ILLINOIS POLLUTION CONTROL BOARD
    January
    5,
    1989
    VILLAGE OF WINNETKA,
    )
    Petitioner,
    )
    V.
    )
    PCB 88-164
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    )
    Respondent.
    HARVEY
    M.
    SHELDON AND SHELL J. BLEIWEISS OF McDERMOTT,
    WILL,
    & EMERY APPEARED
    DN BEHALF
    OF PETITIONER THE VILLAGE OF W~NNETKA.
    WILLIAM
    0.
    INGERSOLL APPEARED ON BEHALF OF RESPONDENT THE
    ILLINOIS
    ENVIRONMENTAL PROTECTION AGENCY.
    OPINION OF THE BOARD (by J. Theodore Meyer):
    On December
    15, 1988,
    the
    Board granted
    the Village of Winnetka
    (Winnetka)
    a
    variance from 35
    Ill. Adm. Code 212.201
    until
    September 30,
    1991.
    The variance, which
    is subject
    to conditions, will
    allow Winnetka time
    to design, install, and test control equipment sufficient
    to comply with
    Section 212.201.
    This Opinion
    supports
    the December
    15,
    1988 grant of the
    variance.
    Background
    Winnetka owns
    and operates an electric generating plant
    on Tower Road at
    Lake Michigan.
    The plant consists primarily of five boilers and two diesel
    engines.
    Boiler
    ~4
    burns natural
    gas, boilers ~5, 6 and
    7 burn only coal, and
    boiler
    #8 can burn natural gas,
    coal, or a combination of the two fuels.
    The
    two diesel
    engines and boilers ~4 and 8 are presently permitted to operate.
    Only boiler ~8 is equipped with particulate controls.
    One comon
    stack serves
    all equipment.
    The coal burning operation ~f boiler ~3 is
    the subject
    of
    Winnetka’s variance request.
    In
    1986 the Board promulgated Section
    212.201, from which Winnetka now
    seeks
    a variance.
    That section establishes
    a particulate emission limit of
    0.1 pounds
    of particulate matter per million British thermal
    units
    (ibs/MBtu)
    (0.15 KgI~—hr)for coal-fired boilers
    in the Chicago area,
    In the same
    rulemaking (R82—1), the Board
    provided a temporary site-specific limit
    of 0.25
    lbs/MBtu
    for the Winnetka plant.
    The site-specific limit,
    found
    at
    35 Ill.
    Mm. 212.209, was effective
    until
    January
    1,
    1989,
    or until
    the Board took
    final
    action
    in
    a
    site—specific rulemaking.
    Winnetka
    then petitioned for
    a
    permanent 0.25 lbs/MBt~limit.
    The Board denied that petition on August
    4,
    1988.
    Proposed Amendment to
    35
    Ill. Adm. Coae 212.209, Village
    of Winnetka
    ~5—45

    —2-
    Generating Station, R86-41, August
    4,
    1988.
    On November
    3,
    1988,
    the Board
    denied Winnetka*s motion for reconsideration.
    Thus, Section
    212.201
    is now
    applicable to the Winnetka plant.
    Relief Requested and Compliance Plan
    Winnetka does not presently have sufficient control
    equipment on
    its
    boilers
    to comply with the 0.1 lbs/MBtu
    limit while burning coal.
    Thus,
    Winnetka
    seeks this variance
    to allow some operation on coal
    while the
    necessary control equipment is being designed, installed,
    and tested.
    The
    variance request, which was apparently discussed
    and agreed upon with the
    Illinois Environmental
    Protection Agency
    (Agency) prior
    to the
    filing
    of the
    petition,
    is designed to minimize the amount
    of coal
    used by Winnetka during
    the period
    of the variance.
    Only boiler ~8 is covered by the requested
    variance, although Winnetka apparently plans
    to
    install
    control equipment
    on
    boilers
    #7
    and 8.
    (Boiler
    #7
    is not presently permitted
    and
    thus cannot
    be
    operated.)
    The variance would mandate Winnetka~suse of reasonably available
    gas or electricity from other sources, including:
    (1) WinnetKa~sown
    production using
    gas
    or diesel
    oil;
    (2)
    electricity purchases from other
    utilities; and
    (3)
    use of natural
    gas.
