ILLINOIS POLLUTION CONTROL BOARD
    May 5, 1988
    C.S. NORCROSS, INC.,
    Petitioner,
    V.
    )
    PCB 87—206
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    MR. MICHAEL A. STICK, ESQ, APPEARED ON BEHALF OF PETITIONER, C..S.
    NORCROSS, INC.;
    MR. JOSEPH E. SVOBODA, ESQ.., APPEARED ON BEHALF OF RESPONDENT,
    ILLINOIS ENVIRONMENTAL PROTECTION AGENCY.
    OPINION AND ORDER OF THE BOARD (by J.D. Dumelle):
    This matter comes before the Board upon Petitioner, C,.S.
    Norcross, Inc’s., filing of a PeLition For Variance on December
    22, 1987. In sum, Petition requests a 15 month variance from
    this Board’s nighttime prohibition against impact forging
    cperations (set forth at 35 Ill. Adm. Code 90L105). issuance of
    the requested variance would allow Petitioner to conduct forging
    cperations from 1:00 am. to 7:00 a.m.
    As noted above, this Petition was initially filed on
    December 22, 1987. On January 7, 1988, the Board issued an Order
    mandating the submission of additional information. On January
    15, 1988, Petitioner supplied the additional data by filing its
    Response. On January 21, 1988, the Board accepted the Petition
    as an Amended Petition For Variance and set the matter for
    hearing.. Hearing was held on March 18, 1988, at 138 E. Hall,
    City of Bushnell, McDonough County, Illinois; no members of the
    public attended. After hearing this matter was submitted to the
    Board without briefs; however, on March 14, 1988, the Agency
    filed its “Agency Statement”. On March 24, 1988, the Board
    issued an Order construing the Agency Statement as the Agency
    Recommendation mandated by Ill. Rev. Stat. ch. 111 1/2 par.
    1037. Pursuant to statute, Petitioner is entitled to a final
    decision on its Petition no later than May 16, 1988.
    BACKGROUND
    Petitioner has conducted a forging operations facility
    currently employing approximately 157 people at 195 N. Dean
    Street, Bushnell, Illinois for approximately 81 years.. During
    89—91

    —2—
    much of that time it operated on a 24—hour, three shift
    schedule. tn October of 1983, this Board promulgated noise
    emission limitations, which limit impulsive sound levels at
    daytime and nighttime levels. Daytime emissions for existing
    impact forging operations are limited to 58.5 Leq. and nighttime
    emissions are limited to 53.5 Leq.
    Because Petitioner’s facility could not meet the nighttime
    standards the practical effect of the promulgated rule was to
    restrict Petitioner’s hours of operation; nighttime is defined
    at 35 Ill. Adm. Code 901.105 as “those 8 hours between 10:00 p.m.
    and 7:00 a.m. which are not part of the 16 continuous daytime
    hours
    .
    On May 2, 1985, Petitioner obtained a site—specific rule
    change effectively allowing forging operation until 1:00 a.m.
    Monday thru Saturday. In the matter of C.S. Norcross and Sons
    Co., R83—3l.
    Petitioner’s operation results in impulse sounds which are
    regulated as noted above. Metal is heated to approximately 2200
    degrees Fahrenheit, then inserted between dies; pressure is then
    applied. The pressure is supplied by repeated impact of the
    upper and lower die, which is fastened to an anvil. The anvil, a
    guided ram and the attached machinery are commonly known as a
    “forge hammer”. The sounds produced by the forge hammer are
    impulsive in nature andoriginate primarily from the impact
    between the upper die and the lower die. Petitioner’s facility
    utilizes thirteen forging hammers ranging in size from 800 to
    5,000 pounds, the largest hammers producing the most noise. R.
    26. It should be noted that Petitioner’s two largest hammers
    4,000 pounds and 5,000 pounds are not involved in this
    Petition. Pet. p. 10; R.. pp. 26, 27.
    ENVIRONMENTAL IMPACT
    Although it is true that noise emissions from Petitioner’s
    facility are not an immediate danger to health, noise emissions
    are regulated by the Environmental Protection Act and by Board
    regulations. At page 5 of the Petition For Variance, it is
    admitted that in 1983 forty—five residences had potential
    exposure to sound levels in excess of the maximum allowed under
    35 Ill. Adm. Code 901.105(c). Petitioner asserts that the total
    number of residences exposed to excess emission has decreased
    ——
    although no lesser figure is given.. Pet.. p. 6.
    It should be noted that in preparing its variance
    application Petitioner consulted with the neighboring
    community. According to the testimony of John Gormley, at least
    one resident from each neighboring household was solicited in
    order to ascertain and accommodate community concerns.. R. 30.
    This explains why the largest hammers are not included in this
    variance. With one exception the community favors granting
    Petitioner the requested variance. Furthermore, it should be
    89—92

