ILLINOIS POLLUTION CONTROL BOARD
May 5, 1988
C.S. NORCROSS, INC.,
Petitioner,
V.
)
PCB 87—206
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
MR. MICHAEL A. STICK, ESQ, APPEARED ON BEHALF OF PETITIONER, C..S.
NORCROSS, INC.;
MR. JOSEPH E. SVOBODA, ESQ.., APPEARED ON BEHALF OF RESPONDENT,
ILLINOIS ENVIRONMENTAL PROTECTION AGENCY.
OPINION AND ORDER OF THE BOARD (by J.D. Dumelle):
This matter comes before the Board upon Petitioner, C,.S.
Norcross, Inc’s., filing of a PeLition For Variance on December
22, 1987. In sum, Petition requests a 15 month variance from
this Board’s nighttime prohibition against impact forging
cperations (set forth at 35 Ill. Adm. Code 90L105). issuance of
the requested variance would allow Petitioner to conduct forging
cperations from 1:00 am. to 7:00 a.m.
As noted above, this Petition was initially filed on
December 22, 1987. On January 7, 1988, the Board issued an Order
mandating the submission of additional information. On January
15, 1988, Petitioner supplied the additional data by filing its
Response. On January 21, 1988, the Board accepted the Petition
as an Amended Petition For Variance and set the matter for
hearing.. Hearing was held on March 18, 1988, at 138 E. Hall,
City of Bushnell, McDonough County, Illinois; no members of the
public attended. After hearing this matter was submitted to the
Board without briefs; however, on March 14, 1988, the Agency
filed its “Agency Statement”. On March 24, 1988, the Board
issued an Order construing the Agency Statement as the Agency
Recommendation mandated by Ill. Rev. Stat. ch. 111 1/2 par.
1037. Pursuant to statute, Petitioner is entitled to a final
decision on its Petition no later than May 16, 1988.
BACKGROUND
Petitioner has conducted a forging operations facility
currently employing approximately 157 people at 195 N. Dean
Street, Bushnell, Illinois for approximately 81 years.. During
89—91
—2—
much of that time it operated on a 24—hour, three shift
schedule. tn October of 1983, this Board promulgated noise
emission limitations, which limit impulsive sound levels at
daytime and nighttime levels. Daytime emissions for existing
impact forging operations are limited to 58.5 Leq. and nighttime
emissions are limited to 53.5 Leq.
Because Petitioner’s facility could not meet the nighttime
standards the practical effect of the promulgated rule was to
restrict Petitioner’s hours of operation; nighttime is defined
at 35 Ill. Adm. Code 901.105 as “those 8 hours between 10:00 p.m.
and 7:00 a.m. which are not part of the 16 continuous daytime
hours
.
On May 2, 1985, Petitioner obtained a site—specific rule
change effectively allowing forging operation until 1:00 a.m.
Monday thru Saturday. In the matter of C.S. Norcross and Sons
Co., R83—3l.
Petitioner’s operation results in impulse sounds which are
regulated as noted above. Metal is heated to approximately 2200
degrees Fahrenheit, then inserted between dies; pressure is then
applied. The pressure is supplied by repeated impact of the
upper and lower die, which is fastened to an anvil. The anvil, a
guided ram and the attached machinery are commonly known as a
“forge hammer”. The sounds produced by the forge hammer are
impulsive in nature andoriginate primarily from the impact
between the upper die and the lower die. Petitioner’s facility
utilizes thirteen forging hammers ranging in size from 800 to
5,000 pounds, the largest hammers producing the most noise. R.
26. It should be noted that Petitioner’s two largest hammers
4,000 pounds and 5,000 pounds are not involved in this
Petition. Pet. p. 10; R.. pp. 26, 27.
ENVIRONMENTAL IMPACT
Although it is true that noise emissions from Petitioner’s
facility are not an immediate danger to health, noise emissions
are regulated by the Environmental Protection Act and by Board
regulations. At page 5 of the Petition For Variance, it is
admitted that in 1983 forty—five residences had potential
exposure to sound levels in excess of the maximum allowed under
35 Ill. Adm. Code 901.105(c). Petitioner asserts that the total
number of residences exposed to excess emission has decreased
——
although no lesser figure is given.. Pet.. p. 6.
It should be noted that in preparing its variance
application Petitioner consulted with the neighboring
community. According to the testimony of John Gormley, at least
one resident from each neighboring household was solicited in
order to ascertain and accommodate community concerns.. R. 30.
This explains why the largest hammers are not included in this
variance. With one exception the community favors granting
Petitioner the requested variance. Furthermore, it should be
89—92
—3—
noted that attached to the Petition For Variance, Petitioner has
included the signatures and addresses of 41 neighbors, all
residing within 1500 feet of the forging plant and all supporting
the requested variance. The one exception was merely an inquiry
which sought to ensure that Petitioner would not operate the two
largest hammers as a result of the variance. As noted above the
two largest hammers are not involved in this variance request and
will not be operated between 1:00 a.m. and 7:00 a.m..
Additionally, the record of hearing indicates that the public did
not attend the hearing
——
notwithstanding proper notice. This
also indicates a lack of community opposition to the variance.
Noise emissions of this sort are often in the nature of a
nuisance—type of activity and the Board is not unmindful that the
community supports the proposal.
Notwithstanding, the Board is also aware that Petitioner is
operating on the third shift despite this being a violation of
Petitioner’s site—specific rule and despite the violation of this
Board’s general regulations. R. 46. Petitioner should be
advised that violations of this order will not be tolerated.
