ILLINOIS POLLUTION CONTROL BOARD
    January 25, 1990
    MOTOROLA, INC.,
    Petitioner,
    v.
    )
    PCB 90—9
    ) (Provisional Variance)
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    )
    Respondent.
    ORDER OF THE BOARD (3, Marlin):
    This matter comes before the Board upon receipt of an Agency
    Recommendation dated January 23, 1990. The recommendation refers
    to a request from Petitioner, Motorola, Inc. for a 30 day
    provisional variance from the 90—day on—site limitations for
    hazardous wastes set forth in 35 Ill. Adm. Code 722.134(b).
    Upon receipt of the request the Agency issued its
    recommendation, concluding that the hazardous wastes must remain
    on—site for longer than 90 days due to unforeseen, temporary and
    uncontrollable circumstances and failure to grant the requested
    30—day provisional variance would impose an arbitrary or
    unreasonable hardship on Petitioner.
    Having received and examined the Agency Recommendation, the
    Board hereby grants the Petitioner a provisional variance from 35
    Ill. Adm. Code 722.134(b) from December 5, 1989 to January 4,
    1990.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certif’ that the above Order was adopted on
    the ~
    day of ____________________________, 1990, by a
    vote of
    _________.
    ~,
    Dorothy M.jGunn1 Clerk
    Illinois Pollution Control Board
    107—20’)

    Back to top