ILLINOIS POLLUTION CONTROL BOARD
February 2,
1989
JOHN SEXTON CONTRACTORS COMPANY,
Petitioner,
v.
)
PCB 88—139
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
DISSENTING OPINION
(by J.
Anderson and
14.
Nardulli):
We must respectfully dissent
from the action of the majority
in this case.
~3yits action today,
the majority has,
we believe,
risked
seriously undermining the integrity of
the solid waste
permitting system and ignored
both the Act and
its own
regulations relating to closure
and post—closure care of solid
waste management
facilities.
At the outset, we wish
to emphasize
that we are not
questioning the technical
role the Agency must play
in
implementing
any regulatory scheme.
However,
in any regulatory
system,
there must be statutory and regulatory provisions
somewhere which enunciate that
role by way of directives,
criteria or other similar devices which guide or provide
boundaries
for Agency determinations.
The problem with this
case,
in our view,
is
that
the Agency’s determinations
are devoid
of
such underpinnings;
indeed,
the majority in
its own
determination on appeal
has veered away
from such
underpinnings.
We believe
such an approach
is inherently
incompatible with the essential rationale
for requiring
a
regulatory framework within which all decision—makers are
to make
their determinations.
This unusually lengthy dissenting opinion
reflects the nature and depth of our concern
in this matter.
The Nature of Closure
and Post—Closure Plan Aoplications
The majority essentially agrees with the Agency’s view that
a closure plan application
is,
in fact,
a supplemental permit
application
(Pes.
Br.
at
21; Op.
at
4).
The majority claims both
Sections 21.1 and
22 of the Act as statutory authority
for this
view.
However, Section
21.1
of the Act,
which establishes the
solid waste closure and post-closure financial assurance
requirement,
makes no reference
to any such permit modification
system.
It specifically limits the Agency’s options to approval
or disapproval
of the financial assures;
in so doing,
it
stands
~)6—12I
—2—
in stark contrast
to the permit conditioning discretion conferred
by Section
39(a)
of the Act.
Nor can Section 22 of the Act, which
sets forth
the Board’s
general rulemaking authority,
be cited
as support
for the
proposition that
a closure plan application
is
a supplemental
permit application.
First,
that Section’s
list of Board
regulatory powers includes a specific provision
for requirements
and standards relative
to closure and post—closure care of
hazardous waste disposal sites,
yet
is silent r~arding non—
hazardous solid waste disposal sites which
are the subject of
Section 21.1.
Even though the introductory paragraph of Section
22 indicates the listed powers are not
to be viewed
as limiting
the generality of the grant of regulatory authority
to the Board,
that grant of authority is itself limited
to such regulations
as
“promote the purposes of this Title”.
The “purposes of this
Title”
as regards closure and post—closure care plans
for non—
hazardous
solid waste sites
is
found
exclusively
in Section
21.1.
Wishful thinking will not make
it otherwise.
In adopting
the closure
and post—closure
(“CPC”) plan
(35
Ill.
Adm.
Code
807,
Subparts
F and F),
this Board
in 1985 acted
consistently with Section 21.1
(and by extension,
inconsistently
with its Opinion
today).
In the Section describing
the purpose,
scope
and applicability of the regulations
(35 Ill.
Adm.
Code
807.501)
the Board explicitly states as follows:
1.
Closure plans are not permits, but “will become permit
conditions pursuant to Section 807.206”
(subsection
(b);
emphasis added);
2.
The closure
and post—closure care plans are limited
in
purpose to
forming the basis
of the cost estimates and
financial assurance required by Subpart
F
for disposal
sites as well as
for determining whether
a unit
is
a
disposal unit
or
indefinite storage
unit, which must
provide financial assurance
(subsection
(C)).
As
to the former,
the majority seeks to read out of the
section the “will
become” qualifier.
It does so despite
its own
Opinion supporting
the adopting of
the temporary CPC regulations
(IN THE MATTER OF:
FINANCIAL ASSURANCE FOR CLOSURE AND POST-
CLOSURE CARE OF WASTE DISPOSAL SITES
(TEMPORARY RULES),
R84—22B,
OPINION OF THE BOARD, April
4,
1985).
