ILLINOIS POLLUTION CONTROL BOARD
January
5,
1989
VILLAGE OF WINNETKA,
)
Petitioner,
)
V.
)
PCB 88-164
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
)
Respondent.
HARVEY
M.
SHELDON AND SHELL J. BLEIWEISS OF McDERMOTT,
WILL,
& EMERY APPEARED
DN BEHALF
OF PETITIONER THE VILLAGE OF W~NNETKA.
WILLIAM
0.
INGERSOLL APPEARED ON BEHALF OF RESPONDENT THE
ILLINOIS
ENVIRONMENTAL PROTECTION AGENCY.
OPINION OF THE BOARD (by J. Theodore Meyer):
On December
15, 1988,
the
Board granted
the Village of Winnetka
(Winnetka)
a
variance from 35
Ill. Adm. Code 212.201
until
September 30,
1991.
The variance, which
is subject
to conditions, will
allow Winnetka time
to design, install, and test control equipment sufficient
to comply with
Section 212.201.
This Opinion
supports
the December
15,
1988 grant of the
variance.
Background
Winnetka owns
and operates an electric generating plant
on Tower Road at
Lake Michigan.
The plant consists primarily of five boilers and two diesel
engines.
Boiler
~4
burns natural
gas, boilers ~5, 6 and
7 burn only coal, and
boiler
#8 can burn natural gas,
coal, or a combination of the two fuels.
The
two diesel
engines and boilers ~4 and 8 are presently permitted to operate.
Only boiler ~8 is equipped with particulate controls.
One comon
stack serves
all equipment.
The coal burning operation ~f boiler ~3 is
the subject
of
Winnetka’s variance request.
In
1986 the Board promulgated Section
212.201, from which Winnetka now
seeks
a variance.
That section establishes
a particulate emission limit of
0.1 pounds
of particulate matter per million British thermal
units
(ibs/MBtu)
(0.15 KgI~—hr)for coal-fired boilers
in the Chicago area,
In the same
rulemaking (R82—1), the Board
provided a temporary site-specific limit
of 0.25
lbs/MBtu
for the Winnetka plant.
The site-specific limit,
found
at
35 Ill.
Mm. 212.209, was effective
until
January
1,
1989,
or until
the Board took
final
action
in
a
site—specific rulemaking.
Winnetka
then petitioned for
a
permanent 0.25 lbs/MBt~limit.
The Board denied that petition on August
4,
1988.
Proposed Amendment to
35
Ill. Adm. Coae 212.209, Village
of Winnetka
~5—45
—2-
Generating Station, R86-41, August
4,
1988.
On November
3,
1988,
the Board
denied Winnetka*s motion for reconsideration.
Thus, Section
212.201
is now
applicable to the Winnetka plant.
Relief Requested and Compliance Plan
Winnetka does not presently have sufficient control
equipment on
its
boilers
to comply with the 0.1 lbs/MBtu
limit while burning coal.
Thus,
Winnetka
seeks this variance
to allow some operation on coal
while the
necessary control equipment is being designed, installed,
and tested.
The
variance request, which was apparently discussed
and agreed upon with the
Illinois Environmental
Protection Agency
(Agency) prior
to the
filing
of the
petition,
is designed to minimize the amount
of coal
used by Winnetka during
the period
of the variance.
Only boiler ~8 is covered by the requested
variance, although Winnetka apparently plans
to
install
control equipment
on
boilers
#7
and 8.
(Boiler
#7
is not presently permitted
and
thus cannot
be
operated.)
The variance would mandate Winnetka~suse of reasonably available
gas or electricity from other sources, including:
(1) WinnetKa~sown
production using
gas
or diesel
oil;
(2)
electricity purchases from other
utilities; and
(3)
use of natural
gas.
Wirrnetka would
be allowed
to ourn
COCi
to produce electricity only when
it
is
unable
to purchase electricity from
another source
for less than 31 mils per kilowatt hour (miis/KWH),
or purchase
natural
gas
at
a
price
such
that
the
cost
of
production
is
1C55
than
31
mils/KWH.
(31 mils/KWH
is
3.1
cents
per
kilowatt
hour:
1000
mils=
S1.OO.)
The only exception to this restriction
is
that
coal could
be
burned
in
small
quantities
as
necessary to
maintain
the
protective
ash
on
the boiler grate.
(See R.
33—34.)
Unless
unusually severe weather conditions or other events
occur which might
affect the normal
availability of
gas and electricity,
Winnetka expects not to have to rely on coal more than
60 days
per year.
This
compares
to Winnetka’s past operations, where coal
was
used about 300 days per
year.
(R.
32.)
Finally,
the requested variance would
require Winnetka
to
maintain its existing controls
(a multiple cyclone)
in good working order and
perform stack tests
to show that
it
is ~ieeting
the interim particulate limit
of 0.25 lbs/MBtu.
During the course
of the requested variance, Winnetka will
proceed with
the design, permitting,
and construction
of control equipment which will
achieve compliance with the 0.1 lbs/MBtu particulate limit.
Time within the
variance period
is
to
be
used for study of control
options, seiect~onof
an
architect—engineering firm
for design
of t~iechosen
control
equipment,
application
for
a
construction
permit, bidding
and selection of ~uppiiersand
contractors, installation of equipment,
testing of the equipment,
and
application for an operating permit.
(R.
25—31.)
Winnetka’s construction
permit application
is
to
be submitted to
the Agency by November
i,
1989.
Construction must begin by February
1,
1990, and be completed by ~June
1,
1991.
The variance would
expire on September
30,
1991.
