ILLINOIS POLLUTION CONTROL BOARD
    May
    5,
    1988
    BROWNING
    FERRIS INDUSTRIES
    OF ILLINOIS,
    INC.,
    Petitioner,
    v.
    )
    PCB 84—136
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    FRED
    C.
    PRILLAMAN, ATTORNEY-AT—LAW, APPEARED
    ON
    BEHALF OF
    BROWNING FERRIS
    INDUSTRIES OF ILLINOIS,
    INC.;
    AND
    E.
    WILLIA!4 HUTTON, ATTORNEY-AT-LAW, APPEARED
    ON
    BEHALF OF
    ILLINOIS ENVIRONMENTAL PROTECTION AGENCY.
    OPINION AND ORDER OF THE BOARD
    (by
    B.
    Forcade):
    This matter comes before the Board on the August
    30,
    1984
    petition of Browning Ferris Industries
    of Illinois,
    Inc.
    (“EFI”)
    appealin~ the July 27,
    1984 permit decision by the Environmental
    Protection
    Agency
    (“Agency”).
    The
    facility involved
    is
    the
    Davis
    Junction
    Landfill,
    located
    south
    of
    Rockford
    in
    Ogle
    County.
    The
    Board
    held
    a
    public
    hearina
    on
    this
    matter
    in
    Ogle
    County
    on
    February
    3,
    1988.
    No member
    of
    the public was present.
    BFI
    submitted
    its post-hearing
    brief
    on March 10,
    1988.
    The Agency
    submitted
    its brief on April
    1,
    1988 and an “Attachment
    A”
    on
    April
    4,
    1988.
    BFI submitted
    a reply brief on April
    8,
    1988.
    BFI challenges
    five permit conditions
    imposed by the Agency ~ihen
    i~issued
    its July
    27,
    1984 Closure/Post—Closure
    Care Permit
    to
    BFI
    for the Davis Junction Landfill.
    Factual Summary
    E3FI
    submitted its application for development of
    a solid
    waste disposal site
    in Ogle County
    to the Agency on November
    20,
    1974
    (Ex.
    22
    &
    Ex.
    30),
    and the Agency granted
    it development
    permit number 1975—11—DE on February 27,
    1975
    (Ex.
    30).
    BFI
    submitted
    an application
    for
    an amended development permit and an
    operating permit on October
    15,
    1976,
    together with
    a minor
    modification request
    (Ex.
    24)
    to reflect
    its intent
    to phase site
    development and modify leachate management
    (Ex.
    25).
    BFI
    submitted entirely new site plans to reflect the proposed changes
    (Ex.
    26,
    27,
    28
    &
    29).
    The estimated refuse space was 2,868,000
    cubic
    yards
    of compacted waste,
    and the site was
    to have an
    overall
    life of
    23 years
    (Ex.
    26).
    The Agency granted
    89--~3

    —2—
    supplemental
    site development permit 1975—626 on October
    28,
    1976
    as
    a result
    of the BFI application
    (Ex.
    23).
    The Agency
    subsequently
    issued operating permit
    1975—11—OP
    for this solid
    waste disposal facility on December
    16,
    1976.
    BFI commenced operations at Davis Junction and received
    1,900,000 cubic yards of uncompacted wastes into Phase
    1
    from
    December,
    1976 until January,
    1983.
    The incoming wastes included
    87
    common municipal wastes,
    11
    special
    (non—hazardous) wastes,
    and
    2
    Part 721
    (40 CFR
    261)
    hazardous wastes
    (Ex.
    6;
    Ex.
    12,
    p.
    3).
    The record
    indicates that between late 1978 and early 1982,
    BFI obtained several permits
    for the disposal
    of liquid solvent
    wastes
    of various
    types,
    compositions,
    and quantities up to
    1,500,000 gallons.
    Many are not described
    fully,
    but the permits
    included methylene chloride,
    l,l,l—trichloroethane,
    and
    trichioroethylene
    (Ex.
    18).
    The
    record does not indicate
    the
    identities and volumes
    of hazardous wastes received
    into Phase
    1
    prior
    to
    1978.
    BFI
    kept detailed hazardous wastes records only
    from November
    19,
    1980 through January
    25,
    1983
    (Ex.
    12,
    p.
    14).
    As
    a
    result of BFI’s
    receipt of wastes containing the three
    chlorinated organic solvents,
    the Agency required BFI
    to begin
    analyzing
    its groundwater samples
    for total organic carbon
    (TOC),
    total organic halide
    (Tax),
    methylene chloride,
    1,1,1—
    trichioroethane,
    and trichloroethylene by
    a June
    18,
    1982 letter
    (Ex.
    19).
    The subsequent permit
    issued December
    20,
    1983,
    however, did not include the three specific chlorinated solvent
    parameters
    (Ex.
    12, Att.
    9).
    On September
    16,
    1982,
    BFI
    requested the Agency to amend
    its
    operating permit
    to allow leachate removal from Phase
    1
    at the
    rate of 5,000 gallons per week for disposal on the dry active
    fill at
    the site.
    The leachate was to remain at
    the
    site.
    Removal was
    to occur whenever the leachate level exceeded
    elevation
    725.5
    feet,
    so the maximum leachate level would remain
    at 726 feet
    (14 foot depth)
    (Ex.
    21).
    The Agency issued
    supplemental permit 1982—l24—SUPP on October
    28,
    1982
    for this
    activity, with
    the proviso that
    no leachate or leachate—
    contaminated water
    be discharged
    to any groundwater, surface
    water,
    or sewer
    without
    a permit
    (Ex.
    20).
    The application and
    permit included
    no reference
    tp leachate characterization or
    composition,
    or
    to groundwater monitoring.
    The U.S. Environmental Protection Agency requested on August
    8,
    1983
    that BFI submit its Part B application by January 31,
    1984
    (See Ex.
    16; See also
    35
    Ill. Mm.
    Code 703.150(b)
    (1984)).
    The record
    is silent
    as
    to when SF1
    filed
    its Part A
    application and obtained facility identification No.
    ILD
    980700751
    for the Davis Junction Phase
    1.
    BFI
    instead chose
    to
    cease accepting hazardous wastes and close Phase
    1 of its
    facility, which was near capacity anyway
    (See
    Ex.
    16; See also
    35
    89—04

    —3—
    Ill.
    Adm.
    Code 703.157(b)
    (1984)).
    BFI submitted
    a partial
    Closure/Post—Closure Plan
    to the Agency on January
    30,
    1984
    (Ex.
    16; See also
    35
    Ill. Mm.
    Code 725.210
    725.220 (1984);
    Ex.
    32).
    The Agency responded on March 16,
    1984 by notifying
    BFI
    of
    numerous deficiencies
    in
    its plan
    (Ex.
    11).
    SF1 submitted
    the
    entirety of
    its Closure/Post—Closure Plan to the Agency on April
    13,
    1984
    (Ex.
    12).
    Andrews Environmental Engineering,
    Inc.
    prepared the plan.
    The Agency again responded on April
    27,
    1984
    by notifying BFI
    of its rejection due
    to numerous lingering
    deficiencies
    (Ex.
    9).
    BFI submitted
    a partial response on June
    4,
    1984
    (Ex.
    6)
    and
    a final response on July
    25,
    1984
    (Ex.
    2).
    The Agency finally modified the BFI Davis Junction Phase
    1
    Closure/post—Closure Plan on July
    27,
    1984
    (Ex.
    1;
    See
    35 Ill.
    Adm. Code 725.212(d)
    & 725.218(d)
    (1984)).
    The Agency received
    public inquiry about the BFI plan from one member of
    the general
    public (See Ex.
    3,
    7
    &
    13).
    The Agency held no public hearing
    (Petition,
    par.
    13).
    BFI now appeals
    the Agency’s modification
    of its
    Closure/Post—Closure Plan on August 30,
    1984.
    The Agency made
    numerous modifications.
    SF1 appealed only the five summarized
    below
    (Ex.
    1;
    Petition Ex.
    “A”):
    Par.
    3:
    BFI was
    to characterize
    its leachate
    by
    performing
    analyses
    for
    the
    375
    hazardous
    constituents
    listed
    in
    40
    CFP.
    261 Appendix
    VIII
    and
    submit
    a
    plan
    for leachate disposal;
    Par.
    4:
    BFI
    was
    to
    decrease
    the
    maximum
    depth
    of
    leachate maintained
    in
    the
    hazardous
    area
    from
    14
    feet
    to less
    than one foot;
    Par.5(j): SF1
    was
    to
    monitor
    the groundwater
    quality
    quarterly
    for
    Methylene
    Chloride,
    l,l,l—Trichloroethane
    and
    Trichloroethylene;
    Par.5(1): BFI
    was
    to
    perform
    statistical
    analyses
    on
    the
    monitoring
    data
    using
    the
    .1
    level
    of
    Cochran’s
    Approximation
    of
    Behrens—Fisher
    Student’s T—Test;
    and
    Proviso:
    The
    Agency
    reserved
    the
    right
    to
    amend BFI’s Closure and Post—Closure
    Plan.
    Each
    of these
    issues
    is discussed below.
    89—05