Some background should be noted
here.
The temporary rules
adopted
in docket P84—22B bridged
the gap between
prior emergency
rules (R84—22A)
and
the final
rules (R84—22C) during
the period
of time an Economic Impact Study was underway.
The emergency
rules were preceeded by an even earlier effort; this earliest
version of the CPC rules was proposed
for first notice under
the
Administrative Procedure Act on July
19,
1984
(P84—22).
It
contained proposed
section 35
Ill. Adm.
Code 501(d), which
96—122
—3—
required existing disposal sites subject
to the new regulations
through operation of Section
21.1
to file their closure and post—
closure care plans
in the form of “applications for permit
modification” pursuant
to 35
Ill. l~dm.Code 807.209(c)
(emphasis
added).
Had this view prevailed,
today’s majority opinion could
claim substance.
Unfortunately for the majority,
that view did
not prevail:
even before
the emergency rules of docket P84—22(A)
were promulgated, the second notice for R84—22 had dropped
Section
501(d).
The reason or dropping
this originally—proposed
subsection
is made clear
in the April
4,
1985 Opinion of the Board
in P84—
22B,
cited previously.
That Opinion states that “fthe
closure
and post—closure care plans will become conditions of the site
permits”
(pg.
15) (emphasis added),
and reported that
the Board
had considered and rejected
the possibility of adopting an
alternative rule which
“just requires preparation
and maintenance
of
a plan even by permitted sites”
(Ibid, pg.
15).
Rejection of
that alternative,
it noted, was due
to two reasons.
First,
in
a
scheme where permits are required “it seems unwise”
to leave
closure
and post—closure elements out of the permit; second,
“because the plan is essential
to the cost estimate
and amount of
financial assurance,
prior Agency review
is necessary to
accomplish the purposes of Section 21.1 of the Act”.
In the
interim
until
full implementation of the CPC requirements, the
Board stated “operators will be required
to formalize plans only
with the first permit modifications”
(emphasis added)
(Id.)
The
OpThion of
the Board supporting adoption of
the permanent
rules
which now exist
(R84—22C, November
21,
1985) did not alter
the
scheme enunciated
in support of the temporary rules.
In view of the foregoing
it
is clear beyond dispute
that
closure plan applications are not themselves applications
for
permit modifications and that, except
at
the very inception of
docket P84—22,
this Board
has
not viewed them as such.
The
decision to attach the closure plans
to existing permits as
conditions
thereof was done
for policy reasons, not because of
a
strained
interpretation of Section 21.1
or Section
22,
and was
implemented
as an adjunct
to,
rather than an integral part of,
the permit modification process.
With respect
to
the point made by Section 807.501(c),
namely,
that closure plans are limited
in purpose
to satisfying
the financial assurance requirements of Section
21.1
of the Act,
the Board
has likewise affirmed
its position over the years.
It
did
so
in
its Opinion
in support
in the adoption of
final CPC
regulations
(IN THE MATTER
OF:
FINANCIAL ASSURANCE FOP CLOSURE
AND
POST-CLOSURE
CAPE
OF
WASTE
DISPOSAL
SITES
(ECONOMIC
IMPACT
OF
TEMPORARY
REGULATIONS
AND
ADOPTION
OF
FINAL
REGULATIONS),
P84—
22C,
OPINION OF THE BOARD, November
21,
1985).
That Opinion
states,
at page
1,
as
follows:
96—123
—4—
“Public
Act
83—775
became
effective
on
September
24,
1983.
Provisions
of
this
law,
which
are
fully
set
out
below,
prohibited
certain
non—hazardous
waste
disposal
operations
after
March
1,
1985
without
a
performance
bond
or
other
security
for
the
purpose
of
insuring
closure
of
the
site
and
post—closure
care
in
accordance
with
the
Environmental
Protection
Act
and
Board
rules.
Section
21.1(b)
of
the
Act
required
the
Board
to
adopt
by
January
1,
1985
rules
which
specified
the
type
and
amount
of
the
bonds or other
securities.
On June
8,
1984,
the Board opened
this Docket
for
the
purpose
of
promulgating
regulations
implementing P.
A.
83—775”.
(Emphasis added).
