ILLINOIS POLLUTION CONTROL BOARD
January 5, 1989
ThE EUREKA COMPANY,
)
)
Petitioner,
)
)
v.
)
PCB 88—85
)
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
1
Respondent.
GREGORY D. COLLINS, COLLINS & FLYNN, APPEARED ON BEHALF OF THE PETITIONER, THE
EUREKA COMPANY; AND
JAMES J. O’DONNELL, APPEARED ON BEHALF OF ThE RESPONDENT, ILLINOIS
ENVIRONMENTAL PROTECTION AGENCY.
OPINION AND ORDER OF THE BOARD (by J. Anderson):
This matter comes before the Board upon a request for variance initially
filed on May 10, 1988, and amended August 17, 1988, by The Eureka
Company
(Eureka). Eureka requests variance from 35 111. Adm. Code 215.204(3)(5) which
regulates volatile organic compound (VOC) emissions for manufacturing plants
with miscellaneous metal parts coating processes.
On November 7, 1986, the Agency issued two permits for VOC emissions from
Eureka’s two paint shops. These permits terminated on October 22, 1991 and
included a compliance program to be achieved by December 31, 1987. Eureka
subsequently encountered difficulty in meeting compliance by that date and
petitioned the Board for a five year variance on
May
10. 1988. On
May
19,
1988, the Board accepted Eureka’s petition and set the matter for hearing but
noted that the petition provided “indefinite plans for compliance without a
particular time—table for ultimate compliance”. (Board Order 88—85, May 19,
1988) On August 17, 1988, Eureka filed an amended petition which requested a
42 month variance and included a time-table with ultimate plans for
compliance. The Agency’s recommendation of August 25, 1988, was to grant the
variance with the conditions contained in Eureka’s amended petition. HearIng
was held August 25, 1983; no members of the public were present.
The Facility
The Eureka plant is located in Bloomington, McLean County. The facility
is located in
an
industrial, coamiercial and residential area and is zoned for
aheavy industry”. McLean County is an ozone attainment county and is not
contiguous to a non-attaInment county. Eureka employs an average of 1,200
employees in the manufacturing of vacuum cleaners at its Bloomington plant.
(Pet. at 2)
95—23
-2-
VOC emissions come from two separate paint shops located ii Eureka’s
Bloomington plant. In each shop (known as Department 31 and Department 32),
miscellaneous metal parts are painted with solvent based alkyd baking enamel.
(Pet. at 3) Each shop has four automatic electrostatic spray booths and two
manual air spray booths. Paint from mixing rooms next to each shop is pumped
through transfer lines into the shops. After the parts are coated, they flow
into a baking oven to dry. (Pet. at 4)
Paint usage records, cited in Eureka’s petition, indicate that Eureka
used an average of 4,026 gallons of solvent based alkyd baking enamel per
month from May through December, 1987. (Pet. at 4) Taking into account the 23
different colors used during those months, the average emission ii pounds of
VOC per gallon of paint was 4.87, in violation of the 3.0 lb/gal VOC emission
limits under 35 Ill. Adm. Code 215.204(j)(5). Eureka and the Agency agree
that the annualized VOC emissions from the plant are 117.6 tons, which is
45.13 tons of excess VOC emissions. (Pet. at 4, Agency Rec. at 4, R. at 92,
93) According to Eureka, ozone concentrations in their area have only
exceeded the 0.125 ppm limit in one monitoring during the last three years 3nd
that was by 0.001 ppm. (Pet. at 5)*
Past
Compliance Efforts
ifl 1930, Eureka began testing high—solids paints. However, Eureka
suspended testing from late 1981 until February, 1985. Eureka provides two
reasons for this suspension in its petition for variance: “the anticipated
compliance date of December 31, 1982 was extended until the end of 1987, and
due to the fact that it was thought that ‘compliance~might not be requ~redin
attainment areas.” (Pet. at 8)
In attempting to comply with 35 III.
Adni.
Code 215.204(j)(5), Eureka
identified three possible options:
1)
installation of a thermal incinerator
as a control technology; 2) use of paints with a lower VOC content than the
conventional paints in use at the time and 3) installation of a ~‘beil”system
to improve the use of high—solids paints, if chosen as the compliant coating.