    —4—
    Discussion
    The Board must confront some preliminary issues
    before
    it
    considers the substantive issues involved in
    the Agency
    modifications
    to the Closure/Post—Closure Plan which
    BFI now
    challenges.
    A discussion
    of each
    of
    the five substantive points
    will follow these preliminary discussions.
    The first preliminary issue regards
    the regulatory status
    of
    this permit appeal.
    The Resource Conservation and Recovery Act
    (hereinafter
    “RCRA”)
    authorized USEPA
    to
    adopt regulations
    governing various aspects of hazardous waste management.
    42
    U.S.C.
    Sec.
    6901 et
    seq.
    (1986).
    The Illinois Environmental
    Protection Act (hereinafter “the Act”)
    includes
    a provision
    allowing
    the Board
    to adopt regulations
    identical
    in substance
    to
    the federal regulations.
    Ill.
    Rev.
    Stat.
    ch.
    111
    1/2,
    Sec.
    1022.4 (1988).
    A regulation adopted
    by USEPA or this Board
    pursuant
    to RCRA authority
    is
    a RCRA regulation,
    a permit issued
    by USEPA
    or the Agency pursuant
    to RCRA authority
    is
    a RCRA
    permit.
    See 35
    Ill.
    Adm.
    Code 700.255
    &
    700.260
    (1984).
    Although the disposition of this proceeding centrally
    involves
    the Board’s RCRA regulations,
    it
    is not
    a “RCRA appeal”
    in the
    strict,
    technical sense.
    RCRA permit appeals invoke certain
    unique regulatory procedures not involved in this appeal.
    See
    35
    Ill. Mm.
    Code 705
    (1984).
    The standard Board procedures
    for
    Agency permit denials apply here.
    See
    35
    Ill. Mm.
    Code 105
    (1984).
    The RCRA regulations provide
    a two—step application
    procedure.
    Owners and operators
    of hazardous waste management
    facilities existing on November 19,
    1980 were given an
    opportunity
    to submit
    a Part A application containing certain
    facility information.
    35
    Ill. Mm.
    Code 703.150(a),
    703.181
    &
    725.101(b)
    (1984).
    These facilities were deemed
    to have achieved
    “interim status” and were
    required
    to comply with the “interim
    status standards”
    of Part 725
    of the Board’s regulations.
    35
    Ill.
    Adm.
    Code 703.153
    &
    703.156
    (1984).
    This
    is the current
    regulatory status of the BFI facility involved in this
    proceeding.
    The owner
    or operator of
    the interim status facility
    was
    to submit
    a Part B application containing more detailed
    information within
    a certain time
    of an Agency notice that
    it was
    due,
    thus terminating
    its interim status upon final disposition
    of
    its application.
    35
    Ill. Mm.
    Code 703.150(b),
    703.157
    &
    703.182
    (1984).
    A more comprehensive body of hazardous waste
    management regulations would
    then apply
    to the facility.
    35
    Ill.
    Mm.
    Code 724.101
    & 724.103
    (1984).
    Part 725 interim status standards are generally implemented
    directly without
    a permit application or review.
    These standards
    include several “mini—procedures”
    for Agency review
    of
    a facility
    without
    a complete RCRA permit application.
    This closure plan
    involves one
    of these mini—procedures.
    The mini—procedures
    are
    89—06

    —5—
    based on similar procedures
    in
    40 CFR
    265.
    However,
    the Board
    modified the parallel federal procedures
    to provide
    for appeal
    of
    Agency decisions
    to the Board.
    35
    Ill.
    Adm.
    Code 725.218(g)
    (1984)
    Parts
    702,
    703,
    and 705 govern Part
    B RCRA permit
    issuance.
    These procedures
    are generally inapplicable
    to
    proceedings concerning
    interim status.
    35
    Ill. Mm.
    Code 702.107
    (1984).
    As stated by the Board
    in
    the past:
    Although
    the Board intends the Agency’s action
    with
    respect
    to
    interim
    status
    to
    be
    in
    the
    nature of permit actions,
    and hence appealable
    to
    the Board,
    the detailed procedures
    of Part
    705 are not applicable.
    In
    re
    Phase
    II
    RCRA
    Rules,
    53
    PCB
    131,
    150
    (July
    26,
    1983);
    See Commonwealth
    Edison
    Co.
    v.
    IPCB,
    127
    Ill.App.3d
    446,
    449—450;
    468
    N.E.2d
    1339,
    1342—43
    (3d Dist.
    1984).
    Therefore,
    Part 725 RCRA interim status closure/post—closure
    plans
    are not RCRA permits,
    and appeals
    of Agency decisions
    relating
    to these plans are not RCRA permit appeals.
    While
    the
    SF1 Closure/Post—Closure permit did legitimately contain
    conditions based on RCRA regulations adopted
    by the Board,
    the
    permit itself was not issued
    pursuant to RCRA authority and
    is
    therefore not
    a RCRA permit.
    The second preliminary issue involves the breadth
    of Agency
    discretion with regard to
    its disposition of the BFI
    Closure/Post—Closure Plan
    in light
    of prior Agency actions.
    BFI
    contends that by issuing the 1975 permit,
    the 1976 permits, and
    the 1982 supplemental operating permit,
    the Agency somehow cannot
    now alter
    those earlier determinations and require BFI
    to accept
    more stringent permit conditions.
    This contention
    is without
    merit.
    Essentially,
    this argument
    is
    an estoppel argument.
    When
    a
    state agency acts
    in a governmental,
    as opposed
    to
    a proprietary,
    capacity,
    public policy militates against circumscribing
    the
    agency’s discretion by an estoppel.
    Estoppel could
    impair the
    proper function of government and will only arise under
    extraordinary or
    compelling circumstances.
    Illinois
    Environmental Protection Agency
    v. Modine Manufacturing Co.,
    PCB
    86—27, Slip Op.
    at
    4—5
    (Feb.
    4,
    1988).
    In this case,
    the Agency
    acted
    in a governmental capacity,
    and no extraordinary or
    compelling circumstances appear
    in the record.
    As stated by the
    Board:
    Such application of the doctrine
    of
    estoppel
    would
    impair
    the
    functioning
    of
    the
    State
    in
    89—07

    —6—
    its
    role
    of
    protecting
    valuable
    interests
    in
    the
    environment.
    “Tb
    allow
    estoppel
    here
    would
    be
    to permit
    the people
    of
    Illinois
    to
    be
    denied
    their
    constitutional
    right
    to
    a
    healthful environment.”
    Modine Manufacturing,
    PCB 86—27
    at
    5
    (Feb.
    4,
    1988)
    (quoting
    Tn—County
    Landfill
    v.
    Pollution
    Control
    Board,
    41
    Ill.App.3d
    249,
    255,
    353 N.E.2d 316
    (2d Dist.
    1976)).
    Second, BFI’s argument ignores one fact:
    the Agency’s 1975,
    1976,
    and
    1982 permit decisions were made under
    a regulatory
    control program,
    and with
    a scientific understanding,
    that would
    change over time.
    A decision that was correct under
    general
    scientific knowledge and regulatory control programs that existed
    in 1976
    ,
    may not
    be correct under scientific kno’~1edgeand
    regulatory control programs that existed
    in 1984.
    The Agency’s permit decisions
    of
    1975,
    1976,
    and 1982 ~ere
    premised exclusively on
    the Board’s solid waste regulationsL
    Those regulations were originally adopted
    by the Board
    in 1973
    (R72—5,
    adopted July
    19,
    1973),
    and made no distinction between
    landfills acceptj~ngmunicipal refuse and those accepting
    hazardous waste.~
    All landfills were simply called “sanitary
    landfills.”
    Those regulations
    remained effectively unchanged
    through the 1984 time frame involved in
    this proceeding.
    By 1984,
    the legal principles upon which hazardous waste
    decisions
    could
    be made had changed dramatically.
    The statutory
    and regulatory control program for
    the management
    of hazardous
    waste under RCRA reflected
    a consensus that this particular
    type
    of waste posed special problems and deserved special and more
    rigorous control standards
    (See Ill.Rev.Stat.
    ch.
    111—1/2,
    Section l020(a)(4)
    (1984)).
    BFI’s first permit which
    contained
    conditions implementing
    the RCRA hazardous waste regulatory
    scheme
    is the permit now at issue.
    ‘See
    the discussion of
    Second Supplemental
    issue beginning on
    page
    25
    of this Opinion and Order.
    2Pollution Control Board
    Rules and Regulations,
    Chapter
    7:
    Solid
    Waste
    (subsequently revised and codified at
    35 Ill. Mm.
    Code 807
    (1984)); see 35
    Ill. Mm.
    Code 700.106
    (1984).
    ~These
    regulations,
    however, did broadly define “hazardous
    waste,” but only required that
    a landfill must obtain
    a permit
    to
    receive
    it.
    35 Ill.
    Adm. Code 807.104
    & 807.310
    (1984).
    89—08

    —7—
    BFI’s argument presumes
    that an Agency decision finding
    a
    facility is properly operated as
    a “sanitary landfill” somehow
    is
    controlling
    on whether the facility
    is
    a properly closed
    hazardous waste facility.
    The Board
    is unable
    to accept this
    argument either
    in logic or
    as
    law.
    The issue before the Board
    is not whether prior Agency decisions are binding on the Board
    today.
    Rather,
    the issue now
    is whether
    the permit application
    submitted by BFI,
    and any other information available at the time
    of the permit decision, demonstrates compliance with the relevant
    statutory and regulatory requirements governing closure
    of
    a
    hazardous waste facility.
    In summary, SF1 arguments
    that the 1975,
    1976,
    and 1982
    permitting activities
    of the Agency somehow circumscribed the
    Agency’s discretion
    in reviewing
    the Davis Junction Closure/Post—
    Closure Plan
    in 1984 are unavailing.
    As discussed,
    Illinois law
    would not support any theory
    of estoppel against
    the Agency.
    The
    fact that
    the Agency reviewed the plan under
    a new and distinct
    body of
    regulations militates
    in favor of
    increased Agency
    discretion.
    Finally, increased knowledge and articulated
    regulatory concern
    tends
    to favor
    not limiting the Agency’s range
    of regulatory
    choices
    in 1984 as
    to what may have been reasonable
    in 1976 or
    1982.
    A third preliminary matter which the Board must determine
    is
    that of the standard
    of review.
    In its post—hearing brief, BFI
    correctly reiterates the standard of
    review in permit appeal
    proceedings:
    The
    sole
    question
    before
    the
    Board
    is
    whether
    the
    applicant
    proves
    that
    the
    application,
    as
    submitted
    to
    the
    Agency,
    demonstrated
    that
    no
    violation
    of
    the
    Environmental
    Protection
    Act
    would
    have
    occurred
    if
    the
    requested
    permit
    had
    been
    issued.
    Petitioner’s Brief
    at
    18
    (quoting Joliet
    Sand
    & Gravel
    Co.
    v.
    Pollution Control
    Board,
    163
    Ill.App.3d
    830,
    833,
    516 N.E.2d
    955,
    958
    (3d
    Dist.
    1987)
    (citation omitted).
    SF1 then properly proceeds
    to assert that BFI bears
    the burden
    to
    prove
    the Agency—imposed permit conditions unnecessary, but that
    the Agency
    is not required
    to justify
    its actions with regard
    to
    the application.
    Petitioner’s Brief at
    19 (citing Environmental
    Protection Agency v.
    Pollution Control Board,
    118 Ill.App.3d
    772,
    780, 455 N.E.2d 188,
    194
    (1st Dist.
    l9~3)).
    The Board would agree with BFI’s assessment
    of the current
    law with regard
    to the legal
    standard and burden of proof
    in this
    proceeding.
    After
    its appraisal of
    the current state of
    the law,
    89—09