Again,
on page
7,
the Board stated
the purposes of these
rules:
“The
rules
implement
the
bond
requirement
of
Section
21.1
of
the
Act
by
requiring
the
preparation
of
closure
and
post—closure
care
plans,
and
cost
estimates
based
on
these
plans.
The operator
is
required
to
provide
financial
assurance
in
an amount equal
to
the
cost
estimate.
Financial
assurance
can
be
given
by several mechanisms,
including
a trust
fund,
surety
bond,
letter
of
credit,
closure
insurance,
and,
for
non—commercial
sites,
self—insurance”.
Emphasis
added).
It
is difficult to imagine how the Board could
have more
explicitly
or more closely linked
the closure
and post—closure
requirements
of Subpart
E with the financial
assurance
requirements of Subpart
F.
The closure
and post—closure
requirements, therefore, must be viewed
not as
stand—alone
requirements but as necessary components of the financial
assurance mechanism mandated by Section
21.1 of the
7\ct.
As
such,
the Board’s power
to regulate
in this area
is derived
from
and governed by Section 21.1
of the Act,
not Section
22.
In sum, whatever difficulty
the majority has
in
distinguishing
an original closure plan application
from
a
conventional permit application
is of recent origin; as noted
above, this Board has clearly and consistently articulated
the
difference between
the two types of applications
for most of the
last five years.
Given the policy reasons enunciated and the
procedures
adopted by the Board
for “marrying”
closure plans
to
facility permits,
it
is obvious
that closure plan applications
progressed down
a separate administrative
track until
such time
as approved,
after which,
for policy reasons,
the plans became
9~--124
—5—
conditions of the respective permits.
This gradual
approach
to
assimilation of closure plans
(i.e., by incorporation with the
next permit modification submitted by the applicant during
the
transition period)
was carefully articulated
and purposely
designed
to avoid an unmanageable administrative burden.
To hold
otherwise
now,
at the end of that period of transition,
is to
rewrite the history of the Board’s closure
and post—closure
rules.
Policy
Implications
Statutory and regulatory authority
issues aside, we also do
not agree with the policy position
implicitly embraced by the
majority
in
this case.
This position
is that
the Agency should
not
be precluded,
in
imposing closure
and post—closure care
requirements
as conditions
of CPC plans,
from reasonable reliance
upon the current body of technical
knowledge.
It
is true that
some
of
the
older
permits
issued
by
the
Agency
were
issued
without
the benefit of today’s
technical knowledge.
It
is also
true
that today we have more knowledge of what can be harmful,
and
a better
idea of how and where
to monitor
for these
contaminants
than we did even
a few years
ago.
It
is another
thing, however,
to conclude that the closure
and post—closure
plan approval process
is the appropriate vehicle
for updating
requirements applicable
to existing sites.
In its Opinion supporting
the adoption of permanent
regulations governing
the preparation of closure and post—closure
care plans and cost estimates,
the Board
noted
the problems posed
by the potential change
in solid waste handling regulations
(then
under consideration by the Board
in docket P84—17;
now under
consideration
in docket P88—7).
It unequivocally rejected the
notion that the closure and post—closure
rules then being
adopted
had any such “updating”
effects, stating instead that “t)he
rules rely on
the existing closure and post—closure care
requirements
for sanitary landfills
in Part 807.
These are
subject
to revision
in P84—17.
Operators may be required to base
cost estimates on the existing regulations pending modification”
(Emphasis added).
In
the Matter
of:
Financial Assurance for
Closure
and Post—Closure Care of Waste Disposal Sites
(Economic
Impact of Temporary Regulations and Adoption of Final
Regulations), R84—22C (November
21,
1985,
page 7).
Sexton
correctly observes that “the Board did
not contemplate
that the
Agency would require everything
in Section 807.316(a), as
if the
information had never been furnished previously”
(Pet.
Br.
at
24,
citing
the Board’s Opinion
in P84—22C at
pg.
18).
Sexton might
have added
that neither
the Agency nor any other participant i~
the P84—22 proceedings,
including
the authors
of the Economic
Impact Study fEdS),
suggested otherwise.
The Board has previously noted
the shortcomings
in the
present
Solid Waste Rules.