(Pet. at 25,26) Eureka rejected installation of thermal incinerators because
the cost of installation and operation was beyond its financial means; the
purchase price for each paint shop was estimated at $1,365,000, plus an
installation cost of $175,000. The operational costs for each incinerator was
estimated at $49,580 per year. (Pet. at 25, Pet. Grp. Ex. 1) ~dditionolly,
Eureka asserts that there is some uncertainty whether the incinerators would
be an effective method of compliance, given Eureka’s particular exhaust
design. Eureka asserts that the incinerator is most effective at a low
exhaust air volume with tiigh concentration of solvent vapor. In contrast,
Eureka has a high exhaust air volume with a low concentration of solvent
vapor. A study could be performed to ascertain an incinerator’s potential
effectiveness under those conditions for ~5,000,which would be credited
towards purchase. (Pet. at 26) However, due to the overall costs, Eureka has
*
Note: According to the Board’s calculations, Eureka’s annualized
VOC
emissions are in excess by 45.17 tons. Also, the ambient air quality standard
for ozone is 0.12 ppm not 0.125 ppm (see 35 Ill. Adin. Code 243.125).
95~~24
—3—
centered its compliance efforts primarily on the formulation of low VOC
paints.
The bell system would not be used as control technology in order to
directly reduce emissions but is used primarily to complement the use of high—
solids paints. The bell system would replace Eureka’s present spray gun
system because it breaks the paint up into fine particles and produces a
better “wrap” (edge coverage) when used with high—solids paints. Thus, the
bell system increases the utility of high—solids paints by decreasing the
amount of rejects produced and reduces the use of conventional paints with
higher VOC content. Eureka has rejected installing the bell system presently
due to cost concerns (approximately $500,000 for both shops) and uncertainty
regarding the bell system’s actual ability to SOIVC the “wrap” problem. (Pet.
at 26)
Eureka investigated four possible compliant paints: high-solids,
waterborne, powder coating and electrodeposition. Eureka decided that the
waterborne paints were too costly and its finish was unacceptable. Powder
coating had an unacceptable film appearance and handling problems. ~inaily,
electrodeposition requires huqe tanks, making color changes difficult,
according to Eureka. Thus, high-solids were chosen as the best possibility of
developing compliant coatings. (Pet, at 5-S)
Eureka explains in its petition that there were several problems in its
attempts to adapt high—solids into its paint lines: paint formulation;
incompatibility between high-solids and conventional paints in production
runs; and equipment. ifl its Plan of Compliance, Eureka proposes several means
of eliminating these problems in order to implement the use of compliant
coatings.
Proposed Compliance Plan
Eureka’s plan of compliance is set forth in its amended petition in three
major stages over a 42 month period. The first eighteen months focus on the
formulation of high—solids paints. Eureka will replace and upgrade equipment
to increase the utility of compliant paints at a cost of approximately
$86,000. in addition to the equipment changes, Eureka will conduct a
nationwide survey of coating suppliers for comoliant coatings. There are
milestone months and reporting commitments scheduled during this stage.
Eureka will also study the feasibility of installing thermal incinerators in
these first eighteen months. (Amended Pet, at 2—4)
The second stage begins after eighteen months. At that point, if
compliant paints across Eureka’s color spectrum have not been found, then
Eureka will install a bell system or an incinerator in its paint shop with the
highest volume of emissions. Eureka anticipates that the use of plastics
will
eliminate the need for the second paint shop. However, Eureka is not basing
its ability to achieve compliance on the developing use of plastics because of
the inherent difficulty in predicting actual figures which are dictated by
“market factors such as overall growth and demand for plastic.” (R. at 67).
If Eureka does not shut down its second paint shop and does ~othave
conioliant
coatings by the end of the 30th month, the plan will proceed to the final
stage. (Pet. at 5,6)
95—25
—4-
In the final stage, months 31—42, Eureka agrees to install either a bell
system or control technology in the second paint shop, if it is still in
operation and not in compliance. If necessary, Eureka agrees to continue
testing and formulation of paints throughout all three stages. Eureka agrees
to be in compliance no later than at the end of the 42 month variance.