    —8—
    however, BFI abandons that standard and attempts
    to place
    the
    burden on the Agency.
    SF1 begins nine assertions
    in
    its brief
    with,
    “The Agency has failed
    to demonstrate
    ...
    that the
    condition
    is
    necessary,”
    or similar words.
    Petitioner’s Brief
    at
    26—28.
    By the submission of
    its Reply Brief,
    SF1 completely
    abandons the standard of review previously articulated.
    For
    example,
    BFr
    asserts:
    The burden was on
    the Agency,
    and
    it failed
    to
    meet
    its
    burden
    in
    that
    it
    failed
    to
    demonstrate
    the
    environmental
    necessity
    of
    a
    one—foot
    leachate)
    head
    as opposed
    to 14 feet
    or
    some
    intermediate
    point
    between
    one
    foot
    and fourteen
    feet.
    Indeed,
    the Agency did no
    groundwater
    monitoring
    or
    scientific
    testing
    to
    determine
    whether
    the
    14—foot
    head
    was
    excessive.
    (Reply Brief,
    p.
    14).
    The Board emphasizes
    that the burden of proof
    is on BFI,
    not the
    Agency.
    The Agency has no obligation
    to conduct groundwater
    monitoring
    or scientific testing
    at BFI’s facility.
    SF1
    is
    entitled
    to
    a favorable decision
    if,
    and only
    if,
    it has
    successfully proven
    that the record before the Agency indicated
    that BFI’s Closure/Post—Closure Plan,
    as originally submitted and
    supplemented prior
    to July 27,
    1984, was sufficient
    to establish
    that the Davis Junction landfill would not cause
    a violation of
    the Act or Board regulations governing hazardous waste disposal
    facilities.
    Initially, SF1 correctly identified
    the standard of
    review
    and burden
    of proof.
    Therefore,
    the Board expected much of BFI’s
    presentation
    at hearing, and that
    its briefs would focus on the
    facts
    in the record
    to logically demonstrate
    that its original
    plan would not violate
    the Act and applicable Board
    regulations.
    Unfortunately,
    SF1 spent most
    of its efforts,
    at
    hearing and
    in briefs,
    trying
    to “put the Agency on trial.”
    That
    is not what case
    is about.
    This Board must focus,
    and the Board
    will focus,
    on whether
    the
    facts
    in the record demonstrate future
    compliance.
    BFI’s unwillingness
    to
    focus on
    that central
    issue
    is noted,
    but not controlling.
    The Board further observes
    a
    fundamental problem with BFI’s
    Closure/Post—Closure
    Plan as submitted
    to the Agency in April,
    1984.
    The plan comprised
    21 pages containing numerous references
    to various attachments for plan details.
    (Ex.
    12).
    Many of the
    attachments are apparently pre—existing documents.
    For example,
    Attachment
    2:
    Site Design Criteria
    is actually a copy of the
    October,
    1976 application for
    a supplemental
    permit.
    (Compare
    Ex.
    12 Att.
    2 with Ex.
    26); Attachment
    3:
    Soil Data
    is actually
    a May,
    1973 soiFTeport
    (Ex.
    12 Att.
    3); and Attachment
    8:
    89—10

    —9—
    Leachate Collection System Data
    is merely copies of
    a September,
    1982 letter from BFI and an October,
    1982 Agency letter
    (2 pages
    total),
    regarding
    a supplemental permit to operate
    a leachate
    collection system.
    (Ex.
    12 Att.
    8).
    While such use
    of pre-
    existing documents itself presents no problem, how
    it was done
    here does.
    The BFI plan presented difficulty
    in locating much
    of
    the pertinent information necessary to determine
    the nature of
    various aspects
    of the facility.
    Further, where the plan speaks
    in multiple places on the same
    issues
    it
    is occasionally
    internally inconsistent.
    This made evaluation more difficult.
    Some
    of these problems are noted
    in the discussion of
    the
    substantive issues which follows.
    SUBSTANTIVE ISSUES
    I.
    Leachate Head
    The first substantive
    issue before the Board
    is Modification
    Paragraph
    4,
    which would require SF1
    to maintain a maximum
    leachate depth of one foot
    (elevation
    713 feet),
    rather than the
    14
    foot (elevation
    726 feet)
    originally proposed by SF1
    in its
    plan.
    The Board believes that two provisions of the Act and two
    regulations should be applied
    to the facts
    in determining whether
    BFI has met its burden
    of proving
    that its proposed
    14
    foot
    maximum leachate head would
    not result
    in
    a violation.
    The
    provisions
    of the Act which seem particularly
    relevant are
    Sections 12(a)
    and 3.55.
    They provide:
    No person shall:
    a.
    Cause
    or
    threaten
    to
    cause
    or
    allow
    the
    discharge
    of
    any
    contaminants
    into
    the
    environment
    ...
    so as
    to cause or tend
    to
    cause
    water
    pollution
    ...
    or
    so
    as
    to
    violate
    regulations
    or
    standards
    adopted
    by the Pollution Control Board
    11l.Rev.,Stat.
    ch.
    111—1/2,
    Section
    1012
    (1988)
    “WATER
    POLLUTION”
    is
    such
    alteration
    of
    the
    physical,
    thermal,
    chemical,
    biological
    or
    radioactive
    properties
    of
    any
    waters
    of
    the
    State,
    or
    such
    discharge
    of
    any
    contaminant
    into
    any waters
    of
    the
    State,
    as
    will
    or
    is
    likely
    to
    create
    a
    nuisance
    or
    render
    such
    waters harmful
    or
    detrimental
    or
    injurious
    to
    public
    health,
    safety
    or
    welfare,
    or
    to
    domestic,
    commercial,
    industrial,
    agricul-
    tural, recreational,
    or other legitimate uses,
    or
    to livestock,
    wild animals,
    birds,
    fish,
    or
    other
    aquatic
    life.
    89—i 1

    —10—
    Ill.Rev.Stat.
    ch.
    111—1/2,
    Section
    1003.55
    (1988)
    The Act would therefore require that the record on review at
    least demonstrate that no contaminant will
    leave
    the facility as
    a part
    of the leachate and enter
    the underground waters of the
    state
    in
    a quantity or concentration that would cause
    a violation
    of the Board’s water quality standards.
    Those standards are
    found at 35
    Ill. Mm.
    Code Part
    302;
    see
    35 Ill.
    Adm. Code
    807.313
    (1984).
    The regulatory standards for closure performance and closure
    and post—closure care of
    an interim status hazardous waste
    facility are also directly applicable
    to the decision before the
    Board:
    The
    owner
    or
    operator must close
    his facility
    in
    a manner
    that:
    a)
    Minimizes
    the
    need
    for
    further
    maintenance;
    and
    b)
    Controls,
    minimizes or eliminates,
    to the
    extent
    necessary
    to protect human
    health
    and the environment,
    post—closure
    escape
    of
    hazardous
    waste,
    hazardous
    waste
    constituents,
    leachate,
    contaminated
    rainfall
    or
    waste
    decomposition products
    to the ground
    or surface waters
    35
    Ill. Mm.
    Code
    725.211
    (1984);
    see
    35
    111.
    Mm.
    Code
    807.313
    (1984)
    (codified version
    of
    pre—existing
    Chapter
    7:
    Solid
    Waste,
    Rule
    313).
    To this end,
    several specific facilities management
    requirements
    apply to the closure and post—closure care of
    a
    hazardous waste landfill.
    Pertinent
    to leachate management,
    the
    Board’s rules provide:
    b)
    In
    the
    closure
    and
    post—closure
    plans,
    the
    owner
    or
    operator
    must
    address
    the
    following
    objectives
    and
    indicate
    how
    they will be achieved:
    1)
    Control
    of
    pollutant
    migration
    from
    the
    facility
    via
    groundwater,
    surface water
    and air
    ...;
    C)
    The
    owner
    or
    operator
    must
    consider
    at
    least
    the following factors
    in addressing
    89—12

    —11—
    the
    closure
    and
    post—closure
    care
    objective
    of
    paragraph
    (b)
    of
    this
    Section:
    1)
    Type
    and
    amount
    of
    hazardous
    waste
    and hazardous waste
    constituents
    in
    the
    landfill;
    2)
    The mobility
    and
    the
    expected
    rate
    of migration
    of the hazardous waste
    and
    hazardous
    waste
    constituents;
    and
    3)
    Site
    location,
    topography
    and
    surrounding
    land use with respect
    to
    the
    potential
    effects
    of
    pollutant
    migration
    (e.g.,
    proximity
    to
    groundwater,
    surface
    water
    and
    drinking water sources);
    and
    d)
    During
    the post—closure care period the
    owner
    or
    operator
    of
    a
    hazardous
    waste
    landfill must:
    2)
    Maintain
    and
    monitor
    the
    leachate
    collection,
    removal
    and
    treatment
    system
    ...
    to
    prevent
    excess
    accumulation
    of
    leachate
    in
    the
    system
    35 Ill. Mm.
    Code 725.410
    (1984).
    Taken together, these various requirements establish a narrative
    standard for the review of the facts
    in this case.
    The facility
    operator must prevent
    the accumulation of excess leachate which
    would foster the migration
    of hazardous waste constituents,
    or
    other pollutant migration,
    into groundwater
    in
    a quantity or
    concentration that would cause water pollution.
    In evaluating
    whether water pollution might occur,
    the Board’s water quality
    standards would provide at least minimal guidance.
    The
    regulations also provide
    that the factors
    in Section 725.410
    (c)
    must
    be addressed
    in demonstrating whether
    the narrative standard
    will
    be met.
    In effect then,
    the Board must review BFI’s application
    to
    determine
    if
    it evaluates
    the necessary factors and contains
    sufficient factual
    information to at least demonstrate that
    a
    14
    foot leachate head will
    not cause migration
    of contaminants
    into
    groundwaters
    in
    a quantity
    or concentration that would violate
    the Board’s water quality standards.
    This
    is the standard which
    must be applied
    to the facts of
    this case.
    89—13

