ILLINOIS POLLUTION CONTROL BOARD
February 23, 1989
HYDRO—LINE MANUFACTURING CO.
(Winnebago County, L2010305085)
)
Petitioner,
)
v.
)
PCB 89—39
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
ORDER OF THE BOARD (by 3. Marlin):
This matter comes before the Board upon receipt of an Agency
Recommendation dated February 22, 1989. The recommendation
refers to a request from Petitioner, Hydro—Line Manufacturing
Company for a 30 day provisional variance from the 90—day on—site
limitations for hazardous wastes set forth at 35 Iii. Adm. Code
722.134(b).
Upon receipt of the request of the Agency issued its
reconimendation, concluding that the hazardous wastes must remain
on—site for longer than 90 days due to unforeseen, temporary and
uncontrollable circumstances and failure to grant the requested
30—day provisional variance would impose an arbitrary or
unreasonable hardship on Petitioner.
The Board concurs with the Agency Recommendation; Petitioner
is granted a provisional variance from 35 Iii. Adm. Code
722.134(b) from January 22, 1989 to February 21, 1989.
IT IS SO ORDERED.
I, Dorothy ~4Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the above Order was adopted on the
____________
day of ________________________, 1989, by a vote of
7~—o
Dorothy M./)~3unn, Clerk,
Illinois P’ollution Control Board