It
has
emphasized
the
importance
and
urgency of modernizing
the State’s rules
for
the management of
96—125
—6—
non—hazardous wastes.
In the Matter of:~Development, Operating
and Reporting Requirements For Non—Hazardous Waste Landfills,
R88—7 (February 25,
1988, pages
1,
24,
25,
33,
48 and 62).
Nevertheless,
the Board should
not allow the Agency to open up
pre—existing permits
to impose requirements (as special
conditions
to closure and post—closure plans or otherwise)
which
are not authorized by the Act or current Board regulations.
It cannot be overlooked
that Sexton’s permit is of
relatively recent origin
(1983—1984).
Wider examination at
hearing,
the Agency’s permit reviewer, ?~r.
Schoenhard, was unable
to
identify any new “rules and
regulations” which might require
new special conditions,
or any new wastestreams received or any
groundwater monitoring results reported which might warrant
imposition of changes
to the approved groundwater monitoring plan
(T.
19—33).
Hence,
even if this application were
to be construed
as re—opening
the permit for reconsideration of existing permit
conditions and
terms,
the Agency has failed
to articulate
persuasively why Sexton’s permit should be
so reconsidered and
modified.
It
should also be noted that there were no suspect
monitoring readings or other environmentally related concerns
involved.
It
is also important
to remember
that it
is not
the function
of
a closure and post—closure plan and its financial assurance
instruments to serve
as an environmental liability insurance
policy.
Such liability insurance policies, unlike CPC plans,
relate
to liability that may be incurred for actual
or threatened
violations of the Act; irrespective of the presence
or absence of
CPC plans or financial assurances,
a site owner/operator remains
liable
under
an enforcement action
for any actual or threatened
environmental “upsets”
in violation of the Act
or
Board
regulations.
In fact,
the CPC financial assurances
are not
available
to the Agency or
the site’s owner/operator for use
in
addressing such liability.
Similarly, even though
the requirements of the
Act and Board
regulations relative
to closure and post—closure care and
monitoring may change*, such changes do not affect
the
owner/operator’s
ongoing liability for any environmental
damage.
In other words,
financial assurances
for closure and
post—closure care are
intended solely to assure that funds will
be available
to
the Agency to accomplish
the closure and post-
closure care provided
for
in the closure and post—closure care
plans (permit conditions)
in the event
that the owner/operator
*
The Board
notes
that Section 22.17
of
the Act required
5 years’
monitoring of gas, water
and settling at
a “completed”
sanitary
landfill
site at
the
time the Board’s closure and post—closure
rules were adopted.
Since
then,
Section 22.17
has been amended
to increase the monitoring
requirement
to
15 years
(P.A.
E~5—l240,
effective July
1,
1990).
96—12~
—7—
fails
to do so
(see 35
Ill. Adm. Code 807.600, 807.620 and
807.622).
Costs are
to be estimated with respect to the area
to
be filled, costs of cover materials,
and the cost of moving,
grading, seeding and venting the cover
at the most expensive
point in
the site’s operating life
(Id.;
see also 35
Ill. Adm.
Code 807.624).
The financial assurance regulations provide that,
when the operator completes closure and post—closure care,
financial assurance is no longer required.
Thus,
closure and post—closure plans
and
financial
assurances are not designed to provide
for remediation of
releases, determination of the existence or non—existence of
releases or threats of releases,
or
for
any other purposes which
may be appropriate
to enforcement actions or
removals.
The
Agency’s attempted use of the closure and post—closure plan
approval process for such purposes is improper and contrary to
the best
interests of the Agency and the environment.
If,
for
instance, an apparent upset or
release of wastes should occur
at
a facility operating or closed
under
an Agency—conditioned
closure plan,
the effect of such conditions could
in some cases
serve
to limit
the Agency’s options.
It
is manifestly impossible
for
a closure plan,
per
Se,
to anticipate
the actions and
expenses which may be
imposed or assumed
in the event of
an
actual threat
to the environment.
Finally, with respect to policy,
one
is
left
to ponder
the
meaning and purpose of the State’s solid waste permitting system
and the Board’s strenuous efforts
in P84—17
and P88—7
to develop
new solid waste regulations.