    Wirrnetka would
    be allowed
    to ourn
    COCi
    to produce electricity only when
    it
    is
    unable
    to purchase electricity from
    another source
    for less than 31 mils per kilowatt hour (miis/KWH),
    or purchase
    natural
    gas
    at
    a
    price
    such
    that
    the
    cost
    of
    production
    is
    1C55
    than
    31
    mils/KWH.
    (31 mils/KWH
    is
    3.1
    cents
    per
    kilowatt
    hour:
    1000
    mils=
    S1.OO.)
    The only exception to this restriction
    is
    that
    coal could
    be
    burned
    in
    small
    quantities
    as
    necessary to
    maintain
    the
    protective
    ash
    on
    the boiler grate.
    (See R.
    33—34.)
    Unless
    unusually severe weather conditions or other events
    occur which might
    affect the normal
    availability of
    gas and electricity,
    Winnetka expects not to have to rely on coal more than
    60 days
    per year.
    This
    compares
    to Winnetka’s past operations, where coal
    was
    used about 300 days per
    year.
    (R.
    32.)
    Finally,
    the requested variance would
    require Winnetka
    to
    maintain its existing controls
    (a multiple cyclone)
    in good working order and
    perform stack tests
    to show that
    it
    is ~ieeting
    the interim particulate limit
    of 0.25 lbs/MBtu.
    During the course
    of the requested variance, Winnetka will
    proceed with
    the design, permitting,
    and construction
    of control equipment which will
    achieve compliance with the 0.1 lbs/MBtu particulate limit.
    Time within the
    variance period
    is
    to
    be
    used for study of control
    options, seiect~onof
    an
    architect—engineering firm
    for design
    of t~iechosen
    control
    equipment,
    application
    for
    a
    construction
    permit, bidding
    and selection of ~uppiiersand
    contractors, installation of equipment,
    testing of the equipment,
    and
    application for an operating permit.
    (R.
    25—31.)
    Winnetka’s construction
    permit application
    is
    to
    be submitted to
    the Agency by November
    i,
    1989.
    Construction must begin by February
    1,
    1990, and be completed by ~June
    1,
    1991.
    The variance would
    expire on September
    30,
    1991.
    Winnetka has
    not
    yet
    specifically
    identified
    what
    control
    equipment
    it
    will
    install, although
    it has preliminarily decided
    to install
    a ~*baghouse~
    fabric filter.
    (Petition at
    6;
    R.
    27.)
    In connection with
    its site—specific
    rulemaking
    petition (R86—41), Winnetka submitted
    a report by HDR Techserv,
    Inc. which presented costs of five control equipment options.
    (R85—41,
    Ex.
    p5—46

    -3-
    15, Appendix
    F.)
    That report was
    not submitted
    as an
    exhibit
    in
    this
    proceeding,
    although the transcripts of the two hearings
    in that rulemaking
    were admitted
    as Exhibits
    1 and
    2
    in support of this variance request.
    Those
    transcripts contain some discussion of the options identified by
    HDR.
    Additionally,
    the Board will take official notice of the analysis of
    control
    alternatives
    in its
    August
    4,
    1988 Opinion and Order
    in
    R86—41,
    at pages
    5-
    7.
    At hearing on the rulemaking petition, Winnetka stated
    that adding fabric
    filter control equipment to boilers
    #7 and 8 would cost between $2.7 million
    and $4.4 million, with annual
    operating costs between $26,000 and
    $32,000.
    (Ex.
    2,
    p.
    106.)
    In its recommendation, the Agency states
    that the length
    of the
    compliance
    schedule
    requested
    by
    Winnetka
    is
    reasonable
    in
    these
    circumstances.
    The Agency notes that Winnetka
    is undertaking
    a major
    engineering and construction project which w~licost several million
    dollars.
    The Agency further maintains that
    a baghouse fabric
    filter system,
    which Winnetka has preliminarily chosen, should easily achieve compliance with
    the 0.1 lb/MBtu limit.
    Environmental
    Impact
    Winnetka contends that there would
    be no adverse envIronnental
    impact
    if
    its variance requested
    is granted.
    It states that the dispersion modeling
    and
    nuisance dust studies introduced
    in the rulemaking proceeding show that
    operation of the plant’s boilers
    on coal
    at 0.25 lbs/MBtu does
    not endanger
    the National
    Ambient Air Quality Standard
    (NAAQS) for particulates or PM—1O
    (particulate matter under
    10 microns
    in
    size).
