ILLINOIS POLLUTION CONTROL BOARD
    August 18, 1988
    NEW JERSEY ZINC COMPANY,
    )
    Petitioner,
    v.
    )
    PCB 88—130
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    Respondent.
    ORDER OF THE BOARD (by B. Forcade):
    On August 18, 1988, New Jersey Zinc Company filed a plan for
    compliance and request for extension of variance. The Board must
    treat these documents as a new petition for variance. That
    petition is deficient in that it:
    1. fails to specifically request or waive a
    hearing in this matter, as required by 35
    Ill. Adm. Code 104.124. If hearing is
    waived, an affidavit in support of the
    facts alleged in the petition is
    required; and
    2. fails to specify with sufficient clarity
    the exact timeframes required for
    completion of the IRM upstream trench
    lining, 1PM slurry wall construction, and
    IRM collection sump, and how these
    interim dates relate to the requested
    final compliance date of November 30,
    1993.
    Unless an amended petition is filed within 45 days of the
    date of this Order, curing the above—noted defect, this matter
    will be subject to dismissal.
    IT IS SO ORDERED
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Order was adopted on
    the
    /,F~
    day of ~
    ,
    1988, by a vote
    of~-~.
    CI
    ~
    Dorothy M. ~inn, Clerk
    Illinois Pollution Control Board
    91—391

    Back to top