ILLINOIS POLLUTION CONTROL BOARD
July 13,
1989
SPARTON MANUFACTURING CO./FLORA
)
(L0250100007, CLAY COUNTY),
)
)
Petitioner,
v.
)
PCB 89—110
)
ILLINOIS ENVIRONMENTAL PROTECTION
)
AGENCY,
Respondent.
ORDER OF THE BOARD
(by J. Marlin):
This matter comes before the Board upon receipt of an Agency
Recommendation dated July 11, 1989.
The recommendation refers to
a request from Petitioner,
Sparton Manufacturing Co.
for
a
30 day
provisional variance from the 90—day on—site limitations for
hazardous wastes set forth at
35
Iii. Adm. Code 722.134(b).
Upon receipt of the request the Agency issued
its
recommendation,
concluding that the hazardous wastes must remain
on—site for longer than 90 days due
to unforeseen,
temporary and
uncontrollable circumstances and failure to grant the requested
30—day provisional variance would impose an arbitrary
or
unreasonable hardship on Petitioner.
The Board concurs with the 1~gencyRecommendation;
Petitioner
is granted a provisional variance from
35 Iii. Mm.
Code
722.134(b)
from June 12, 1989 to
July
12, 1989.
IT
IS SO ORDERED.
I, Dorothy M.
Gunn,
Clerk
of the Illinois Pollution Control
Board, ~hereby certif
that the above Order was adopted on
the /j~day of
_____________
,
1989,
by a vote of
7_co
Dorothy M. ~nn,
C1er~
Illinois Pc~ution Control Board
101—117