(Amended Pet, at 7)
Alleged Hardship
Eureka asserts that ‘it does not have enough high—solids paints which meet
Agency limitations and Eureka’s quality standards. (R. at 71) Therefore,
Eureka insists that it must be able to use non—compliant paints in order to
meet production demands during the variance period. (R. at 71) Consequently,
Eureka’s only means of achieving compliance right now is to purchase and
install thermal incinerators, at a cost of over $3 million for both paint
shops. Eureka argues that this would be an arbitrary or unreasonable
hardship. (R. at 71)
Asserted Envtronmentai Effect of Emissions
Eureka asserts that the variance will not have a significant
environmental impact because: a) its facility is in an attainment county and
not contiguous to a non—attainment county; b) monitored ozone levels show that
its past emissions have not caused ozone proolems: and c) its actua emissions
will not increase during the term of variance. (R. at 19). The Agency notes
that its records do not contain any citizen complaints or inquiries regarding
Eureka’s facility (Agency Rec. at 2) and concludes that “Eureka’s emissions
should not cause any violations of the NMQS.” (Agency Rec. at 3)
Agency Recommendation
The Agency recommends that the Board grant the variance with the
conditions proposed by Eureka in its Amended Petition. The Agency also
requests that Eureka make progress reports to the Agency every three months
for the duration of the variance. (Agency Rec. at 5)
Concl us ion
The time lost by, and Eureka’s less than fully oersuasive reasons for,
the suspension of its compliance efforts From late 1981 Ufltji February 1985
suggest that Eureka’s hardshio in significant measure is self—imposed.
Further, the Board notes the absence of any explanation by Eureka for its
failure to timely file the variance petition before the December 31, 1987
deadline. However, since early 1985, Eureka has worked diligently to come
into compliance. On balance, tne Board is persuaded that it is most important
that Eureka get on a firm compliance plan. ifl so saying, the Board cautions
Eureka that
it w~i1not look kindly on any failure by Eureka to diligently
pursue and achieve compliance during the term of this variance.
Regarding Eureka’s proposed conditions, the Board has re-drafted some of
them to
better insure enforceability. The Board also has declined to include
two agreed upon conditions. Fi’st, Eureka proposed that the Board retain
jurisdiction in this matter. The Board declines to do so. Neither Eureka nor
95—26
—5—
the Agency explained why retaining jurisdiction was advisable in this matter
and the Board does not itself discern what compliance benefits would accrue
from retaining jurisdiction. Given the nature of some of the conditions, the
Board does perceive a potential need for the Board to resolve disputes that
might arise over whether certain required steps have in fact been complied
with. There are ways to bring such issues to the Board apart from an
enforcement action, e.g., a variance petition.
Next, the Board declines to add as a condition to the variance Eureka’s
agreement not to file for a site-specific rule change. Site-specific
petitions are separate proceedings, and the Board would address the merits
of
such a
petition in that
proceeding. The
Board emphasizes, however, that the
filing
of a site-specific petition
in
no
manner
would relieve Eureka from
compliance with the terms of
this variance.
In light of the above considerations, as well as the insignificant
environmental impact during the term of this variance, the Board finds that
Eureka has presented adequate proof that compliance with 35 Ill. Adm. Code
215.204(j)(5)~would impose an arbitrary or unreasonable hardship.
Accordingly, variance relief with conditions will be granted for the time
requested.
This Opinion constitutes the Board’s findings of fact and conclusions of
law in this matter.
ORDER
Petitioner, The Eureka Company (“Eureka”), is hereby granted variance
from 35 Ill.
Adrn. Code 2l5.204(j)(5) for its facility located in Bloomington,
illinois, subject to the
following conditions:
1. This variance will expire ~Juiy5, 1992 or at such earlier
time as compliance is achieved with VOC limitations. If
at any time during the period of
this variance, Eureka
achieves compliance under 35
Iii.
Adni. Code
215.204(j)(5), with or without use of the internal offset
rule, Eureka shall notify the Illinois Environmental
Protection Agency (“Agency”) at the following address:
Environmental Protection Agency
Division of Air Pollution Control
Control °rogramsCoordinator
2200 Churchill Road
Springfield, IL 62706
By the end of this variance, Eureka shall be in
compliance with the VOC regulation applicable to its
paint shops.
2. During the period of this variance from January 5, 1989
until
July
5, 1990:
95—27
—6-
A. Eureka shall purchase and install any equipment
necessary to achieve compliance including new air
make—up machines, paint pumps, paint heaters and
upgrade its associated parts washer cleaning
process.
B. Eureka shall continue testing, data collecting and
sharing results with its vendors.
C. Eureka shall provide listing of detailed coating
specifications and testing procedures to the Agency.
0. Eureka shall make a detailed survey of coating
suppliers using a comprehensive directory of
formu-
lators and suppliers to the coating industry.
E.
Eureka shall send out a letter to all suppliers and
formulators identified from the above survey, giving
the detailed coating specifications and testing pro-
cedures by March 5, 1989.
