ILLINOIS POLLUTION CONTROL BOARD
    January
    19,
    1989
    NEW JERSEY ZINC COMPANY,
    Petitioner,
    v.
    )
    PCB 88—130
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Resoondent.
    JAMES
    F.
    ALLEN,
    ESQ.,
    OF SQUIRES,
    SANDERS
    AND DEMPSEY,
    COLUMBUS,
    OHIO,
    APPEARED ON BEHALF OF THE PETITIONER.
    THOMAS DAVIS,
    ESQ.,
    APPEARED ON BEHALF
    OF THE RESPONDENT.
    OPINION AND ORDER OF THE BOARD
    (by M.
    Nardulli):
    This matter comes before
    the Boar~ on
    a August
    18,
    1988
    Request
    for Extension
    for Variance filed
    on behalf of the New
    Jersey Zinc Company (hereinafter “NJZ”).
    In an order dated
    August
    18,
    1988,
    the Board informed the Petitioner
    that the
    matter must be treated
    as
    a new petition
    for variance.
    In
    response, the Petitioner
    filed
    a Petition
    for Variance on August
    31,
    1988.
    On October
    12,
    1988,
    the Illinois
    Environmental
    Protection Agency (hereinafter ~Agency~)
    filed
    a recommendation
    that variance
    be granted.
    Hearing was held on
    this matter
    on
    October 28,
    1988
    in Princeton, Bureau County.
    The Board hereby
    grants the requested variance subject
    to conditions.
    BACKGROUND
    The NJZ plant,
    located at Dc
    Pue,
    Bureau County,
    is engaged
    in the manufacture of zinc dust
    for the coatings industry.
    In
    a
    predominately agricultural
    area,
    it employs approximately 26
    people.
    In previous years, NJZ’s processing and manufacturing
    activities generated
    residues from
    zinc
    smelting, and lithopone
    waste
    from pigment production.
    These waste materials, which are
    not produced by current operations, were placed
    on
    a field
    at the
    plant
    site.
    The zinc smelting residues were deposited
    in one
    pile at the southern end
    of
    the property, known
    as the “cinder
    bank.”
    North of this pile, lithopone
    residues were collected
    in
    five ridges.
    At one time,
    an open ditch surrounded
    the cinder
    bank.
    Runoff from the cinder bank and
    lithopone piles drained
    into the ditch,
    which
    then flowed
    in
    a generally southerly
    direction into
    a storm drain
    for Marquette Street.
    The
    groundwater table
    for this area
    is high,
    and
    in
    times of heavy
    95—305

    —2—
    rainfall, groundwater
    would seep
    into
    the ditch, and combine with
    land runoff.
    The Marquette Street drain carried
    the runoff
    to
    Lake DePue,
    a shallow oxbow lake created
    by the changing course
    of the Illinois River.
    Lake DePue
    is
    in equilibrium with the
    Illinois River,
    rising and falling as the river
    level varies.
    In March of
    1978,
    the State of Illinois commenced
    a civil
    action against NJZ
    in
    Bureau County,
    Illinois Circuit Court.
    (People of
    the State of Illinois
    v.
    Gulf
    & Western Industries and
    the New Jersey Zinc
    Co., Case
    No. 78-CH—4).
    The Agency asserted
    that water conveyed by the open ditch contained levels of metals
    in excess of the contaminant levels
    in
    35
    111. Mm.
    Code 304.124
    (or Rule 408,
    as
    it was then identified).
    The Agency sought
    injunctive relief that would require NJZ
    to take action
    to reduce
    the metals contained
    in
    the ditch water.
    The action was resolved
    by entry of
    a Consent Order and Agreement on October
    30,
    1981.
    This Order
    directed NJZ
    to make certain physical
    changes
    to
    reduce
    the amount of metals picked up by stormwater runoff and
    to
    convey that stormwater runoff
    in
    a manner
    so as to isolate
    it
    from groundwater
    seepage.
    The remedial measures
    required under
    the Court
    Order were completed by August
    1985,
    to the Agency’s
    satisfaction.
    The Agency subsequently approved the construction
    and released $200,000
    of
    a
    $225,000 performance bond.
    The
    remaining $25,000 was released at the expiration of the Consent
    Order
    on October
    30,
    1986.
    Pursuant
    to the
    terms of
    the Consent Order, and subsequent
    federal regulations
    found
    at
    40 CFR Section 122.26, NJZ
    is
    required
    to secure an NPDES permit.
    The present NPDES permit
    places effluent limits on
    the discharge of certain parameters.
    NJZ’s variance petition requests relief from six
    of those
    parameters.
    All Concent1rations
    in mg/i
    Current Limits
    Requested Limits
    Parameter
    30—Day Average
    &
    Daily Max.
    30—Day Average
    &
    Daily Max
    cadium
    0.15
    0.3
    0.3
    1.0
    copper
    0.5
    1.0
    2.0
    4.0
    iron
    2.0
    4.0
    3.0
    6.0
    manganese
    1.0
    2.0
    5.0
    10.0
    TSS
    15
    30
    150
    zinc
    1.0
    2.0
    25
    50
    NJZ requests that
    it
    be allowed
    to subtract the upsteam
    concentration of any parameter
    in determining
    its effluent
    values.
    In
    the Opinion and Order
    in PCB 86—187,
    the Board granted
    NJZ
    a variance until November
    30,
    1988
    at which time NJZ was
    to
    submit
    a plan
    for ultimate compliance
    with
    the Agency.
    The
    1.
    These values are directly from 35 Ill. Mm. Code 304.124(a).
    and
    the
    Averaging rule at
    35 Ill. Mm. Code 304.104(a).
    95—306