If the Agency can impose
its
current ideas
upon permittees without regard either
as to what
the
facility’s permit has authorized
to be done or as
to what
wastes have been received at
the
facility in
the past, precisely
what role does
a permit play?
Landfill operators hereafter have
no assurance that the terms of their permits delineate
the
requirements with which
they will actually be compelled
to
comply.
Without
a shred
of evidence of violation of
the Act
or
of environmental harm,
such operators hereafter may be required
to
re—design their landfills
in the eleventh hour of their
operating lives
to suit the Agency’s latest concept of technical
propriety.
Similarly,
for what purpose does this Board
strive to
update
its solid waste regulations?
Landfill operators hereafter
have
no
assurance that
the
terms of Board regulations define
the
technical standards with which
they will actually be compelled to
comply.
Without an opportunity
to participate
in rulemaking
affecting
their concerns,
such operators hereafter may be
required
to restudy and redesign
their landfills in the eleventh
hour of their operating lives
or,
indeed, at any time
for new
landfill units,
to suit
the Agency’s latest concept of
technically appropriate requirements.
The Agency has candidly
admitted
that
these
concepts
may
be
untested,
unpublished
and
highly subjective.
They can be
found
in
draft
memos,
in
uncirculated guidelines,
in unexplained
“boiler plate” language
lodged
in
the Agency’s word—processing equipment, and
in the
96—127
—8—
individual permit reviewer’s subjective inclinations
(T. ~30—
31,33—34,66—69).
Even
if one were
to endorse the
idea that the
Agency can impose special conditions
in CPC plans, we cannot
understand how such unsupported concepts can be viewed as
technically substantiated.
It is no answer
to
these concerns
to say, as the majority
does, that appeals may be taken
to the Board from “incorrect”
special conditions.
Having
thus authorized
the Agency to use
a
CPC plan application to re—open for decision matters settled
years ago
in the permitting process and/or
to impose updated
engineering judgments untested by the rulemaking process, how
will the Board
review such special conditions?
What criteria
will
it apply?
Must such criteria relate
to the provision of
financial assurances?
The majority asserts that the Agency may
impose conditions on closure plans “so long as those conditions
relate only
to closure and post—closure care”
(Op. at
4;
emphasis
in original).
This supposed standard
is of no value
in real—
world
terms.
Virtually
no activity at
a landfill
is devoid
of
impact on its closure
and
post—closure
care
needs.
Conversely,
few
if any “conditions”
on closure and post—closure care
requirements will have no
impact on daily landfilling
activities.
That is,
indeed,the point.
BURDEN
OF
PROOF
The
majority
correctly
asserts
that
the
burden
of
proof
is
on the applicant
in permit appeal cases.
Most of the majority’s
conclusions on the respective Special Conditions under
appeal are
premised upon Sexton’s failure
to carry this burden,
noting
in
several cases
that Sexton’s “primary thrust”
in support of
its
cause
is “directed against the Agency—imposed special condition”
(e.g., pg.
7,
re: Special Condition
6).
As Sexton noted
(Pet.
Br.,
1—4),
Sexton introduced three witnesses
to establish
its
prima facie case;
it contends that the burden of “going forward”
thereby passed
to the Agency.
We cannot but agree
with Sexton for two reasons.
First,
Sexton’s witnesses not only attacked the Agency’s special
conditions
as
not
necessary,
but
also
asserted
that
Sexton’s
plan
as proposed was adequate.
For example,
in the extensive expert
testimony by Mr.
Eldredge on behalf of Sexton with regards to
Special Condition(s)
17
(T.l14—l30),
Mr.
Eldredge not only
asserts that the Agency conditions are unneeded
(T.126), but
implicitly and explicitly defends
the adequacy of
the Sexton plan
as proposed and originally permitted by the Agency
in
1984
(e.g.,
Tl24,
127,128—129).
Second,
the Agency’s permit reviewer
utterly failed
to articulate any authority for imposing
conditions
in 1988 that are different
from those
imposed
in 1984
(T.