    —12—
    The Davis Junction Landfill
    is located on ground sloping
    towards
    the north—northwest.
    The direction of apparent
    groundwater
    flow is
    in the same
    direction.
    The excavation was
    in
    clayey bess and colluvial deposits;
    through water—bearing
    Farmdale sands; and into
    a dense,
    low—permeability
    till.
    About
    14 feet beneath
    the landfill invert
    is
    the “uppermost aquifer”:
    A 10 foot
    thick Kansan sand.
    (Ex.
    12, att.
    9).
    The Farmdale
    sand and Kansan sand aquifers apparently converge at some point
    north of
    the site.
    (Ex.
    12,
    Att.
    3,
    p.10).
    The landfill
    invert
    slopes 0.5
    from
    717 feet at the south end to
    712 feet at the
    north end.
    The lowermost natural contour along
    the perimeter of
    the Phase
    I excavation,
    which
    is at
    its north end,
    is about
    723
    feet.
    (Ex.
    27
    &
    29).
    At least
    the southern portion
    of the site
    is
    a groundwater recharge zone.
    (Ex.
    12, Att.
    3,
    p.
    11).
    The
    piezometric surface
    is nearly parallel
    to and about
    two feet
    below
    the invert.
    (Ex.
    12, Att.
    3).
    The record also
    conflictingly places the piezometric level slightly lower
    in an
    idealized cross—sectional drawing of the facility.
    It was on
    this idealized level
    that BFI
    based its containment
    calculations.
    (Ex.
    12, Att.
    2;
    Ex.
    26).
    Adjustment
    of the
    idealized level to the actual level otherwise indicated by the
    record could affect BFI’s containment estimates.
    A maximum leachate depth
    of
    14
    feet,
    at elevation 726 feet,
    is six feet below the top of the north berm, but between about
    one and five feet above
    the ground level north of the berm.
    (Ex.
    12, Att.
    2;
    Ex.
    28).
    The berm therefore acts as
    a dike retaining
    leachate
    in the fill.
    BFI calculated that the landfill would
    retain the leachate about 164 years before
    it migrated into the
    lower aquifer.
    To achieve
    this containment
    a gradient of less
    than 1.0 was deemed necessary,
    dictating
    a maximum leachate depth
    of 14
    feet at elevation
    726
    feet.
    Increased gradient would
    result
    in less containment.
    (Ex.
    12,
    Att.
    2,
    pp.
    6—7).
    Examination of BFI’s calculations reveals that
    the
    containment time
    is inversely proportional
    to the gradient and
    directly proportional
    to variation
    in the leachate depth.
    It
    appears that
    a one foot decrease
    in leachate depth from 726 feet
    decreases
    the gradient by 5.9
    and increases containment by 6.3,
    so decreasing
    the leachate depth
    to one foot
    (from 14
    feet)
    decreases the gradient
    to 0.235
    and
    increases
    contai,nment to 697
    years.
    This assumes
    a clay permeability
    of
    1
    x l0’
    cm/sec,
    or
    0.103
    feet per year,
    as relied on by BFI.
    (Ex.
    12, Att.
    2,
    p.
    10;
    Ex.
    26).
    The Agency asserted
    that the SF1 estimate of 164 years
    is
    based on ideal assumptions and does not reflect what
    is actually
    Occurring.
    The Agency believes that the formula employed, called
    Darcy’s
    Law,
    is
    the least accurate
    of
    a few options
    for
    estimating leachate losses from the fill under
    the circumstances
    here.
    (R.
    139).
    Further,
    the Agency believes
    that BFI’s
    application of Darcy’s
    Law may have inflated leachate retention
    89—14

    —13—
    by
    up
    to three
    times by failing
    to account
    for soil porosity.
    (R.
    145—46).
    In summary,
    BFI believes leachate will reach
    the lower
    aquifer
    in 164 years,
    and the Agency believes
    it will
    reach
    the
    lower
    aquifer
    in as little as about
    55 years.
    Unfortunately,
    this dispute misses the central
    issue.
    The question
    is not when
    leachate will
    reach the lower
    aquifer, but rather, what impact
    will
    it have when
    it does arrive?
    Contamination of
    an aquifer
    does not become acceptable simply because
    it will happen a
    specified number
    of years
    in the future.
    The record contains no
    evaluation
    of the impact the leachate will have
    on the aquifer,
    regardless
    of when
    it occurs.
    This
    is
    a serious deficiency
    in
    EFI’s
    case.
    The Agency expressed concern
    in its review of the original
    closure application because
    the data did not account for
    the
    movement
    of liquid through
    the landfill by calculating
    the amount
    of liquid entering and leaving
    the landfill.
    The Agency calls
    this method “water mass balancing” and asserts
    it
    is
    a more
    reliable method
    of estimating leachate
    loss
    in this particular
    case.
    (R.
    139).
    In effect, water entering the landfill by
    infiltration ultimately must either increase the leachate head or
    it must leave
    the landfill.
    BFI
    indicates
    that
    it has never
    removed leachate from the landfill, except
    to recirculate
    it back
    into the fill material.
    The leachate level achieved 726 feet
    in
    October,
    1982 and has not exceeded this level
    (R. 95—99; SF1
    Answers
    to Interrogatories).
    Since
    the evidence indicates no
    increase
    in the leachate head,
    the water must be exiting
    the
    landfill.
    Therefore,
    the respective estimates
    of how much
    infiltration
    is occurring become quite relevant.
    Estimates
    of infiltration submitted
    by BFI
    in
    response
    to
    the second Agency rejection of
    its plan indicate 8.64 inches
    of
    water
    per year percolate through the topsoil
    into the cover.
    SF1
    estimated
    a “conservative”
    1.96
    inches per year percolate through
    the cover
    into the waste.
    BFI does not account
    for the 6.68
    inches (8.64 inches less 1.96
    inches)
    of water per year which
    percolate
    through the topsoil
    but somehow do not penetrate
    to the
    waste.
    (Ex.
    6).
    The Phase
    I area
    is about
    22 acres
    (see Ex.
    27);
    See also
    Ex.
    16,
    p.
    3
    (indicating
    25 acres)),
    so
    infiltration
    of l.~6inches
    of water translates
    to about 98,100
    gallons
    per month.
    The “Soils Data” portion of BFI’s
    plan
    contains
    an engineer’s estimate from
    1973 that normal anticipated
    infiltration through the cover
    should amount
    to six
    inches per
    year,
    or
    4,000 cubic feet per day of leachate accumulation
    for
    4Phase
    1 occupies 22.1 acres
    (Ex.
    27).
    1.96 inches of
    infiltration through this area results
    in 1.18 million gallons
    per year,
    or 98,100 gallons per month,
    average.
    89—15

    —14—
    the entire
    70 acre area
    of all three phases
    of the landfill
    area.
    (Ex.
    12 Att.
    3
    p.
    16).
    This translates
    to 3.60 million
    gallons per year,
    or
    an average
    of 300,000 gallons
    per month,
    for
    a 22 acre area.
    The Agency testimony indicates an estimated
    313,000 gallons
    of infiltration per month based on BFI’s estimated figures.
    (R.
    149—50).
    The Agency did not provide
    the specifics
    of the
    calculation they used,
    but BFI did not rebut their figure with
    testimony at hearing
    or arguments
    in the briefs.
    In summary, BFI’s figures would show about 98,100 gallons
    per month will enter the landfill,
    the Agency believes about
    313,000 gallons
    per month will enter.
    Regardless
    of the exact
    amount,
    two critical question remain:
    (1) Where has
    this liquid
    gone
    in the past,
    and where will
    it go
    in the future when it
    leaves the landfill?; and
    (2) What
    is
    its impact on local
    groundwater quality?
    There are only two methods by which liquid
    will leave the landfill:
    by the drawdown sump or through
    the
    liner
    and into the groundwater.
    BFI variously proposed removing
    5000 gallons
    of leachate per
    month or 5000 gallons of leachate per week from the drawdown sump
    as
    a part
    of their proposed Closure/Post—Closure Plan
    (Ex.
    2;
    Ex.
    12, Att.
    8).
    Even assuming the higher weekly withdrawal
    rate,
    this leaves
    a substantial amount
    of leachate volume unaccounted
    for
    in
    the record.
    Assuming
    a 5000 gallon per week withdrawal
    rate and the SF1—based figures
    of 98,100 gallons
    per month
    infiltration, this leaves over 900,000 gallons of
    leachate
    migration out of
    the landfill per year
    in an unknown manner.
    Using
    the Agency estimate of 313,000 gallons
    of infiltration per
    month,
    the estimated annual loss would be
    3.5 million gallons.
    The Board would find the discrepancy between 900,000 gallons
    per year and 3.5 million gallons per year
    to be insignificant so
    long
    as
    the destination
    of this leachate were properly
    characterized and its impact properly evaluated.
    Unfortunately,
    that
    is not the case.
    The record does not provide guidance on
    where this leachate
    is going or its possible impact on
    destination.
    In
    fact,
    as shown
    in
    the next section of this
    opinion,
    the record does not provide an evaluation of what
    contaminant levels might exist
    in the leachate.
    This deficiency
    is
    fatal
    to BFI’s
    case.
    The Board
    is
    unwilling
    to conclude
    as
    a matter
    of law that over 900,000
    gallons of leachate per
    year from
    a hazardous waste landfill
    cannot cause pollution,
    and BFI has provided no information to
    allow that conclusion as
    a matter
    of
    fact.
    The Board must
    therefore conclude that BFI has not proven
    that the leachate head
    at
    14 feet will not cause migration of contaminants
    into
    groundwater
    in
    a quantity or concentration that would violate
    Board water quality standards
    or
    risk harm
    to the environment.
    89—16

