
originally enacted section 28.1.
The Board therefore finds that it is not now, nor has it
been, the legislative intent of the variance process in Illinois
to require granting of variances for the reasons here advocated
by Alton. Moreover, the Board affirms that pursuit of a site—
soecific limitation does not of itself constitute a compliance
plan sufficient to meet the requirements for granting of a
variance. See
Modine
Manufacturing v. I~PA, PCB 71—112, August
18, 1982; Modine Manufacturing v. IEPA, PCB 85—59, May 16, 1985;
City of Mendota v. IEPA, PCB 85—182, July 11, 1986; Borden
Chemical v. IEPA, PCB 82—82, December 5, 1985; Schro~k7~E~appan
Division v. I~PA,PC~385—205, March 5, 1997.
86—300
—13—
CONCLUSION
The Board finds that Alton has not persuasively shown that
it would sffer arbitrary or unreaso~ab1e har ship if denied
variance relief in this matter.
Petitioner has not proven that
it or its parent company,
390,
would be faced with economic
hardship if required to comply with Section 214.141 (see pgs. 5—
7). In addition, .Alton has failed to meet another necessary
prerequisite to the granting of variance relief. That
orerequisite
is a commitment to the imposition of a compliance
plan which ensures that compliance will be achieved by a date
certain.
For either reason the Board mu3t deny the relief
requested.
The Board does note that Altos has presen~eda great deal of
modeling data, which Petitioner has provided for its own purpose
of showing that the requested variance relief will not cause a
violation of the SO2 NAAQS.
Alton has also presented testimony
regarding
the “steam sales” and “notification” agreements it has
entered into with LaClede. These agreements, from Pilton’s
perspective, also serve the purpose of showing that the requested
relief would not cause a violation of the NAAQS for SO2.
Notwithstanding the volume of information presented on these
points, the fact is that this evidence only meets the threshhold
condition here, since under federal law the Board cannot grant a
variance where a NAAQS violation would result. Even the mounds
of modeling data presented by Petitioner cannot overcome the
basic inadequacy of its case.
That is, it has failed to show
that it would suffer arbitrary or unreasonable hardship if
required to comply with Section 214.141.
However, Alton’s modeling data is quite relevant to the
showing it must make in the ongoing proceeding in which it seeks
an alternative standard for the ~lton Mill pursuant to Section
214.201 (PCB 83—55). The Board’s determination in this matter is
in no way premised on a belief that Altos’s modeling data is
inaccurate or invalid. Moreover, the Board’s decision today does
not indicate any predisposition in the pending PCB 83—55
proceeding.
This Opinion constitutes
the Board’s findings of fact and
conclusions of law in this matter.
ORDER
The February 17, 1987, amended petition filed by Alton
Packaging Corporation for variance from 35 Ill. Adrn. Code 214.141
is hereby denied.
Section 41 of the Environmental Protection Act, Ill. Rev.
Stat. 1985 ch. 1111/2 par. 1041, provides for appeal of final
86—30 1
—14—
Orders of the Board within 35 days. The Rules of the Supreme
Court of Illinois establish filing requirements.
IT IS SO ORDERED.
Board Member J. Theodore Meyer concurred.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the above ppiiion and Order was
adopted on the ~Z
day of
~
,
1988, by a
vote of
7-
p
.
Dorothy M. 9~nn, Clerk
Illinois Pollution Control Board
86—302