    (Those studies were introduced
    as
    Exs 3A,
    38,
    3C, and
    4
    in this proceeding.)
    Winnetka maintains that
    readings
    at
    the
    Agency’s
    total
    suspended
    particulates
    (TSP) monitor
    at Crow
    Island School
    ,
    about
    2 kilometers
    southwest of the generating plant, show the
    cleanest
    air
    in the state.
    Finally, Winnetka notes
    that the model ing studies
    analyzed the effect
    of
    all
    four of Winnetka’s boilers operating
    simultaneously.
    Because
    the requested variance would allow only boiler
    #8
    to
    use coal
    ,
    Winnetka contends that the variance would
    result
    in an actual
    reduction
    in
    particulate
    emissions.
    The Agency agrees that the modeling study shows no violation of the NAAQS
    for particulates
    or PM—10.
    The Agency also concurs with Winnetka’s statement
    that
    the conditions of the variance will
    result
    ii
    a
    significant reduction
    in
    emissions.
    The Board
    is
    persuaded that the NMQS for Darticulates
    or PM-b
    are not likely to be exceeded.
    Rardsh
    I p
    Winnetka
    states that
    the Board~sdenial
    of
    its site—specific rulemaking
    petition (R36—41), without allowing time for compliance, makes
    iuiiiediate
    compliance with the 0.1 lbs/MBtu standard impossible.
    The requested variance
    would
    allow time for necessary design and installation of control equipment
    sufficient
    to meet that standard.
    Wiinetka asserts that denial
    of
    the
    variance would force
    it to close the electric plant.
    Winnetka contends that
    given the plant’s insignificant environmental
    impact, denial
    of
    a transition
    period
    in which
    to add control equipment would
    result
    in
    an arbitrary and
    95—47

    -4-
    unreasonable
    hardship
    on
    Winnetka
    and
    its
    citizens.
    The
    Agency
    agrees
    that
    denial
    of
    the
    variance
    would
    create
    a
    hardship
    on
    Winnetka.
    Consistency
    with
    Federal
    Law
    Both
    Winrietka
    and
    the
    Agency
    maintain
    that
    the
    Board
    may
    grant
    the
    requested
    variance
    consistent
    with
    the
    Clean
    Air
    Act.
    The
    Agency
    notes
    that
    on
    November
    3,
    1988,
    the
    United
    States
    Environmental
    Protection
    Agency
    (USEPA)
    proposed
    to
    approve
    Sections
    212.201
    and
    212.209
    as revisions to the Illinois
    State
    Implementation Plan (SIP).
    53 Fed. Reg. 44494 (1988).
    In
    the proposed
    approval,
    USEPA finds the Winnetka provision
    in Section 212.209 approvable
    because Winnetka
    is
    in
    a TSP attainment area
    and the 0.25 lbs/MBtu
    limit
    would
    not relax any current limits.
    Because the variance conditions would
    reduce
    the
    use of coal
    at the plant,
    thus reducing particulates emissions, the Agency
    feels that the variance
    should
    be
    approvable by USEPA.
    Concl usions
    The Board
    finds that Winnetka has presented adequate proof that
    it would
    incur
    an arbitrary or unreasonable hardship if
    it were required to irnediately
    comply with the 0.1 lbs/MBtu limit.
    This finding,
    in combination with the
    presence
    of
    a comitment
    to comply and the minimal
    environmental
    impact
    expected during the variance, persuade the
    Board that the requested relief
    should
    be
    granted.
    Thus,
    the
    Board will grant Winnetka
    a var1ance
    from 35
    Ill. Mm. Code 212.201 until
    September
    30,
    1991,
    subject
    to conditions.
    Finally,
    the Board wishes
    to note that this case
    is
    an example of the
    speed
    with which Board
    proceedings can be resolved, where the parties show a
    comitment to
    proceeding
    as quickly
    as possible.
    This Opinion constitutes the Board’s findings of fact and conclusions of
    law.
    I,
    Dorothy
    M.
    Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby
    cert
    y that the above Opinion was adopted
    on
    the
    -‘
    day
    of
    ~~.4A._7
    ,
    1989,
    by
    a vote of
    70
    orothy
    M•
    Gun~-, Clerk
    Illinois Poii~onControl
    Board
    95—48

    Back to top