    —15—
    Having concluded that
    the
    14
    foot
    leachate head
    is
    unacceptable,
    the Board will now evaluate wheth~r the Agency’s
    imposition
    of
    a one foot head was unreasonable.~ First, SF1 does
    not dispute
    that
    it
    is
    technically possible to withdraw leachate
    to a one foot head
    (R.
    89—90;
    172—73).
    The question
    is whether
    such action
    is
    reasonable when the economic cost
    is measured
    against
    the environmental benefit.
    SF1 has estimated
    the cost of
    removal at 40.5c~ per gallon for transportation,
    treatment, and
    disposal at Chem—Clear,
    based
    on the assumption
    of treatm~ntas a
    hazardous waste.
    This totals about
    $9.9 million
    (R. 89).° The
    record does not indicate whether
    BFI has considered
    lower cost
    alternatives
    or whether BFL merely presented the highest cost
    method
    of disposal
    to the Board.
    The record does not directly indicate the impact of such
    a
    removal, but some
    inferences are possible.
    Despite any alleged
    inaccuracy
    in BFI’s application of
    Darcy’s Law,
    the formula
    indicates
    that the rate
    of
    leachate retention increases
    proportionately with the decrease
    in maximum leachate depth.
    This would
    indicate
    a concommitant decrease
    in the rate
    of
    leachate
    loss.
    Further,
    assuming
    no change
    in the rate of
    infiltration, reducing the leachate depth could enhance
    the
    dilution effect of this
    infiltration over time.
    Unfortunately,
    BFI has not provided
    information which would
    allow an evaluation of the environmental
    impact of the 14 foot
    level,
    so
    it left the Agency to
    infer
    a substantial environmental
    benefit of
    reducing the level
    to one foot.
    Therefore,
    the Board
    cannot conclude that the economic cost
    to BFI
    of reducing the
    leachate head outweighs
    the resulting environmental benefit.
    The
    Board notes
    that the Agency repeatedly asked SF1
    to provide
    information that would have allowed Agency and Board evaluation
    of the reduced impact which would occur at
    the one foot head
    ~
    engaging
    in
    this concluding analysis,
    the Board
    has not
    placed the Agency
    “on trail,”
    as previously noted on page
    8 of
    this Opinion and Order.
    The Board merely augments its analysis
    by exploring
    the options available
    to the Agency as
    a result of
    BFI’s recalcitrance
    in forwarding necessary information
    to the
    Agency.
    6The Agency argues that the economic cost of compliance
    is
    immaterial
    (Agency Response at
    21).
    Whatever the pursuasive
    appeal
    of this argument
    in another
    context,
    it does not apply in
    such
    a proceeding
    as
    this,
    where
    the Board must exercise
    discretion,
    and the Agency must impose conditions “where
    environmental control standards are pliant
    to differing
    conditions
    ....“
    Commonwealth Edison Co.
    v.
    Pollution Control
    Board,
    127
    Ill.
    App.
    3d
    446,
    448,
    468 N.E.2d
    1339,
    1341
    (3d Dist.
    1984)
    89—17

    —16—
    level,
    but SF1 declined
    to provide
    it
    (Ex.
    2,
    6,
    8,
    9
    &
    11).
    Therefore,
    the Board must conclude that
    the one foot head level
    cannot
    be considered unreasonable.
    In summary,
    SF1 has failed
    to prove that the
    14 foot maximum
    leachate depth
    it originally provided
    in its Closure/Post—Closure
    Plan would
    not result
    in
    a violation of the Act.
    The record
    supports reducing
    the leachate depth
    to the minimum practicable
    level,
    and
    that the one
    foot level
    is technically feasible.
    SF1
    declined
    to provide information for the record which would allow
    a conclusion that the one foot level
    is unreasonable.
    Therefore
    the Agency imposition of
    a one foot leachate head level
    is
    affirmed.
    II.
    Leachate Characterization
    and Disposal
    The second substantive
    issue before the Board
    is
    Modification Paragraph
    3,
    which would require SF1
    to analyze
    its
    leachate and provide
    a proposed method
    of disposal:
    By
    October
    1,
    1984,
    a
    leachate
    evaluation
    report shall
    be submitted,
    which discusses the
    hazardous constituents, amount accumulated and
    suitable
    means
    of
    disposal
    of
    accumulated
    leachate.
    Analysis
    of
    the leachate shall
    be
    performed
    to
    determine
    concentration
    of
    all
    toxic
    or
    hazardous
    constituents
    which
    are
    hazardous
    by
    characteristic
    or
    are
    listed
    in
    40
    CFR
    261
    Appendix
    VIII.
    A
    proposal
    for
    disposal of the leachate shall be made.
    The Board believes that the same two provisions
    of the Act and
    same two regulations
    listed
    in Section
    I
    of this opinion,
    Leachate Head,
    should be applied
    to the facts here.
    Taken
    together,
    these statutory and regulatory requirements establish
    a
    narrative standard
    for review
    of the facts
    in this case.
    The
    facility operator must have sufficient information
    in the record
    regarding
    the characteristics
    of the hazardous wastes and
    the
    leachate
    in the landfill
    to demonstrate that migration of
    hazardous waste constituents,
    or other pollutant migration,
    into
    groundwater would
    not cause water pollution or environmental
    harm.
    In evaluating whether water pollution or environmental
    harm might occur,
    the Board’s water quality standards would
    provide at least minimal guidance.
    The regulations also provide
    that the factors
    in Section 725.410(c) must
    be addressed
    in
    demonstrating whether
    the narrative standard will be met.
    This standard will
    be particularly difficult
    for SF1
    to
    achieve,
    since
    the record already demonstrates that annually
    900,000
    to 3.5 million gallons
    of leachate leave
    the SF1 facility
    in an unknown manner.
    The burden
    is even more difficult
    for SF1,
    Since the record contains absolutely no chemical analysis
    of
    the
    89—18

    —17—
    leachate.
    Any
    evaluation
    of
    the
    character
    of
    the
    leachate
    must
    therefore be premised on knowledge of the wastes which were
    disposed of
    at the facility.
    Facility records indicate that SF1 disposed of about
    1,900,000 cubic yards
    (384 million gallons)
    of uncompacted waste
    in the landfill,
    of which about 36,000 cubic yards
    (7,300,000
    gallons),
    or
    about
    2
    are hazardous waste
    (Ex.
    12,
    pp.
    33
    & 14;
    Ex.
    6,
    p.
    3).
    BFI broadly describes
    the compositions of
    its
    hazardous wastes
    in
    a single paragraph:
    Of
    the
    hazardous
    wastes
    placed
    in
    the
    facility,
    approximate
    sic
    85
    were
    in
    solid
    or
    semi—solid
    form,
    while
    approximately
    15
    were
    in
    liquid form.
    Approximately 96
    of
    the
    hazardous
    wastes
    handled
    were
    heavy
    metal
    sludges
    typically
    produced
    by
    Rockford
    area
    industry.
    Of
    the
    total
    hazardous
    waste
    receipts,
    approximately
    60
    were
    waste
    classification
    F006
    (waste
    water
    treatment
    sludges
    from
    the electroplating
    industry)
    and
    31
    were waste classification DOOl—DOll
    (heavy
    metal
    EP
    toxicity).
    Approximately
    4
    (less
    than
    1,500
    cubic
    yards)
    of
    the
    hazardous
    wastes
    accepted
    are other
    than
    metal
    bearing
    sludges.
    This
    other
    category
    includes
    spent
    solvent
    still
    bottoms/sludges,
    petroleum
    refining
    residues
    and
    minor
    amounts
    of
    chemicals
    such
    as
    rodenticide,
    glycol,
    polystyrene
    and phthalic anhydride.
    (Ex.
    12,
    p.
    14)
    The 1,500 cubic yards
    (300,000 gallons)
    of hazardous wastes which
    BFI described as “other
    than metal bearing sludges” constitutes
    only 0.079
    of the total waste volume,
    but still represents
    a
    significant volume.
    The Board notes
    that use
    of compacted waste
    volumes would severely affect BFI’s hazardous waste proportion
    estimates.
    BFI further
    states that
    less than 0.1
    of the total waste
    volume
    (less than 1,900 cubic yards or 380,000 gallons)
    “consists
    of wastes
    that might produce volatile vapor which might contain
    hazardous constituents.”
    Included
    in this 0.1
    is the 0.000634
    of
    the total waste volume
    (12 cubic yards or
    2,400 gallons) which
    consists
    of
    solvents and petroleum refining resides
    (Ex.
    8,
    p.
    2;
    see
    R.
    160).
    This number,
    “0.000634,”
    is repeated frequently by
    BFI
    in the transcripts and briefs; however,
    its significance and
    accuracy are debatable
    in light of other record information.
    The record includes
    a June
    1,
    1982 survey of solvent
    disposal
    in
    Illinois landfills.
    The survey indicates BFI
    then
    held
    24 still—valid
    (at the
    time
    of the survey)
    disposal permits
    89—19