F. Eureka
shall
call the suppliers not responding and
document the reason(s) for no response, after April
5, 1989.
G.
Eureka shall compile a listing of all suppliers and
resoonses, including all correspondence, by
May 5,
1989.
H.
Eureka shall schedule and conduct the necessary
tests for
possible compliant coatings identified by
the above-mentioned survey, by March 5, 1990.
I. If
compliant coatings have not been found for all
Eureka’s 23 colors, Eureka shall compile all test
results for all colors where
compliant coatings have
not been found, by April
5,
1990.
J.
Eureka shall give priority in paint formulation and
testing to the two non—compliant colors that Eureka
uses most and shall identify these colors to the
Agency.
K.
Eureka shall supply copies of all documents prepared
under items 2(E), 2(G) and 2(1) to the Agency.
L.
Eureka shall continue its study of technically
feasible control technology,
as well as the bell
system, as a means of achieving compliance with or
without high-solids paint. Eureka shall conclude
its study and its results shall be seat to the
Agency by July 5, 1990.
05—28
—7—
3. If compliant coatings across Eureka’s color spectrum have
not been found by July 5, 1990:
A. Eureka shall purchase and install a bell system in
its paint shop with the highest volume, if Eureka
determines that the bell system will be effective
under the studies conducted in item
2(L)
above.
If
the bell system is not installed, Eureka shall
determine
alternative
methods
of
compliance,
including but not limited to the purchase and
installation of control technology.
B. Unless Eureka installs
control technology, it
shall
continue its paint formulation and testing
program.
If compliant coatings have not been found
by July 5, 1990, Eureka shall engage
the services of
a coating consultant and have a thorough review made
of all the work done and data compiled on paint
formu1ation for all colors not in
compliance.
C.
Eureka
shall paint
at
least Sot ~f all its handle
sockets with high—solids paint meeting Board
limitations.
4. If Eureka has not come in compliance with 35 Ill. Adm.
Code 215.204(j)(5) by July 5, 1991, and if its second
paint shop is still in existence:
A.
Eureka shall install a bell system in its second
paint shop, if
installation
in the first paint shop
has proved effective. However, if Eureka installed
control technology in its first paint shop, it shall
install like controls in the second shop to bring
Eureka into compliance.
B. Eureka shall continue its testing and formulation
process and shall perform any further tests as
directed by the coating consultant referred to in
item 3(8).
5. Beginning April 5, 1989, and every third month
thereafter, Eureka shall submit written reports to the
Agency detailing all progress made in achieving
compliance with Section 215,204(j)(5).
To the extent
these activities
involve
testing
for
replacement
coatings, said reports shall include information on the
names of replacement
coating and the manufacturer’s
specifications, including percent solids by volume and
weight, percent VOC by volume and weight, percent water
by volume and weight, density of coating, and recornended
operating parameters; detailed description of each test
conducted including test protocol, number of runs, and
complete original test results; the quantities and VOC
95—29
-8-
content of all coatings utilized during the reporting
period; the quantity of VOC reduction during the
reporting period; and any other related information which
may be requested by the Agency.
6. Within 45 days after the date of this Order, Eureka shall
execute a Certificate of Acceptance and Agreement to be
bound to all terms and conditions of the variance. Said
Certification shall be submitted to James 1. O’Donnell,
Enforcement Attorney, at the address specified in
paragraph one. The 45-day period shall be held in
abeyance during any period that this matter is being
appealed. Failure to execute and forward the Certificate
within 45 days renders this variance void and of no force
and effect as a shield against enforcement of rules from
which variance was granted.
The form of said
Certification shall be as follows:
CERT IF I CAT ION
I, (We)
____
__________________________________, having read the
Opinion and Drder3T~’he ilinois Pollution Control 3oard in PCB 88-85, dated
January 5, 1989, understand and accept the said Opinion and Order, realizing
that such acceptance renders all terms and conditions thereto binding and
enforceable.
Petitioner
Authorized Agent
Title
—
Date
Section 41 of the Environmental Protection Act, Ill. Rev. Stat. 1987, ch.
111-1/2, par. 1041, provides for appeal of final Orders of the Board
within 35
days. The Rules of the Supreme Court of Illinois establish filing
requi rements.
ii IS SO ORDERED.
95—30
-9-
J. D. Dumelle concurred.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby
certify
_______
________________________ 1989, by a vote of
7~~)
—.
of ~
Opinion and Order was adopted on the S~ day
Doro~nn
Clerk
Illinois Pollution Control Board
95—31