26—29);
this Board has within
its knowledge and may take
notice of the fact that,
contrary
to
the ~.gencypermit reviewer’s
implicit assertion (T.26),
rio
new Board
rules and
regulations
have been adopted since
1984 that would warrant re—opening
96—12S
—9—
Sexton’s permit.
Surely,
something more than mere curiosity must
be
required
of
the
Agency
to
allow
it
to
summarily
discard
already
established
permit
requirements.
THE
SPECIAL
CONDITIONS
This dissenting opinion would
be incomplete without briefly
discussing
the contested special conditions which
the majority
has today ratified.
It should be remembered
that had the
majority joined
in our view of this case (i.e.,
that the Agency
cannot unilaterally add conditions to CPC plans),
the Agency,
under Section 21.1 of this Act
still could have refused
to
approve the plan,
and could have stated
the same reasons as
support
for its denial as
it has stated
in support of its
conditions.
Under
no circumstances would
these core issues have
been prevented from being presented to this Board on
appeal.
One should also note
in passing that these conditions were
evidently inserted by the Agency in substantial reliance upon
apparently erroneous assumptions,
e.g.,
the presumed
receipt by
Sexton
of “thousands of gallons” of liquid and other special
wastes.
While
it
is the applicant’s burden
to provide
the Agency
with
the
information
upon which
the Agency will base
its
determinations,
it
is
incumbent
upon
the
Agency
to
reasonably
apprise the applicant of what kinds of information will be
required, particularly where data before
the Agency
(e.g.,
supplemental waste stream permits)
is
inherently suspect.
It is
obvious from the record of this proceeding
that the mere grant of
a supplemental waste stream permit does not necessarily mean that
the permitted wastestream will be actually received, and that
the
Agency knew this
(Tr.
51—53,
156).
Nevertheless,
the majority in
effect authorizes the Agency
to rely upon such information.
Special Condition
4 requires Sexton
to prepare
and file
a
~parate
closure and post—closure care plan for
a “gas control
faci1fE~”.
A revised CPC plan
for the landfill and
a separate
CRC plan for the gas control activity
is
to be sent to
the Agency
within 90 days.
It cannot be contended that
a requirement
to
create
a plan in
the future, where
the conclusions of such
a
future plan are unknown and unlimited
in range,
can
serve
as
a
legitimate basis
for current “approval”
of
a plan or for
determining the appropriate amount of financial assurance
required at this time.
Moreover,
it
is clear
that the Agency
intends by this condition to impose closure and post—closure care
requirements that
run beyond
the 5—year statutory obligation
imposed by Section 22.17 of
the Act.
Since
the
majority has
determined
that the closure plan requirements of Subpart
E of its
Part 807
rules may require this result,
it should identify both
such “longer period
of
time”
as the Agency
is authorized
to
require,
and the specific regulation by which the Board has
established
such
period.
96—12 9
—10—
In its Opinion
(pg.
6),
the majority notes with
regard
to
Special Condition
4
(and elsewhere with regard
to other Agency—
imposed conditions)
that “the Agency simply did not
have
enough
information
from
Sexton
to
determine
appropriate
gas
control
measures”
and
that
in
the
absence
of
such
determination
“any
cost projection
is inappropriate”.
This
is manifestly true,
and
as true for the Agency as
it is for Sexton.
That being so, one
again
is led
to conclude that the Agency’s
“approval”
of Sexton’s
closure and post—closure care plans has no value as
a basis
for
implementing the bond requirement of Section 21.1 of the Act,
but
rather has value,
in the Agency’s view,
solely as an excuse
to
re—open matters previously settled by the
facility’s permit.
~pecial Condition
6 likewise
requires Sexton
to undertake
future action having uncertain outcomes.
In this case,
that
future action
is
a proposal
for
a leachate management program.
No time limit
for performance
is specified.
As noted previously,
no
hazardous
wastes
were
deposited
in
the landfill
as presumed
by
the Agency
in devising this Special Condition.
No cost impact
was evidently considered
by the Agency (although Sexton suggests
that this requirement could
result
in requiring
a leachate
collection system
retrofit costing
$800,000).
No support
is
cited by the Agency for
the permit reviewer’s “impression”
that
this condition
is necessary.