    —18—
    for
    a total
    of 2,190,000 gallons
    of solvent—containing wastes
    for
    this facility.
    Of these permits, six were for 1,1,1—
    trichloroethane,
    four were for alcohols,
    two for acetone,
    two for
    mineral spirits,
    and one for naptha.
    The survey concedes that
    Agency experience
    indicates that actual disposal volumes are
    substantially less than the permitted volumes.
    A detailed
    listing of
    the permits
    for
    the facility (which included permits
    which had expired
    prior
    to the survey date)
    indicates
    a total
    authorized volume of 3,460,000 gallons
    of various organic and
    chlorinated organic solvent—bearing wastes
    of various solvent
    contents,
    and
    of
    individual permitted volumes ranging
    up to 1.5
    million gallons
    (Ex.
    18).
    SF1 disputes this survey only by affirming that
    the volumes
    actually received were
    less than those permitted.
    BFI then
    singles out one entry,
    “1,500,000
    gallons
    solvents
    (97.5),”
    and states that BFI actually received 871,450 gallons
    of what
    “should have
    read,
    water
    and water soluble solvents
    97.5 percent”
    (R.
    92—93;
    Ex.
    18).
    Substantial clarification
    is necessary
    to
    harmonize the record information regarding SF1 solvent—bearing
    waste permits
    and BF1’s 0.000634
    assertion.
    In summary,
    the facility operated from December
    1976
    to
    January,
    1983.
    The record contains no information on the
    identities
    or volumes
    of hazardous waste received prior
    to
    1978.
    From 1978
    to November
    19,
    1980,
    the record contains
    generalized information
    that does not identify the wastes with
    particularity.
    The information on wastes disposed
    from November
    19,
    1980 onward may
    be adequate in content but only covers about
    35
    of the facility’s operational
    lifetime.
    Further, BFI’S
    Closure/post—Closure Plan only
    included “detailed” waste
    records
    for October and December,
    1982
    (Ex.
    12, Att.
    5).
    With such
    limited
    information the Board cannot conclude that SF1 has
    demonstrated that the identities and quantities
    of contaminants
    in the leachate are sufficiently characterized
    to prove
    that they
    will not cause environmental harm when released to the
    underground waters.
    In
    a similar vein, the Board must conclude that the Agency’s
    imposition
    of full Appendix VIII
    testing
    is appropriate and
    reasonable.
    With
    the quantity of leachate which
    is escaping from
    this facility to an unknown location the Board believes
    a full
    and complete chemical analysis to characterize that leachate
    is,
    at
    a minimum,
    reasonable.
    Therefore
    the Agency modification
    regarding leachate testing
    is affirmed.
    The Board
    is aware of
    89—20

    —19—
    the ~ost estimated by
    SF1
    as about $7,000 per sample
    (B.
    84—
    87).
    However,
    this cost may prove insignificant
    if
    an aquifer
    is
    at
    a significant risk of contamination.
    The second issue regarding Modification Paragraph
    3
    is the
    requirement that BFI submit
    a plan
    for leachate disposal.
    The
    BFI Closure/Post—Closure Plan submitted April
    13,
    1984 merely
    incidentally provided that SF1
    could remove excess leachate
    from
    the landfill
    if necessary
    (Ex.
    12, pp.
    13,
    17,
    18
    & Att.
    2,
    p.
    7).
    BFI
    included
    in
    its plan the October
    5,
    1976 Application for
    Supplemental Development Permit which changed the original plan
    for leachate disposal at
    a sewage treatment plant
    to one of
    containment and natural soil attenuation
    (Ex.
    12, Att.
    2,
    p.
    5;
    Ex.
    26,
    p.
    5).
    This document did not and could not provide
    for
    the hazardous waste nature of the facility and
    leachate.
    Another
    attachment from September
    16,
    1982 regarded a supplemental permit
    for leachate removal.
    It provided
    for disposal
    in the “active
    dry refuse daily fill”
    (Ex.
    12,
    Att.
    8;
    Ex.
    21).
    The plan
    included
    no other provisions
    for leachate disposal.
    SF1 did not
    address
    leachate disposal
    in
    its June
    4,
    1984 reply
    to the
    initial
    Agency rejection,
    but highlighted
    the containment—natural
    attenuation provision of
    its October,
    1976 Application
    (Ex.
    8,
    p.
    4).
    It
    is apparent from the SF1 brief that this plan of
    containment and natural attenuation
    is its leachate disposal plan
    (Petitioner’s Brief at 23).
    This brief, however, was not before
    the Agency on July 27,
    1984
    any merit or lack
    of merit
    to this
    mode
    of disposal notwithstanding.
    BFI finally proposed
    in
    its July
    25,
    1984
    letter to the
    Agency
    to remove 5,000 gallons
    per month,
    analyze
    it
    for
    hazardous characteristics
    and constituents,
    and “dispose of the
    waste
    in accordance with applicable
    state regulations.”
    BFI
    conceded
    it would consider the waste hazardous because derived
    from hazardous wastes,
    and expressed
    a possible intent
    to file
    for delisting
    and withdraw less from the landfill
    if experience
    proved
    it
    to not possess hazardous characteristics
    or contain
    hazardous constituents
    (Ex.
    2,
    p.
    2).
    The SF1 plan did not provide any single, acceptable
    provision which outlined any sound method
    for disposal
    of excess
    7There
    is some confusion as
    to the actual cost of this screen-
    ing.
    Agency Modification Paragraph
    3
    at
    issue
    required BFI
    to
    submit only
    a single report characterizing
    the leachate
    (Ex.
    I,
    p.
    1).
    BFI understood
    this to mean performing each analysis on
    four replicate samples
    (R.
    86).
    This inflates the cost
    to
    the
    $28,000 asserted by BFI
    (See
    R.
    84—87; Petitioner’s Brief
    at
    12).
    Nothing
    in the record clarifies this apparent
    discrepancy.
    The Board makes no attempt to give
    any opinion on
    this apparent discrepancy,
    but merely observes its existence.
    89—21

    —20—
    leachate during
    the closure and post—closure periods.
    The BF’I
    plan must include such
    a provision and outline
    a procedure for
    leachate disposal with reasonable particularity.
    The Board gives
    no opinion as
    to what constitutes an acceptable plan or method
    of
    disposal,
    beyond the determination that the plan outlined
    by BFI
    did not satisfy the requirements
    of the Act and regulations.
    The
    Board affirms
    the Agency condition requiring SF1
    to submit
    a
    disposal plan.
    III.
    Groundwater Monitoring
    The third substantive issue before the Board
    is groundwater
    monitoring criteria and Agency Modification Paragraph
    5(j).
    This
    imposes
    the additional
    requirement that BFI monitor
    the
    groundwater for three specific halogenated otganic solvents:
    l,l,1—trichloroethane,
    trichloroethylene,
    and methylene chloride
    (EX.
    1,
    pp.
    2—3).
    SF1 already monitors the groundwater
    for
    total
    organic carbon
    (TOC)
    and total organic halide
    (TOX)
    (Ex.
    12,
    Att.
    9;
    Petition at 7—8;
    Petitioner’s Brief at 34—35).
    BF1 estimates
    that the cost of these additional analyses
    is $300 per monitoring
    sample,
    or about $252,000 throughout
    the post—closure period
    (Petitioner’s Brief
    at
    36;
    R.
    90).
    SF1 contends that the testing
    for TOC and TOX would sufficiently detect groundwater
    contamination because
    they would both detect the presence of all
    three halogenated solvents
    (Petitioner’s Brief at 35).
    The regulations require the owner
    or operator
    of
    a landfill
    to “implement
    a groundwater
    monitoring program capable
    of
    determining the facility’s
    impact on the quality of groundwater
    in the uppermost aquifer underlying the facility
    ....“
    35 Ill.
    Mm.
    Code 725.190(a)
    (1984).
    The regulations provide
    for testing
    for various criteria,
    including TOC and TOX,
    but not explicitly
    including
    the three organic solvent parameters
    imposed by the
    Agency.
    35
    Ill.
    Adm.
    Code 725.192(b)
    & App.
    C
    (1984);
    see
    40 CFR
    265 App.
    III
    (1984).
    The regulations do provide for more
    extensive monitoring
    once contamination
    is suspected
    based on the
    routine monitoring results, when the facility
    is engaged
    in
    assessment monitoring.
    35 Ill.
    Adm.
    Code 725.193
    (1984).
    This
    would provide
    a firm basis for selecting additional
    testing
    criteria
    in such
    a circumstance, but this does not specifically
    require inclusion of additional criteria as part of
    the routine
    monitoring.
    The Agency once did notify SF1 on June
    18,
    1982 that
    it would require groundwater monitoring
    for the three halogenated
    solvent parameters
    (Ex.
    19),
    but did not include them in the
    testing criteria stipulated
    in BFI’s December
    20,
    1983
    Supplemental Permit No.
    1983—74
    (Ex.
    12,
    Att.
    9).
    The record
    indicates that unknown quantities
    of 1,1,1—
    trichloroethane,
    trichloroethylene, and methylene chloride are
    likely resident
    in
    the landfill.
    All are named
    as having been
    permitted
    for disposal
    at the site
    in various quantities and
    concentrations
    (Ex.
    18).
    The record indicates controversy as
    to
    89—22