    —3—
    petition
    for
    variance
    includes
    the
    Petitioner’s
    compliance
    plan.
    PETITIONERtS
    COMPLIANCE
    PLAN
    In
    the
    compliance
    plan,
    NJZ
    proposes
    the
    use
    of
    “iron-rich
    material”
    (hereinafter
    “IRM”)
    as
    a
    medium
    for
    control
    of
    heavy
    metals
    in
    the
    seepage
    and
    runoff.
    The
    IRM
    is
    a
    granular,
    porous
    product
    with
    high
    internal
    surface
    area
    of
    up
    to
    10
    square
    meters
    per
    gram.
    The natural basicity of this material
    (9.0—10.5)
    is
    ideally
    suited
    to
    the precipitation of heavy metals from aqueous
    systems
    and
    the
    high
    internal
    porosity
    acts
    to
    capture
    the
    precipitated
    hydroxides
    and
    hold
    them within
    the matrix.
    In
    the
    August
    18,
    1988
    filing,
    of
    the Petition
    for Extension
    of
    Variance,
    NJZ
    stated
    that
    it
    had
    successfully employed
    this
    control
    system
    at
    another
    plant
    and offered
    the following
    explanation
    of
    the
    compliance
    plan.
    As
    part
    of
    its
    compliance
    plan,
    the
    company
    proposes
    to
    line
    the
    trench
    upstream
    of
    the
    cinder
    bank
    with
    a
    layer
    of iron—rich
    material.
    This trench has been observed
    to have
    a number
    of sub—
    surfac2 seeps
    from the high ground water
    table.
    By forcing
    these
    seeps
    to percolate
    through
    a layer of
    IRM,
    the contained heavy
    metals should
    be precipitated
    and absorbed.
    The IRM material
    will
    be held
    in place by
    a layer
    of six—inch crushed stone,
    allowing
    for
    flow of all surface
    water
    from the surrounding
    prope r t
    y.
    A second phase
    of the project
    will
    be
    to install
    a “slurry
    wall”
    of
    IRM between
    the cinder bank and the storm water
    sewer.
    This IRM barrier
    should act
    to
    intercept heavy metals which would
    migrate
    toward the storm sewer and toward Lake DePue.
    The Company also proposes
    to obtain
    the necessary permission
    to replace broken sewer lines beneath Marquette Street to
    install
    an
    IRM—lined collection sump at the south
    end of Marquette Street
    where there
    is some evidence of heavy metal migration through
    hydrosta tic pressure.
    In addition
    to this work,
    the Company proposes
    to
    perform
    annual
    water
    quality
    surveys
    in
    Lake DePue
    and
    will
    provide
    regular
    monitoring
    of water quality at
    its Site
    III sample
    point.
    To allow for completion
    of
    the proposed
    improvements and
    a
    meaningful
    evaluation
    of
    results thereafter, the Company will
    require
    a
    variance
    through November
    30,
    1993.
    NJZ has committed
    to implementing
    the compliance plan
    in
    accordance with
    the following schedule:
    a.
    Begin to construct
    IRM upstream trench
    lining
    outlined
    in
    the
    compliance
    plan
    by
    April
    30,
    1989.
    Construction
    would
    95—307