The majority thus today ratifies
a
condition which, besides being
intrinsically incapable of serving
as the basis
for current “approval”
of
a closure plan or
as
the
basis
for determining the currently appropriate amount of
financial assurance,
is without support
in the record.
Special Condition 17 shares
the characteristics of Special
Conditions
4 and
6
in that
its subsections
(a)(b)
and
(c)
require
Sexton
to undertake future actions having uncertain outcomes.
Subsection
(a)
requires Sexton to retest
its groundwater
monitoring wells
for an expanded number of parameters
for four
quarters.
Subsection
(b)
requires Sexton
to propose by a
supplemental permit request to be submitted within
61) days,
a
revised groundwater monitoring program, to include
at least one
additional up—gradient well and an unspecified number of
additional downgradient wells.
Subsection
(c)
requires Sexton
to
determine gradients and directions of qroundwaters through the
potential
leachate migration pathways and
to identify potentially
impacted water
sources.
No
timeframe for satisfaction of
subsection
(c)
is provided.
No
new
regulatory or other
requirements are cited by the Agency
in explanation as
to why the
groundwater monitoring program approved by the Agency
in
1984 has
been so altered.
The outcomes and the range of outcomes
from
these conditions are unspecified.
Once again,
the majority has
thus affirmed conditions which are unsuitable
for serving
as
a
basis
for current approval
of
a CPC plan or
for determining
the
currently appropriate amount of financial
assurance.
Special Condition 19(b)
imposes
a “twice background”
triggering number
for
initiation of assessment groundwater
monitoring.
Sexton correctly argues
that this
is arbitrary and
96—130
—11—
without
statutory,
regulatory
or
scientific
basis.
While
it
could
be
argued
that
Sexton’s
own
proposal
is
at
best
ambiguous
and
arbitrary,
that
is
not
the
point.
The
majority
today
ratifies
wholly
arbitrary
conditions
as
a
“cure”
for
ambiguity.
Consider
the
hypothetical
situation
in
which
adjacent
facilities
may
thus
have
completely
different
triggering
numbers
for
the
same
parameter
and
where
the
downgradient
facility
“benefits”
from
the
omissions
and
violations
of
its
up—gradient
neighbor:
if,
for
instance, the up—gradient facility releases leachate
containing
500
ppm
tetrachlorodibenzo—p—dioxins
into
the
groundwater,
the downgradient facility’s “triggering point”,
under
the
majority’s
opinion, becomes
1000 ppm.
This
is
neither
rational nor protective of
the environment.
Special Condition 20 imposes conditions on the use
of
municipal wastewater treatment plant sludge as
a
soil
conditioner.
Sexton
asserts
this
is subject solely to permitting
requirements imposed
by the Agency’s Division of Water Pollution
Control
under
the NPDES program.
Here,
we would concur with the
outcome,
if not
the
reasoning,
of the majority.
NPDES
requirements clearly do
not apply
in this regard
to the use of
wastes in
a sanitary landfill.
In
summary,
we
believe
that
the
majority,
in
its
understandable
desire
to
“do
something”
about
the
landfill
situation,
has
overridden
its
own
regulatory system,
present and
future;
in
a
very
real
sense,
the
majority
has
encouraged
instead
a “desktop” regulation—by—permit—reviewer “system”
to be reviewed
by
the
Board,
from
scratch,
case
by
case,
in
a
contested
case
setting.
This creates
a chaotic, balkanized, environmentally
unsubstantiated system
for landfill design and operation, weakens
enforcement, and cuts out the full public participation and
careful scientific assessment otherwise available
in
a regulatory
proceeding.
We
firmly believe that such an
ad hoc system serves
to
weaken,
not
strengthen,
true environmental protection.
For
the
foregoing
reasons,
we
dissent
from
the
opinion
of
the
majority.
~‘
~
an Anderson,
Board Member
96—131
—12—
I,
Dorothy
M.
Gunn,
Clerk
of
the
Illinois
Pollution
Control
Board,
hereby
certify
that
the
above
Dissenting
Opinion
was
submitted
on
the
~Q’~”
day
of
~-t--.--~tJ
,
1989.
Dorothy
M.
inn,
Clerk
Illinois
Poflution
Control
Board
96—132