    —21—
    whether these solvents are among several
    that may significantly
    increase
    the permeability
    of landfill clay liners
    (Ex.
    18; Ex.
    8,
    pp.
    2—3).
    These parameter—specific tests may prove of special
    concern
    for this reason,
    but also
    for their greater sensitivity
    and specificity.
    The record indicates
    that TOC includes both
    naturally—occurring
    and man—made organic compounds.
    TOX
    specifically detects chlorinated organic compounds,
    including
    these three specific chlorinated solvents
    (R.
    115;
    Petitioner’s
    Brief at 35).
    The detection limits for the TOC and TOX testing
    procedures, however,
    are higher than
    those
    for
    the specific
    compounds
    (B.
    116;
    Agency Brief at
    22).
    Further, the TOC and TOX
    procedures would detect broad classes of compounds
    of no
    environmental concern
    (Agency Srief
    at
    22).
    These
    facts force
    the conclusion that the more specific testing
    for the individual
    compounds
    is more desirable,
    especially since
    they are probably
    present
    in the landfill
    in some quantities and they are of
    particular
    technical
    and regulatory concern.
    Further, testing
    for these specific solvent parameters would likely prove more
    protective
    of the environment.
    In Waste Management,
    Inc.
    v.
    Illinois Environmental
    Protection Agency,
    PCB 84—45,
    PCB 84—61
    & PCB 84—68
    (Oct.
    1,
    1984),
    aff’d sub
    norn.
    Environmental Protection Agency
    v.
    Pollution Control Board,
    138 Ill.App.3d
    550,
    486 N.E.2d
    293
    (3d
    Dist.
    1985),
    aff’d
    115 Ill.2d 65,
    503 N.E.2d
    343
    (1986),
    the
    Board observed that the Agency has traditionally had
    discretionary authority
    to prescribe reasonable groundwater
    monitoring criteria as part of
    its landfill permitting
    authority.
    Waste Management at
    23.
    One restriction on this
    authority
    was
    that
    the
    criteria
    imposed
    must
    be
    necessary
    to
    accomplish the purposes
    of the Act and not
    be inconsistent with
    Board regulations.
    Id.
    at
    19.
    A second restriction was that the
    criteria selection must be based on what wastes are resident in
    the landfill.
    Id.
    at
    24.
    The present proceeding
    is very similar
    to Waste Management,
    with one major exception:
    SF1 has failed
    to
    characterize
    its leachate either by analysis or
    by providing
    a
    detailed inventory of
    the wastes
    in the landfill.
    In the absence of
    necessary information;
    in light of the
    fact that l,l,l—trichloroethane,
    trichloroethylene, and methylene
    chloride are probably present
    in the landfill; and because the
    specific analyses
    for these criteria
    is more sensitive and
    conveys more pertinent information,
    the Board concludes
    that the
    Agency acted properly
    to require testing for these specific
    parameters
    to assure
    that
    no violation of the Act or regulations
    would occur.
    This conclusion results
    from the inadequacy
    of the
    information which BFI provided the Agency.
    The Board affirms
    the
    Agency modification.
    89—23

    —22—
    IV.
    Statistical Analysis
    The fourth substantive
    issue concerns Agency Modification
    Paragraph
    5(1),
    which requires SF1
    to statistically analyze
    its
    groundwater monitoring results using
    the .1 level
    of Cochran’s
    Approximation of the Behrens—Fisher Student’s T—Test
    as set forth
    in the regulations.
    35
    Ill.
    Adm.
    Code 725 App. D (1984);
    40 CFR
    265 App.
    IV
    (1984).
    The BFI submissions
    to the Agency included
    no provision for
    a test for significance.
    (See Ex.
    2,
    6,
    8,
    & 12
    Att.
    9.)
    Even
    if they had provided another
    test,
    it would have
    riot complied with Board regulations.
    The regulations require the
    test imposed by
    the Agency.
    35 Ill. Adm. Code 725.193(b)
    (1984).
    SF1 argues that controversy surrounds the use of this test
    and that more reliable tests exist
    (Petition at
    8; Petitioner’s
    Brief
    at 36—37;
    see B.
    51—52).
    This
    is irrelevant because
    the
    Agency lacks authority
    to substitute
    any alternative
    in the face
    of
    an explicit regulatory directive.
    Ill.Rev.Stat.
    Ch. 111—1/2,
    Section 1039
    (1988);
    35 Ill.
    Adm. Code 702.108(a)
    (1984).
    The
    Agency modification
    is affirmed.
    V.
    Agency Plan Modification
    The final
    substantive
    issue concerns
    a proviso set forth by
    the
    Agency
    in
    its
    final
    modification
    of
    the
    SF1
    plan:
    If
    the
    Agency
    determines
    that
    implementation
    of
    the Closure
    and Post—Closure Plan fails
    to
    satisfy
    requirements
    of
    35
    Ill.
    Mm.
    Code
    725.211,
    the
    Agency
    reserves
    the
    right
    to
    amend
    this
    Closure
    and
    Post—Closure
    Plan.
    (Ex.
    1,
    p.
    5).
    BFI argues that the Agency lacks authority to modify the plan and
    that such a unilateral modification would violate
    its due process
    rights (Petitioner’s Brief at 38—39; Petitioner’s Reply Brief
    at
    17—18).
    The Board’s regulations include
    a provision whereby the
    Director
    of the Agency can modify
    a plan “if he deems
    it
    necessary
    to prevent threats
    to human health and the
    environment.”
    35
    Ill. Adm. Code 725.218(f)(2)
    (1984).
    This
    provision includes an opportunity for public notice,
    public
    hearing,
    and consideration
    of comments prior
    to
    a final decision,
    and provides
    criteria for decisionmaking.
    Further, the rules
    give SF1 a
    right
    to appeal the Agency modification,
    just as SF1
    has done
    in this proceeding.
    35
    111. Mm.
    Code 725.218(g)
    (1984).
    The Agency asserts no extra—statutory authority in this
    concluding proviso which does not comport with BFI’s due process
    rights.
    See Waste Management at 20—21.
    The Agency modification
    is affirmed.
    89—24

    —23—
    In summary,
    the Board affirms
    all five modifications
    to the
    BFI Closure/Post—Closure Plan.
    This decision
    is largely
    predicated
    on
    a
    lack
    of
    necessary
    information
    in
    the
    record
    to
    adequately support BFI’s plan as submitted to the Agency.
    The
    Board acknowledges
    that the real issues involved in this case are
    the leachate depth and groundwater monitoring
    issues.
    These are
    the “big ticket”
    items which will cost SF1 many dollars over
    several years.
    The Board notes, however,
    that SF1 will
    be free
    to petition the Agency
    for modification, when
    it has assembled
    sufficient information
    to demonstrate that less stringent
    requirements are justified.
    See 35
    Ill.
    Adm. Code 725.218
    (1988).
    To do
    this,
    BFI must acquire
    the necessary data
    data
    which are lacking
    in this proceeding.
    Supplemental Issues
    Two supplemental issues
    in
    this proceeding deserve
    attention.
    The first supplemental
    issue before the Board regards
    the scope and content
    of the Agency record on review.
    The Board
    must constrain
    its review to the record before the Agency when
    it
    modified the SF1 Closure/Post—Closure Plan on July 27,
    1984 and
    that developed at
    the hearing.
    Environmental Protection Agency
    v. Pollution Control Board,
    118 Ill.App.3d 772,
    780—781, 455
    N.E.2d
    188,
    194 (1st Dist.
    1983);
    1l1.Rev.Stat.
    ch.
    111—1/2,
    Section 1040(d)
    (1988);
    35
    Ill. Mm.
    Code l05.103(b)(2)
    (1982).
    The Board
    rules governing permit appeals provide that the Agency
    has a certain
    time
    following the filing of an appeal petition to
    file “the entire Agency record of the permit application
    ....“
    35
    Ill. Mm.
    Code l05.102(a)(4)
    (1982).
    The issue arises
    in this
    proceeding whether certain evidence
    is admissible
    in light of
    these restrictions.
    By the April
    4,
    1988 “Attachment
    A”
    to its April
    1,
    1988
    Respondent’s Brief,
    the Agency seeks
    to admit several additional
    documents
    to the Board record.
    BFI has challenged the admission
    of these documents
    in its April
    8,
    1988 Petitioner’s Reply
    Brief.
    These include the following documents which were not part
    of the Agency record submitted
    in 1985:
    1.
    A July
    29, 1982 BFI submission
    of ground-
    water
    monitoring
    results
    from
    April
    8,
    1982
    indicating
    an
    elevated lead content
    in the groundwater;
    2.
    A
    March
    2,
    1983
    Andrews
    Engineering
    letter
    to
    the
    Agency
    indicating
    that
    several
    revisions
    and
    upgradirigs
    were
    necessary
    to the BFI groundwater monitor-
    ing
    wells
    so
    they
    might
    provide
    more
    reliable
    results
    from
    the
    lower
    Kansan
    Sand
    aquifer
    underlying
    the
    fill,
    rather
    than
    the
    upper
    Farmdale
    Sand
    aquifer
    89—25

    —24—
    which
    “pinches
    out” down gradient
    of
    the
    fill,
    which
    the fill
    transects,
    and
    which
    is
    cut—off
    from
    the
    fill
    by
    a
    clay
    barrier wall
    (See
    B. Exs.
    27—29);
    3.
    A May
    20,
    1983 Andrews Engineering letter
    to
    the Agency regarding
    the
    installation
    of
    10 new groundwater monitoring wells,
    7
    immediately
    and
    3
    at
    a
    future
    time,
    and
    acknowledging
    Agency
    stringency
    on
    monitoring criteria selection;
    4.
    A
    May
    27,
    1983
    Agency
    letter
    to
    SF1
    granting
    supplemental
    permit
    1983—74
    for
    the
    installation
    of
    11
    monitoring
    wells,
    three
    in
    the future,
    imposing
    a require-
    ment
    for quarterly
    analysis
    for
    TOC
    and
    TOX,
    and
    requiring
    collection
    of
    data
    that
    could
    indicate
    both
    horizontal
    and
    vertical
    groundwater
    flow
    at
    the
    site;
    and
    5.
    A September
    26,
    1984 Agency
    letter to SF1
    identifying
    three
    apparent
    violations
    of
    the Board rules:
    a.
    failure
    to
    perform
    the
    required
    Student’s
    T—Test
    statistical
    analysis
    of
    groundwater
    monitoring
    data
    (See
    35
    Ill.
    Adm.
    Code
    725.l93(5T(l984)
    b.
    failure
    to provide written notice
    to
    the Agency
    that
    the landfill may
    be
    affecting groundwater quality if the
    statistical
    test
    indicates
    a signi-
    ficant
    increase
    in
    groundwater
    quality indicators
    or decrease
    in pH
    (See 35
    Ill. Adm. Code 725.l93(d)(l)
    (1984));
    and
    c.
    failure
    to
    submit
    a
    certified
    groundwater
    quality
    assessment
    program
    to
    the
    Agency
    (See
    35
    Ill.
    Mm.
    Code 725.l93(d)(2)
    (1984)).
    based
    on
    May
    18,
    1984
    groundwater moni-
    toring
    data,
    which
    showed
    statistically
    significant
    increases
    in
    specific
    conductance
    and
    decreases
    in
    pH
    at
    various
    downgradient
    site
    monitoring
    wells,
    and
    on
    August
    7,
    1984
    data which
    89—26