    —4—
    commence
    in
    the
    spring
    construction
    season
    immediately
    following
    the
    Board’s
    grant
    of
    a
    variance.
    b.
    Complete
    construction
    of
    IRM
    upstream
    trench
    lining
    by
    August
    31,
    1989.
    c.
    Complete
    construction
    of
    IRM
    slurry
    wall
    by
    August
    30,
    1990.
    d.
    Complete construction of the
    IRM
    collection sump by April
    30,
    1991.
    e.
    Submit
    an
    interim
    report
    evaluating
    the
    effectiveness
    of
    the
    compliance
    plan
    by
    November
    30,
    1992.
    f.
    Submit
    a
    final
    report
    evaluating
    the
    effectiveness of the compliance plan by
    November
    30,
    1993.
    After construction
    of
    the improvements by April
    30,
    1991,
    their effect on effluent concentrations must be analyzed.
    NJZ
    proposes
    to collect one year~sworth of effluent data
    (from April
    1991 through April
    1992)
    to aid
    in this analysis.
    The results
    of
    lake water quality sampling performed
    in April
    of
    1992 will
    also
    be examined
    to prelimii~arilyassess the effect of
    the
    improvements.
    The proposed schedule provides
    for seven months
    to
    compile
    the data,
    prepare
    a
    report,
    and
    review
    the
    result
    with
    Illinois
    EPA,
    by November
    of
    1992.
    The company believes that
    an
    additional
    year
    of
    evaluation
    (November
    1992
    through
    November
    1993)
    is required
    to determine
    the
    longer—term
    effecti~’eness
    of
    the
    improvements.
    In addition
    to
    the improvements, NJZ proposes
    to conduct
    annual
    studies
    of
    Lake DePue during
    the project construction and
    evaluation period:
    a.
    Perform annual water quality sampling
    at
    Lake
    DePue
    in
    1989 through
    1993
    in
    April
    or May of each year.
    b.
    By September
    30 each year,
    1989 through
    1993,
    submit
    results
    of water quality
    sampling
    and
    report
    to
    Illinois
    EPA.
    HARDSHIP AND ENVIRONMENTAL IMPACT
    In
    its petition for variance, NJZ
    fails
    to present
    an
    argument
    that
    compliance
    with
    Section
    304.124 during
    the
    requested variance would result
    in
    an arbitrary
    or unreasonable
    95—308

    —5—
    hardship.
    However,
    based
    on
    the
    record, there
    is
    no apparent way
    for
    NJZ
    to
    come
    into
    compliance
    during
    the
    requested
    compliance
    period.
    Contrasting with the issue
    of hardship is
    the
    issue of
    environmental impact.
    Both the Agency and NJZ believe
    that the
    risk of environmental harm
    is minimal
    at present levels of
    discharge.
    The
    Agency
    states
    that
    the
    impact
    of
    discharges
    on
    Lake
    DePue
    and
    the
    Illinois
    River
    has
    shown
    improvement
    since
    the
    Petitioner
    implemented
    remedial
    efforts.
    The
    Agency
    did
    express
    concern about water quality in
    the
    lake and
    in
    the groundwater
    as
    well
    as concern
    for the effect of the metals upon
    fish and
    wildlife.
    However,
    the Agency concluded
    that there was no
    apparent threat
    to public health because of the present
    discharge.
    NJZ’s
    timely
    compliance
    with
    35
    Ill.
    Mm.
    Code
    304.124 should significantly reduce
    the risk
    to the environment.
    AGENCY RECOMMENDATION
    In
    its recommendation of October
    12,
    1988,
    the Agency stated
    that
    it would recommend
    that the variance request be granted
    and
    that the interim effluent
    limitations continue
    in effect
    if
    concerns about
    the possible hazardous nature of
    IRM can be
    reduced.
    In response, NJZ filed information
    regarding the non—
    hazardous
    status of IRM with
    the Board
    on October
    25,
    1988.
    Further, NJZ addressed
    the
    issue of
    the non—hazardous nature of
    IRM at hearing.
    After receiving the materials submitted
    and the
    additional
    testimony,
    the Agency recommended
    that
    the
    variance
    be
    granted.
    (R.
    71).
    CONCLUSION
    The Board
    finds
    that compliance with
    the regulations would
    result
    in an arbitrary or
    unreasonable hardship on NJZ.
    Accordingly,
    the variance will
    be granted
    with conditions
    consistent with
    this Opinion.
    This Opinion constitutes
    the Board’s findings of
    fact and
    conclusions
    of law
    in this matter.
    ORDER
    New Jersey Zinc Company
    is hereby granted
    a variance from
    35
    Ill. Mm.
    Code 304.124(a), as
    it pertains
    to cadmium,
    copper,
    iron, manganese,
    zinc, and
    total
    suspended solids, subject
    to the
    following
    conditions:
    1.
    This variance will
    expire November
    30,
    1993.
    2.
    During
    the
    term
    of
    this
    variance,
    the
    95—309

