    ORDER OF THE BOARD (by S.T. Lawton, Jr.):
    A complaint in the above-captioned matter was filed on August 28, 2000. The complaint alleges that the
    respondents caused or allowed the construction of a water main known as the Eads Water Main, without a permit in
    violation of Sections 15(a) and 18(a) of the Environmental Protection Act (Act) (415 ILCS 5/15(a), 18(a) (1998)) and
    35 Ill. Adm. Code 602.101(a). The Board accepts this matter for hearing.
    The Board directs that this matter proceed to hearing as expeditiously as practicable. The assigned hearing
    officer must set the matter for hearing in accordance with the requirements of the Act and the Board’s procedural
    rules. Accordingly, this matter must be set for hearing within 90 days after the filing of the complaint unless the
    hearing officer, after appropriate consultation with the parties, determines that a later date is appropriate and that
    no undue delay or material prejudice in the resolution of this matter would result. See 35 Ill. Adm. Code 103.125(a).
    In any event, it is the responsibility of the hearing officer to guide the parties toward prompt resolution or
    adjudication of this matter, through whatever status calls and hearing officer orders he or she determines are
    necessary and appropriate.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that the above order was
    adopted on the 7th day of September 2000 by a vote of 7-0.