    —25—
    confirmed the pH decrease in these wells,
    the
    specific
    conductance
    increase
    in
    some,
    a
    TOX
    increase
    in
    one,
    and
    a
    TOC
    increase
    in another.
    The Agency failed
    to explain
    in
    its April
    1,
    1988 brief why it
    did not tender these documents with the Agency record on October
    25, 1985.
    The July 29,
    1982 letter,
    the March
    2,
    1983 proposal,
    the
    May 20, 1983 application,
    and the May 27,
    1983 supplemental
    permit were before the Agency when it made its July
    27,
    1984
    decision
    to modify BFI’s Closure/Post—Closure Plan.
    Therefore,
    the Agency could have properly included those documents into the
    record for Board
    review.
    The September
    26,
    1984 letter post-
    dated
    the Agency permit decision and could not have been properly
    included
    in the record.
    However,
    the letter itself cited May 18,
    1984 monitoring data which
    indicated possible contamination.
    This information could have been included
    in the Agency record.
    The Board admonishes
    the Agency to assure that such infor-
    mation
    is submitted with the Agency record or brought out prior
    to the hearings.
    Since the Board has made its decision based on information
    submitted by the Agency on October
    25,
    1985,
    and without
    considering
    these late—filed documents,
    the question of
    the
    admissibility of this late—filed information need not be decided.
    The second supplemental
    issue before the Board
    is the
    applicability of the regulations at
    35 Ill. Mm.
    Code Part 724
    to
    BFI’s facility.
    Both parties agreed that Part 725 regulations
    applied
    to the permit decisions,
    and that Part 724 did not
    directly apply.
    The Agency contended
    that Part
    724 provides at
    least minimal guidance.
    The Board has avoided Part 724.
    It has
    decided
    this proceeding based solely on Illinois law and
    regulations as they stood on July 27, 1984 and applied under Part
    725
    to interim status facilities.
    The Board observes,
    however,
    that certain state and federal regulatory changes are now
    in
    progress that will affect the future application of
    this
    decision.
    SF1
    asserts:
    The
    Agency
    attempted
    to
    apply
    the
    more
    stringent
    closure/post—closure
    standards
    of
    Section
    724
    to
    the
    subject site
    based
    on
    its
    belief
    that
    as
    an
    interim
    status
    site,
    SF1
    would
    ultimately
    have
    to
    obtain
    a
    Part
    B
    permit
    and
    would
    then
    be
    subject
    to
    the
    Section 724 standards.
    T.
    41—42,
    T.
    131.
    BFI
    has
    reviewed
    the
    relevant
    statutes
    and
    89—27

    —26—
    regulations,
    together
    with
    the
    relevant
    preambles
    and
    USEPA
    memos,
    and
    has
    concluded
    that
    no
    further
    post—closure
    permit
    would
    be
    required
    by
    the
    facility
    once
    it
    filed
    and
    obtained approval
    of its closure plan.
    Petitioner’s Brief,
    p.
    30.
    The Board agrees that
    in 1984 the Agency could
    not properly have
    applied the Part 724 standards
    to BFI’s facility,
    and that
    no
    further permits would have been required.
    That
    is not,
    however,
    true
    today.
    In 1984, Congress amended RCRA to add new Section 3005
    (i).
    That provision
    requires all hazardous waste facilities
    which had received hazardous wastes after July 26,
    1982,
    to
    comply with certain regulatory
    requi.rerner.ts
    for new facilities.
    On
    December
    1,
    1987,
    USEPA
    adopted
    final
    regulations
    implementing
    Section
    3005
    (i)
    at Volume
    52, page 45788
    of
    the
    Federal
    Register.
    That regulation
    not only requires compliance with the
    federal equivalent
    of Part
    724,
    but the preamble to the
    regulation makes
    it clear that such facilities must submit
    a Part
    B application and obtain
    a RCRA permit:
    Therefore,
    today’s
    final
    rule
    differs
    from
    the
    proposed
    revision
    to
    Section
    270.1(c)
    by
    requiring
    post—closure
    permits
    for
    any
    landfill,
    surface
    impoundment,
    waste
    pile,
    or
    land
    treatment
    unit
    which
    received
    waste
    after
    July
    26,
    1982,
    or
    which
    closed
    after
    January
    26,
    1983.
    The term
    “closure”
    in this
    context
    has
    been
    clarified
    to
    mean
    certification
    of
    closure according
    to Section 265.115.
    52 Fed. Reg.
    45794—95
    (Dec.
    1,
    1987).
    Since
    BFI’s facility received hazardous waste
    after July
    26,
    1982, and did not certify closure prior
    to January 26,
    1983
    (see
    35
    Ill.
    Adm.
    Code 725.215
    (1988);
    40 CFR, Section 265.215
    (1987)), SF1
    is clearly subject
    to the December
    1,
    1987
    regulations.
    Further,
    those federal regulations are legally
    applicable
    to SF1
    as
    of December
    1,
    1987:
    Prior
    to
    FISWA
    a State with final authorization
    administered
    its
    hazardous
    waste
    program
    entirely
    in
    lieu
    of
    the
    Federal program.
    The
    Federal
    requirements
    no
    longer
    applied
    in the
    authorized
    State,
    and
    EPA
    could
    not
    issue
    permits
    for
    any
    facilities
    in
    a
    state
    where
    the
    State
    was
    authorized
    to
    issue
    permits.
    When
    new,
    more
    stringent Federal
    requirements
    were
    promulgated
    or
    enacted,
    the
    State
    was
    obligated
    to enact equivalent authority within
    89—28

    —27-
    specified
    time
    frames.
    New
    Federal
    requirements
    did
    not
    take
    effect
    in
    an
    authorized
    State
    until
    the
    State
    adopted
    the
    requirements
    as State
    law.
    In contrast,
    under
    Section
    3006(g)
    of
    RCRA,
    42
    U.S.C.
    6926(g),
    new
    requirements
    and
    prohibitions
    imposed
    by
    the
    HSWA
    take
    effect
    in
    authorized
    States
    at
    the
    same
    time
    they
    take
    effect
    in
    nonauthorized States.
    EPA
    is
    directed
    to
    carry
    out
    those
    requirements
    and
    prohibitions
    in
    authorized
    States,
    including
    the
    issuance
    of
    permits,
    until
    the
    State
    is
    granted authorization
    to
    do
    so.
    While States
    must
    still
    adopt
    HSWA—related
    provisions
    as
    State
    law
    to
    retain
    final
    authorization,
    the
    HSWA
    requirements
    are
    applied
    by
    EPA
    in
    authorized States
    in the interim.
    Today’s
    rule
    is
    promulgated
    pursuant
    to
    RCRA
    Sections 3004(u),
    3004(v)
    and
    3005(t).
    These
    provisions were added by HSWA.
    Therefore,
    the
    Agency
    is adding the requirement
    to Table
    1
    in
    Section
    271.1(j)
    which
    identifies
    the Federal
    program
    requirements
    that
    are
    promulgated
    pursuant
    to
    HSWA
    and
    that
    take
    effect
    in
    all
    States,
    regardless
    of
    their
    authorization
    status.
    52
    Fed.
    Reg.
    45796
    (Dec.
    1,
    1987).
    Therefore, while the Agency could not,
    in
    1984, properly apply
    the state counterpart of the
    federal Part 264 regulations to SF1,
    a substantial portion
    of the impact of today’s decision has been
    undercut by developments
    in federal law during the pendancy of
    this permit appeal.
    Those federal regulations do apply
    to BFI’s
    facility today as
    a matter
    of federal
    law,
    and they have since
    December,
    1987.
    Today’s Board decision does not imply
    that they
    do
    not.
    On February
    25,
    1988,
    the Board proposed state regulatory
    counterparts
    to the USEPA December
    1,
    1987 regulations
    (R87—39)
    for public comment.
    (R87—39; see
    12 Ill.
    Beg.
    6476
    (Apr.
    8,
    1988)).
    Any final adoption
    of these regulations would apply
    to
    BFI’s facility.
    The Board
    is specifically not making any
    decision as
    to what actions,
    if
    any, would be required at the BFI
    facility under any final adoption of these proposed regulations.
    Once the R87—39 and several other regulatory proceedings are
    final,
    the State will attempt to secure HSWA approval from
    USEPA.
    Today’s decision interprets 1984
    law and has no bearing
    on the State’s HSWA regulatory
    package.
    89—29

    —28—
    This
    Opinion
    constitutes
    the Board’s findings of facts
    and
    conclusions of law
    in this matter.
    ORDER
    The Illinois Environmental Protection Agency’s Modification
    Plan
    of July 27,
    1984
    for Browning—Ferris
    Industries of Illinois,
    Inc.
    Closure and Post—Closure Plan
    for
    its Davis Junction
    Landfill facility
    is hereby affirmed by the Board.
    Section
    41
    of the Environmental Protection Act,
    Ill.
    Rev.
    Stat.
    1985,
    ch.
    111—1/2,
    par.
    1041, provides
    for appeal
    of final
    Orders
    of the Board within
    35 days.
    The Rules
    of the Supreme
    Court
    of Illinois establish filing requirements.
    IT
    IS SO ORDERED
    I,
    Dorothy
    M. Gunn, Clerk
    of the Illinois Pollution Control
    Board, hereby certify
    that the above Opinion and Order was
    adopted
    on the
    ...ftz
    day of
    —~c_~
    ,
    1988,
    by
    a
    voteof
    7_o
    /
    Dorothy
    NI. Gum,
    Clerk
    Illinois Pollution Control Board
    89—30

    Back to top