ORDER OF THE BOARD (by J. Marlin):
This matter comes before the Board upon receipt of an Agency
Recommendation dated September 11, 1989. The recommendation
refers to a request from Petitioner, Hydro—Line Manufacturing Co.
for a 30 day provisional variance from the 90—day on—site
limitations for hazardous wastes set forth at 35 Iii. Adm. Code
722.134(b).
Upon receipt of the request the Agency issued its
recommendation, concluding that the hazardous wastes must remain
on—site for longer than 90 days due to unforeseen, temporary and
uncontrollable circumstances and failure to grant the requested
30—day provisional variance would impose an arbitrary or
unreasonable hardship on Petitioner.
The Board concurs with the Agency Recommendation; Petitioner
is granted a provisional variance from 35 Ill. Adm. Code
722.134(b) from August 23, 1989 to September 22, 1989.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the/above Order was adopted on
the
/~i~day of _________________________, 1989, by a
vote of
________
~).
~Dorothy M.~unn, Clerk,
Illinois Pdllution Control Board
103—79