Winnetka has
not
yet
specifically
identified
what
control
equipment
it
will
install, although
it has preliminarily decided
to install
a ~*baghouse~
fabric filter.
(Petition at
6;
R.
27.)
In connection with
its site—specific
rulemaking
petition (R86—41), Winnetka submitted
a report by HDR Techserv,
Inc. which presented costs of five control equipment options.
(R85—41,
Ex.
p5—46
-3-
15, Appendix
F.)
That report was
not submitted
as an
exhibit
in
this
proceeding,
although the transcripts of the two hearings
in that rulemaking
were admitted
as Exhibits
1 and
2
in support of this variance request.
Those
transcripts contain some discussion of the options identified by
HDR.
Additionally,
the Board will take official notice of the analysis of
control
alternatives
in its
August
4,
1988 Opinion and Order
in
R86—41,
at pages
5-
7.
At hearing on the rulemaking petition, Winnetka stated
that adding fabric
filter control equipment to boilers
#7 and 8 would cost between $2.7 million
and $4.4 million, with annual
operating costs between $26,000 and
$32,000.
(Ex.
2,
p.
106.)
In its recommendation, the Agency states
that the length
of the
compliance
schedule
requested
by
Winnetka
is
reasonable
in
these
circumstances.
The Agency notes that Winnetka
is undertaking
a major
engineering and construction project which w~licost several million
dollars.
The Agency further maintains that
a baghouse fabric
filter system,
which Winnetka has preliminarily chosen, should easily achieve compliance with
the 0.1 lb/MBtu limit.
Environmental
Impact
Winnetka contends that there would
be no adverse envIronnental
impact
if
its variance requested
is granted.
It states that the dispersion modeling
and
nuisance dust studies introduced
in the rulemaking proceeding show that
operation of the plant’s boilers
on coal
at 0.25 lbs/MBtu does
not endanger
the National
Ambient Air Quality Standard
(NAAQS) for particulates or PM—1O
(particulate matter under
10 microns
in
size).
(Those studies were introduced
as
Exs 3A,
38,
3C, and
4
in this proceeding.)
Winnetka maintains that
readings
at
the
Agency’s
total
suspended
particulates
(TSP) monitor
at Crow
Island School
,
about
2 kilometers
southwest of the generating plant, show the
cleanest
air
in the state.
Finally, Winnetka notes
that the model ing studies
analyzed the effect
of
all
four of Winnetka’s boilers operating
simultaneously.
Because
the requested variance would allow only boiler
#8
to
use coal
,
Winnetka contends that the variance would
result
in an actual
reduction
in
particulate
emissions.
The Agency agrees that the modeling study shows no violation of the NAAQS
for particulates
or PM—10.
The Agency also concurs with Winnetka’s statement
that
the conditions of the variance will
result
ii
a
significant reduction
in
emissions.
The Board
is
persuaded that the NMQS for Darticulates
or PM-b
are not likely to be exceeded.
Rardsh
I p
Winnetka
states that
the Board~sdenial
of
its site—specific rulemaking
petition (R36—41), without allowing time for compliance, makes
iuiiiediate
compliance with the 0.1 lbs/MBtu standard impossible.
The requested variance
would
allow time for necessary design and installation of control equipment
sufficient
to meet that standard.
Wiinetka asserts that denial
of
the
variance would force
it to close the electric plant.
Winnetka contends that
given the plant’s insignificant environmental
impact, denial
of
a transition
period
in which
to add control equipment would
result
in
an arbitrary and
95—47
-4-
unreasonable
hardship
on
Winnetka
and
its
citizens.
The
Agency
agrees
that
denial
of
the
variance
would
create
a
hardship
on
Winnetka.
Consistency
with
Federal
Law
Both
Winrietka
and
the
Agency
maintain
that
the
Board
may
grant
the
requested
variance
consistent
with
the
Clean
Air
Act.
The
Agency
notes
that
on
November
3,
1988,
the
United
States
Environmental
Protection
Agency
(USEPA)
proposed
to
approve
Sections
212.201
and
212.209
as revisions to the Illinois
State
Implementation Plan (SIP).
53 Fed. Reg. 44494 (1988).
In
the proposed
approval,
USEPA finds the Winnetka provision
in Section 212.209 approvable
because Winnetka
is
in
a TSP attainment area
and the 0.25 lbs/MBtu
limit
would
not relax any current limits.
Because the variance conditions would
reduce
the
use of coal
at the plant,
thus reducing particulates emissions, the Agency
feels that the variance
should
be
approvable by USEPA.
Concl usions
The Board
finds that Winnetka has presented adequate proof that
it would
incur
an arbitrary or unreasonable hardship if
it were required to irnediately
comply with the 0.1 lbs/MBtu limit.
This finding,
in combination with the
presence
of
a comitment
to comply and the minimal
environmental
impact
expected during the variance, persuade the
Board that the requested relief
should
be
granted.
Thus,
the
Board will grant Winnetka
a var1ance
from 35
Ill. Mm. Code 212.201 until
September
30,
1991,
subject
to conditions.
Finally,
the Board wishes
to note that this case
is
an example of the
speed
with which Board
proceedings can be resolved, where the parties show a
comitment to
proceeding
as quickly
as possible.
This Opinion constitutes the Board’s findings of fact and conclusions of
law.
I,
Dorothy
M.
Gunn,
Clerk of the Illinois Pollution Control
Board, hereby
cert
y that the above Opinion was adopted
on
the
-‘
day
of
~~.4A._7
,
1989,
by
a vote of
70
orothy
M•
Gun~-, Clerk
Illinois Poii~onControl
Board
95—48