    —6—
    following
    interim
    limits
    shall
    apply
    to
    New Jersey Zinc’s discharge:
    Parameter
    30—Day
    Av.
    Daily
    Max.
    cadmium
    0.5
    1.0
    copper
    2.0
    4.0
    iron
    3.0
    6.0
    manganese
    5.0
    10.0
    TSS
    75
    150
    zinc
    25
    50
    3.
    Sampling
    and analysis of effluent
    parameters
    shall
    be
    in accordance with New
    Jersey Zinc’s NPDES permit.
    However,
    in
    determining whether compliance has
    occurred,
    New
    Jersey
    Zinc
    may
    subtract
    the
    concentration of any background
    level
    of
    contaminant determined
    by sampling
    at
    Point
    II
    of their NPDES permit.
    All
    sampling
    and analysis data shall
    be
    reported
    to the Illinois Environmental
    Protection Agency;
    4.
    New Jersey Zinc shall submit quarterly
    reports
    to the Illinois Environmental
    Protection Agency, within
    15 days
    of each
    calendar quarter;
    5.
    Within
    45 days after
    the date
    of this
    Opinion and Order,
    New Jersey Zinc shall
    execute and send
    to:
    Illinois Environmental Protection
    Agency
    Attention:
    Thomas Davis
    Enforcement Programs
    2200 Churchill
    Road
    Springfield,
    IL
    62794—9276
    a certificate of acceptance of
    this
    variance by which
    it agrees
    to be bound by
    the
    terms and conditions contained
    herein.
    This variance will be void
    if New
    Jersey
    Zinc
    fails
    to execute and
    forward
    the certificate within the 45—day
    period.
    The 45—day period shall
    be held
    in
    abeyance
    for
    any
    period
    during
    which
    the matter
    is appealed.
    The form of
    the
    certification shall
    be as
    follows:
    95—310

    —7—
    CERTIFICATION
    I,
    (We)
    ,
    having
    read the Opinion and Order of the Illinois Pollution Control
    Board
    in PCB 88—130,
    dated January 19,
    1989, understand
    and
    accept the
    said Opinion and Order,
    realizing that such acceptance
    renders all
    terms and conditions thereto binding and enforceable.
    Petitioner
    Authorized Agent
    Ti.tie
    Date
    Section
    41
    of the Environmental Protection Act
    (Ill.
    Rev.
    Stat.
    ch.
    1111/2,
    par.
    1041,
    1985,
    provides
    for appeal of final
    Orders of the Board within
    35 days.
    The Rules
    of the Supreme
    Court of Illinois establish
    filing requirements.
    IT
    IS SO ORDERED.
    I,
    Dorothy M Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Opinion and Order was
    adopted on the
    /9iC~
    day of
    ~
    1989, by
    a vote of
    ~
    .
    Dor’bthy M. Gun,
    Clerk,
    Illinois Pollution Control
    Board
    95—311

    Back to top