    —3—
    noted that attached to the Petition For Variance, Petitioner has
    included the signatures and addresses of 41 neighbors, all
    residing within 1500 feet of the forging plant and all supporting
    the requested variance. The one exception was merely an inquiry
    which sought to ensure that Petitioner would not operate the two
    largest hammers as a result of the variance. As noted above the
    two largest hammers are not involved in this variance request and
    will not be operated between 1:00 a.m. and 7:00 a.m..
    Additionally, the record of hearing indicates that the public did
    not attend the hearing
    ——
    notwithstanding proper notice. This
    also indicates a lack of community opposition to the variance.
    Noise emissions of this sort are often in the nature of a
    nuisance—type of activity and the Board is not unmindful that the
    community supports the proposal.
    Notwithstanding, the Board is also aware that Petitioner is
    operating on the third shift despite this being a violation of
    Petitioner’s site—specific rule and despite the violation of this
    Board’s general regulations. R. 46. Petitioner should be
    advised that violations of this order will not be tolerated.
    EFFORTS AT COMPLIANCE
    As noted above, Petitioner’s facility is old. Nonetheless,
    Petitioner has indicated several attempts at lowering
    emissions. Petitioner’s witness Mr. Dale Stump, outlined several
    attempts to limit sound emissions including the use of acoustical
    absorbers, pads, mats and sound/shock absorbers. R. 50.
    Additionally the facility is looking for a way to segregate the
    loudest operations (the wheelabrator) from other, less noisy
    operations. However Mr. Stump also testified that no final
    decisions have, as yet, been made.
    HARDSHIP
    Petitioner has introduced much evidence that it is suffering
    hardship based upon the current standards. Specifically, the
    company must forgo realizable profits as a result of the
    nighttime noise limitations..
    Because customer orders cannot be adequately filled,
    business is slipping away. Petitioner has already lost several
    major customers. R. 13. The loss of these customers includes
    not only short term injury but also long term losses in terms of
    unrealized future revenues (the amount of current lost sales was
    estimated at $1.5
    $2 million). This does not include
    additional, future business turned away for inability to accept
    the additional contracts. Notably, Petitioner is too heavily
    burdened to fill orders from its parent company. R. 10.
    Unfilled orders from the parent company, alone, amount to losses
    of $120,000
    $150,000/month.
    89—93

    —4—
    Because Petitioner has been unable to operate during
    nighttime it has been forced to utilize overtime hours among its
    current workcrew. Petitioner is averaging fourteen hours of
    overtime per man per week, R. 11. This has added to financial
    pressures due to additional costs of production.
    The main purpose of the requested variance is to provide
    Petitioner with sufficient time to make a final business decision
    as to whether there is adequate, continuing business to justify
    increased permanent production. Petitioner states that it would
    examine the feasibility of designing a new facility which would
    be located far from residential uses, with a metal structure and
    which would afford the use of several baffling devices. R. 18.
    By allowing Petitioner to operate according to the requested
    variance, Petitioner claims it will be able to reduce its backlog
    of orders satisfying existing customers; and accept new orders
    enhancing its ability to attract continuing new businesses
    This, it is asserted, will correct a current poor cash flow and
    provided the necessary information for a decision on whether to
    build the additional facility. At the end of the variance,
    Petitioner may decide to construct the new facility or may decide
    against it
    ——
    but Petitioner will discontinue its third shift and
    return to operations congruent with the conditions set forth in
    R8 3—3 1.
    Whatever ambiguities remain concerning Petitioner’s plant(s)
    and operations, the fact remains that at the end of 15 months
    Petitioner will once again be in compliance.
    By all evidence presented, Petitioner has been a good
    neighbor and citizen. Its facility is old
    ——
    but working
    ——
    and
    orders are picking up. Short term expansion of Petitioner’s
    operation hours is expected to generate many new jobs and income
    for the community; long term plant construction will generate
    permanent jobs and growth. Petitioner’s anticipated period of
    non—compliance is short and any adverse environmental impact
    would be minimal. The request for variance is granted.
    The Board notes that Petitioner’s plan of (eventual)
    compliance is not truly a compliance plan; rather it is solely a
    promise to halt nighttime operations upon the expiration of the
    variance. The Board’s action in granting this variance is
    limited to the unique facts of this case, only. And should not
    be construed as precedence concerning a compliance plan of this
    sort.
    ORDER
    C.S. Norcross, tnc.., is hereby granted variance from 35 Ill.
    Adm. Code 901.105(c) for its manufacturing complex located at 195
    N. Dean Street, Bushnell, McDonough County, Illinois, subject to
    the following conditions.
    89—94

    —5—
    1. This variance shall expire on July 31, 1989.
    2. Petitioner shall not operate its 4,000 lb. or 5,000 lb.
    forging hammers, or any similar such equipment during
    the nighttime hours between 1:00 a.m. and 7:00 a.m.
    3. Petitioner shall conduct its operations such that the
    noise emission measured at the nearest class ‘A’ land
    is no greater than 70 Leg.
    4. Petitioner shall conduct its facility in compliance
    with all applicable rules of the Board and the
    Environmental Protection Act..
    5.. Within forty five (45) days of the date of this Order,
    the Petitioner shall execute a Certificate of
    Acceptance and Agreement agreeing to be bound by the
    terms and conditions of this variance which shall be
    sent to:
    Illinois Environmental Protection Agency
    Division of Water Pollution Control
    Compliance Assurance Section
    2200 Churchill Road, P.O. Box 19276
    Springfield, Il 62794—9276
    This variance shall be void if Peitioner fails to
    execute and forward the certificate within the forty
    five day period.. The forty five day period shall be
    held in abeyance during any period that this matter is
    being appealed. The form of said Certification shall
    be as follows:
    CERTI Fl CATION
    I, (We), C..S. Norcross, Inc.., having read the Order of the
    Illinois Pollution Control Board, in PCB 87—106, dated May 5,
    1988, understand and accept the said Order, realizing that such
    acceptance renders all terms and conditions thereto binding and
    enforceable.
    Petitioner
    By: Authorized Agent
    Title
    Date
    89—95

    —6—
    Section 41 of the Environmental Protection Act, Ill. Rev..
    Stat. 1985 ch. 111 1/2 par. 1041, provides for appeal of final
    Orders of the Board within 35 days. The Rules of the Supreme
    Court of Illinois establish filing requirements.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Opinion and Order was
    adopted on the
    .3~-’
    day of
    Yh
    ,
    1988 by a vote
    of
    7-0
    Dorothy M.. Gunn, Clerk
    Ilinois Pollution Control Board
    89—9 6

    Back to top