EFFORTS AT COMPLIANCE
As noted above, Petitioner’s facility is old. Nonetheless,
Petitioner has indicated several attempts at lowering
emissions. Petitioner’s witness Mr. Dale Stump, outlined several
attempts to limit sound emissions including the use of acoustical
absorbers, pads, mats and sound/shock absorbers. R. 50.
Additionally the facility is looking for a way to segregate the
loudest operations (the wheelabrator) from other, less noisy
operations. However Mr. Stump also testified that no final
decisions have, as yet, been made.
HARDSHIP
Petitioner has introduced much evidence that it is suffering
hardship based upon the current standards. Specifically, the
company must forgo realizable profits as a result of the
nighttime noise limitations..
Because customer orders cannot be adequately filled,
business is slipping away. Petitioner has already lost several
major customers. R. 13. The loss of these customers includes
not only short term injury but also long term losses in terms of
unrealized future revenues (the amount of current lost sales was
estimated at $1.5
—
$2 million). This does not include
additional, future business turned away for inability to accept
the additional contracts. Notably, Petitioner is too heavily
burdened to fill orders from its parent company. R. 10.
Unfilled orders from the parent company, alone, amount to losses
of $120,000
—
$150,000/month.
89—93
—4—
Because Petitioner has been unable to operate during
nighttime it has been forced to utilize overtime hours among its
current workcrew. Petitioner is averaging fourteen hours of
overtime per man per week, R. 11. This has added to financial
pressures due to additional costs of production.
The main purpose of the requested variance is to provide
Petitioner with sufficient time to make a final business decision
as to whether there is adequate, continuing business to justify
increased permanent production. Petitioner states that it would
examine the feasibility of designing a new facility which would
be located far from residential uses, with a metal structure and
which would afford the use of several baffling devices. R. 18.
By allowing Petitioner to operate according to the requested
variance, Petitioner claims it will be able to reduce its backlog
of orders satisfying existing customers; and accept new orders
enhancing its ability to attract continuing new businesses
This, it is asserted, will correct a current poor cash flow and
provided the necessary information for a decision on whether to
build the additional facility. At the end of the variance,
Petitioner may decide to construct the new facility or may decide
against it
——
but Petitioner will discontinue its third shift and
return to operations congruent with the conditions set forth in
R8 3—3 1.
Whatever ambiguities remain concerning Petitioner’s plant(s)
and operations, the fact remains that at the end of 15 months
Petitioner will once again be in compliance.
By all evidence presented, Petitioner has been a good
neighbor and citizen. Its facility is old
——
but working
——
and
orders are picking up. Short term expansion of Petitioner’s
operation hours is expected to generate many new jobs and income
for the community; long term plant construction will generate
permanent jobs and growth. Petitioner’s anticipated period of
non—compliance is short and any adverse environmental impact
would be minimal. The request for variance is granted.
The Board notes that Petitioner’s plan of (eventual)
compliance is not truly a compliance plan; rather it is solely a
promise to halt nighttime operations upon the expiration of the
variance. The Board’s action in granting this variance is
limited to the unique facts of this case, only. And should not
be construed as precedence concerning a compliance plan of this
sort.
ORDER
C.S. Norcross, tnc.., is hereby granted variance from 35 Ill.
Adm. Code 901.105(c) for its manufacturing complex located at 195
N. Dean Street, Bushnell, McDonough County, Illinois, subject to
the following conditions.
89—94
—5—
1. This variance shall expire on July 31, 1989.
2. Petitioner shall not operate its 4,000 lb. or 5,000 lb.
forging hammers, or any similar such equipment during
the nighttime hours between 1:00 a.m. and 7:00 a.m.
3. Petitioner shall conduct its operations such that the
noise emission measured at the nearest class ‘A’ land
is no greater than 70 Leg.
4. Petitioner shall conduct its facility in compliance
with all applicable rules of the Board and the
Environmental Protection Act..
5.. Within forty five (45) days of the date of this Order,
the Petitioner shall execute a Certificate of
Acceptance and Agreement agreeing to be bound by the
terms and conditions of this variance which shall be
sent to:
Illinois Environmental Protection Agency
Division of Water Pollution Control
Compliance Assurance Section
2200 Churchill Road, P.O. Box 19276
Springfield, Il 62794—9276
This variance shall be void if Peitioner fails to
execute and forward the certificate within the forty
five day period.. The forty five day period shall be
held in abeyance during any period that this matter is
being appealed. The form of said Certification shall
be as follows:
CERTI Fl CATION
I, (We), C..S. Norcross, Inc.., having read the Order of the
Illinois Pollution Control Board, in PCB 87—106, dated May 5,
1988, understand and accept the said Order, realizing that such
acceptance renders all terms and conditions thereto binding and
enforceable.
Petitioner
By: Authorized Agent
Title
Date
89—95
—6—
Section 41 of the Environmental Protection Act, Ill. Rev..
Stat. 1985 ch. 111 1/2 par. 1041, provides for appeal of final
Orders of the Board within 35 days. The Rules of the Supreme
Court of Illinois establish filing requirements.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the above Opinion and Order was
adopted on the
.3~-’
day of
Yh
,
1988 by a vote
of
7-0
Dorothy M.. Gunn, Clerk
Ilinois Pollution Control Board
89—9 6